CN110513142A - The polyurethane sealing aperture apparatus and its construction method of Underwell anti-injection hole anti-leak - Google Patents

The polyurethane sealing aperture apparatus and its construction method of Underwell anti-injection hole anti-leak Download PDF

Info

Publication number
CN110513142A
CN110513142A CN201910874992.3A CN201910874992A CN110513142A CN 110513142 A CN110513142 A CN 110513142A CN 201910874992 A CN201910874992 A CN 201910874992A CN 110513142 A CN110513142 A CN 110513142A
Authority
CN
China
Prior art keywords
partition
polyurethane
hole
sealing
injection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910874992.3A
Other languages
Chinese (zh)
Other versions
CN110513142B (en
Inventor
刘军
王立国
安丰华
杨通
贾宏福
张露伟
袁军伟
陈立伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan University of Technology
Original Assignee
Henan University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan University of Technology filed Critical Henan University of Technology
Priority to CN201910874992.3A priority Critical patent/CN110513142B/en
Publication of CN110513142A publication Critical patent/CN110513142A/en
Application granted granted Critical
Publication of CN110513142B publication Critical patent/CN110513142B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices or the like
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F7/00Methods or devices for drawing- off gases with or without subsequent use of the gas for any purpose

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The polyurethane sealing aperture apparatus and its construction method of Underwell anti-injection hole anti-leak, including the extraction arranged along the longitudinal direction or pressure-measuring pipe, the first filling tube, the second filling tube and gas injection or liquid injection pipe, first partition, the first polyurethane foamed bags, second partition, third partition, the second polyurethane foamed bags and the 4th partition are disposed in extraction or pressure-measuring pipe from the front to the back, the first sealing section is formed between first partition and second partition, elastic extrusion chamber is formed between second partition and third partition, forms the second sealing section between third partition and the 4th partition.The present invention adheres to drilling crushed zone coal and rock to form an entirety, block the channel of Gas Flow, increase the route of gas migration, frictional resistance increases, and barometric gradient is unchanged, to increase the difficulty of gas migration, sealing of hole effect is substantially increased, while reducing chemical agent to the injury of human body and reducing artificial physical work amount.

Description

The polyurethane sealing aperture apparatus and its construction method of Underwell anti-injection hole anti-leak
Technical field
The invention belongs to Safety of Coal Mine Production technical fields, and in particular to a kind of polyurethane sealing of Underwell anti-injection hole anti-leak Aperture apparatus and its construction method.
Background technique
Gas is predicted and carried out to the coal-bed gas pressure basic parameter important as coal-bed gas in Coal Seam Outburst Hazard Extracting result inspection etc. plays a significant role.Especially during carrying out gas pressure measurement, due to coal seam itself The influence of the factors such as the mode of geological conditions, sealing of hole, so that actual borehole sealing of hole effect and expected effect generate certain difference Away from.Sealing of hole effect how is improved, is of great significance for the measurement of coal-bed gas pressure.
For highly gassy mine, the work of gas pre-drainage is the envelope that the necessary links of mine safety production ensure to drill Hole effect is to improve the first step of extraction rate and extracting result.Although the method for drilling and sealing technology gradually increases, every kind Mode, the method for sealing of hole have its respective advantage and disadvantage and the scope of application.
Drilling and sealing is carried out using polyurethane, principle is: polyurethane A liquid is sufficiently mixed with B liquid, and polyurethane has Polyurethane mixed liquor is placed in drilling by the characteristic of high-expansion, carries out expanding substantial borehole space in a short time, is had viscous The liquid polyurethane of attached property will enter in hole-crack of drilling wall surface, block the channel of Gas Flow, while the crushed zone that will drill Coal and rock sorption sticks to form an entirety, prevents the gas in coal seam from flowing out from the near wall of drilling, to influence sealing of hole Effect.It is had the following problems during using polyurethane sealing of hole:
1) existing polyurethane sealing of hole technology, at sealing of hole initial stage since polyurethane does not solidify completely, gas pressure is larger in coal seam When, there is extraction or pressure-measuring pipe goes out drilling, may cause the casualties and equipment damage of drilling outside;
2) polyurethane is before dilatancy hardening, and there are the air of larger space in drilling, and in closed drilling, air can not be arranged It removes, then can be compressed into hole-crack of drilling wall surface, so that the polyurethane for the state of sticking together be made to be difficult to enter, can not block The channel of Gas Flow and the crushed zone coal and rock sorption that will drill stick to form an entirety, in the broken of drilling wall peripheral Broken band still can exist for the channel of Gas Flow offer, and then influence the sealing of hole effect of drilling;
3) during polyurethane dilatancy hardening, it may appear that a degree of shrinkage phenomenon is full of the drilling of polyurethane originally, due to The generation of contraction and will appear hole, to influence sealing of hole effect;
4) during broadcasting extraction or pressure-measuring pipe, drilling central location, especially drilling front end are placed it in, is carrying out sealing of hole In the process, the problems such as extraction or pressure-measuring pipe are located at the edge of drilling, are unfavorable for sealing of hole and influence sealing of hole effect.
Summary of the invention
The object of the present invention is to provide a kind of polyurethane sealing aperture apparatus of Underwell anti-injection hole anti-leak and its construction method, with There are sealing of hole initial stages for the solution prior art since polyurethane does not solidify completely, gas pressure is larger in coal seam, extraction or survey occurs Pressure pipe goes out drilling, may cause the casualties of drilling outside;Polyurethane is before dilatancy hardening, and there are larger in drilling The air in space, in closed drilling centre, air be cannot exclude, then can be compressed into hole-crack of drilling wall surface, To make the polyurethane for the state of sticking together cannot be introduced into, and then influence the sealing of hole effect of drilling;During polyurethane dilatancy hardening, meeting There is a degree of shrinkage phenomenon, originally be full of polyurethane drilling, due to contraction generation and will appear hole, thus shadow Ring sealing of hole effect;During broadcasting extraction or pressure-measuring pipe, extraction or pressure-measuring pipe are placed in drilling central location always, are conducive to seal Hole and raising sealing of hole effect, while also no the problems such as placing this chemical agent of polyurethane, reducing its injury to human body.
In order to solve the above technical problems, the present invention adopts the following technical scheme: the polyurethane sealing of Underwell anti-injection hole anti-leak Aperture apparatus is guiding with the direction in the aperture of drilling to bottom hole, from the front to the back successively includes the extraction arranged along the longitudinal direction Or pressure-measuring pipe, the first filling tube, the second filling tube and gas injection or liquid injection pipe, it is set gradually on extraction or pressure-measuring pipe from the front to the back There are first partition, the first polyurethane foamed bags, second partition, third partition, the second polyurethane foamed bags and the 4th partition, first Form the first sealing section between partition and second partition, form elastic extrusion chamber between second partition and third partition, third every The second sealing section is formed between plate and the 4th partition, the first filling tube passes through first partition and connect with the first polyurethane foamed bags, Second filling tube is connect after sequentially passing through first partition, second partition, third partition from the front to the back with the second polyurethane foamed bags, Gas injection or liquid injection pipe are connected to after sequentially passing through first partition, second partition from the front to the back with elastic extrusion chamber.
First partition and the 4th partition pass through fastener and are fixedly connected on extraction or pressure-measuring pipe, second partition and third Partition, which passes through to lead, to be set on extraction or pressure-measuring pipe, has certain rub between guide sleeve inner wall and extraction or pressure-measuring pipe outer circle Wipe power, first partition, second partition, third partition and the 4th partition periphery be equipped with rubber seal.
Second partition be equipped with can from the first check valve of the first sealing section one-way flow into elastic extrusion chamber, third every Plate is equipped with can be from the second one-way valve of the second sealing section one-way flow into elastic extrusion chamber.
4th partition leading flank is equipped with the rigid barrier device being located in the second sealing section;After rigid barrier device is thick before being integrally in Thin circular cone barrel structure, rigid barrier device include upper half taper cone barrel and lower half taper cone barrel, upper half taper cone barrel rear end and lower half circle Cone cylinder rear end passes through hinge and torsional spring is connected to the 4th partition leading flank.
The construction method of the polyurethane sealing aperture apparatus of Underwell anti-injection hole anti-leak, includes the following steps,
A, first drilled using drilling machine in underground, form cylindrical hole, reuse hydraulic slotted liner technique measure in hole into Row reaming forms at least two annular grooves;
B, rigid barrier device is installed to the 4th partition leading flank, first partition, second partition, third partition eccentric position It opens for passing through the first filling tube, the second filling tube and gas injection or the perforation of liquid injection pipe, in first partition, second partition, the Rubber seal is installed in the periphery of three partitions and the 4th partition, and it is unidirectional to install first respectively on second partition and third partition Valve and second one-way valve;
C, by the 4th partition, the second polyurethane foamed bags, third partition, second partition, the first polyurethane foamed bags and first every Plate is sequentially arranged at from the front to the back on extraction or pressure-measuring pipe;
D, the first filling tube, the second filling tube and gas injection or liquid injection pipe are passed through into corresponding perforation, the first filling tube passes through the Connect with the first polyurethane foamed bags after one partition by quick plug, the second filling tube sequentially pass through from the front to the back first every It is connect by quick plug with the second polyurethane foamed bags after plate, second partition, third partition, gas injection or liquid injection pipe are from the front to the back It is connected to after sequentially passing through first partition, second partition with elastic extrusion chamber, assembles the poly- ammonia of Underwell anti-injection hole anti-leak since then Ester hole sealing device;
E, the polyurethane sealing aperture apparatus of assembled Underwell anti-injection hole anti-leak is extended rearward into hole by the aperture of hole, when Stop conveying Underwell anti-injection backward when first partition enters in hole and rigid barrier device is located in one of on rear side of annular groove The polyurethane sealing aperture apparatus of hole anti-leak;
F, polyurethane mixing is injected into the first sealing section and the second sealing section by the first filling tube and the second filling tube respectively Liquid carries out sealing of hole;
G, by gas injection or liquid injection pipe gas injection or fluid injection into elastic extrusion chamber, make second partition and third partition respectively forwardly and Not fully hardened polyurethane is squeezed backward, improves the sealing of hole effect of the first sealing section and the second sealing section;
H, after polyurethane is fully hardened, certain pressure is kept in elastic extrusion chamber, prevent gas further to tunnel The valve at gas injection or liquid pipe front port is closed in the migration at place;
I, it is more than completion all drilling and sealings work, by extraction or pressure-measuring pipe start carry out coal-bed gas pressure measurement or The development of gas drainage work.
The detailed process of step f is, by the feed inlet of the first filling tube and the second filling tube respectively with the material feeding outside hole Polyurethane mixed liquor is delivered to the first polyurethane foamed bags and the second polyurethane foam by material feeding pump by pump interface connection respectively In bag, polyurethane foamed bags are burst in the polyurethane mixed liquor expansion in the first polyurethane foamed bags and the second polyurethane foamed bags Into in hole, until full of the space in entire first sealing section and the second sealing section;The sky in space where polyurethane Gas is squeezed by it, is entered in elastic extrusion chamber by the first check valve and second one-way valve, and polyurethane is allow to enter aperture wall In the hole-crack in face, hole crushed zone coal and rock is adhered to form an entirety, blocks the channel of Gas Flow;Meanwhile elasticity The polyurethane of extrusion chamber front and rear sides will push second partition and move backward makes elasticity squeeze space with the forward movement of third partition Become smaller;Material feeding closes the valve at two filling tube feed inlets after finishing.
The detailed process of step g is to connect the import of gas injection or liquid pipe with gas injection or liquid pump, and gas injection or liquid pump will be to bullets Property squeeze space in injection gas or liquid to certain pressure after, while push second partition move forward and third partition to Mobile afterwards that elasticity extruding space is made to become larger, second partition and third partition squeeze the not fully hardened poly- ammonia in front and rear sides respectively Ester is further the compactness for improving the first sealing section and the second sealing section inner urethane, again will be because of the hole of curing shrinkage Gap is full of.
Sealing of hole initial stage due to polyurethane not completely solidification, go out in boring procedure in extraction or pressure-measuring pipe, in coal seam watt When this pressure is larger, the gas pressure of hole bottom pushes whole device to move forward, when what is be arranged on the 4th partition leading flank When moving forward in neighbouring annular groove on front side of upper half taper cone barrel and lower half taper cone barrel, under the action of torsional spring, upper semi-circle Cone cylinder is pivoted upwardly into the top of annular groove, and lower half taper cone barrel rotates down the lower part into annular groove, to play positioning The effect of device, avoids the occurrence of spray orifice.
By adopting the above technical scheme, the beneficial effects of the present invention are:
(1) the columnar rigid barrier device that the present invention is connected on front side of the 4th partition by torsional spring and hinge, in hole Wall passes through the annular groove formed after hydraulic slotted liner technique reaming.At sealing of hole initial stage due to polyurethane not solidification, gas pressure in coal seam completely It when power is larger, is gone out in boring procedure in extraction or pressure-measuring pipe, rigid barrier device is being turned round when moving forward to cylindrical cavity It under the driving of spring, is entered in annular groove on front side of Circular Rigid barrier device, to limit the 4th partition and extraction or pressure-measuring pipe Position prevents extraction or pressure-measuring pipe from going out drilling, avoids the casualties and equipment damage that may cause drilling outside
(2) present invention is filled during polyurethane dilatancy hardening by passing through the annular groove formed after hydraulic slotted liner technique in hole The drilling of full polyurethane.Under the barometric gradient of coal-bed gas, script gas is migrated along the crushed zone straight line of drilling near wall, The annular groove formed after present hydraulic slotted liner technique has been also filled with polyurethane, and the route of gas migration increases, and frictional resistance increases, and presses Force gradient is unchanged, to increase the difficulty of gas migration, improves sealing of hole effect.
It is (3) of the invention by being connected in extraction or pressure-measuring pipe in the inner hole of second partition and third partition by guide sleeve, There is certain frictional force between guide sleeve inner wall and extraction or pressure-measuring pipe outer circle, it is ensured that its leakproofness, and by one It can be moved along extraction or pressure-measuring pipe after constant-pressure, while the first check valve and being installed on second partition and third partition Two check valves.Polyurethane is before dilatancy hardening, and there are the air of larger space in hole, and in expansion process, polyurethane will Air extrusion discharge in closed hole, enters elastic extrusion chamber through the first check valve and second one-way valve, to make to stick together shape The polyurethane of state can enter in hole-crack of hole wall, adhere to drilling crushed zone coal and rock to form an entirety, block The channel of Gas Flow, and then improve the sealing of hole effect of hole.
(4) during polyurethane dilatancy hardening, it may appear that a degree of shrinkage phenomenon, by gas injection (or liquid) pipe to bullet Property extrusion chamber in injection gas or liquid, and increase its internal pressure, drive the guide sleeve of second partition and third partition along taking out It adopts or pressure-measuring pipe is mobile, and then squeeze the not fully hardened polyurethane in two sides, hole will be generated because of contraction and filled up again, thus Improve the sealing of hole effect of hole.
(5) present invention by before broadcasting extraction or pressure-measuring pipe, in and rear portion be both provided with partition, extraction or pressure-measuring pipe Always be placed in the position of center line of hole, during carrying out sealing of hole, avoid extraction or pressure-measuring pipe be located at the edge of hole without Appearance conducive to sealing of hole, and then the problems such as influence sealing of hole effect, to improve the sealing of hole effect of drilling.
(6) after polyurethane dilatancy hardening, gas or liquid are injected into elastic extrusion chamber by gas injection or liquid pipe, and make it Internal pressure increases to certain pressure value.The extraction in hole deep or gas near pressure-measuring pipe rear port are under barometric gradient Migrate, since there are higher pressure at elastic extrusion chamber, and then prevent gas further to the fortune at tunnel It moves, to improve the sealing of hole effect of hole;Meanwhile gas or liquid inside elastic extrusion chamber filled with certain pressure, at it In the case where preceding sealing of hole effect failure, the effect of secondary hole sealing can be played, provides alternative scheme to improve the effect of sealing of hole.
(7) present invention is by there is no polyurethane is used, reducing chemical agent during broadcasting extraction or pressure-measuring pipe Injury to human body and reduce artificial physical work amount, and avoids and can not be carried out since the polyurethane dilatancy hardening time is fast The disadvantage of longer-distance drilling and sealing.
Detailed description of the invention
Fig. 1 is structural schematic diagram of the present invention before injecting polyurethane;
Fig. 2 is structural schematic diagram of the present invention after injecting polyurethane.
Specific embodiment
As depicted in figs. 1 and 2, the polyurethane sealing aperture apparatus of Underwell anti-injection hole anti-leak of the invention, with the aperture of drilling It is from the front to the back, including the extraction arranged along the longitudinal direction or pressure-measuring pipe 1, the first filling tube 2, the second note to the direction of bottom hole First partition 5, the first polyurethane are disposed on expects pipe 3 and gas injection or liquid injection pipe 4, extraction or pressure-measuring pipe 1 from the front to the back Foam bag 6, second partition 7, third partition 8, the second polyurethane foamed bags 9 and the 4th partition 10, first partition 5 and second partition The first sealing section 11 is formed between 7, forms elastic extrusion chamber 12 between second partition 7 and third partition 8, third partition 8 and the The second sealing section 13 is formed between four partitions 10, the first filling tube 2 passes through first partition 5 and connect with the first polyurethane foamed bags 6, Second filling tube 3 sequentially pass through from the front to the back after first partition 5, second partition 7, third partition 8 with the second polyurethane foamed bags 9 Connection, gas injection or liquid injection pipe 4 are connected to after sequentially passing through first partition 5, second partition 7 from the front to the back with elastic extrusion chamber 12.
First partition 5 and the 4th partition 10 are fixedly connected on extraction or pressure-measuring pipe 1 by fastener 14, second partition 7 and third partition 8 be arranged in extraction or pressure-measuring pipe 1 by guide sleeve 15,15 inner wall of guide sleeve and extraction or 1 outer circle of pressure-measuring pipe it Between there is certain frictional force, first partition 5, second partition 7, third partition 8 and the 4th partition 10 periphery be equipped with rubber Sealing ring 16.
Second partition 7 is equipped with can be from the first check valve of the first sealing section 11 one-way flow into elastic extrusion chamber 12 17, third partition 8 is equipped with can be from the second one-way valve 18 of the second sealing section 13 one-way flow into elastic extrusion chamber 12.
4th partition, 10 leading flank is equipped with the rigid barrier device being located in the second sealing section 13;Before rigid barrier device is integrally in Thin circular cone barrel structure after thick, rigid barrier device includes upper half taper cone barrel 19 and lower half taper cone barrel 20,19 rear end of upper half taper cone barrel Portion and 20 rear end of lower half taper cone barrel pass through hinge and torsional spring is connected to 10 leading flank of the 4th partition.
The construction method of the polyurethane sealing aperture apparatus of Underwell anti-injection hole anti-leak, includes the following steps,
A, it is first drilled using drilling machine in underground, forms cylindrical hole 21, reuse hydraulic slotted liner technique measure in hole 21 Interior carry out reaming forms at least two annular grooves 22;
B, rigid barrier device is installed to 10 leading flank of the 4th partition, first partition 5, second partition 7, third partition 8 it is inclined Heart position is opened for passing through the first filling tube 2, the second filling tube 3 and gas injection or the perforation of liquid injection pipe 4, in first partition 5, the Rubber seal 16 is installed in the periphery of two partitions 7, third partition 8 and the 4th partition 10, in second partition 7 and third partition 8 It is upper that first check valve 17 and second one-way valve 18 are installed respectively;
C, by the 4th partition 10, the second polyurethane foamed bags 9, third partition 8, second partition 7,6 and of the first polyurethane foamed bags First partition 5 is sequentially arranged at from the front to the back on extraction or pressure-measuring pipe 1;
D, the first filling tube 2, the second filling tube 3 and gas injection or liquid injection pipe 4 are passed through into corresponding perforation, the first filling tube 2 is worn It is connect by quick plug with the first polyurethane foamed bags 6 after crossing first partition 5, the second filling tube 3 sequentially passes through from the front to the back It is connect by quick plug with the second polyurethane foamed bags 9 after first partition 5, second partition 7, third partition 8, gas injection or fluid injection Pipe 4 is connected to after sequentially passing through first partition 5, second partition 7 from the front to the back with elastic extrusion chamber 12, assembles Underwell anti-injection since then The polyurethane sealing aperture apparatus of hole anti-leak;
E, the polyurethane sealing aperture apparatus of assembled Underwell anti-injection hole anti-leak is extended rearward into hole 21 by the aperture of hole 21 It is interior, stop when first partition 5 enters in hole 21 and rigid barrier device is located in one of 22 rear side of annular groove defeated backward Send the polyurethane sealing aperture apparatus of Underwell anti-injection hole anti-leak;
F, poly- ammonia is injected into the first sealing section 11 and the second sealing section 13 respectively by the first filling tube 2 and the second filling tube 3 Ester mixed liquor carries out sealing of hole;
G, by gas injection or liquid injection pipe 4 gas injection or fluid injection into elastic extrusion chamber 12, distinguish second partition 7 and third partition 8 Not fully hardened polyurethane is forwardly and rearwardly squeezed, the sealing of hole effect of the first sealing section 11 and the second sealing section 13 is improved;
H, after polyurethane is fully hardened, keep certain pressure in elastic extrusion chamber 12, prevent gas further to lane The valve at gas injection or liquid pipe front port is closed in migration at road;
I, more than completion all drilling and sealings work, starts the measurement for carrying out coal-bed gas pressure by extraction or pressure-measuring pipe 1 Or the development of gas drainage work.
The detailed process of step f is, by the feed inlet of the first filling tube 2 and the second filling tube 3 respectively and outside hole 21 Polyurethane mixed liquor is delivered to the first polyurethane foamed bags 6 and the second poly- ammonia by material feeding pump by the connection of material feeding pump interface respectively In ester foaming bag 9, the polyurethane mixed liquor in the first polyurethane foamed bags 6 and the second polyurethane foamed bags 9 is expanded polyurethane Foaming bag is burst into hole 21, until full of the space in entire first sealing section 11 and the second sealing section 13;Polyurethane Air in the space at place is squeezed by it, is entered in elastic extrusion chamber 12 by the first check valve 17 and second one-way valve 18, Enter polyurethane in hole-crack of 21 wall surface of hole, adhere to 21 crushed zone coal and rock of hole to form an entirety, blocks up Fill in the channel of Gas Flow;Meanwhile the polyurethane of elastic extrusion chamber front and rear sides will push second partition 7 and move backward and third The forward movement of partition 8 makes elasticity extruding space become smaller;Material feeding closes the valve at two filling tube feed inlets after finishing It closes.
The detailed process of step g is to connect the import of gas injection or liquid pipe with gas injection or liquid pump, and gas injection or liquid pump will be to bullets Property squeeze space in injection gas or liquid to certain pressure after, while push second partition 7 move forward and third partition 8 Moving backward, which makes elasticity squeeze space, becomes larger, and second partition 7 and third partition 8 squeeze that front and rear sides are not fully hardened to gather respectively Urethane is further the compactness for improving the first sealing section 11 and 13 inner urethane of the second sealing section, will be received again because of hardening The hole of contracting is full of.
Sealing of hole initial stage due to polyurethane not completely solidification, go out in boring procedure in extraction or pressure-measuring pipe 1, in coal seam watt When this pressure is larger, the gas pressure of 21 bottom of hole pushes whole device to move forward, and sets when on 10 leading flank of the 4th partition When the front side of the upper half taper cone barrel 19 and lower half taper cone barrel 20 set is moved forward in neighbouring annular groove 22, in the effect of torsional spring Under, upper half taper cone barrel 19 is pivoted upwardly into the top of annular groove 22, and lower half taper cone barrel 20 is rotated down into annular groove 22 Lower part avoids the occurrence of spray orifice to play the role of positioning device.
The present embodiment not makes any form of restriction shape of the invention, material, structure etc., all according to this hair Bright technical spirit any simple modification, equivalent change and modification to the above embodiments, belong to the technology of the present invention side The protection scope of case.

Claims (8)

1. the polyurethane sealing aperture apparatus of Underwell anti-injection hole anti-leak, it is characterised in that: the direction with the aperture of drilling to bottom hole is Guiding, successively include from the front to the back the extraction arranged along the longitudinal direction or pressure-measuring pipe, the first filling tube, the second filling tube and Be disposed with from the front to the back on gas injection or liquid injection pipe, extraction or pressure-measuring pipe first partition, the first polyurethane foamed bags, second every Plate, third partition, the second polyurethane foamed bags and the 4th partition, form the first sealing section between first partition and second partition, Elastic extrusion chamber is formed between second partition and third partition, and the second sealing section is formed between third partition and the 4th partition, the One filling tube pass through first partition connect with the first polyurethane foamed bags, the second filling tube sequentially pass through from the front to the back first every It is connect after plate, second partition, third partition with the second polyurethane foamed bags, gas injection or liquid injection pipe sequentially pass through first from the front to the back It is connected to after partition, second partition with elastic extrusion chamber.
2. the polyurethane sealing aperture apparatus of Underwell anti-injection hole according to claim 1 anti-leak, it is characterised in that: first partition Pass through fastener with the 4th partition to be fixedly connected on extraction or pressure-measuring pipe, second partition and third partition are set by guide sleeve It sets in extraction or pressure-measuring pipe, there is certain frictional force, first partition, the between guide sleeve inner wall and extraction or pressure-measuring pipe outer circle The periphery of two partitions, third partition and the 4th partition is equipped with rubber seal.
3. the polyurethane sealing aperture apparatus of Underwell anti-injection hole according to claim 2 anti-leak, it is characterised in that: second partition Being equipped with can be from the first check valve of the first sealing section one-way flow into elastic extrusion chamber, and third partition is equipped with can be by second The second one-way valve of sealing section one-way flow into elastic extrusion chamber.
4. the polyurethane sealing aperture apparatus of Underwell anti-injection hole according to claim 3 anti-leak, it is characterised in that: the 4th partition Leading flank is equipped with the rigid barrier device being located in the second sealing section;Thin circular cone barrel structure after rigid barrier device is thick before being integrally in, Rigid barrier device includes upper half taper cone barrel and lower half taper cone barrel, and upper half taper cone barrel rear end and lower half taper cone barrel rear end pass through Hinge and torsional spring are connected to the 4th partition leading flank.
5. the construction method of the polyurethane sealing aperture apparatus using Underwell anti-injection hole as claimed in claim 4 anti-leak, feature It is: includes the following steps,
A, first drilled using drilling machine in underground, form cylindrical hole, reuse hydraulic slotted liner technique measure in hole into Row reaming forms at least two annular grooves;
B, rigid barrier device is installed to the 4th partition leading flank, first partition, second partition, third partition eccentric position It opens for passing through the first filling tube, the second filling tube and gas injection or the perforation of liquid injection pipe, in first partition, second partition, the Rubber seal is installed in the periphery of three partitions and the 4th partition, and it is unidirectional to install first respectively on second partition and third partition Valve and second one-way valve;
C, by the 4th partition, the second polyurethane foamed bags, third partition, second partition, the first polyurethane foamed bags and first every Plate is sequentially arranged at from the front to the back on extraction or pressure-measuring pipe;
D, the first filling tube, the second filling tube and gas injection or liquid injection pipe are passed through into corresponding perforation, the first filling tube passes through the Connect with the first polyurethane foamed bags after one partition by quick plug, the second filling tube sequentially pass through from the front to the back first every It is connect by quick plug with the second polyurethane foamed bags after plate, second partition, third partition, gas injection or liquid injection pipe are from the front to the back It is connected to after sequentially passing through first partition, second partition with elastic extrusion chamber, assembles the poly- ammonia of Underwell anti-injection hole anti-leak since then Ester hole sealing device;
E, the polyurethane sealing aperture apparatus of assembled Underwell anti-injection hole anti-leak is extended rearward into hole by the aperture of hole, when Stop conveying Underwell anti-injection backward when first partition enters in hole and rigid barrier device is located in one of on rear side of annular groove The polyurethane sealing aperture apparatus of hole anti-leak;
F, polyurethane mixing is injected into the first sealing section and the second sealing section by the first filling tube and the second filling tube respectively Liquid carries out sealing of hole;
G, by gas injection or liquid injection pipe gas injection or fluid injection into elastic extrusion chamber, make second partition and third partition respectively forwardly and Not fully hardened polyurethane is squeezed backward, improves the sealing of hole effect of the first sealing section and the second sealing section;
H, after polyurethane is fully hardened, certain pressure is kept in elastic extrusion chamber, prevent gas further to tunnel The valve at gas injection or liquid pipe front port is closed in the migration at place;
I, it is more than completion all drilling and sealings work, by extraction or pressure-measuring pipe start carry out coal-bed gas pressure measurement or The development of gas drainage work.
6. construction method according to claim 5, it is characterised in that: the detailed process of step f is, by the first filling tube and The feed inlet of second filling tube is connect with the material feeding pump interface outside hole respectively, and polyurethane mixed liquor is defeated respectively by material feeding pump It send to the first polyurethane foamed bags and the second polyurethane foamed bags, in the first polyurethane foamed bags and the second polyurethane foamed bags Polyurethane mixed liquor expansion polyurethane foamed bags are burst into hole, until be full of entire first sealing section and the second envelope Space in hole section;The air in space where polyurethane is squeezed by it, is entered by the first check valve and second one-way valve In elastic extrusion chamber, enters polyurethane in hole-crack of hole wall, adhere to hole crushed zone coal and rock to form one A entirety blocks the channel of Gas Flow;Meanwhile the polyurethane of elastic extrusion chamber front and rear sides will push second partition and move back The forward movement of dynamic and third partition makes elasticity extruding space become smaller;Material feeding finish after by the valve at two filling tube feed inlets It is closed.
7. construction method according to claim 5, it is characterised in that: the detailed process of step g is, by gas injection or liquid pipe Import is connect with gas injection or liquid pump, and gas injection or liquid pump will squeeze to elasticity and inject gas or liquid in space to certain pressure Afterwards, while second partition is pushed to move forward and third partition moves backward makes elasticity squeeze space to become larger, second partition and the Three partitions squeeze the not fully hardened polyurethane in front and rear sides respectively, are improved in the first sealing section and the second sealing section The compactness of portion's polyurethane will be full of again because of the hole of curing shrinkage.
8. construction method according to claim 5, it is characterised in that: sealing of hole initial stage due to polyurethane not completely solidification, When extraction or pressure-measuring pipe are gone out in boring procedure, and gas pressure is larger in coal seam, the gas pressure of hole bottom pushes entire Device moves forward, and moves forward to neighbour on front side of the upper half taper cone barrel and lower half taper cone barrel being arranged on the 4th partition leading flank When in close annular groove, under the action of torsional spring, upper half taper cone barrel is pivoted upwardly into the top of annular groove, lower half taper cone barrel to Under be rotated into the lower part of annular groove, to play the role of positioning device, avoid the occurrence of spray orifice.
CN201910874992.3A 2019-09-17 2019-09-17 Underground polyurethane hole sealing device capable of preventing spray holes from leakage and construction method thereof Active CN110513142B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910874992.3A CN110513142B (en) 2019-09-17 2019-09-17 Underground polyurethane hole sealing device capable of preventing spray holes from leakage and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910874992.3A CN110513142B (en) 2019-09-17 2019-09-17 Underground polyurethane hole sealing device capable of preventing spray holes from leakage and construction method thereof

Publications (2)

Publication Number Publication Date
CN110513142A true CN110513142A (en) 2019-11-29
CN110513142B CN110513142B (en) 2024-03-01

Family

ID=68632608

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910874992.3A Active CN110513142B (en) 2019-09-17 2019-09-17 Underground polyurethane hole sealing device capable of preventing spray holes from leakage and construction method thereof

Country Status (1)

Country Link
CN (1) CN110513142B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111485936A (en) * 2020-06-08 2020-08-04 徐州工程学院 Hole sealing method for improving gas extraction effect
CN116122891A (en) * 2023-03-01 2023-05-16 中国矿业大学(北京) Device and method for improving extraction effect through secondary intelligent hole sealing of gas extraction drilling

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2054717A (en) * 1979-07-21 1981-02-18 Korfmann Gmbh Maschf Suction of gases from boreholes in coal mining
CN102628352A (en) * 2012-04-23 2012-08-08 中国矿业大学 Multi-section fixed point hydraulic fracturing method
WO2019137073A1 (en) * 2018-01-10 2019-07-18 河南理工大学 Multi-stage pressure bearing permeable hole sealing method and device
CN110173231A (en) * 2019-07-08 2019-08-27 中煤科工集团重庆研究院有限公司 Long-distance downward drilling segmented compact hole sealing pressure measuring device and method
CN210599084U (en) * 2019-09-17 2020-05-22 河南理工大学 Polyurethane hole sealing device for preventing underground spray hole from leaking

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2054717A (en) * 1979-07-21 1981-02-18 Korfmann Gmbh Maschf Suction of gases from boreholes in coal mining
CN102628352A (en) * 2012-04-23 2012-08-08 中国矿业大学 Multi-section fixed point hydraulic fracturing method
WO2019137073A1 (en) * 2018-01-10 2019-07-18 河南理工大学 Multi-stage pressure bearing permeable hole sealing method and device
CN110173231A (en) * 2019-07-08 2019-08-27 中煤科工集团重庆研究院有限公司 Long-distance downward drilling segmented compact hole sealing pressure measuring device and method
CN210599084U (en) * 2019-09-17 2020-05-22 河南理工大学 Polyurethane hole sealing device for preventing underground spray hole from leaking

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨宏民;王振亚;刘军;: "本煤层测压黄泥-聚氨酯快速封孔技术", 煤矿安全, no. 09, 10 September 2012 (2012-09-10), pages 63 - 64 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111485936A (en) * 2020-06-08 2020-08-04 徐州工程学院 Hole sealing method for improving gas extraction effect
CN111485936B (en) * 2020-06-08 2021-07-09 徐州工程学院 Hole sealing method for improving gas extraction effect
CN116122891A (en) * 2023-03-01 2023-05-16 中国矿业大学(北京) Device and method for improving extraction effect through secondary intelligent hole sealing of gas extraction drilling

Also Published As

Publication number Publication date
CN110513142B (en) 2024-03-01

Similar Documents

Publication Publication Date Title
CN105239965B (en) Halogen method is arranged in salt hole air reserved storeroom gas injection
CN109209472B (en) Punching, blasting and water injection mutual coupling coal seam pressure relief and outburst prevention method
CN113250670B (en) Single-hole multi-section synchronous control fracturing coal body permeability increasing system and method
CN210977392U (en) Gas drainage drilling hole sealing device
CN110984130B (en) Slurry stopping system and method for preventing blockage and slurry return outside hole of crushing belt
CN110513142A (en) The polyurethane sealing aperture apparatus and its construction method of Underwell anti-injection hole anti-leak
CN110608062B (en) Multi-section hollow grouting anchor cable and supporting method
CN111764837B (en) Double-end water plugging detection rod, overburden fracture drilling and measuring integrated device and drilling and measuring method
CN114135321A (en) Step-by-step sectional type tunnel curtain grouting construction pipe set, device and construction method
CN210599084U (en) Polyurethane hole sealing device for preventing underground spray hole from leaking
WO2019205472A1 (en) Controllable pressure injection apparatus based on hydraulic accumulator and method therefor
CN112943157B (en) Ball-throwing type leaking stoppage bypass valve for well drilling
CS276967B6 (en) Method of a rock consolidation and apparatus for making the same
CN106639962B (en) Secondary hole sealing pressure measuring device based on expanding agent
CN111140232B (en) Coal mining method for cutting coal by drilling-expanding-hydraulic expanding
CN111155978B (en) Oil field horizontal well multistage fracturing tubular column structure
CN111140252A (en) Circulating layering slip casting device
CN207863945U (en) A kind of underground coal mine long drilled holes gas flow test device
CN113481986B (en) Anti-floating anchor rod construction method in karst area
CN113006750B (en) Construction tool and method for improving recovery ratio of low-permeability reservoir horizontal well
CN109539916B (en) Explosive loading device and loading method capable of accurately controlling loading quantity and loading position
CN112031704B (en) Explosion nesting and leaking stoppage method for karst cave leakage loss well section
CN210509112U (en) Quick slip casting device of segmentation marching type drilling rod, system
CN216894429U (en) Step-by-step sectional type tunnel curtain grouting construction device
CN220791195U (en) Improved water injection plugging device for underground segmented upward hole water injection test fracture zone

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant