CN110512895A - A kind of high-rise cast-in-place concrete building demolition construction method - Google Patents

A kind of high-rise cast-in-place concrete building demolition construction method Download PDF

Info

Publication number
CN110512895A
CN110512895A CN201910778932.1A CN201910778932A CN110512895A CN 110512895 A CN110512895 A CN 110512895A CN 201910778932 A CN201910778932 A CN 201910778932A CN 110512895 A CN110512895 A CN 110512895A
Authority
CN
China
Prior art keywords
load bearing
bearing wall
column
wall
place concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910778932.1A
Other languages
Chinese (zh)
Inventor
张肇敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wenzhou Jinmao Construction Co Ltd
Original Assignee
Wenzhou Jinmao Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wenzhou Jinmao Construction Co Ltd filed Critical Wenzhou Jinmao Construction Co Ltd
Priority to CN201910778932.1A priority Critical patent/CN110512895A/en
Publication of CN110512895A publication Critical patent/CN110512895A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/08Wrecking of buildings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a kind of high-rise cast-in-place concrete building demolition construction methods, comprising the following steps: S1: building protective equipment on building periphery to be onstructed, and builds the upper and lower building channel of construction material and lower waste residue channel;S2: structure is shored in setting between contiguous floors to be onstructed, and the structure of shoring holds out against upper and lower floor respectively;S3: it is successively removed by the sequence of floor, non-load bearing wall, beam, load bearing wall, column;S4: when removing to load bearing wall, building temporary support structure in load bearing wall two sides, to load bearing wall according at least 3 equal points of cuttings, and preferentially removes by intermediate load bearing wall wall, finally removes the load bearing wall wall on both sides;S5: when removing to column, being first fixed column, then implements cutting operation to column bottom, subsequently pushes over column by assigned direction.The Demolition Construction method comprehensively improves each working security for removing part, reduces the dependence to big machinery construction, improves work efficiency.

Description

A kind of high-rise cast-in-place concrete building demolition construction method
Technical field
The present invention relates to building engineering field, in particular to a kind of high-rise cast-in-place concrete building demolition construction method.
Background technique
With the continuous propulsion of China's urban modernization, old house is removed and the demands such as extending old building, renovation are being continuously increased. Currently, most of building is all built using concrete, common side during being removed to entire building room Method are as follows: three kinds of forms such as mechanical removal, demolition blasting and manual demolition.Demolition blasting is generated using explosive in instant of detonation High temperature, high pressure gas do work to medium, carry out brokenness to building or toppling property is demolished;Usually in Government-Leading, peripheral ring Border is preferable, coordinates relatively small difficulty, uses in the case where Yi Yinqi media and masses' concern, in the more harsh city of condition City business district, relatively fewer use.Manual demolition, be by by hand plus some simple tools (such as drill rod, hammer, air drill, Lever Blocks, wirerope etc.), it is struck mainly by hammer, rod sled, is disintegrated with physical strength to building implementation with worker, is crushed to reach and tear open The purpose removed.Mechanical removal, long-armed tear open building machine (long-armed hydraulic shear) is removed in city is removed more generally, low mainly in Layer building.
But it when being removed for high-rise cast-in-place concrete building, is especially built more than 30 meters, is not allow mainframe Upstairs, and skyscraper periphery usually has other houses to tool, and mechanical removal and demolition blasting at this time can not fit Answer this demand.For conventional direct cutting disassembling, it is uneven not only to occur load during cutting, malformation, Vibration is big, crack occurs, results even in cave-in accident, causes casualties.
Summary of the invention
The object of the present invention is to provide a kind of safe and effective construction parties removed to high-rise cast-in-place concrete building Method.
Above-mentioned technical purpose of the invention has the technical scheme that a kind of high-rise cast-in-place concrete is built Build Demolition Construction method, comprising the following steps:
S1: building protective equipment on building periphery to be onstructed, and build on construction material,
Downstairs channel and lower waste residue channel;
S2: structure is shored in setting between contiguous floors to be onstructed, and the structure of shoring holds out against upper and lower floor respectively;
S3: it is successively removed by the sequence of floor, non-load bearing wall, beam, load bearing wall, column;
S4: when removing to load bearing wall, building temporary support structure in load bearing wall two sides, waits a point cutting according at least 3 to load bearing wall, And preferential remove leans on intermediate load bearing wall wall, finally removes the load bearing wall wall on both sides;
S5: when removing to column, being first fixed column, then implements cutting operation to column bottom, subsequently pushes away by assigned direction Column.
Through the above technical solutions, when being removed to high-rise cast-in-place concrete building, it is interim into building to load bearing wall Then support construction carries out the cutting of at least 3 equal parts to load bearing wall, first remove intermediate wall, then remove the wall on both sides;I.e. Take load bearing wall the mode of dividedly dismantling, and cooperate the temporary support structure of two sides so that load bearing wall when being removed more Add stabilization, can effectively prevent load bearing wall total collapse.When in addition being removed to column, first then column is fixed to column bottom Portion cuts and pushes over segmentation and carries, and effectively prevents cylinder run-off the straight when being removed and collapses, substantially increases Demolition Construction When safety and validity.
Further, in step s 4, temporary support structure can only be built at the load bearing wall wall on both sides.
Through the above technical solutions, the load bearing wall wall due to middle section will be removed preferentially, it is having built Fixed function is played in wall cutting, but when wall cutting vibration and it is little, and cut also only wall is vertically divided, Its bottom is still fixed on floor, therefore the part can not build temporary support structure, and this saves time and materials.
Further, in step s 5, when column being fixed, hanging ring is installed in the middle part surrounding of column, and led with rope Draw, the other end of the rope is securable on four angles of floor or on lower layer's beam, column.
Through the above technical solutions, cylinder is usually cuboid, hanging ring is installed at its four sides and is fixed with cable traction, this The mode of sample is very firm, can prevent it from collapsing toward any direction, and when pushing over cylinder, utilize the traction of hanging ring and rope Implementation soft landing can be pushed over to column, cylinder is avoided to cause compared with major injury the floor or beam of wanting toppling direction.
Further, before pushing over column, extra hanging ring and rope is removed according to direction to be pushed over and recycled, only stay 1-2 Hanging ring is used to control and trussed shore pushes over, and remaining hanging ring conjunction rope is recycled after pushing over column.
Through the above technical solutions, due to before pushing over cylinder its four sides be assembled with hanging ring and rope structure, we Wherein 1-2 hanging ring and rope structure be can choose to control the direction that it is pushed over, it is very easy to use, and hanging ring and rope Structure can be used repeatedly, and save cost.
Further, when removing fine strain of millet, the column that do not removed using this layer installs bottle gouard moved by hands, then to beam as supporting point Unwrapping wire segmentation, lifts the part beam section that will be removed, then implements to remove operation.
It is first fixed when through the above technical solutions, removing fine strain of millet, effectively controls its position fallen, be avoided that it is tumbled To downstairs and other positions and cause unexpectedly to injure accident by a crashing object, substantially increase the safety of construction;And using column as Support, installation bottle gouard moved by hands lifting are very convenient quick.
Further, when being removed to non-load bearing wall, temporary support structure is built in non-load bearing wall one or both sides, is held to non- Weight wall is according at least 3 equal points of cuttings, and preferential dismounting finally removes the non-load bearing wall wall on both sides by intermediate non-load bearing wall wall Body.
Through the above technical solutions, although the collapsing of non-load bearing wall does not easily cause the collapsing of monolithic architecture, in order to construct Safety, with load bearing wall remove, the dismounting of non-load bearing wall can also be taken and build temporary support structure and segmentation The mode of dismounting is effectively reduced a possibility that unexpected cave-in accident occurs, greatly improves the safety of integral construction.
Further, before removing operation, to floor to be removed, non-load bearing wall, beam, load bearing wall, column dedusting, watering. And when removing operation, installation depositing dust spraying apparatus is dusted.
Through the above technical solutions, can effectively be avoided before removing operation and the processing that is all dusted when removing operation The generation of fugitive dust, reduces air pollution when construction, maintains the cleaning of construction site, i.e., also provides construction worker better Construction environment, the maloperation for reducing construction worker occur.
Further, the temporary support structure is timber or steel pipe.
Through the above technical solutions, the intensity difference that can be more reinforced support selects different temporary support structures, wood Stake can directly abut fixation it is very convenient, quick, steel pipe then can by punching fix, intensity is big, and stability is strong.
In conclusion the invention has the benefit that implement to reinforce to load bearing wall and non-load bearing wall and dividedly dismantling, it is right Beam carries out lifting dismounting, reinforce to cylinder and directed traction pushes over dismounting, comprehensively improves each dismounting part Working security, and when removing, it is used as support organization mutually to utilize between beam, column, floor upper and lower level, effectively reduces Dependence to big machinery construction, greatly improves work efficiency.
Specific embodiment
This specific embodiment is only explanation of the invention, is not limitation of the present invention, those skilled in the art Member can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but as long as at this All by the protection of Patent Law in the scope of the claims of invention.
Embodiment:
Prepare before site operation:
(1) it is familiar with the as-constructed drawing of split building first, understands fully structure situation, building situation, water power and the equipment of building Pipe condition, underground concealed facility situation.Building site responsible person will tear open according to Design of Construction Organization and act of technique for security to participation The staff removed carries out detailed tell somebody what one's real intentions are.
(2) goods and materials within the scope of clear collapsed building to be removed, equipment;Electric wire, gas pipeline, water pipe, heat supply are set The standby branch line cutting or migration for waiting main lines and the building;Treating the door in demolition of buildings, window can also first be removed;Inspection Dilapidated house around is looked into, carries out temperature pier when necessary;It issues a notice to reassure the public to the masses around, forbidden zone is set around danger area removing Fence, caution notice send special messenger to guard, non-dismounting personnel are forbidden to enter construction site.
After completing above-mentioned previous work, the crucial dismounting of progress can be built to high-rise cast-in-place concrete to be removed and is applied Work, specific method the following steps are included:
Step 1: protective equipment is built on building periphery to be onstructed, and build on construction material,
Downstairs channel and lower waste residue channel;Including and be not limited to construction fence and pavement frame and lifter apparatus etc..
Step 2: structure is shored in setting between contiguous floors to be onstructed, and the structure of shoring holds out against upper and lower building respectively Plate;Structure mainly is shored using the materials production such as steel pipe, plank, pin or bamboo pole, according to the required bearing capacity of floor to be removed, In conjunction with floor bearing capacity itself be calculated should lay shore number of structures and position.
Step 3: carry out dismounting gradually from top to bottom since the floor of roof, and by floor, non-load bearing wall, beam, Load bearing wall, column sequence successively removed.Floor is pinpointed when removing floor and is crossed, cut zone block-by-block is removed, and It is to be carried out by the intermediate sequence to surrounding, avoids floor from removing the accident for causing to collapse carelessly and occur.
Wherein, when being removed to load bearing wall, load bearing wall is waited according to 3 and is crossed, then to the wall temporary support knot on both sides Structure is reinforced, then presses scribing position punching fixed-point, is split using cutting equipment to wall, then using tool to wall block-by-block It abolishes, and preferential remove leans on intermediate load bearing wall wall, finally removes the load bearing wall wall on both sides.When abolishing wall, to break Except cushion is laid on the floor of wall direction, avoids broken wall block from splashing and other object or person are damaged.Certainly Following up the width of load bearing wall can be even more to 4 equal part of wall, 5 equal parts, can not in addition to that block wall that will remove Temporary support structure is done, remaining block is all reinforced.In addition, also have more selection form about temporary support structure, According to the intensity of wall and the requirement of construction, different degrees of temperature pier can be taken, it is desirable that the intensity of reinforcing it is high and The time of construction is longer, can choose steel pipe reinforcing, both ends are fixed in wall and floor punching with bolt respectively.It is required that The intensity of reinforcing is not high, can be shored using timber, and the both ends cutting of timber is angled to be born against in wall and building Between plate, which, which is located at that end on floor, to be adjusted with wedge block clamping.Preferably in wall when doing temporary support structure Body two sides symmetrically reinforce, so also more stable.
It, as needed can also be using above-mentioned construction method used when being removed to load bearing wall when being removed to non-load bearing wall.
Wherein, to column remove when, column middle part surrounding turn hole and hanging ring is installed, then use cable traction, be fixed, this The other end of rope is securable on four angles of floor or on lower layer's beam, column;After the completion of fixation, then column bottom is implemented to cut Operation is cut, the bar construction including cutting off column body.Before pushing over column, extra hanging ring and rope are removed according to direction to be pushed over Rope simultaneously recycles, and only stays 1-2 hanging ring for controlling the direction of pushing over of column, and during pushing over column, can use hang always Ring and rope structure are drawn, and column can slowly be led down, avoid causing to hurt to the floor or beam of its collapse direction Evil.And recycle remaining hanging ring after pushing over column and close rope to utilize again, column subsequently is pushed over by assigned direction, finally to column Piecemeal cuts and transports.Certainly, if columnar volume is smaller, can not also dismantle hanging ring, be further added by hanging ring instead and rope is strong Degree, directly transports whole lifting of cylinder.If cylinder is the outermost in building, the other end of rope can also be fixed on On the protective fence built, the protective fence to be reinforced again certainly, reinforcing can use lower floor's post or girder construction.
Wherein, when removing fine strain of millet, it can use column that this layer is not removed as supporting point, installation bottle gouard moved by hands, then to beam Unwrapping wire segmentation, lifts the part beam section that will be removed, then implements to remove operation.In addition it can be combined shoring structure, Interim slope track is set up on the basis of beam body is withstood, cooperates the lifting of bottle gouard moved by hands, by the beam body of dismounting along oblique Slope track slip reduces the lifting pressure of bottle gouard moved by hands, also avoids the decentralization of beam body is overweight from damaging to floor, mention The high safety of construction.
When in addition being removed to Special-shaped objects such as balcony, stair, it can be removed to using the partitioning scheme of three-stage, including benefit It is lifted with structure and bottle gouard moved by hands etc. is shored, implements soft landing to object is removed, ensure the safety of construction.
Before removing operation, to floor to be removed, non-load bearing wall, beam, load bearing wall, column dedusting, watering.And it is removing When operation, installation depositing dust spraying apparatus is dusted.In addition the underdrainage system where building to be removed is carried out real-time Sundries cleaning, avoids blocking, more in order to create good construction environment, guarantees effective development of Demolition Construction.

Claims (9)

1. a kind of high-rise cast-in-place concrete building demolition construction method, which comprises the following steps:
S1: building protective equipment on building periphery to be onstructed, and build on construction material,
Downstairs channel and lower waste residue channel;
S2: structure is shored in setting between contiguous floors to be onstructed, and the structure of shoring holds out against upper and lower floor respectively;
S3: it is successively removed by the sequence of floor, non-load bearing wall, beam, load bearing wall, column;
S4: when removing to load bearing wall, building temporary support structure in load bearing wall two sides, waits a point cutting according at least 3 to load bearing wall, And preferential remove leans on intermediate load bearing wall wall, finally removes the load bearing wall wall on both sides;
S5: when removing to column, being first fixed column, then implements cutting operation to column bottom, subsequently pushes away by assigned direction Column.
2. a kind of high-rise cast-in-place concrete building demolition construction method according to claim 1, it is characterised in that: in step In rapid S4, temporary support structure is only built at the load bearing wall wall on both sides.
3. a kind of high-rise cast-in-place concrete building demolition construction method according to claim 1, it is characterised in that: in step In rapid S5, when column is fixed, hanging ring is installed in the middle part surrounding of column, and with cable traction, the other end of the rope can be consolidated Due on four angles of floor or on lower layer's beam, column.
4. a kind of high-rise cast-in-place concrete building demolition construction method according to claim 3, it is characterised in that: push over Before column, extra hanging ring and rope are removed according to direction to be pushed over and recycled, only stays 1-2 hanging ring for control simultaneously trussed shore It pushes over, and recycles remaining hanging ring after pushing over column and close rope.
5. a kind of high-rise cast-in-place concrete building demolition construction method according to claim 1, it is characterised in that: remove When fine strain of millet, the column that do not removed using this layer is installed bottle gouard moved by hands, is then segmented to beam unwrapping wire, to what will be removed as supporting point The lifting of part beam section, then implement to remove operation.
6. a kind of high-rise cast-in-place concrete building demolition construction method according to claim 1, it is characterised in that: to non- When load bearing wall is removed, temporary support structure is built in non-load bearing wall one or both sides, non-load bearing wall is waited according at least 3 and is cut It cuts, and preferential remove leans on intermediate non-load bearing wall wall, finally removes the non-load bearing wall wall on both sides.
7. a kind of high-rise cast-in-place concrete building demolition construction method according to claim 1, it is characterised in that: tearing open Before operation, to floor to be removed, non-load bearing wall, beam, load bearing wall, column dedusting, watering.
8. a kind of high-rise cast-in-place concrete building demolition construction method according to claim 1, it is characterised in that: tearing open When except operation, installation depositing dust spraying apparatus is dusted.
9. a kind of high-rise cast-in-place concrete building demolition construction method according to claim 1, it is characterised in that: described Temporary support structure be timber or steel pipe.
CN201910778932.1A 2019-08-22 2019-08-22 A kind of high-rise cast-in-place concrete building demolition construction method Pending CN110512895A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910778932.1A CN110512895A (en) 2019-08-22 2019-08-22 A kind of high-rise cast-in-place concrete building demolition construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910778932.1A CN110512895A (en) 2019-08-22 2019-08-22 A kind of high-rise cast-in-place concrete building demolition construction method

Publications (1)

Publication Number Publication Date
CN110512895A true CN110512895A (en) 2019-11-29

Family

ID=68627311

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910778932.1A Pending CN110512895A (en) 2019-08-22 2019-08-22 A kind of high-rise cast-in-place concrete building demolition construction method

Country Status (1)

Country Link
CN (1) CN110512895A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111173312A (en) * 2019-12-31 2020-05-19 哈尔滨理工大学 Method for heating-cooling demolition of high-rise brick structure
CN111877798A (en) * 2020-08-07 2020-11-03 中电建十一局工程有限公司 Static force dismantling construction process for concrete structure of continuous construction project
CN112065095A (en) * 2020-09-11 2020-12-11 中国水利水电第十二工程局有限公司 Reinforced concrete support beam dismantling device and using method thereof
CN113463943A (en) * 2021-07-08 2021-10-01 温州高达建设有限公司 High-rise cast-in-place concrete building demolition construction method
CN113482397A (en) * 2021-06-30 2021-10-08 上海宝冶集团有限公司 Static force dismantling construction method for high-altitude suspension independent frame beam
CN113482398A (en) * 2021-06-30 2021-10-08 上海宝冶集团有限公司 Gravity overturning building dismantling construction method
CN113833309A (en) * 2021-09-29 2021-12-24 山东建筑大学 Construction method for mechanically dismantling building group and application
WO2022077892A1 (en) * 2020-10-16 2022-04-21 上海建工四建集团有限公司 Outer wall reinforcing device and method in building reconstruction
CN115030559A (en) * 2022-05-24 2022-09-09 四川农业大学 Method for dismantling cast-in-situ concrete beam slab column of constructed building
CN115162772A (en) * 2022-04-21 2022-10-11 广东碧通百年科技有限公司 High-rise building demolition process

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102852344A (en) * 2012-08-17 2013-01-02 重庆市***工程建设有限责任公司 Construction method for dismounting high-rise cast-in-place concrete building
JP2017002489A (en) * 2015-06-05 2017-01-05 三菱電機株式会社 Chipping device
CN106812073A (en) * 2017-01-12 2017-06-09 浙江交工金筑交通建设有限公司 It is quick to remove bridge pier column construction method
CN107642251A (en) * 2017-09-20 2018-01-30 江山(福建)建设工程有限公司 A kind of high-rise cast-in-place concrete building demolition construction method
CN109972858A (en) * 2019-02-28 2019-07-05 广东天盛装饰消防工程有限公司 Shockproof concrete building structures method for dismounting

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102852344A (en) * 2012-08-17 2013-01-02 重庆市***工程建设有限责任公司 Construction method for dismounting high-rise cast-in-place concrete building
JP2017002489A (en) * 2015-06-05 2017-01-05 三菱電機株式会社 Chipping device
CN106812073A (en) * 2017-01-12 2017-06-09 浙江交工金筑交通建设有限公司 It is quick to remove bridge pier column construction method
CN107642251A (en) * 2017-09-20 2018-01-30 江山(福建)建设工程有限公司 A kind of high-rise cast-in-place concrete building demolition construction method
CN109972858A (en) * 2019-02-28 2019-07-05 广东天盛装饰消防工程有限公司 Shockproof concrete building structures method for dismounting

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
迪特里希•科尔特等: "《拆除工程准备与实施》", 31 December 1983, 冶金部建筑研究总院技术情报研究室 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111173312A (en) * 2019-12-31 2020-05-19 哈尔滨理工大学 Method for heating-cooling demolition of high-rise brick structure
CN111173312B (en) * 2019-12-31 2020-10-23 哈尔滨理工大学 Method for heating-cooling demolition of high-rise brick structure
CN111877798A (en) * 2020-08-07 2020-11-03 中电建十一局工程有限公司 Static force dismantling construction process for concrete structure of continuous construction project
CN112065095A (en) * 2020-09-11 2020-12-11 中国水利水电第十二工程局有限公司 Reinforced concrete support beam dismantling device and using method thereof
WO2022077892A1 (en) * 2020-10-16 2022-04-21 上海建工四建集团有限公司 Outer wall reinforcing device and method in building reconstruction
CN113482398A (en) * 2021-06-30 2021-10-08 上海宝冶集团有限公司 Gravity overturning building dismantling construction method
CN113482397A (en) * 2021-06-30 2021-10-08 上海宝冶集团有限公司 Static force dismantling construction method for high-altitude suspension independent frame beam
CN113482398B (en) * 2021-06-30 2023-02-28 上海宝冶集团有限公司 Gravity overturning building dismantling construction method
CN113463943A (en) * 2021-07-08 2021-10-01 温州高达建设有限公司 High-rise cast-in-place concrete building demolition construction method
CN113833309A (en) * 2021-09-29 2021-12-24 山东建筑大学 Construction method for mechanically dismantling building group and application
CN115162772A (en) * 2022-04-21 2022-10-11 广东碧通百年科技有限公司 High-rise building demolition process
CN115162772B (en) * 2022-04-21 2024-05-10 广东碧通百年科技有限公司 Demolishing process for high-rise building
CN115030559A (en) * 2022-05-24 2022-09-09 四川农业大学 Method for dismantling cast-in-situ concrete beam slab column of constructed building

Similar Documents

Publication Publication Date Title
CN110512895A (en) A kind of high-rise cast-in-place concrete building demolition construction method
CN107419918B (en) A kind of Historical Buildings periphery single-layer frame retains method for dismounting
CN102808526A (en) Nondestructive demolition construction method of reinforced concrete frame beam
CN110904867B (en) Construction method for dismantling upper-span existing line arch bridge
CN113235467A (en) Construction method for dismantling large-span prestressed cast-in-place box girder
CN110820608A (en) Existing railway passenger station-entering overbridge dismantling method
CN110905232A (en) Mechanical static force dismantling method for concrete structure
CN108193894A (en) The construction method of rope saw dismantling concrete wall
CN106638336A (en) Over-line continuous beam removing method and support for removing
CN110847915A (en) Construction process for jumping-cutting demolishing and subsection back-jacking of double-side-wall temporary support of shallow-buried fine sand layer
JP6603824B2 (en) Upper scattering prevention curing system and upper scattering prevention curing method at the time of multi-story building dismantling
CN112727147A (en) Outdoor suspended step dismantling method
CN108979198A (en) A kind of skyscraper tears building machine open and its tears building method open
CN106320192A (en) Beam section replacement reinforcement method for large-span concrete continuous beam bridge
JP5617130B2 (en) Building demolition method and demolition equipment
CN117166814A (en) Multi-high-rise reinforced concrete bearing wall self-supporting structure and construction method thereof
CN111593681B (en) Pier stud retaining cast-in-place box girder ecological dismantling system and construction method
Menon et al. Comparative study of demolition methods
CN206143650U (en) Cross -line continuous beam is demolishd and is used support
CN115538340A (en) Rapid dismantling device and construction method for old bridge precast beam plate
CN114134828A (en) Method for quickly dismantling upper structure of truss arch bridge
CN114045758A (en) Construction method for dismantling old bridge of precast beam
Li et al. Study on construction technology of hydraulic climbing formwork for super high-rise building under aluminum formwork system
CN112227814A (en) Method for dismantling straight-barrel type concrete tower body
CN217106161U (en) Assembled building aluminum mould board strutting arrangement

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191129

RJ01 Rejection of invention patent application after publication