CN110512783A - The building cover structure being made of cast-in-place concrete Vierendeel girder and reinforced concrete slab - Google Patents

The building cover structure being made of cast-in-place concrete Vierendeel girder and reinforced concrete slab Download PDF

Info

Publication number
CN110512783A
CN110512783A CN201910207370.5A CN201910207370A CN110512783A CN 110512783 A CN110512783 A CN 110512783A CN 201910207370 A CN201910207370 A CN 201910207370A CN 110512783 A CN110512783 A CN 110512783A
Authority
CN
China
Prior art keywords
laminated floor
floor slab
concrete
frame beam
preformed layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910207370.5A
Other languages
Chinese (zh)
Other versions
CN110512783B (en
Inventor
姚开明
吴映栋
林鸳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG GAD CO Ltd
Original Assignee
ZHEJIANG GAD CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG GAD CO Ltd filed Critical ZHEJIANG GAD CO Ltd
Priority to CN201910207370.5A priority Critical patent/CN110512783B/en
Publication of CN110512783A publication Critical patent/CN110512783A/en
Application granted granted Critical
Publication of CN110512783B publication Critical patent/CN110512783B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B5/18Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly cast between filling members

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to a kind of building cover structures being made of cast-in-place concrete Vierendeel girder and reinforced concrete slab, comprising: concrete frame beam, reinforced concrete slab;Reinforced concrete slab bottom is preformed layer, top is concrete cast-in-situ layer, wherein: when concrete frame beam is connect with reinforced concrete slab, laminated floor slab preformed layer and the concrete frame beam parting in 1.5 times of Vierendeel girder high scopes of beam-ends disengage, parting disengages in range, laminated floor slab preformed layer reinforcing bar does not stretch out edges of boards, is attached with in-situ layer interface additional bar with concrete frame beam by setting laminated floor slab preformed layer;When concrete frame beam is connect with reinforced concrete slab, range is Chong Die other than 1.5 times of deck-moldings of beam-ends shelves for laminated floor slab preformed layer and concrete frame beam, and overlapping is shelved in range, and laminated floor slab preformed layer reinforcing bar protrudes into concrete frame beam and is attached.The present invention improves building structure entirety anti-seismic performance, reaches the conceptual design requirement of " strong column and weak beam ".

Description

The building cover structure being made of cast-in-place concrete Vierendeel girder and reinforced concrete slab
Technical field
The invention belongs to building engineering fields, and in particular, to one kind is by cast-in-place concrete Vierendeel girder and concrete folding The building cover structure that floor is constituted.
Background technique
Assembled architecture has many advantages, such as energy conservation and environmental protection, high-efficiency high-quality, meets the requirement of building industrialization, and various regions are just emerging Play assembled architecture heat;Currently, assembled architecture is in the eruptive growth stage.By Project, our rational thinkings Find after summary, there are still many problems for existing assembled architecture: construction and transportation cost are high compared with conventional building construction, vertical Load-bearing and the main assembled node of lateral resistant member (such as frame column, shear wall) are connected using grout sleeve mode in the presence of safety Hidden danger and antidetonation defect, globality are not as good as cast-in-place structural, and anti-seismic performance is poor etc..Undergo Wenchuan earthquake in 2008, jade in 2010 Earthquake is set, our countries are continuously improved in terms of building structure aseismatic standard to be required, in terms of antidetonation existing for assembled architecture Hidden danger or defect obviously run in the opposite direction with this.Main member of the laminated floor slab as assembled architecture, due to constructing structure and Reason in terms of prefabricated rate, thickness is more compared with cast-in-place structural plate thickness, so that the Vierendeel girder bearing capacity being attached thereto is superpower, It can not really realize the aseismic design concept requirement of building structure " strong column and weak beam ".
Summary of the invention
For the anti-seismic performance for improving assembled architecture, the requirement of building structure " strong column and weak beam " is realized, the present invention proposes one The building cover structure that kind is made of cast-in-place concrete Vierendeel girder and reinforced concrete slab.
To achieve the above object, the invention adopts the following technical scheme:
The building cover structure being made of cast-in-place concrete Vierendeel girder and reinforced concrete slab, comprising: concrete frame beam, concrete Laminated floor slab;Concrete frame beam is connect with whole pour of concrete frame trestle;Reinforced concrete slab bottom is with certain thickness Preformed layer, preformed layer top is concrete cast-in-situ layer, in which: folded when concrete frame beam is connect with reinforced concrete slab It closes floor preformed layer and the concrete frame beam parting in 1.5 times of Vierendeel girder high scopes of beam-ends to disengage, parting disengages in range, folds It closes floor preformed layer reinforcing bar and does not stretch out edges of boards, pass through setting laminated floor slab preformed layer and in-situ layer interface additional bar and coagulation Native Vierendeel girder is attached;When concrete frame beam is connect with reinforced concrete slab, laminated floor slab preformed layer and concrete frame The range overlapping other than 1.5 times of deck-moldings of beam-ends of setting a roof beam in place is shelved, and overlapping is shelved in range, and laminated floor slab preformed layer reinforcing bar protrudes into coagulation Native Vierendeel girder is attached.
Preferably, parting slit width 5-10mm takes off filled and process item at seam, shelves depth 10-15mm.
Preferably, truss bars are set in preformed layer, and laminated floor slab preformed layer is cast-in-place by truss bars and laminated floor slab Layer connection.
Preferably, overlapping building is arranged in laminated floor slab in-situ layer and concrete frame beam in concrete frame beam length range Plate in-situ layer reinforcing bar simultaneously whole pours connection;Laminated floor slab in-situ layer reinforcing bar, which protrudes into concrete frame beam length, need to meet anchoring requirement.
Preferably, laminated floor slab preformed layer protrudes into laminated floor slab in-situ layer length with in-situ layer interface additional bar and need to expire Foot anchoring require, protrude into concrete frame beam length need to meet it is attached not less than 5 times of laminated floor slab preformed layers and in-situ layer interface Add bar diameter and the requirement of concrete frame beam center line need to be extended through;Laminated floor slab preformed layer and in-situ layer interface add steel Muscle quantity is identical as respective range preformed layer reinforcing bar.
Preferably, protruding into concrete frame beam length need to meet not less than 5 times of laminated floor slab preformed layer bar diameters and need Extend through the requirement of concrete frame beam center line.
The construction method of the above-mentioned building cover structure being made of cast-in-place concrete Vierendeel girder and reinforced concrete slab, step It is as follows:
(1), laminated floor slab preformed layer is produced, according to laminated floor slab preformed layer in 1.5 times of Vierendeel girder high scopes and cast in place frame Beam side parting disengages and the requirement shelved Chong Die with in-situ frame beam determines planar dimension outside 1.5 times of Vierendeel girder high scopes; Edges of boards are not stretched out according to laminated floor slab reinforcing bar in parting disengagement range and overlapping shelves laminated floor slab reinforcing bar in range and stretches out edges of boards Requirement arrange laminated floor slab preformed layer reinforcing bar;
(2), floor beam-and-slab support system is set up in construction site;
(3), frame column, frame beam steel are bound by design working drawing and relevant design atlas requirement;
(4), lift laminated floor slab preformed layer, be accurately positioned guarantee laminated floor slab preformed layer in 1.5 times of Vierendeel girder high scopes with Frame beam sides parting disengages, while be overlapped need to shelve outside 1.5 times of Vierendeel girder high scopes with Vierendeel girder;
(5), laminated floor slab preformed layer and in-situ layer interface additional bar are set, and protruding into laminated floor slab in-situ layer length needs to meet Anchorage length requirement, protrudes into the requirement that frame beam length need to meet not less than 5 times of bar diameters and extend through Vierendeel girder center line;
(6), laminated floor slab in-situ layer reinforcing bar is bound by design working drawing and relevant design atlas requirement;
(7), closed concrete frame column, concrete frame beam forms;
(8), foam strip is set at laminated floor slab preformed layer and Vierendeel girder parting disengagement, spillage when preventing concreting;
(9), casting concrete completes the building cover structure being made of concrete frame beam and laminated floor slab.
Compared with the existing technology, it the invention has the following beneficial effects: building structure entirety anti-seismic performance is improved, realizes The three level aseismic fortification objects of " small earthquakes are not bad, medium ones can be repaired, and large ones cannot fall ", dissipative member (cut by Vierendeel girder in building structure Power wall coupling beam) it need to be surrendered under geological process prior to frame column, shear wall, that is, it is initially formed plastic hinge.To ensure Vierendeel girder etc. Dissipative member really realizes energy consumption under geological process, and Aseismic Design needs accomplish that " strong column and weak beam, is cut by force the weak component of strong node It is weak curved " three aspects.The board-like building cover structure of conventional cast-in-place beams of concrete, often because superpower effect of the floor to Vierendeel girder can not It is initially formed plastic hinge, that is, cannot achieve the requirement of " strong column and weak beam ".The present invention passes through the certain model in laminated floor slab preformed layer quadrangle The rational structure connecting in enclosing with concrete frame beam effectively weakens superpower effect of the floor to frame beam-ends.So that building Building structure can take the lead in plastic hinge occur in frame beam-ends according to preset path under geological process, reach the general of " strong column and weak beam " Design requirement is read, the whole anti-seismic performance of building structure is greatly improved.
Detailed description of the invention
Fig. 1 is the floor map for the building cover structure being made of cast-in-place concrete Vierendeel girder and reinforced concrete slab;
Fig. 2A is the A-A diagrammatic cross-section for the building cover structure being made of cast-in-place concrete Vierendeel girder and reinforced concrete slab;
Fig. 2 B is the B-B diagrammatic cross-section for the building cover structure being made of cast-in-place concrete Vierendeel girder and reinforced concrete slab;
In figure: 1, concrete frame beam, 2, reinforced concrete slab, 3, concrete frame trestle, 4, laminated floor slab preformed layer, 5, folded Close floor in-situ layer, 6, laminated floor slab preformed layer reinforcing bar, 7, laminated floor slab preformed layer truss bars, 8, laminated floor slab in-situ layer steel Muscle, 9, laminated floor slab preformed layer and in-situ layer interface additional bar, 10, foam strip.
Specific embodiment
Shown in A, Fig. 2 B as shown in Figure 1, Figure 2, the building cover structure being made of cast-in-place concrete Vierendeel girder and reinforced concrete slab, It include: concrete frame beam 1, reinforced concrete slab 2;Concrete frame beam 1 is connect with whole pour of concrete frame trestle 3;Coagulation Native 2 bottom of laminated floor slab is with certain thickness preformed layer 4, and 4 top of preformed layer is concrete cast-in-situ layer 5, is set in preformed layer Truss bars 7 are set, laminated floor slab preformed layer 4 is connect by truss bars 7 with laminated floor slab in-situ layer 5;Wherein:
When concrete frame beam 1 is connect with reinforced concrete slab 2, laminated floor slab preformed layer 4 and concrete frame beam 1 are in beam-ends Parting disengages in 1.5 times of Vierendeel girder high scopes, slit width 5-10mm, filled and process item 10 at parting disengagement;Parting disengages in range, Laminated floor slab preformed layer reinforcing bar 6 does not stretch out edges of boards, by setting laminated floor slab preformed layer and in-situ layer interface additional bar 9 with Concrete frame beam 1 is attached, in which: laminated floor slab preformed layer and in-situ layer interface additional bar 9 protrude into laminated floor slab 5 length of in-situ layer need to meet anchoring and require, and not less than 5 times laminated floor slab preformed layers need to be met by protruding into 1 length of concrete frame beam With 9 diameter of in-situ layer interface additional bar and the requirement of 1 center line of concrete frame beam need to be extended through;Laminated floor slab preformed layer with 9 quantity of in-situ layer interface additional bar is identical as respective range preformed layer reinforcing bar 6.
When concrete frame beam 1 is connect with reinforced concrete slab 2, laminated floor slab preformed layer 4 and concrete frame beam 1 exist Range overlapping is shelved other than 1.5 times of deck-moldings of beam-ends, shelves depth 10-15mm;Overlapping is shelved in range, laminated floor slab preformed layer steel Muscle 6 protrudes into concrete frame beam 1 and is attached, and protruding into 1 length of concrete frame beam, need to meet not less than 5 times laminated floor slabs prefabricated Layer 6 diameter of reinforcing bar and the requirement that 1 center line of concrete frame beam need to be extended through.
When concrete frame beam 1 is connect with reinforced concrete slab 2, laminated floor slab in-situ layer 5 and concrete frame beam 1 exist Setting laminated floor slab in-situ layer reinforcing bar 8 and whole connection is poured in 1 length range of concrete frame beam;Laminated floor slab in-situ layer reinforcing bar 8 Anchoring requirement need to be met by protruding into 1 length of concrete frame beam.
The construction method of the above-mentioned building cover structure being made of cast-in-place concrete Vierendeel girder and reinforced concrete slab, step is such as Under:
(1), produce laminated floor slab preformed layer 4, according to laminated floor slab preformed layer 4 in 1.5 times of Vierendeel girder high scopes with cast-in-place frame 1 side parting of setting a roof beam in place disengages and the requirement shelved Chong Die with in-situ frame beam 1 determines plane meter outside 1.5 times of Vierendeel girder high scopes It is very little;Edges of boards are not stretched out according to laminated floor slab reinforcing bar 6 in parting disengagement range and overlapping is shelved laminated floor slab reinforcing bar 6 in range and stretched out Laminated floor slab preformed layer reinforcing bar 6 is arranged in the requirement of edges of boards;
(2), floor beam-and-slab support system is set up in construction site;
(3), frame column 3,2 reinforcing bar of Vierendeel girder are bound by design working drawing and relevant design atlas requirement;
(4), laminated floor slab preformed layer 4 is lifted, is accurately positioned and guarantees laminated floor slab preformed layer 4 in 1.5 times of Vierendeel girder high scopes It disengages with frame beam sides parting, while be overlapped need to be shelved outside 1.5 times of Vierendeel girder high scopes with Vierendeel girder;
(5), laminated floor slab preformed layer and in-situ layer interface additional bar 9 are set, and protruding into 5 length of laminated floor slab in-situ layer need to expire Sufficient anchorage length requirement, not less than 5 times 9 diameters of reinforcing bar need to be met and extend through wanting for 1 center line of Vierendeel girder by protruding into 1 length of Vierendeel girder It asks;
(6), laminated floor slab in-situ layer reinforcing bar 8 is bound by design working drawing and relevant design atlas requirement;
(7), closed concrete frame column 3,2 template of concrete frame beam;
(8), foam strip 10 is set at laminated floor slab preformed layer 4 and 1 parting disengagement of Vierendeel girder, leakage when preventing concreting Slurry;
(9), casting concrete completes the building cover structure being made of concrete frame beam and laminated floor slab.

Claims (7)

1. a kind of building cover structure being made of cast-in-place concrete Vierendeel girder and reinforced concrete slab, comprising: concrete frame beam, Reinforced concrete slab, concrete frame beam are connect with whole pour of concrete frame trestle;Reinforced concrete slab bottom is with one Determine the preformed layer of thickness, preformed layer top is concrete cast-in-situ layer;It is characterized by: laminated floor slab preformed layer and concrete frame Beam parting in 1.5 times of Vierendeel girder high scopes of beam-ends disengages, and parting disengages in range, and laminated floor slab preformed layer reinforcing bar does not stretch out plate Side is attached with in-situ layer interface additional bar with concrete frame beam by setting laminated floor slab preformed layer;Overlap building Range is Chong Die other than 1.5 times of deck-moldings of beam-ends shelves for plate preformed layer and concrete frame beam, and overlapping is shelved in range, laminated floor slab Preformed layer reinforcing bar protrudes into concrete frame beam and is attached.
2. the building cover structure according to claim 1 being made of cast-in-place concrete Vierendeel girder and reinforced concrete slab, Be characterized in that: parting slit width 5-10mm takes off filled and process item at seam, shelves depth 10-15mm.
3. the building cover structure according to claim 1 to 2 being made of cast-in-place concrete Vierendeel girder and reinforced concrete slab, It is characterized by: truss bars are arranged in preformed layer, laminated floor slab preformed layer is connected by truss bars and laminated floor slab in-situ layer It connects.
4. the building cover structure according to claim 1 to 3 being made of cast-in-place concrete Vierendeel girder and reinforced concrete slab, Show it is characterized by: laminated floor slab is arranged in laminated floor slab in-situ layer and concrete frame beam in concrete frame beam length range It pours layer reinforcing bar and whole pours connection;Laminated floor slab in-situ layer reinforcing bar, which protrudes into concrete frame beam length, need to meet anchoring requirement.
5. the building cover structure being made of described in -4 cast-in-place concrete Vierendeel girder and reinforced concrete slab according to claim 1, It is characterized by: laminated floor slab preformed layer and in-situ layer interface additional bar protrude into laminated floor slab in-situ layer length and need to meet anchor Gu requiring, protruding into concrete frame beam length need to meet not less than 5 times of laminated floor slab preformed layers and the additional steel of in-situ layer interface Muscle diameter and the requirement that concrete frame beam center line need to be extended through;Laminated floor slab preformed layer and in-situ layer interface additional bar number It measures identical as respective range preformed layer reinforcing bar.
6. the building cover structure being made of described in -5 cast-in-place concrete Vierendeel girder and reinforced concrete slab according to claim 1, It is characterized by: laminated floor slab preformed layer reinforcing bar protrudes into concrete frame beam length, need to meet not less than 5 times laminated floor slabs prefabricated Layer bar diameter and the requirement that concrete frame beam center line need to be extended through.
7. the construction for the building cover structure being made of described in claim 1-6 cast-in-place concrete Vierendeel girder and reinforced concrete slab Method, steps are as follows:
(1), laminated floor slab preformed layer is produced, according to laminated floor slab preformed layer in 1.5 times of Vierendeel girder high scopes and cast in place frame Beam side parting disengages and the requirement shelved Chong Die with in-situ frame beam determines planar dimension outside 1.5 times of Vierendeel girder high scopes; Edges of boards are not stretched out according to laminated floor slab reinforcing bar in parting disengagement range and overlapping shelves laminated floor slab reinforcing bar in range and stretches out edges of boards Requirement arrange laminated floor slab preformed layer reinforcing bar;
(2), floor beam-and-slab support system is set up in construction site;
(3), frame column, frame beam steel are bound by design working drawing and relevant design atlas requirement;
(4), lift laminated floor slab preformed layer, be accurately positioned guarantee laminated floor slab preformed layer in 1.5 times of Vierendeel girder high scopes with Frame beam sides parting disengages, while be overlapped need to shelve outside 1.5 times of Vierendeel girder high scopes with Vierendeel girder;
(5), laminated floor slab preformed layer and in-situ layer interface additional bar are set, and protruding into laminated floor slab in-situ layer length needs to meet Anchorage length requirement, protrudes into the requirement that frame beam length need to meet not less than 5 times of bar diameters and extend through Vierendeel girder center line;
(6), laminated floor slab in-situ layer reinforcing bar is bound by design working drawing and relevant design atlas requirement;
(7), closed concrete frame column, concrete frame beam forms;
(8), foam strip is set at laminated floor slab preformed layer and Vierendeel girder parting disengagement, spillage when preventing concreting;
(9), casting concrete completes the building cover structure being made of concrete frame beam and laminated floor slab.
CN201910207370.5A 2019-03-19 2019-03-19 Floor structure composed of cast-in-place concrete frame beam and concrete composite floor slab Active CN110512783B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910207370.5A CN110512783B (en) 2019-03-19 2019-03-19 Floor structure composed of cast-in-place concrete frame beam and concrete composite floor slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910207370.5A CN110512783B (en) 2019-03-19 2019-03-19 Floor structure composed of cast-in-place concrete frame beam and concrete composite floor slab

Publications (2)

Publication Number Publication Date
CN110512783A true CN110512783A (en) 2019-11-29
CN110512783B CN110512783B (en) 2020-09-08

Family

ID=68622463

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910207370.5A Active CN110512783B (en) 2019-03-19 2019-03-19 Floor structure composed of cast-in-place concrete frame beam and concrete composite floor slab

Country Status (1)

Country Link
CN (1) CN110512783B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111058562A (en) * 2019-12-31 2020-04-24 浙江工业大学 Laminated floor slab structure and construction process thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103470040A (en) * 2013-09-16 2013-12-25 南京工业大学 Splicing method of composite floor slab and beam
AU2015200378A1 (en) * 2014-02-26 2015-09-10 Duckshin Housing Co., Ltd Spacer for stripping deck plate, and stripping deck plate using thereof
CN205063133U (en) * 2015-10-14 2016-03-02 山东凝华建筑科技有限公司 Superimposed sheet superstructure system of prestressing force bottom plate based on take truss
CN207194146U (en) * 2017-06-22 2018-04-06 中国建筑股份有限公司 Prestressing force assembly concrete frame joint attachment structure
CN108265822A (en) * 2018-03-26 2018-07-10 华东建筑设计研究院有限公司 A kind of prefabricated board connecting structure
CN208267234U (en) * 2017-10-30 2018-12-21 中国建筑股份有限公司 A kind of prefabricated PC concrete large-span frame system
CN209891421U (en) * 2019-03-19 2020-01-03 上海杰地建筑设计有限公司 Cast-in-place concrete frame beam and concrete coincide floor connection structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103470040A (en) * 2013-09-16 2013-12-25 南京工业大学 Splicing method of composite floor slab and beam
AU2015200378A1 (en) * 2014-02-26 2015-09-10 Duckshin Housing Co., Ltd Spacer for stripping deck plate, and stripping deck plate using thereof
CN205063133U (en) * 2015-10-14 2016-03-02 山东凝华建筑科技有限公司 Superimposed sheet superstructure system of prestressing force bottom plate based on take truss
CN207194146U (en) * 2017-06-22 2018-04-06 中国建筑股份有限公司 Prestressing force assembly concrete frame joint attachment structure
CN208267234U (en) * 2017-10-30 2018-12-21 中国建筑股份有限公司 A kind of prefabricated PC concrete large-span frame system
CN108265822A (en) * 2018-03-26 2018-07-10 华东建筑设计研究院有限公司 A kind of prefabricated board connecting structure
CN209891421U (en) * 2019-03-19 2020-01-03 上海杰地建筑设计有限公司 Cast-in-place concrete frame beam and concrete coincide floor connection structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111058562A (en) * 2019-12-31 2020-04-24 浙江工业大学 Laminated floor slab structure and construction process thereof

Also Published As

Publication number Publication date
CN110512783B (en) 2020-09-08

Similar Documents

Publication Publication Date Title
CN206503230U (en) A kind of fabricated steel building
CN104631659B (en) Prefabricated assembled band steel plate concealed bracings overlaid plate type concrete coupled shear wall
CN206308796U (en) A kind of post insertion prefabricated PC concrete frame frame system
CN207878747U (en) A kind of laminated floor slab prefabricated board
CN112282115A (en) Prefabricated assembled concrete wallboard and connecting structure and construction method thereof
CN104763085B (en) The double T floor frames structures of assembled integral prestressing force and its construction method
CN202925716U (en) Integrally assembled type concrete filled steel tube frame shear wall
CN206016011U (en) A kind of steel plate concrete composite beam panel structure system
CN105064529A (en) Prefabricated and assembled large-board shear wall structure with concealed bracings
CN108179809A (en) The connection method of assembled steel tendon concrete frame structure component
CN106121087B (en) A kind of steel building and its wall construction method, beam column steel member
CN107447901A (en) Anti-seismic prefabricated floor and floor antidetonation splicing construction
CN108005265A (en) A kind of prefabricated steel reinforced concrete shear wall structure of multilayer and its preparation and construction method
CN111424850A (en) Prefabricated reinforced concrete shear wall and construction method
CN207812741U (en) Pre-manufactured steel structure overlapped shear wall
CN108005264A (en) A kind of steel framework constraint precast reinforced concrete shear wall structure and preparation and installation method
CN109469204A (en) Fabricated steel reinforced concrete mixed frame structure based on superposed beams and construction method
CN106760036B (en) A kind of prefabricated steel-combined concrete shear wall
CN112695914B (en) Assembly type shear wall structure system and construction method thereof
CN215630801U (en) Connecting structure of prefabricated assembled concrete wallboard
CN206722216U (en) A kind of prefabricated girder of laminated floor slab
CN105649259B (en) A kind of wallboard structural system of the dark framework of band of precast concrete wall panel and its structure
CN110512783A (en) The building cover structure being made of cast-in-place concrete Vierendeel girder and reinforced concrete slab
CN204804129U (en) Prefabricated concrete floor entirely for building
CN209040348U (en) A kind of assembled double steel plate combined shear wall construction with ribbing

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant