CN110486087A CN201910724557.2A CN201910724557A CN110486087A CN 110486087 A CN110486087 A CN 110486087A CN 201910724557 A CN201910724557 A CN 201910724557A CN 110486087 A CN110486087 A CN 110486087A
Authority
CN
China
Prior art keywords
reservoir
centre drain
centre
drain
setting pot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910724557.2A
Other languages
Chinese (zh)
Inventor
吕理军
贾佳欣
张玉堂
张克阳
周鑫均
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 11 Co Ltd
PowerChina 11th Bureau Engineering Co Ltd
Original Assignee
Sinohydro Bureau 11 Co Ltd
PowerChina 11th Bureau Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 11 Co Ltd, PowerChina 11th Bureau Engineering Co Ltd filed Critical Sinohydro Bureau 11 Co Ltd
Priority to CN201910724557.2A priority Critical patent/CN110486087A/en
Publication of CN110486087A publication Critical patent/CN110486087A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/103Dams, e.g. for ventilation
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/16Modification of mine passages or chambers for storage purposes, especially for liquids or gases

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a kind of firewater systems for vcehicular tunnel.The system comprises reservoir, centre drain high-order portion, centre drain low portion and the protecting walls for surrounding centre drain high-order portion, reservoir, centre drain low portion, divider wall is equipped on the left of reservoir, reservoir is set between centre drain low portion and centre drain high-order portion, and centre drain high-order portion, reservoir, centre drain low portion gradually decrease.It is high that the present invention solves the problems, such as that the firewater system for vcehicular tunnel consumes energy.

Description

A kind of firewater system for vcehicular tunnel
Technical field
The present invention relates to tunnel drainage field of engineering technology, use in particular to a kind of fire-fighting for vcehicular tunnel Water system.
Background technique
Vcehicular tunnel firewater system plays the role of vital for operation phase emergency management and rescue, disappears under fire condition Effective performance of anti-systematic protection ability needs enough fire demand waters.
Currently, vcehicular tunnel firewater system in the prior art includes multiple fire prevention zones, each fire prevention zone is equal Including at least one moisturizing pond, use will be located at the high-order water at Highway Tunnel Portal both ends and barrel service gallery hole both ends Fire demand water in pond is pumped by multistage pressure conveys fire demand water into each moisturizing pond being located in vcehicular tunnel, in case answering First aid is helped to be used under operating condition.
Such as the patent of invention that China Patent Publication No. is CN109316698A discloses a kind of double-hole tunnel two-way subregion Relay moisturizing pipeline dry type water fire fighting system, the system include two tunnels, at least one Lateral Hole and four fire-fighting water storages Pond, each tunnel portal are respectively set a fire-fighting reservoir outside, two-way fire-fighting area are respectively equipped in each tunnel, every road disappears Defence area all includes multiple groups fire prevention zone, and every group of fire prevention zone all includes at least one relay moisturizing pond, multiple fire hydrant boxes, pipeline Groove, moisturizing pipeline, multiple fire-fighting pressure (hydraulic) water pipe-line systems, multiple fire pumps and multiple rapid escape valves, the relay moisturizing Pond scattering device is equipped with fire pump, each relay under the side wall in affiliated fire-fighting area or road surface in each relay moisturizing pond Moisturizing pond corresponds to a fire-fighting pressure (hydraulic) water pipe-line system, and a side of the Tunnel in affiliated fire-fighting area is arranged in multiple fire hydrant boxes On wall;The invention, which has, saves maintenance cost, using electricity wisely, saves the area, the flexible beneficial effect of fire-fighting reservoir setting.
Following problems exist in the prior art in inventor:
Vcehicular tunnel firewater system in the prior art is pumped using multistage pressure to each of multiple fire prevention zones Moisturizing pond convey fire demand water, cause fire demand water is generated in multistage transmission process loss and multistage pressure pump running When electricity consumption it is big, the energy consumption for causing Current Highway tunnel firewater system is high.
Aiming at the problem that vcehicular tunnel firewater system highly energy-consuming in the prior art, effective solution is not yet proposed at present Scheme.
Summary of the invention
The purpose of the present invention is to provide a kind of firewater systems for vcehicular tunnel, to solve to be used for vcehicular tunnel Firewater system consume energy high problem.
The system comprises reservoir, centre drain high-order portion, centre drain low portion and it surround center row Ditch high-order portion, reservoir, centre drain low portion protecting wall, divider wall is equipped on the left of reservoir, reservoir is set Between centre drain low portion and centre drain high-order portion, centre drain high-order portion, reservoir, center row Ditch low portion gradually decreases.
Further, centre drain high-order portion includes that the L-type inlet channel being sequentially communicated, the first setting pot and second are heavy Sand pond, the second setting pot are connected to reservoir, and the first setting pot is greater than the second setting pot.
Further, centre drain low portion includes the exhalant canal being sequentially communicated and third setting pot, and water outlet is logical Road is connected to reservoir.
Further, suction pump is equipped in reservoir.
Further, multiple drain holes are offered on protecting wall, each drain hole passes through a tunnel in multiple drain holes Bottom horizontal drainpipe is connected to centre drain high-order portion.
Compared with the existing technology, system of the present invention has following significant superior effect:
1, the setting of centre drain low portion is higher than by centre drain high-order portion, so that infiltration flows into water storage Chi Zhong, so that making the energy consumption of system entirety reduces.
2, by the setting of setting pot, the impurity in infiltration has been purified, has reduced infiltration fire equipments and natural ring The influence in border.
Detailed description of the invention
Fig. 1 is the floor plan of system of the present invention;
Fig. 2 is the sectional view of the line A-A along Fig. 1;
Fig. 3 is the sectional view of the line B-B along Fig. 1.
It is as shown in the figure:
1- centre drain high-order portion, 11-L type inlet channel, the first setting pot of 12-, the second setting pot of 13-, 2- water storage Pond, 3- divider wall, 4- centre drain low portion, 41- exhalant canal, 42- third setting pot, 5- protecting wall, 6- tunnel bottom are horizontal To drainpipe, 7- drain hole.
Specific embodiment
The present invention is further described in detail with specific embodiment with reference to the accompanying drawings of the specification.
As shown in Figure 1 to Figure 3, the present invention relates to a kind of firewater system for vcehicular tunnel, the system comprises: Reservoir 2, centre drain high-order portion 1, centre drain low portion 4 and circular centre drain high-order portion 1, water storage Pond 2, centre drain low portion 4 protecting wall 5, divider wall 3 is equipped on the left of reservoir 2, reservoir 2 is set to centre drain Between low portion 4 and centre drain high-order portion 1, centre drain high-order portion 1, reservoir 2, centre drain low level Part 4 gradually decreases, so that the infiltration that centre drain high-order portion 1 is collected flows into water storage by centre drain high-order portion 1 In pond 2, the energy consumption of the system is reduced.
Further, as depicted in figs. 1 and 2, centre drain high-order portion 1 include be sequentially communicated L-type inlet channel 11, First setting pot 12 and the second setting pot 13, the second setting pot 13 are connected to reservoir 2, and the first setting pot 12 is greater than the second sand setting Pond 13.
In the present embodiment, the side wall and base plate thickness of the first setting pot 12 and the second setting pot 13 are 20cm, are used Concrete prefabricated, the strength grade of concrete is preferably C30 model, the match ratio of water, cement, sand and stone in C30 concrete Be: 0.38:1:1.11:2.72, the size of the first setting pot 12 are long 2 × wide by 1.5 × depth 1m, and the size of the second setting pot 13 is Long 1.5 × wide by 1.5 × depth 1m, it is spare that infiltration flows into reservoir 2 after the sedimentation of the first setting pot 12 and the second setting pot 13.
Further, as shown in Figure 1, centre drain low portion 4 includes the exhalant canal 41 being sequentially communicated and third Setting pot 42, exhalant canal 41 are connected to reservoir 2.
In the present embodiment, the size of third setting pot 42 is long 1.5 × wide by 1.5 × depth 1m, is arranged for settling from center The impurity in infiltration that ditch low portion 4 is discharged reduces infiltration adverse effect caused by natural environment.
Further, suction pump (not shown) is equipped in reservoir 2, it is required when for extracting emergency management and rescue operating condition Fire demand water.
Further, as shown in Figure 1, offering multiple drain holes 7 on protecting wall 5, each drain hole in multiple drain holes 7 7 are connected to by a tunnel bottom horizontal drainpipe 6 with centre drain high-order portion 1, so that the infiltration of wall-rock crack be made to be discharged into In centre drain high-order portion 1, the safety in tunnel is increased.
The working principle of system of the present invention is as follows:
The infiltration that wall-rock crack is collected by the circumferential flexible porous tube (not shown) being arranged in outside protecting wall 5, encloses The infiltration of lithofraction gap sequentially enters centre drain height by tunnel bottom horizontal drainpipe 6 by the drain hole 7 on protecting wall 5 again After L-type inlet channel 11, the first setting pot 12 and the second setting pot 13 that bit position 1 includes, into reservoir 2, when reservoir 2 After reaching preset reservoir storage, extra infiltration is discharged into the exhalant canal that centre drain low portion 4 includes from reservoir 2 In 41, then be discharged into natural environment after the sedimentation of third setting pot 42, when there is emergency management and rescue operating condition, using suction pump from It extracts required fire demand water in reservoir 2, so the not only reasonable utilization infiltration of wall-rock crack, but also reduces the system Energy consumption.
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field For art personnel, the invention may be variously modified and varied.All within the spirits and principles of the present invention, made any to repair Change, equivalent replacement, improvement etc., should all be included in the scope of protection of the claims of the present invention.

Claims (5)

1. a kind of firewater system for vcehicular tunnel characterized by comprising reservoir (2), centre drain are high-order Partially (1), centre drain low portion (4) and surrounding said central gutter high-order portion (1), the reservoir (2), institute State the protecting wall (5) of centre drain low portion (4);
Divider wall (3) are equipped on the left of the reservoir (2), the reservoir (2) is set to the centre drain low portion (4) It is the centre drain high-order portion (1), the reservoir (2), described between the centre drain high-order portion (1) Centre drain low portion (4) gradually decreases.
2. firewater system according to claim 1, which is characterized in that centre drain high-order portion (1) packet Include the L-type inlet channel (11), the first setting pot (12) and the second setting pot (13) being sequentially communicated;
Second setting pot (13) is connected to the reservoir (2), and first setting pot (12) is greater than second sand setting Pond (13).
3. firewater system according to claim 2, which is characterized in that centre drain low portion (4) packet The exhalant canal (41) and third setting pot (42) being sequentially communicated are included, the exhalant canal (41) is connected to the reservoir (2).
4. firewater system according to claim 3, which is characterized in that be equipped with suction pump in the reservoir (2).
5. firewater system according to claim 4, which is characterized in that offer multiple let out on the protecting wall (5) Water hole (7), each drain hole (7) passes through a tunnel bottom horizontal drainpipe (6) and the center in the multiple drain hole (7) Gutter high-order portion (1) connection.
CN201910724557.2A 2019-08-07 2019-08-07 A kind of firewater system for vcehicular tunnel Pending CN110486087A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910724557.2A CN110486087A (en) 2019-08-07 2019-08-07 A kind of firewater system for vcehicular tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910724557.2A CN110486087A (en) 2019-08-07 2019-08-07 A kind of firewater system for vcehicular tunnel

Publications (1)

Publication Number Publication Date
CN110486087A true CN110486087A (en) 2019-11-22

Family

ID=68549563

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910724557.2A Pending CN110486087A (en) 2019-08-07 2019-08-07 A kind of firewater system for vcehicular tunnel

Country Status (1)

Country Link
CN (1) CN110486087A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112727542A (en) * 2021-01-12 2021-04-30 中国铁路设计集团有限公司 Underground water comprehensive utilization system for tunnel in water-rich area and use method
CN113554840A (en) * 2021-07-14 2021-10-26 中国水利水电第十四工程局有限公司 Tunnel fire monitoring alarm device

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010092623A (en) * 2000-03-23 2001-10-26 유태성 Drainage system for self fire-off of tunnel fire and apparatus thereof
KR20100022181A (en) * 2008-08-19 2010-03-02 서울메트로 The transfer canal of the underground water which flows out
CN204098206U (en) * 2014-09-25 2015-01-14 姚志军 Underground conservation pool in tunnel
CN104563214A (en) * 2014-12-25 2015-04-29 贵州省交通规划勘察设计研究院股份有限公司 Tunnel firefighting system based on elevated water tank
CN104674890A (en) * 2014-12-25 2015-06-03 贵州省交通规划勘察设计研究院股份有限公司 Tunnel fire system with water sources which are slope surface flowing water and road surface water
CN206319910U (en) * 2016-12-19 2017-07-11 中交第一公路勘察设计研究院有限公司 Infiltration disposal system is reinforced in a kind of tunnel-liner
CN108361065A (en) * 2018-05-07 2018-08-03 中铁工程设计咨询集团有限公司 A kind of tunnel inverted arch filling discharge structure
CN207934927U (en) * 2018-03-15 2018-10-02 四川省交通运输厅公路规划勘察设计研究院 Tunnel fire protection system
CN109316698A (en) * 2018-11-13 2019-02-12 梁勇旗 A kind of double-hole tunnel two-way subregion relay moisturizing pipeline dry type water fire fighting system
CN210948792U (en) * 2019-08-07 2020-07-07 中电建十一局工程有限公司 Fire-fighting water system for highway tunnel

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010092623A (en) * 2000-03-23 2001-10-26 유태성 Drainage system for self fire-off of tunnel fire and apparatus thereof
KR20100022181A (en) * 2008-08-19 2010-03-02 서울메트로 The transfer canal of the underground water which flows out
CN204098206U (en) * 2014-09-25 2015-01-14 姚志军 Underground conservation pool in tunnel
CN104563214A (en) * 2014-12-25 2015-04-29 贵州省交通规划勘察设计研究院股份有限公司 Tunnel firefighting system based on elevated water tank
CN104674890A (en) * 2014-12-25 2015-06-03 贵州省交通规划勘察设计研究院股份有限公司 Tunnel fire system with water sources which are slope surface flowing water and road surface water
CN206319910U (en) * 2016-12-19 2017-07-11 中交第一公路勘察设计研究院有限公司 Infiltration disposal system is reinforced in a kind of tunnel-liner
CN207934927U (en) * 2018-03-15 2018-10-02 四川省交通运输厅公路规划勘察设计研究院 Tunnel fire protection system
CN108361065A (en) * 2018-05-07 2018-08-03 中铁工程设计咨询集团有限公司 A kind of tunnel inverted arch filling discharge structure
CN109316698A (en) * 2018-11-13 2019-02-12 梁勇旗 A kind of double-hole tunnel two-way subregion relay moisturizing pipeline dry type water fire fighting system
CN210948792U (en) * 2019-08-07 2020-07-07 中电建十一局工程有限公司 Fire-fighting water system for highway tunnel

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112727542A (en) * 2021-01-12 2021-04-30 中国铁路设计集团有限公司 Underground water comprehensive utilization system for tunnel in water-rich area and use method
CN113554840A (en) * 2021-07-14 2021-10-26 中国水利水电第十四工程局有限公司 Tunnel fire monitoring alarm device

Similar Documents

Publication Publication Date Title
CN105926676B (en) Pipe gallery system with sponge city function
CN110486087A (en) A kind of firewater system for vcehicular tunnel
CN104929684A (en) Underground rain sewage pre-treatment station connected to deep layer tunnel drainage system
CN108757027B (en) Multifunctional drainage system in tunnel
CN210948792U (en) Fire-fighting water system for highway tunnel
CN103741786A (en) Deep foundation pit rainwater storage pond
CN209154960U (en) Fire fighting water system for the construction of super highrise building stage
CN110219315A (en) A kind of base pit dewatering and interim waterworks for firefighting integral construction method
CN107158759A (en) A kind of precipitation pool structure with desludging device
AU2008286149A1 (en) Damming method for permeable red mud dam with red mud from sintering process
CN106246217A (en) Single hole two-way traffic vcehicular tunnel escape and rescue structure
CN215858009U (en) Water supply system using underground water of super-long tunnel as water source of fire pool in tunnel
CN210002355U (en) high dam reservoir emptying system
CN201620914U (en) Imitated heart structure coal mine drainage system
CN101949145A (en) Water supply and drainage system of plunge pool
CN220415451U (en) Pump house structure easy to install and clean
CN205935150U (en) Rain water pipe assembly
CN214913646U (en) Open-air step precipitation filtration's flood control structure
CN204827524U (en) Insert deep tunnel drainage system's ground following formula rain sewage preliminary treatment station
CN220687399U (en) Automatic pressure release drainage system in tunnel
CN209145635U (en) Channel of coal mining working surface far controls pump drainage water system
CN211849017U (en) Down-through channel large-flow inverted siphon sewage pipe
CN211395720U (en) Foundation pit dewatering structure
CN210597534U (en) Canal lower pipe compound rain and sewage diversion system
CN217325405U (en) Greening slope protection system and building block applied to greening slope protection system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination