CN110441116A - A kind of fissure rock test concrete sample three-dimensional built-in crack manufacturing method - Google Patents

A kind of fissure rock test concrete sample three-dimensional built-in crack manufacturing method Download PDF

Info

Publication number
CN110441116A
CN110441116A CN201910870665.0A CN201910870665A CN110441116A CN 110441116 A CN110441116 A CN 110441116A CN 201910870665 A CN201910870665 A CN 201910870665A CN 110441116 A CN110441116 A CN 110441116A
Authority
CN
China
Prior art keywords
concrete
crack
refrigerating box
mold
test specimen
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910870665.0A
Other languages
Chinese (zh)
Inventor
赵瑜
全大国
王超林
毕靖
滕明阳
李佳申
杨进强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou University
Original Assignee
Guizhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou University filed Critical Guizhou University
Priority to CN201910870665.0A priority Critical patent/CN110441116A/en
Publication of CN110441116A publication Critical patent/CN110441116A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N1/00Sampling; Preparing specimens for investigation
    • G01N1/28Preparing specimens for investigation including physical details of (bio-)chemical methods covered elsewhere, e.g. G01N33/50, C12Q
    • G01N1/286Preparing specimens for investigation including physical details of (bio-)chemical methods covered elsewhere, e.g. G01N33/50, C12Q involving mechanical work, e.g. chopping, disintegrating, compacting, homogenising
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N1/00Sampling; Preparing specimens for investigation
    • G01N1/28Preparing specimens for investigation including physical details of (bio-)chemical methods covered elsewhere, e.g. G01N33/50, C12Q
    • G01N1/36Embedding or analogous mounting of samples
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N1/00Sampling; Preparing specimens for investigation
    • G01N1/28Preparing specimens for investigation including physical details of (bio-)chemical methods covered elsewhere, e.g. G01N33/50, C12Q
    • G01N1/42Low-temperature sample treatment, e.g. cryofixation
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N1/00Sampling; Preparing specimens for investigation
    • G01N1/28Preparing specimens for investigation including physical details of (bio-)chemical methods covered elsewhere, e.g. G01N33/50, C12Q
    • G01N1/36Embedding or analogous mounting of samples
    • G01N2001/366Moulds; Demoulding

Landscapes

  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Biochemistry (AREA)
  • General Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Immunology (AREA)
  • Pathology (AREA)
  • Sampling And Sample Adjustment (AREA)

Abstract

The invention discloses a kind of fissure rock test concrete sample three-dimensional built-in crack manufacturing methods, comprising the following steps: gets out material and tool needed for test;Corresponding hole is made on the two sides of mold according to the data parameters in designed reserved crack;The mold and thickness partial size sandstone, water and cement are put into cooling down in refrigerating box;Mixing concrete;Mold is taken out, concrete is added, hierarchical block is carried out to concrete and is vibrated;The hole of mold two sides is passed through using filament and ice cube is fixed on mould inside;Concrete sample is immediately placed in initial set in refrigerating box after the concrete vibrating on ice cube upper layer is closely knit;Preliminary test specimen is taken out from refrigerating box after concrete final set, and is statically placed in Interior Temperature Environment;Preliminary test specimen after standing is carried out demoulding and is immediately placed in standard curing room to conserve.The utility model has the advantages that can farthest test simulation rock, people is helped more in depth to understand the failure mechanism of rock.

Description

A kind of fissure rock test concrete sample three-dimensional built-in crack manufacturing method
Technical field
The present invention relates to the studying technological domains to crack propagation law in rock, it particularly relates to a kind of crack rock Stone test concrete sample three-dimensional built-in crack manufacturing method.
Background technique
Rock mass refers under the conditions of certain geology, contains such as crack, joint, stratification, the discontinuous structural plane group of tomography At live rock, it is a complicated geologic body.The overwhelming majority of the earth's crust is all made of rock, and old friend's class lives in ground On ball, many activities for producing, living all are closely bound up with rock.Such as exploit underground resources, build reservoir and Dig tunnel and canal etc..However, with the development of production and the needs of life, the exploitation of subterranean resource is transferred to by superficial part Deep rock stratum, the building on rock is also more and more taller and bigger, such as various types of high dams, powerhouse of hydropower station, nuclear power station.Cause Occur more and more rock engineering problems in the production of people.
For example, 2 days December nineteen fifty-nine, French Ma Erpasai thin arch dam cause entire arch dam to be ruined due to dam foundation unstability, Flood rolls downwards suddenly, causes heavy losses to downstream;On October 9th, 1963, Italian tile according to high reservoir rock slope due to Limestone stratification remitted its fury and movement of coming down on a large scale occurs, a large amount of rock pours in reservoir, and moment causes up to count Hundred meters of billow causes the cities and towns in downstream by destructive destruction;There are also the Austrian power stations Ge Erlisi, make Cause lining cutting to rupture due to the surrounding rock failure of water delivery pressure tunnel with period, high pressure water pours Power Plant, make unit by Very big loss, forces halt production to handle.These examples all show that the lesson caused due to the rock failure mechanism of rock is very painful, so For numerous rockwork persons, study of rocks failure law is necessary.
Rock belongs to fragile material, therefore that brittleness can be shown under bearing load and certain condition is broken for most of solid rock Bad property, that is to say, that there is no fairly obvious deformations just to destroy suddenly under load action for these rocks.And it generates This destruction may be caused by crack of the type of load, the structure of material and inside etc., and wherein rock interior crack is in lotus The lower extension of load effect is to lead to the most important reason of the rock failure mechanism of rock.Therefore, study of rocks internal crack propagation law is very must It wants.
However most of research workers remain in the propagation law research in two-dimentional crack, though it achieves quite abundant Research achievement, but the propagation law in test specimen two dimension crack is used and is obviously less applicable in rock three-dimensional fracture, or even meeting Generate completely different result.Also a few peoples carry out the research in three-dimensional built-in crack, but what is used is all analogous to brittleness The transparent materials such as resin, although can be with the expansion process in crack visible in detail, its mechanical property and true rock gap It is larger, mainly due in terms of following two: firstly, most of transparent materials are all plastic materials, still having at low temperature Plastic behavior, particularly with the region that crack point stresses are concentrated, the influence of plastic deformation is all very important.But rock is Brittle, when destruction, is broken suddenly, therefore there is a certain error with the true rock of these material simulations.Secondly, true Rock is heterogeneous material, all shown on the showing and propagate of various physical and mechanical effects complicated noncontinuity, Heterogeneity, anisotropy, therefore its influence of internal crack to mechanical characteristic is especially big, and homogeneous material has ignored this Point is inaccurate to the inside reflection of practical rock.
Instantly, one important of ground worker is had become to the research of rock three-dimensional built-in crack propagation mechanism Business, can not only let us better understand the failure mode of rock, moreover it is possible to shift to an earlier date us to various geotechnical engineering accidents Make the precautionary measures.Because rock is brittleness, heterogeneous, internal the defects of there are countless holes, crack, joints, so It is difficult to summarize crack propagation rule and its influence to material mechanical performance using true rock.In addition true rock also can not be pre- Set certain size, position, direction, quantity buried crack, therefore can not study built-in crack extension Evolution, at present use The test of true rock material is also limited to study external crack situation mostly.And concrete structure is also as rock, be brittleness, It is heterogeneous, it is primary raw material by selecting cement, standard sand, through certain technological means machine-shaping after mixing, after molding Concrete sample main physico-mechanical parameter (such as elasticity modulus, Poisson's ratio, compression strength, tensile strength, bulk density) with True rock is close, and carrying out test can show and stress deformation feature as rock type.And the concrete material prepared Workability it is preferable, make molding convenient for test specimen and be also easier in the embedded three-dimensional fracture in inside and demoulding, thus by Three-dimensional fracture is manufactured in concrete sample to carry out crack propagation law study.
For the problems in the relevant technologies, currently no effective solution has been proposed.
Summary of the invention
For the problems in the relevant technologies, the present invention proposes that a kind of fissure rock test is split with concrete sample three-dimensional built-in Gap manufacturing method can be tested effective for simulation rock, preferably explain the Mechanics Phenomenon of labyrinth and its sheet in rock Structure relationship, to overcome above-mentioned technical problem present in existing the relevant technologies.
For this purpose, the specific technical solution that the present invention uses is as follows:
A kind of fissure rock test concrete sample three-dimensional built-in crack manufacturing method, comprising the following steps:
Be prepared in advance test needed for concrete mold, ice cube, thickness partial size sandstone, water, cement, concrete admixture, Release agent, filament, film, refrigerating box and standard curing room;
Corresponding hole is made on the two sides of the concrete mold according to the data parameters in pre-designed reserved crack Hole;
The concrete mold and the thickness partial size sandstone, the water and the cement are put into the refrigerating box and are cooled down Cooling is spare;
The thickness partial size sandstone after cooling, the water are taken out from the refrigerating box with the cement and mixed by ratio of mud example Concrete processed, and additional proportion is the concrete admixture of 6-9% in mixing;
The concrete mold is taken out while ready-mixed concrete, and the demoulding is uniformly smeared inside the concrete mold Agent is added the good concrete of mixing, and carries out hierarchical block to concrete and vibrate;
The described hole of the concrete mold two sides is passed through using the filament and the ice cube is fixed on the coagulation Native mould inside forms concrete sample;
The concrete sample is immediately placed in initial set in the refrigerating box after the concrete vibrating on ice cube upper layer is closely knit, and is adopted The concrete surface is covered with film, forms preliminary test specimen;
Test specimen preliminary in the refrigerating box is taken out after concrete final set, and the preliminary test specimen is placed on Indoor Temperature It spends and stands number in environment;
The preliminary test specimen after standing is carried out demoulding and be immediately placed in the standard curing room to conserve, can be obtained Concrete sample with crack.
Further, the data parameters include location parameter, angle parameter, dimensional parameters, the number in the reserved crack Mesh parameter and spacing parameter.
Further, the concrete admixture is accelerator.
Further, the crack is made of ice cube.
Further, it is put by the concrete mold and the thickness partial size sandstone, the water and the cement In the refrigerating box in cooling down standby step:
Temperature in the refrigerating box is 6-10 DEG C, and cooling time is more than or equal to 30 minutes.
Further, the concrete mold is immediately placed in after the concrete vibrating on ice cube upper layer is closely knit it is described cold Initial set in case is hidden, and is covered in the concrete mold surface step using film:
Temperature in the refrigerating box is 6-10 DEG C.
Further, test specimen preliminary in the refrigerating box is being taken out after concrete final set, and will be described preliminary Test specimen is placed in Interior Temperature Environment and stands in numbering step:
Being placed on time of repose in Interior Temperature Environment is 12-18 hours.
Further, the preliminary test specimen after standing is carried out demoulding and is immediately placed in the standard curing room to carry out In curing step:
Curing time is 21-28 days.
The invention has the benefit that the present invention using it is hard, facilitate it is prefabricated and with regular shape ice cube, be put into Inside concrete, and melt during concrete curing, melt moisture evaporation or flowed out from hole, thus in coagulation The native internal crack for leaving regular shape.And the position of hole on mold two sides can also be designed, hole is passed through with filament Ice cube is fixed, and adjusts position, the angle, spacing, quantity in crack with this, the concrete sample with such crack has had band The property of fissure rock can be tested farthest simulation rock, people is helped more in depth to understand the failure mechanism of rock.
Detailed description of the invention
It in order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the invention Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings Obtain other attached drawings.
Fig. 1 is a kind of fissure rock test concrete sample three-dimensional built-in crack manufacturer according to an embodiment of the present invention The flow chart of method.
Fig. 2 is Single Fracture test specimen schematic diagram.
Fig. 3 is Single Fracture manufacturing method schematic diagram.
Fig. 4 is parallel double cracks test specimen schematic diagram.
Fig. 5 is coplanar double crack test specimen schematic diagrames.
Fig. 6 is the manufacturing method schematic diagram of coplanar double crack test specimens.
Fig. 7 is double cracks test specimen schematic diagram that misplaces.
Fig. 8 is three crack test specimen schematic diagrames.
In figure: 1, crack;2, ice cube;3, filament;4, hole and bolt;5, concrete mold.
Specific embodiment
To further illustrate that each embodiment, the present invention are provided with attached drawing, these attached drawings are that the invention discloses one of content Point, mainly to illustrate embodiment, and the associated description of specification can be cooperated to explain the operation principles of embodiment, cooperation ginseng Examine these contents, those of ordinary skill in the art will be understood that other possible embodiments and advantages of the present invention, in figure Component be not necessarily to scale, and similar component symbol is conventionally used to indicate similar component.
It is manufactured according to an embodiment of the invention, providing a kind of fissure rock test with concrete sample three-dimensional built-in crack Method.
Now in conjunction with the drawings and specific embodiments, the present invention is further described, as shown in Figure 1, according to embodiments of the present invention Fissure rock test use concrete sample three-dimensional built-in crack manufacturing method, comprising the following steps:
Step S101, be prepared in advance concrete mold, ice cube, thickness partial size sandstone, water, cement, coagulation needed for test Native additive, release agent, filament, film, refrigerating box and standard curing room;
Step S102 makes on the two sides of the concrete mold according to the data parameters in pre-designed reserved crack Corresponding hole;
Specifically, above-mentioned data parameters include the location parameter, angle parameter, dimensional parameters, number of parameters in the reserved crack And spacing parameter.
The concrete mold and the thickness partial size sandstone, the water and the cement are put into institute by step S103 It is spare to state cooling down in refrigerating box;
Specifically, the temperature in above-mentioned refrigerating box is 6-10 DEG C, cooling time is more than or equal to 30 minutes, to make to stir coagulation The heat of hydration generated when native minimizes.
Step S104 takes the thickness partial size sandstone after cooling, the water with the cement from the refrigerating box Ratio of mud example mixing concrete is pressed out, and additional proportion is the concrete admixture of 6-9% in mixing;
Specifically, above-mentioned concrete admixture be accelerator, thus make concrete vibrate complete after rapidly condensation hardening (on Stating accelerator includes that alkali-free liquid setting accelerator and liquid have alkali accelerator, is glue when above-mentioned accelerator is alkali-free liquid setting accelerator The 6-9% of gel material, when above-mentioned accelerator is when liquid has alkali accelerator be cementitious material 3-5%);Above-mentioned ratio of mud example is 0.4。
Step S105 takes out the concrete mold while ready-mixed concrete, inside the concrete mold It is even to smear the release agent, the good concrete of mixing is added, and hierarchical block is carried out to concrete and is vibrated;
Step S106 passes through the described hole of the concrete mold two sides using the filament and is fixed on the ice cube Inside the concrete mold, concrete sample is formed;
The concrete sample is immediately placed in the refrigerating box by step S107 after the concrete vibrating on ice cube upper layer is closely knit Initial set, and the concrete surface is covered using film, form preliminary test specimen;
Specifically, the temperature in above-mentioned refrigerating box is 6-10 DEG C.
Step S108, by test specimen preliminary in refrigerating box taking-up after the concrete final set, and by the preliminary examination Part, which is placed in Interior Temperature Environment, stands number;
Specifically, being placed on time of repose in Interior Temperature Environment is 12-18 hours.
Step S109 carries out demoulding and is immediately placed in the standard curing room to carry out to the preliminary test specimen after standing Maintenance, can be obtained the concrete sample with crack.
Specifically, above-mentioned crack is made of ice cube, curing time is 21-28 days.
Above-mentioned technical proposal of the invention is understood in order to clearer, below by way of specific example to above-mentioned side of the invention Case is described in detail.
Embodiment one: the manufacture of Single Fracture test specimen
As shown in Fig. 2, test specimen is length and width, thickness is 50mm × 50mm × 50mm square respectively, crack is Single Fracture test specimen The cube of sheet, length and width, thickness are 10mm × 10mm × 3mm respectively, and positioned at test specimen center, the angle of crack and horizontal plane is 45 degree.
The manufacturing process in crack is as shown in Figure 3, the specific steps are as follows: gets out concrete mold needed for test in advance 5, ice cube 2, filament 3, thickness partial size sandstone 800g, water 125g(do not include the water in liquid accelerator), cement 350g, concrete 60%) and dry substance (release agent and film) and tool (refrigerating box and mark if water content is in accelerator 20g(liquid accelerator Quasi- fog room).Angle according to the reserved crack of design and horizontal plane is 45 degree, in the top corner angle of mold two sides and lower part Corresponding hole and matched bolt 4 are made on corner angle, while to minimize the heat of hydration generated when ready-mixed concrete, first Mold, thickness partial size sandstone, water, cement are put into togerther in refrigerating box and are cooled to 6 DEG C -10 DEG C at least 30 minutes or more, by water 0.4 mixing concrete of gray scale, and accelerator is added in mixing, it is therefore an objective to making concrete, condensation is hard rapidly after completion of vibrating Change, and take out mold while ready-mixed concrete, smears release agent in mould inside, the good concrete of mixing is added, by rule Model requires to vibrate to concrete progress hierarchical block, while ice cube is fixed on mold with the hole that filament passes through mold two sides Inside, to prevent mould inside ice melting too fast, be immediately placed in after ice cube upper layer concrete vibrating is closely knit temperature be 6 DEG C- It is pre-hardening in 10 DEG C of refrigerating box, surface is covered with fluid-tight film, keeps the humidity of concrete, after concrete final set Test specimen is taken out, stands 12-18 hours in temperature environment indoors, is immediately placed in standard curing room and conserves after demoulding label 21-28 days, the concrete sample with crack can be obtained.Since temperature in the process increases so that inside concrete is ice melting, Thawing water is absorbed or evaporated and flow out in the hole of concrete sample by concrete, to split in inside concrete formation Gap.
Embodiment two: the manufacture of parallel double cracks test specimen
Parallel double crack test specimens are as shown in figure 4, two sheet cube cracks are located at the center of test specimen, spacing 10mm.It is all The angle of crack and horizontal plane is all 30 degree.
Crack manufacture specific step is as follows: be ready in advance test needed for concrete mold 5, ice cube 2, filament 3, Thickness partial size sandstone 800g, water 125g(do not include the water in liquid accelerator), cement 350g, concrete accelerator 20g(liquid 60%) and dry substance (release agent and film) and tool (refrigerating box and standard curing room) if water content is in accelerator.According to Designed reserved crack will be 30 degree with the angle of horizontal plane, and corresponding hole and matched spiral shell are made on mold two sides Bolt 4, the heat of hydration generated when to make ready-mixed concrete minimize, and first mold, thickness partial size sandstone, water, cement are put together Enter to be cooled to 6 DEG C -10 DEG C in refrigerating box at least 30 minutes or more, by 0.4 mixing concrete of the ratio of mud, and speed is added in mixing Solidifying agent, it is therefore an objective to make concrete condensation hardening rapidly after completion of vibrating, and take out mold, In while ready-mixed concrete Mould inside smears release agent, and the good concrete of mixing is added, and carries out layering to concrete by code requirement and vibrates, is worn with filament The ice cube of first layer is fixed on mould inside by the hole crossed on mold two sides, and concrete is then added to second layer ice cube position Place and vibration compacting, then the ice cube of the fixed second layer are set, to prevent mould inside ice melting too fast, after vibration compacting immediately It is put into initial set in the refrigerating box that temperature is 6 DEG C -10 DEG C, surface is covered with fluid-tight film, keeps the humidity of concrete, wait until Test specimen is taken out after concrete final set, stands 12-18 hours in temperature environment indoors, is immediately placed in standard after demoulding label It is conserved 21-28 days in fog room, the concrete sample with crack can be obtained.
Embodiment three: the manufacture of coplanar double crack test specimens
Coplanar double crack test specimens are as shown in figure 5, two sheet cube cracks are located at the center two sides of test specimen.All cracks and water The angle of plane is all 30 degree, and in the same plane.
The manufacturing process in crack is as shown in Figure 6, the specific steps are as follows: gets out concrete mold needed for test in advance 5, ice cube 2, filament 3, thickness partial size sandstone 800g, water 125g(do not include the water in liquid accelerator), cement 350g, concrete If in accelerator 20g(liquid accelerator water content be 60%) and dry substance (release agent and film) and tool (refrigerating box and Standard curing room).To be 30 degree with the angle of horizontal plane according to designed reserved crack, be made on mold two sides corresponding Hole and matched bolt 4, the heat of hydration generated when to make ready-mixed concrete minimizes, first mold, thickness partial size sand Stone, water, cement, which are put into togerther in refrigerating box, is cooled to 6 DEG C -10 DEG C at least 30 minutes or more, by 0.4 mixing concrete of the ratio of mud, And accelerator is added in mixing, it is therefore an objective to make concrete condensation hardening rapidly after completion of vibrating, and in ready-mixed concrete While take out mold, smear release agent in mould inside, the good concrete of mixing be added, layering is carried out to concrete and is vibrated, The hole on mold two sides being passed through with filament, the ice cube of first layer being fixed on mould inside, concrete is then added to second Simultaneously vibration compacting, then the ice cube of the fixed second layer, close wait vibrate to prevent mould inside ice melting too fast at layer ice cube position It is immediately placed in initial set in the refrigerating box that temperature is 6 DEG C -10 DEG C after reality, covers surface with fluid-tight film, keeps concrete Test specimen is taken out after concrete final set, stands 12-18 hours in temperature environment indoors by humidity, is stood after demoulding label It is put into standard curing room and conserves 21-28 days, the concrete sample with crack can be obtained.
Example IV: the manufacture for double cracks test specimen that misplaces
Double crack test specimens misplace as shown in fig. 7, two sheet cube cracks are located at the center two sides of test specimen, splitting sharp spacing is 10mm splits point by center, and the angle of two cracks and horizontal plane is all 45 degree, but not in the same plane.
The manufacturing process in crack is identical as the manufacturing process in coplanar double cracks described in embodiment three, and only ice cube is placed Position and angle difference.
The manufacture of five: three crack test specimen of embodiment
Three crack test specimens are as shown in figure 8, three sheet cube cracks are located at the center of test specimen, spacing 10mm, all cracks Angle with horizontal plane is all identical 30 degree.
The manufacturing process in its crack is identical as the manufacturing process in parallel double cracks described in embodiment two, and three cracks are under And Shangdi successively manufactures by the same way.
In conclusion by means of above-mentioned technical proposal of the invention, the present invention using it is hard, facilitate prefabricated and there are rule The then ice cube of shape is put into inside concrete, and melts during concrete curing, melts moisture evaporation or from hole Middle outflow, to leave the crack of regular shape in inside concrete.And the position of hole on mold two sides can also be designed It sets, passes through hole with filament and fix ice cube, and adjust position, the angle, spacing, quantity in crack with this, with such crack Concrete sample has had the property with fissure rock, can farthest test simulation rock, help people more in depth Understand the failure mechanism of rock.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (8)

1. a kind of fissure rock test concrete sample three-dimensional built-in crack manufacturing method, which is characterized in that including following step It is rapid:
Be prepared in advance test needed for concrete mold, ice cube, thickness partial size sandstone, water, cement, concrete admixture, Release agent, filament, film, refrigerating box and standard curing room;
Corresponding hole is made on the two sides of the concrete mold according to the data parameters in pre-designed reserved crack Hole;
The concrete mold and the thickness partial size sandstone, the water and the cement are put into the refrigerating box and are cooled down Cooling is spare;
The thickness partial size sandstone after cooling, the water are taken out from the refrigerating box with the cement and mixed by ratio of mud example Concrete processed, and additional proportion is the concrete admixture of 6-9% in mixing;
The concrete mold is taken out while ready-mixed concrete, and the demoulding is uniformly smeared inside the concrete mold Agent is added the good concrete of mixing, and carries out hierarchical block to concrete and vibrate;
The described hole of the concrete mold two sides is passed through using the filament and the ice cube is fixed on the coagulation Native mould inside forms concrete sample;
The concrete sample is immediately placed in initial set in the refrigerating box after the concrete vibrating on ice cube upper layer is closely knit, and is adopted The concrete surface is covered with film, forms preliminary test specimen;
Test specimen preliminary in the refrigerating box is taken out after concrete final set, and the preliminary test specimen is placed on Indoor Temperature It spends and stands number in environment;
The preliminary test specimen after standing is carried out demoulding and be immediately placed in the standard curing room to conserve, can be obtained Concrete sample with crack.
2. fissure rock test concrete sample three-dimensional built-in crack manufacturing method according to claim 1, feature It is, the data parameters include location parameter, angle parameter, dimensional parameters, number of parameters and the spacing in the reserved crack Parameter.
3. fissure rock test concrete sample three-dimensional built-in crack manufacturing method according to claim 1, feature It is, the concrete admixture is accelerator.
4. fissure rock test concrete sample three-dimensional built-in crack manufacturing method according to claim 1, feature It is, the crack is made of ice cube.
5. fissure rock test concrete sample three-dimensional built-in crack manufacturing method according to claim 1, feature It is, is put into the refrigerating box by the concrete mold and the thickness partial size sandstone, the water and the cement In cooling down standby step:
Temperature in refrigerating box is 6-10 DEG C, and cooling time is more than or equal to 30 minutes.
6. fissure rock test concrete sample three-dimensional built-in crack manufacturing method according to claim 1, feature It is, it is pre-hardening the concrete mold is immediately placed in the refrigerating box after the concrete vibrating on ice cube upper layer is closely knit, And it is covered in the concrete mold surface step using film:
Temperature in refrigerating box is 6-10 DEG C.
7. fissure rock test concrete sample three-dimensional built-in crack manufacturing method according to claim 1, feature It is, is taking out test specimen preliminary in the refrigerating box after concrete final set, and the preliminary test specimen is placed on room It is stood in numbering step in interior temperature environment:
Being placed on time of repose in Interior Temperature Environment is 12-18 hours.
8. fissure rock test concrete sample three-dimensional built-in crack manufacturing method according to claim 1, feature It is, the preliminary test specimen after standing is carried out demoulding and be immediately placed in the standard curing room to carry out in curing step:
Curing time is 21-28 days.
CN201910870665.0A 2019-09-16 2019-09-16 A kind of fissure rock test concrete sample three-dimensional built-in crack manufacturing method Pending CN110441116A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910870665.0A CN110441116A (en) 2019-09-16 2019-09-16 A kind of fissure rock test concrete sample three-dimensional built-in crack manufacturing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910870665.0A CN110441116A (en) 2019-09-16 2019-09-16 A kind of fissure rock test concrete sample three-dimensional built-in crack manufacturing method

Publications (1)

Publication Number Publication Date
CN110441116A true CN110441116A (en) 2019-11-12

Family

ID=68440241

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910870665.0A Pending CN110441116A (en) 2019-09-16 2019-09-16 A kind of fissure rock test concrete sample three-dimensional built-in crack manufacturing method

Country Status (1)

Country Link
CN (1) CN110441116A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110967237A (en) * 2019-12-24 2020-04-07 贵州大学 Concrete test piece with three-dimensional built-in cracks and manufacturing method thereof
CN111089772A (en) * 2020-02-05 2020-05-01 山东科技大学 Method for preparing rock test piece containing non-filling type internal defects
CN112146960A (en) * 2020-10-14 2020-12-29 中国矿业大学(北京) Method for manufacturing cement mortar test piece with built-in open crack
CN113295484A (en) * 2021-04-21 2021-08-24 重庆交通大学 Method for manufacturing concrete test piece for simulating water-containing cavity defect
CN115901389A (en) * 2022-03-07 2023-04-04 北京市市政工程研究院 Method for forming cracks in concrete

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101462854A (en) * 2009-01-12 2009-06-24 山东大学 Brittle material for manufacturing rocks and preparation of specimen prefabricated crack thereof
CN102519767A (en) * 2011-12-16 2012-06-27 武汉大学 Mould for manufacturing fissure surface of rock like test block
CN102866043A (en) * 2012-09-07 2013-01-09 中国石油天然气集团公司 Manufacturing method for fracture-cave rock core physical model
CN104833555A (en) * 2015-03-09 2015-08-12 绍兴文理学院 Producing method of intermittent-filling fracture rock sample model
CN105277406A (en) * 2015-11-03 2016-01-27 中国建筑股份有限公司 Mold for producing cracked rock test piece of different dip angles and production method thereof
CN105784456A (en) * 2016-03-04 2016-07-20 中国石油大学(华东) Mold for manufacturing random cross-through fractured rock matrix
CN107226650A (en) * 2017-05-16 2017-10-03 中国矿业大学 One kind experiment similar rock of hole rock mass and preparation method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101462854A (en) * 2009-01-12 2009-06-24 山东大学 Brittle material for manufacturing rocks and preparation of specimen prefabricated crack thereof
CN102519767A (en) * 2011-12-16 2012-06-27 武汉大学 Mould for manufacturing fissure surface of rock like test block
CN102866043A (en) * 2012-09-07 2013-01-09 中国石油天然气集团公司 Manufacturing method for fracture-cave rock core physical model
CN104833555A (en) * 2015-03-09 2015-08-12 绍兴文理学院 Producing method of intermittent-filling fracture rock sample model
CN105277406A (en) * 2015-11-03 2016-01-27 中国建筑股份有限公司 Mold for producing cracked rock test piece of different dip angles and production method thereof
CN105784456A (en) * 2016-03-04 2016-07-20 中国石油大学(华东) Mold for manufacturing random cross-through fractured rock matrix
CN107226650A (en) * 2017-05-16 2017-10-03 中国矿业大学 One kind experiment similar rock of hole rock mass and preparation method thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110967237A (en) * 2019-12-24 2020-04-07 贵州大学 Concrete test piece with three-dimensional built-in cracks and manufacturing method thereof
CN111089772A (en) * 2020-02-05 2020-05-01 山东科技大学 Method for preparing rock test piece containing non-filling type internal defects
CN112146960A (en) * 2020-10-14 2020-12-29 中国矿业大学(北京) Method for manufacturing cement mortar test piece with built-in open crack
CN113295484A (en) * 2021-04-21 2021-08-24 重庆交通大学 Method for manufacturing concrete test piece for simulating water-containing cavity defect
CN113295484B (en) * 2021-04-21 2024-01-26 重庆交通大学 Method for manufacturing concrete test piece for simulating water-containing cavity defect
CN115901389A (en) * 2022-03-07 2023-04-04 北京市市政工程研究院 Method for forming cracks in concrete
CN115901389B (en) * 2022-03-07 2023-09-15 北京市市政工程研究院 Method for forming cracks in concrete

Similar Documents

Publication Publication Date Title
CN110441116A (en) A kind of fissure rock test concrete sample three-dimensional built-in crack manufacturing method
Zheng et al. A review on durability of nano-SiO2 and basalt fiber modified recycled aggregate concrete
Xiao et al. Damage to recycled concrete with different aggregate substitution rates from the coupled action of freeze-thaw cycles and sulfate attack
Wang et al. Experimental study on the shear behavior of the bonding interface between sandstone and cement mortar under freeze–thaw
Wu et al. The stability and durability of silt-based foamed concrete: A new type of road engineering material
CN102289980A (en) Method for preparing preset cracks in hydrofracture simulation specimen
CN107271235B (en) Preparation method of rock and mortar combined sample based on rock-mortar interface gas permeation test
Liu et al. Experimental Research on Foamed Mixture Lightweight Soil Mixed with Fly‐Ash and Quicklime as Backfill Material behind Abutments of Expressway Bridge
CN115893938B (en) Limestone similar material with seepage-chemical-vibration coupling characteristic and preparation method thereof
CN105347752A (en) High-strength concrete
Shang et al. Properties of sustainable cellular concrete prepared with environment-friendly capsule aggregates
Cui et al. Exploratory study on improving bond strength of shotcrete in hot and dry environments of high geothermal tunnels
Zhao et al. Experimental and numerical studies of brittle rock-like samples with internal open fractures and cavities under uniaxial compression
CN111470840B (en) Stone cultural relic surface crack repairing material and preparation method thereof
Wu et al. Physical and mechanical properties of coral aggregates in the South China Sea
Jin et al. Research on rock-filled concrete dams: a review
Chen et al. Experimental investigation on triaxial mechanical properties of coral coarse aggregate-sea sand seawater concrete
Tan et al. Mechanical properties and damage characteristics of solidified body-coal combination in continuous driving and gangue backfilling
Wang et al. Concrete 3D printing technology in sustainable construction: A review on raw materials, concrete types and performances
Zhang et al. Experimental Strength of Earth‐Based Construction Materials in Different Regions of China
CN110987557B (en) Method for manufacturing rock-like body built-in open type fracture sample based on polyhydroxyalkanoate
Zhao et al. Crack propagation and material characteristics of rocklike specimens subject to different loading rates
Chen et al. Application of MgO concrete in China Dongfeng arch dam foundation
Li et al. Bearing capacity of stabilized soil with expansive component confined by polyvinyl chloride pipe
Cui et al. Slurry and technology optimization for grouting fissures in Earthen Sites with quicklime

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191112