CN110424394A - A kind of mobile surely stake platform and its construction technology - Google Patents
A kind of mobile surely stake platform and its construction technology Download PDFInfo
- Publication number
- CN110424394A CN110424394A CN201910532167.5A CN201910532167A CN110424394A CN 110424394 A CN110424394 A CN 110424394A CN 201910532167 A CN201910532167 A CN 201910532167A CN 110424394 A CN110424394 A CN 110424394A
- Authority
- CN
- China
- Prior art keywords
- steady stake
- stake platform
- pile
- platform
- steady
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D13/00—Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
- E02D13/04—Guide devices; Guide frames
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The invention discloses a kind of mobile steady stake platforms, the steady stake platform is in concave shape, steady stake platform includes auxiliary pile and support rod, auxiliary pile shares four, four auxiliary piles are vertically arranged on sea bed, and four auxiliary piles are distributed on rectangular four angles, and several support rods are provided between four auxiliary piles, are additionally provided with correction cylinder on support rod.The invention has the advantages that saving the time, shortening the construction period: using the steady stake platform of movable type in the present invention, a working day is lacked in construction of the construction compared to leg platform of each position;Remarkable in economical benefits: the crane ship arrived used in the process of the steady stake platform construction of movable type in the present invention is low relative to the cheap rent of supporting leg ship used in leg platform, in addition short time limit, further reduced the use cost of mobile steady stake platform;Degree control effect is good: carrying out construction verticality of the wind power foundation major diameter without changeover portion flange single pile using this mobile steady stake platform and controls within 3 ‰.
Description
Technical field
The present invention relates to offshore wind farm fields, and in particular to a kind of mobile surely stake platform and its construction technology.
Background technique
China possesses the coastal waters wind energy resources of very abundant, and Oversea wind power generation development prospect is wide.China coastline is about
For 18000km, coastal area is the load center of China's electricity consumption, and offshore wind farm has sufficient wind energy resources and the advantage of scale,
Have preferable access conditions, is suitble to the marine wind electric field of construction effective use wind energy.But the construction of current offshore wind farm exists
A series of risk: specific investment cost is at high cost, and the basis of marine wind electric field, the access costs such as power grid and installation are all much higher than
Land project;Constructional difficulties are big, and requirement of the operation on the sea to construction equipment is very high;To the requirement of offshore wind turbine q&r
It is high.According to the prospect of the Oversea wind power generation in current China and the whole world, the construction of marine wind electric field can effectively reduce cost,
There must be specialized offshore construction equipment.
My company investigates the design scheme and arrangement and method for construction of domestic and international offshore wind farm.From Preliminary design to construction drawing design rank
Section is constantly optimizing scheme, and foundation pattern originally is from five pile leader of pile leader frame-tri- frame of high-rise pile cap-- single pile base
Plinth-is significantly reduced costs without transition single-pile foundation, the optimization of each step in the case where ensuring safe and reliable, but
Difficulty of construction constantly increases.No transition single-pile foundation requires highest to pile sinking verticality, it is necessary to it controls within 3 ‰, when
When European countries offshore wind farm single-pile foundation all using there is a transition single-pile foundation, the effect of transition is mainly to foundation pile
Perpendicularity deviation in pile sinking is more than 3 ‰, is adjusted correction, it is ensured that the levelness of flange meets technical requirements, external
Sinking apparatus be all made of jack up leg platform ship and carry out steady stake, pile sinking, the degree control emphasis of pile sinking is in steady stake work
Skill.And only leg platform " China's electricity 1001 " hoist tonnage (700 tons) domestic at that time cannot fully meet requirement, and hand
It is continuous incomplete.In the case where supporting leg ship is limited, we must study other schemes to solve the problems, such as steady stake pile sinking.
Summary of the invention
In order to solve the above technical problems, the present invention provides a kind of mobile steady stake platform and its construction technologies.
The technical solution adopted by the present invention is that:
A kind of mobile steady stake platform, the steady stake platform is in concave shape, and the steady stake platform includes auxiliary pile and support rod, institute
It states auxiliary pile and shares four, four auxiliary piles are vertically arranged on sea bed, and four auxiliary piles are distributed in rectangle
Four angles on, several support rods are provided between four auxiliary piles, are additionally provided with correction cylinder on the support rod.
Further, the steady stake platform shares three layers, and the support rod includes internal layer support rod, outer layer support rod, tiltedly
Support rod and straightening support bar, the internal layer support rod are connected by inclined support bar with straightening support bar with outer layer support rod,
It is connected between the support rod by column.
Further, the support rod is surrounded on outside the auxiliary pile, and the auxiliary pile passes through reinforcement steel plate and support rod
It is connected.
Further, two right angles of the internal layer support rod are respectively arranged with positioning diagonal brace.
Further, the upper layer and lower layer of the steady stake platform are respectively set there are five correcting cylinder, on every layer of steady stake platform
Five correction cylinders it is fan-shaped be uniformly distributed on internal layer support rod, ten it is described correction cylinders cylinder axis be directed to
Among steady stake platform.
Further, lattice support plate is additionally provided between several support rods.
A kind of construction technology of mobile steady stake platform, which is characterized in that specific step is as follows:
A, steady stake platform is set up: several support bar groups being dressed up steady stake platform semi-finished product first and are arrived by lightering Ship Transportation
Construction site is arranged level governor in the quadrangle of steady stake platform semi-finished product, is then hung steady stake platform semi-finished product using 4 points
Mode lift by crane, crane ship side board is against after lifting, and tied steady stake platform semi-finished product with crane ship with wirerope, then led to
The method for crossing GPS positioning adjusts accommodation, is overlapped the Longkou center of steady stake platform semi-finished product with design engineering pile center,
Steady stake platform semi-finished product are placed on sea bed face, the positioning of steady stake platform is completed, then crane ship by four auxiliary piles according to
Cornerwise principle is successively sling and is inserted on sea bed, lifts by crane vibration hammer after the completion of pitching pile, vibration hammer slowly clamps auxiliary pile slightly
It is micro- pull up after again insertable into, be then turned on when relatively stable vibration hammer carry out pile pulling pitching pile until no drilling depth;
B, it the promotion and fixation of steady stake platform: measures the elevation location of steady stake platform and marks, then mentioned with crane ship
Steady stake platform semi-finished product are risen to marked locations, are finally welded auxiliary pile and the welding of steady stake platform semi-finished product using reinforcement steel plate
It is fixed together;
C, the construction of engineering pile and verticality adjustment: being risen engineering pile using crane ship and lift up into the Longkou among steady stake platform, under
Stake is then adjusted the verticality of engineering pile by correcting cylinder, and adjustment, which is finished, carries out steady stake and pile sinking, work for engineering pile
Auxiliary pile and steady stake platform semi-finished product are successively removed after journey pile driving construction.
Further, the method for the GPS positioning in step a, specific steps are as follows: steady stake platform semi-finished product lifting
Before, crane ship, in design engineering pile near center location, lifts by crane two after steady stake platform semi-finished product according to boat-carrying GPS coarse positioning
GPS rover station is fixed on corresponding ship side position, and the straight line that two GPS rover station centers are constituted is parallel with ship side outer, marks
Vertical and horizontal score line then commands crane ship to adjust accommodation, so that the center of steady stake platform semi-finished product and design engineering
The center of stake is overlapped, and tightens anchor hawser, steady stake platform semi-finished product are placed into sea bed face.
The beneficial effects of the present invention are: 1, save the time, shorten the construction period: using the steady stake platform of movable type in the present invention,
A working day is lacked in construction of the construction of each position compared to leg platform;2, remarkable in economical benefits: the movement in the present invention
The crane ship arrived used in the process of the steady stake platform construction of formula is low relative to the cheap rent of supporting leg ship used in leg platform, then
In addition short time limit further reduced the use cost of mobile steady stake platform;3, degree control effect is good: using this movement
The steady stake platform of formula carries out construction verticality of the wind power foundation major diameter without changeover portion flange single pile and controls within 3 ‰.
Detailed description of the invention
Fig. 1 is the structural diagram of the present invention.
Wherein: 1, auxiliary pile, 2, support rod, 3, correction cylinder, 4, engineering pile, 21, internal layer support rod, 22, outer layer support
Bar, 23, inclined support bar, 24, straightening support bar, 25, lattice support plate, 26, positioning diagonal brace, 27, column, 28, reinforcement steel plate.
Specific embodiment
In order to deepen the understanding of the present invention, the present invention will be described in further detail with reference to the examples below, the embodiment
For explaining only the invention, it does not restrict the protection scope of the present invention.
As shown in Figure 1, a kind of mobile steady stake platform, steady stake platform are in concave shape, steady stake platform includes auxiliary pile 1 and branch
Strut 2, auxiliary pile 1 share four, and four auxiliary piles 1 are vertically arranged on sea bed, and four auxiliary piles 1 be distributed in it is rectangular
On four angles, it is provided with several support rods 2 between four auxiliary piles 1, correction cylinder 3 is additionally provided on support rod 2, steady stake is flat
Platform shares three layers, and support rod 2 includes internal layer support rod 21, outer layer support rod 22, inclined support bar 23 and straightening support bar 24, internal layer
Support rod 21 is connected by inclined support bar 23 with straightening support bar 24 with outer layer support rod 22, passes through column between support rod 21
27 are connected, and support rod 2 is surrounded on outside auxiliary pile 1, and auxiliary pile 1 is connected by reinforcement steel plate 28 with support rod 2, internal layer support
Two right angles of bar 21 be respectively arranged with positioning diagonal brace 26, the upper layer and lower layer of steady stake platform be respectively set there are five correct cylinder
3, five correction cylinders 3 on every layer of steady stake platform are fan-shaped to be uniformly distributed on internal layer support rod 21, ten correction cylinders 3
Cylinder axis is directed among steady stake platform, is additionally provided with lattice support plate 25 between several support rods 2.
A kind of construction technology of above-mentioned mobile steady stake platform, the specific steps are as follows:
A, steady stake platform is set up: several support bar groups being dressed up steady stake platform semi-finished product first and are arrived by lightering Ship Transportation
Construction site is arranged level governor in the quadrangle of steady stake platform semi-finished product, is then hung steady stake platform semi-finished product using 4 points
Mode lift by crane, crane ship side board is against after lifting, and tied steady stake platform semi-finished product with crane ship with wirerope, then led to
The method for crossing GPS positioning adjusts accommodation, is overlapped the Longkou center of steady stake platform semi-finished product with design 4 center of engineering pile,
Steady stake platform semi-finished product are placed on sea bed face, the positioning of steady stake platform is completed, then crane ship by four auxiliary piles according to
Cornerwise principle is successively sling and is inserted on sea bed, lifts by crane vibration hammer after the completion of pitching pile, vibration hammer slowly clamps auxiliary pile slightly
It is micro- pull up after again insertable into being then turned on vibration hammer when relatively stable and carry out pile pulling pitching pile until the GPS in no drilling depth, this step is fixed
The method of position, specific steps are as follows: crane ship is being designed according to boat-carrying GPS coarse positioning before steady stake platform semi-finished product lifting
4 near center location of engineering pile lifts by crane and two GPS rover stations is fixed on corresponding ship side position after steady stake platform semi-finished product,
The straight line that two GPS rover station centers are constituted is parallel with ship side outer, marks vertical and horizontal score line, then commands lifting
Ship adjusts accommodation, so that the center of steady stake platform semi-finished product is overlapped with the center of design engineering pile 4, tightens anchor hawser, will be steady
Stake platform semi-finished product are placed into sea bed face;
B, it the promotion and fixation of steady stake platform: measures the elevation location of steady stake platform and marks, then mentioned with crane ship
Steady stake platform semi-finished product are risen to marked locations, are finally welded auxiliary pile and the welding of steady stake platform semi-finished product using reinforcement steel plate
It is fixed together;
C, engineering pile 4: being acted the Longkou lifted up among steady stake platform using crane ship by the construction of engineering pile 4 and verticality adjustment,
Lower stake is then adjusted the verticality of engineering pile 4 by correcting cylinder, and adjustment, which is finished, to be carried out steady stake for engineering pile 4 and sink
Stake, engineering pile 4 successively remove auxiliary pile and steady stake platform semi-finished product after constructing.
The present invention compared to leg platform, there are it is following the utility model has the advantages that 1, save the time, shorten the construction period: using the present invention
In the steady stake platform of movable type, construction of the construction compared to leg platform of each position lack a working day;2, economic benefit
Significant: the crane ship arrived used in the process of the steady stake platform construction of movable type in the present invention is relative to supporting leg used in leg platform
The cheap rent of ship is low, in addition short time limit, further reduced the use cost of mobile steady stake platform;3, verticality control
Effect processed is good: it is equal to carry out construction verticality of the wind power foundation major diameter without changeover portion flange single pile using this mobile steady stake platform
Control is within 3 ‰.
Claims (8)
1. a kind of mobile steady stake platform, which is characterized in that the steady stake platform is in concave shape, and the steady stake platform includes auxiliary
Stake and support rod, the auxiliary pile share four, and four auxiliary piles are vertically arranged on sea bed, and four auxiliary piles
It is distributed on rectangular four angles, several support rods is provided between four auxiliary piles, are also set on the support rod
It is equipped with correction cylinder.
2. a kind of mobile steady stake platform according to claim 1, which is characterized in that the steady stake platform shares three layers,
The support rod includes internal layer support rod, outer layer support rod, inclined support bar and straightening support bar, the internal layer support rod and outer layer
Support rod is connected by inclined support bar with straightening support bar, is connected between the support rod by column.
3. a kind of mobile steady stake platform according to claim 2, which is characterized in that the support rod is surrounded on described auxiliary
It helps outside stake, the auxiliary pile is connected by reinforcement steel plate with support rod.
4. a kind of mobile steady stake platform according to claim 2, which is characterized in that two of the internal layer support rod are straight
Positioning diagonal brace is respectively arranged at angle.
5. a kind of mobile steady stake platform according to claim 4, which is characterized in that the upper layer and lower layer of the steady stake platform
It is respectively set there are five cylinder is corrected, five correction cylinders on every layer of steady stake platform are fan-shaped to be uniformly distributed in internal layer branch
On strut, the cylinder axis of ten correction cylinders is directed among steady stake platform.
6. a kind of mobile steady stake platform according to claim 4, which is characterized in that between several support rods also
It is provided with lattice support plate.
7. a kind of construction technology of mobile steady stake platform, which is characterized in that specific step is as follows:
A, steady stake platform is set up: several support bar groups being dressed up steady stake platform semi-finished product first and are arrived by lightering Ship Transportation
Construction site is arranged level governor in the quadrangle of steady stake platform semi-finished product, is then hung steady stake platform semi-finished product using 4 points
Mode lift by crane, crane ship side board is against after lifting, and tied steady stake platform semi-finished product with crane ship with wirerope, then led to
The method for crossing GPS positioning adjusts accommodation, is overlapped the Longkou center of steady stake platform semi-finished product with design engineering pile center,
Steady stake platform semi-finished product are placed on sea bed face, the positioning of steady stake platform is completed, then crane ship by four auxiliary piles according to
Cornerwise principle is successively sling and is inserted on sea bed, lifts by crane vibration hammer after the completion of pitching pile, vibration hammer slowly clamps auxiliary pile slightly
It is micro- pull up after again insertable into, be then turned on when relatively stable vibration hammer carry out pile pulling pitching pile until no drilling depth;
B, it the promotion and fixation of steady stake platform: measures the elevation location of steady stake platform and marks, then mentioned with crane ship
Steady stake platform semi-finished product are risen to marked locations, are finally welded auxiliary pile and the welding of steady stake platform semi-finished product using reinforcement steel plate
It is fixed together;
C, the construction of engineering pile and verticality adjustment: being risen engineering pile using crane ship and lift up into the Longkou among steady stake platform, under
Stake is then adjusted the verticality of engineering pile by correcting cylinder, and adjustment, which is finished, carries out steady stake and pile sinking, work for engineering pile
Auxiliary pile and steady stake platform semi-finished product are successively removed after journey pile driving construction.
8. a kind of construction technology of mobile steady stake platform according to claim 7, which is characterized in that the GPS in step a
The method of positioning, specific steps are as follows: crane ship is being set according to boat-carrying GPS coarse positioning before steady stake platform semi-finished product lifting
Engineering pile near center location is counted, lifts by crane and two GPS rover stations is fixed on corresponding ship side position after steady stake platform semi-finished product,
The straight line that two GPS rover station centers are constituted is parallel with ship side outer, marks vertical and horizontal score line, then commands lifting
Ship adjusts accommodation, so that the center of steady stake platform semi-finished product is overlapped with the center of design engineering pile, anchor hawser is tightened, by steady stake
Platform semi-finished product are placed into sea bed face.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910532167.5A CN110424394A (en) | 2019-06-19 | 2019-06-19 | A kind of mobile surely stake platform and its construction technology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910532167.5A CN110424394A (en) | 2019-06-19 | 2019-06-19 | A kind of mobile surely stake platform and its construction technology |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110424394A true CN110424394A (en) | 2019-11-08 |
Family
ID=68408719
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910532167.5A Pending CN110424394A (en) | 2019-06-19 | 2019-06-19 | A kind of mobile surely stake platform and its construction technology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110424394A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113106973A (en) * | 2021-03-04 | 2021-07-13 | 中国铁建港航局集团有限公司 | Construction method of single pile |
CN113957892A (en) * | 2021-11-26 | 2022-01-21 | 中天科技集团海洋工程有限公司 | Pile sinking construction system and process for semi-submersible crane ship |
CN116713629A (en) * | 2023-08-09 | 2023-09-08 | 广州文船重工有限公司 | Assembling method for large pin wheel and supporting rod of portal crane |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105507325A (en) * | 2015-12-31 | 2016-04-20 | 中交第三航务工程局有限公司宁波分公司 | Pile stabilizing and positioning platform |
CN107100193A (en) * | 2017-06-24 | 2017-08-29 | 浙江华东工程咨询有限公司 | A kind of construction technology for blower fan cushion cap |
-
2019
- 2019-06-19 CN CN201910532167.5A patent/CN110424394A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105507325A (en) * | 2015-12-31 | 2016-04-20 | 中交第三航务工程局有限公司宁波分公司 | Pile stabilizing and positioning platform |
CN107100193A (en) * | 2017-06-24 | 2017-08-29 | 浙江华东工程咨询有限公司 | A kind of construction technology for blower fan cushion cap |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113106973A (en) * | 2021-03-04 | 2021-07-13 | 中国铁建港航局集团有限公司 | Construction method of single pile |
CN113957892A (en) * | 2021-11-26 | 2022-01-21 | 中天科技集团海洋工程有限公司 | Pile sinking construction system and process for semi-submersible crane ship |
CN116713629A (en) * | 2023-08-09 | 2023-09-08 | 广州文船重工有限公司 | Assembling method for large pin wheel and supporting rod of portal crane |
CN116713629B (en) * | 2023-08-09 | 2023-10-03 | 广州文船重工有限公司 | Assembling method for large pin wheel and supporting rod of portal crane |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110424394A (en) | A kind of mobile surely stake platform and its construction technology | |
CN102369134B (en) | Installation method and recovery method for offshore wind turbine | |
CN102328732A (en) | Offshore pile driving, pile pressing and installing united engineering ship | |
CN202557745U (en) | Multifunctional wind power engineering catamaran for offshore high-altitude heavy-load hoisting and installation operation | |
CN102514690B (en) | Multifunctional twin-hull wind power engineering ship for offshore high-altitude heavy-duty lifting installation operation | |
CN102653938A (en) | Offshore dismantling construction method of descending form traveler | |
CN218506092U (en) | C-shaped assembly type floating transportation structure for split floating transportation of offshore substation | |
CN216275237U (en) | Offshore large-volume pier finish rolling thread hanging bottom combined platform | |
CN102720386A (en) | Inversing method of inner side clustering hoop of vertical storage tank | |
CN108216506B (en) | Floating drilling platform and construction method | |
CN203238646U (en) | Casing box with built-in bottom board | |
CN102587377B (en) | Drop hammer type pile sinking device and pile sinking method thereof | |
CN111980049A (en) | Foundation device of deep riverbed mast type wharf crane and construction method | |
CN216615834U (en) | Marine wind-power single-pile foundation construction special-purpose ship | |
CN103726505B (en) | Offshore wind plant wind turbine foundation | |
CN202416191U (en) | Descending-type movable mould frame offshore dismounting main beam lifting device | |
CN210140844U (en) | Construction system for pile sinking of vertical pile with hammer for offshore wind power steel pipe pile | |
CN109577323B (en) | Tubular pile reinforcing method | |
CN105133632A (en) | Offshore wind turbine foundation structure and construction method thereof | |
CN105804111A (en) | Unequal-length-leg offshore wind power jacket foundation and construction method thereof | |
CN201817199U (en) | Automatic leveling device for semisubmersible barge crane platform | |
CN213740969U (en) | Movable offshore wind power operation and maintenance support platform | |
CN110820596A (en) | Temporary limiting device for linear adjustment of PC track beam and using method | |
CN217053447U (en) | Beam-slab type four-column combined foundation for power transmission line | |
CN215715169U (en) | Lay down platform and have its marine current conversion station |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191108 |
|
RJ01 | Rejection of invention patent application after publication |