CN110424394A - A kind of mobile surely stake platform and its construction technology - Google Patents

A kind of mobile surely stake platform and its construction technology Download PDF

Info

Publication number
CN110424394A
CN110424394A CN201910532167.5A CN201910532167A CN110424394A CN 110424394 A CN110424394 A CN 110424394A CN 201910532167 A CN201910532167 A CN 201910532167A CN 110424394 A CN110424394 A CN 110424394A
Authority
CN
China
Prior art keywords
steady stake
stake platform
pile
platform
steady
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910532167.5A
Other languages
Chinese (zh)
Inventor
徐成根
蔡慧军
江海涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Guangdong Rudong Offshore Wind Power Co Ltd
Original Assignee
China Guangdong Rudong Offshore Wind Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Guangdong Rudong Offshore Wind Power Co Ltd filed Critical China Guangdong Rudong Offshore Wind Power Co Ltd
Priority to CN201910532167.5A priority Critical patent/CN110424394A/en
Publication of CN110424394A publication Critical patent/CN110424394A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/04Guide devices; Guide frames

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses a kind of mobile steady stake platforms, the steady stake platform is in concave shape, steady stake platform includes auxiliary pile and support rod, auxiliary pile shares four, four auxiliary piles are vertically arranged on sea bed, and four auxiliary piles are distributed on rectangular four angles, and several support rods are provided between four auxiliary piles, are additionally provided with correction cylinder on support rod.The invention has the advantages that saving the time, shortening the construction period: using the steady stake platform of movable type in the present invention, a working day is lacked in construction of the construction compared to leg platform of each position;Remarkable in economical benefits: the crane ship arrived used in the process of the steady stake platform construction of movable type in the present invention is low relative to the cheap rent of supporting leg ship used in leg platform, in addition short time limit, further reduced the use cost of mobile steady stake platform;Degree control effect is good: carrying out construction verticality of the wind power foundation major diameter without changeover portion flange single pile using this mobile steady stake platform and controls within 3 ‰.

Description

A kind of mobile surely stake platform and its construction technology
Technical field
The present invention relates to offshore wind farm fields, and in particular to a kind of mobile surely stake platform and its construction technology.
Background technique
China possesses the coastal waters wind energy resources of very abundant, and Oversea wind power generation development prospect is wide.China coastline is about For 18000km, coastal area is the load center of China's electricity consumption, and offshore wind farm has sufficient wind energy resources and the advantage of scale, Have preferable access conditions, is suitble to the marine wind electric field of construction effective use wind energy.But the construction of current offshore wind farm exists A series of risk: specific investment cost is at high cost, and the basis of marine wind electric field, the access costs such as power grid and installation are all much higher than Land project;Constructional difficulties are big, and requirement of the operation on the sea to construction equipment is very high;To the requirement of offshore wind turbine q&r It is high.According to the prospect of the Oversea wind power generation in current China and the whole world, the construction of marine wind electric field can effectively reduce cost, There must be specialized offshore construction equipment.
My company investigates the design scheme and arrangement and method for construction of domestic and international offshore wind farm.From Preliminary design to construction drawing design rank Section is constantly optimizing scheme, and foundation pattern originally is from five pile leader of pile leader frame-tri- frame of high-rise pile cap-- single pile base Plinth-is significantly reduced costs without transition single-pile foundation, the optimization of each step in the case where ensuring safe and reliable, but Difficulty of construction constantly increases.No transition single-pile foundation requires highest to pile sinking verticality, it is necessary to it controls within 3 ‰, when When European countries offshore wind farm single-pile foundation all using there is a transition single-pile foundation, the effect of transition is mainly to foundation pile Perpendicularity deviation in pile sinking is more than 3 ‰, is adjusted correction, it is ensured that the levelness of flange meets technical requirements, external Sinking apparatus be all made of jack up leg platform ship and carry out steady stake, pile sinking, the degree control emphasis of pile sinking is in steady stake work Skill.And only leg platform " China's electricity 1001 " hoist tonnage (700 tons) domestic at that time cannot fully meet requirement, and hand It is continuous incomplete.In the case where supporting leg ship is limited, we must study other schemes to solve the problems, such as steady stake pile sinking.
Summary of the invention
In order to solve the above technical problems, the present invention provides a kind of mobile steady stake platform and its construction technologies.
The technical solution adopted by the present invention is that:
A kind of mobile steady stake platform, the steady stake platform is in concave shape, and the steady stake platform includes auxiliary pile and support rod, institute It states auxiliary pile and shares four, four auxiliary piles are vertically arranged on sea bed, and four auxiliary piles are distributed in rectangle Four angles on, several support rods are provided between four auxiliary piles, are additionally provided with correction cylinder on the support rod.
Further, the steady stake platform shares three layers, and the support rod includes internal layer support rod, outer layer support rod, tiltedly Support rod and straightening support bar, the internal layer support rod are connected by inclined support bar with straightening support bar with outer layer support rod, It is connected between the support rod by column.
Further, the support rod is surrounded on outside the auxiliary pile, and the auxiliary pile passes through reinforcement steel plate and support rod It is connected.
Further, two right angles of the internal layer support rod are respectively arranged with positioning diagonal brace.
Further, the upper layer and lower layer of the steady stake platform are respectively set there are five correcting cylinder, on every layer of steady stake platform Five correction cylinders it is fan-shaped be uniformly distributed on internal layer support rod, ten it is described correction cylinders cylinder axis be directed to Among steady stake platform.
Further, lattice support plate is additionally provided between several support rods.
A kind of construction technology of mobile steady stake platform, which is characterized in that specific step is as follows:
A, steady stake platform is set up: several support bar groups being dressed up steady stake platform semi-finished product first and are arrived by lightering Ship Transportation Construction site is arranged level governor in the quadrangle of steady stake platform semi-finished product, is then hung steady stake platform semi-finished product using 4 points Mode lift by crane, crane ship side board is against after lifting, and tied steady stake platform semi-finished product with crane ship with wirerope, then led to The method for crossing GPS positioning adjusts accommodation, is overlapped the Longkou center of steady stake platform semi-finished product with design engineering pile center, Steady stake platform semi-finished product are placed on sea bed face, the positioning of steady stake platform is completed, then crane ship by four auxiliary piles according to Cornerwise principle is successively sling and is inserted on sea bed, lifts by crane vibration hammer after the completion of pitching pile, vibration hammer slowly clamps auxiliary pile slightly It is micro- pull up after again insertable into, be then turned on when relatively stable vibration hammer carry out pile pulling pitching pile until no drilling depth;
B, it the promotion and fixation of steady stake platform: measures the elevation location of steady stake platform and marks, then mentioned with crane ship Steady stake platform semi-finished product are risen to marked locations, are finally welded auxiliary pile and the welding of steady stake platform semi-finished product using reinforcement steel plate It is fixed together;
C, the construction of engineering pile and verticality adjustment: being risen engineering pile using crane ship and lift up into the Longkou among steady stake platform, under Stake is then adjusted the verticality of engineering pile by correcting cylinder, and adjustment, which is finished, carries out steady stake and pile sinking, work for engineering pile Auxiliary pile and steady stake platform semi-finished product are successively removed after journey pile driving construction.
Further, the method for the GPS positioning in step a, specific steps are as follows: steady stake platform semi-finished product lifting Before, crane ship, in design engineering pile near center location, lifts by crane two after steady stake platform semi-finished product according to boat-carrying GPS coarse positioning GPS rover station is fixed on corresponding ship side position, and the straight line that two GPS rover station centers are constituted is parallel with ship side outer, marks Vertical and horizontal score line then commands crane ship to adjust accommodation, so that the center of steady stake platform semi-finished product and design engineering The center of stake is overlapped, and tightens anchor hawser, steady stake platform semi-finished product are placed into sea bed face.
The beneficial effects of the present invention are: 1, save the time, shorten the construction period: using the steady stake platform of movable type in the present invention, A working day is lacked in construction of the construction of each position compared to leg platform;2, remarkable in economical benefits: the movement in the present invention The crane ship arrived used in the process of the steady stake platform construction of formula is low relative to the cheap rent of supporting leg ship used in leg platform, then In addition short time limit further reduced the use cost of mobile steady stake platform;3, degree control effect is good: using this movement The steady stake platform of formula carries out construction verticality of the wind power foundation major diameter without changeover portion flange single pile and controls within 3 ‰.
Detailed description of the invention
Fig. 1 is the structural diagram of the present invention.
Wherein: 1, auxiliary pile, 2, support rod, 3, correction cylinder, 4, engineering pile, 21, internal layer support rod, 22, outer layer support Bar, 23, inclined support bar, 24, straightening support bar, 25, lattice support plate, 26, positioning diagonal brace, 27, column, 28, reinforcement steel plate.
Specific embodiment
In order to deepen the understanding of the present invention, the present invention will be described in further detail with reference to the examples below, the embodiment For explaining only the invention, it does not restrict the protection scope of the present invention.
As shown in Figure 1, a kind of mobile steady stake platform, steady stake platform are in concave shape, steady stake platform includes auxiliary pile 1 and branch Strut 2, auxiliary pile 1 share four, and four auxiliary piles 1 are vertically arranged on sea bed, and four auxiliary piles 1 be distributed in it is rectangular On four angles, it is provided with several support rods 2 between four auxiliary piles 1, correction cylinder 3 is additionally provided on support rod 2, steady stake is flat Platform shares three layers, and support rod 2 includes internal layer support rod 21, outer layer support rod 22, inclined support bar 23 and straightening support bar 24, internal layer Support rod 21 is connected by inclined support bar 23 with straightening support bar 24 with outer layer support rod 22, passes through column between support rod 21 27 are connected, and support rod 2 is surrounded on outside auxiliary pile 1, and auxiliary pile 1 is connected by reinforcement steel plate 28 with support rod 2, internal layer support Two right angles of bar 21 be respectively arranged with positioning diagonal brace 26, the upper layer and lower layer of steady stake platform be respectively set there are five correct cylinder 3, five correction cylinders 3 on every layer of steady stake platform are fan-shaped to be uniformly distributed on internal layer support rod 21, ten correction cylinders 3 Cylinder axis is directed among steady stake platform, is additionally provided with lattice support plate 25 between several support rods 2.
A kind of construction technology of above-mentioned mobile steady stake platform, the specific steps are as follows:
A, steady stake platform is set up: several support bar groups being dressed up steady stake platform semi-finished product first and are arrived by lightering Ship Transportation Construction site is arranged level governor in the quadrangle of steady stake platform semi-finished product, is then hung steady stake platform semi-finished product using 4 points Mode lift by crane, crane ship side board is against after lifting, and tied steady stake platform semi-finished product with crane ship with wirerope, then led to The method for crossing GPS positioning adjusts accommodation, is overlapped the Longkou center of steady stake platform semi-finished product with design 4 center of engineering pile, Steady stake platform semi-finished product are placed on sea bed face, the positioning of steady stake platform is completed, then crane ship by four auxiliary piles according to Cornerwise principle is successively sling and is inserted on sea bed, lifts by crane vibration hammer after the completion of pitching pile, vibration hammer slowly clamps auxiliary pile slightly It is micro- pull up after again insertable into being then turned on vibration hammer when relatively stable and carry out pile pulling pitching pile until the GPS in no drilling depth, this step is fixed The method of position, specific steps are as follows: crane ship is being designed according to boat-carrying GPS coarse positioning before steady stake platform semi-finished product lifting 4 near center location of engineering pile lifts by crane and two GPS rover stations is fixed on corresponding ship side position after steady stake platform semi-finished product, The straight line that two GPS rover station centers are constituted is parallel with ship side outer, marks vertical and horizontal score line, then commands lifting Ship adjusts accommodation, so that the center of steady stake platform semi-finished product is overlapped with the center of design engineering pile 4, tightens anchor hawser, will be steady Stake platform semi-finished product are placed into sea bed face;
B, it the promotion and fixation of steady stake platform: measures the elevation location of steady stake platform and marks, then mentioned with crane ship Steady stake platform semi-finished product are risen to marked locations, are finally welded auxiliary pile and the welding of steady stake platform semi-finished product using reinforcement steel plate It is fixed together;
C, engineering pile 4: being acted the Longkou lifted up among steady stake platform using crane ship by the construction of engineering pile 4 and verticality adjustment, Lower stake is then adjusted the verticality of engineering pile 4 by correcting cylinder, and adjustment, which is finished, to be carried out steady stake for engineering pile 4 and sink Stake, engineering pile 4 successively remove auxiliary pile and steady stake platform semi-finished product after constructing.
The present invention compared to leg platform, there are it is following the utility model has the advantages that 1, save the time, shorten the construction period: using the present invention In the steady stake platform of movable type, construction of the construction compared to leg platform of each position lack a working day;2, economic benefit Significant: the crane ship arrived used in the process of the steady stake platform construction of movable type in the present invention is relative to supporting leg used in leg platform The cheap rent of ship is low, in addition short time limit, further reduced the use cost of mobile steady stake platform;3, verticality control Effect processed is good: it is equal to carry out construction verticality of the wind power foundation major diameter without changeover portion flange single pile using this mobile steady stake platform Control is within 3 ‰.

Claims (8)

1. a kind of mobile steady stake platform, which is characterized in that the steady stake platform is in concave shape, and the steady stake platform includes auxiliary Stake and support rod, the auxiliary pile share four, and four auxiliary piles are vertically arranged on sea bed, and four auxiliary piles It is distributed on rectangular four angles, several support rods is provided between four auxiliary piles, are also set on the support rod It is equipped with correction cylinder.
2. a kind of mobile steady stake platform according to claim 1, which is characterized in that the steady stake platform shares three layers, The support rod includes internal layer support rod, outer layer support rod, inclined support bar and straightening support bar, the internal layer support rod and outer layer Support rod is connected by inclined support bar with straightening support bar, is connected between the support rod by column.
3. a kind of mobile steady stake platform according to claim 2, which is characterized in that the support rod is surrounded on described auxiliary It helps outside stake, the auxiliary pile is connected by reinforcement steel plate with support rod.
4. a kind of mobile steady stake platform according to claim 2, which is characterized in that two of the internal layer support rod are straight Positioning diagonal brace is respectively arranged at angle.
5. a kind of mobile steady stake platform according to claim 4, which is characterized in that the upper layer and lower layer of the steady stake platform It is respectively set there are five cylinder is corrected, five correction cylinders on every layer of steady stake platform are fan-shaped to be uniformly distributed in internal layer branch On strut, the cylinder axis of ten correction cylinders is directed among steady stake platform.
6. a kind of mobile steady stake platform according to claim 4, which is characterized in that between several support rods also It is provided with lattice support plate.
7. a kind of construction technology of mobile steady stake platform, which is characterized in that specific step is as follows:
A, steady stake platform is set up: several support bar groups being dressed up steady stake platform semi-finished product first and are arrived by lightering Ship Transportation Construction site is arranged level governor in the quadrangle of steady stake platform semi-finished product, is then hung steady stake platform semi-finished product using 4 points Mode lift by crane, crane ship side board is against after lifting, and tied steady stake platform semi-finished product with crane ship with wirerope, then led to The method for crossing GPS positioning adjusts accommodation, is overlapped the Longkou center of steady stake platform semi-finished product with design engineering pile center, Steady stake platform semi-finished product are placed on sea bed face, the positioning of steady stake platform is completed, then crane ship by four auxiliary piles according to Cornerwise principle is successively sling and is inserted on sea bed, lifts by crane vibration hammer after the completion of pitching pile, vibration hammer slowly clamps auxiliary pile slightly It is micro- pull up after again insertable into, be then turned on when relatively stable vibration hammer carry out pile pulling pitching pile until no drilling depth;
B, it the promotion and fixation of steady stake platform: measures the elevation location of steady stake platform and marks, then mentioned with crane ship Steady stake platform semi-finished product are risen to marked locations, are finally welded auxiliary pile and the welding of steady stake platform semi-finished product using reinforcement steel plate It is fixed together;
C, the construction of engineering pile and verticality adjustment: being risen engineering pile using crane ship and lift up into the Longkou among steady stake platform, under Stake is then adjusted the verticality of engineering pile by correcting cylinder, and adjustment, which is finished, carries out steady stake and pile sinking, work for engineering pile Auxiliary pile and steady stake platform semi-finished product are successively removed after journey pile driving construction.
8. a kind of construction technology of mobile steady stake platform according to claim 7, which is characterized in that the GPS in step a The method of positioning, specific steps are as follows: crane ship is being set according to boat-carrying GPS coarse positioning before steady stake platform semi-finished product lifting Engineering pile near center location is counted, lifts by crane and two GPS rover stations is fixed on corresponding ship side position after steady stake platform semi-finished product, The straight line that two GPS rover station centers are constituted is parallel with ship side outer, marks vertical and horizontal score line, then commands lifting Ship adjusts accommodation, so that the center of steady stake platform semi-finished product is overlapped with the center of design engineering pile, anchor hawser is tightened, by steady stake Platform semi-finished product are placed into sea bed face.
CN201910532167.5A 2019-06-19 2019-06-19 A kind of mobile surely stake platform and its construction technology Pending CN110424394A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910532167.5A CN110424394A (en) 2019-06-19 2019-06-19 A kind of mobile surely stake platform and its construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910532167.5A CN110424394A (en) 2019-06-19 2019-06-19 A kind of mobile surely stake platform and its construction technology

Publications (1)

Publication Number Publication Date
CN110424394A true CN110424394A (en) 2019-11-08

Family

ID=68408719

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910532167.5A Pending CN110424394A (en) 2019-06-19 2019-06-19 A kind of mobile surely stake platform and its construction technology

Country Status (1)

Country Link
CN (1) CN110424394A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113106973A (en) * 2021-03-04 2021-07-13 中国铁建港航局集团有限公司 Construction method of single pile
CN113957892A (en) * 2021-11-26 2022-01-21 中天科技集团海洋工程有限公司 Pile sinking construction system and process for semi-submersible crane ship
CN116713629A (en) * 2023-08-09 2023-09-08 广州文船重工有限公司 Assembling method for large pin wheel and supporting rod of portal crane

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105507325A (en) * 2015-12-31 2016-04-20 中交第三航务工程局有限公司宁波分公司 Pile stabilizing and positioning platform
CN107100193A (en) * 2017-06-24 2017-08-29 浙江华东工程咨询有限公司 A kind of construction technology for blower fan cushion cap

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105507325A (en) * 2015-12-31 2016-04-20 中交第三航务工程局有限公司宁波分公司 Pile stabilizing and positioning platform
CN107100193A (en) * 2017-06-24 2017-08-29 浙江华东工程咨询有限公司 A kind of construction technology for blower fan cushion cap

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113106973A (en) * 2021-03-04 2021-07-13 中国铁建港航局集团有限公司 Construction method of single pile
CN113957892A (en) * 2021-11-26 2022-01-21 中天科技集团海洋工程有限公司 Pile sinking construction system and process for semi-submersible crane ship
CN116713629A (en) * 2023-08-09 2023-09-08 广州文船重工有限公司 Assembling method for large pin wheel and supporting rod of portal crane
CN116713629B (en) * 2023-08-09 2023-10-03 广州文船重工有限公司 Assembling method for large pin wheel and supporting rod of portal crane

Similar Documents

Publication Publication Date Title
CN110424394A (en) A kind of mobile surely stake platform and its construction technology
CN102369134B (en) Installation method and recovery method for offshore wind turbine
CN102328732A (en) Offshore pile driving, pile pressing and installing united engineering ship
CN202557745U (en) Multifunctional wind power engineering catamaran for offshore high-altitude heavy-load hoisting and installation operation
CN102514690B (en) Multifunctional twin-hull wind power engineering ship for offshore high-altitude heavy-duty lifting installation operation
CN102653938A (en) Offshore dismantling construction method of descending form traveler
CN218506092U (en) C-shaped assembly type floating transportation structure for split floating transportation of offshore substation
CN216275237U (en) Offshore large-volume pier finish rolling thread hanging bottom combined platform
CN102720386A (en) Inversing method of inner side clustering hoop of vertical storage tank
CN108216506B (en) Floating drilling platform and construction method
CN203238646U (en) Casing box with built-in bottom board
CN102587377B (en) Drop hammer type pile sinking device and pile sinking method thereof
CN111980049A (en) Foundation device of deep riverbed mast type wharf crane and construction method
CN216615834U (en) Marine wind-power single-pile foundation construction special-purpose ship
CN103726505B (en) Offshore wind plant wind turbine foundation
CN202416191U (en) Descending-type movable mould frame offshore dismounting main beam lifting device
CN210140844U (en) Construction system for pile sinking of vertical pile with hammer for offshore wind power steel pipe pile
CN109577323B (en) Tubular pile reinforcing method
CN105133632A (en) Offshore wind turbine foundation structure and construction method thereof
CN105804111A (en) Unequal-length-leg offshore wind power jacket foundation and construction method thereof
CN201817199U (en) Automatic leveling device for semisubmersible barge crane platform
CN213740969U (en) Movable offshore wind power operation and maintenance support platform
CN110820596A (en) Temporary limiting device for linear adjustment of PC track beam and using method
CN217053447U (en) Beam-slab type four-column combined foundation for power transmission line
CN215715169U (en) Lay down platform and have its marine current conversion station

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191108

RJ01 Rejection of invention patent application after publication