CN110318472A - Steel core concrete column and armored concrete Prefabricated beam connection structure and connection method - Google Patents

Steel core concrete column and armored concrete Prefabricated beam connection structure and connection method Download PDF

Info

Publication number
CN110318472A
CN110318472A CN201910596890.XA CN201910596890A CN110318472A CN 110318472 A CN110318472 A CN 110318472A CN 201910596890 A CN201910596890 A CN 201910596890A CN 110318472 A CN110318472 A CN 110318472A
Authority
CN
China
Prior art keywords
steel
steel bushing
partition
concrete column
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910596890.XA
Other languages
Chinese (zh)
Other versions
CN110318472B (en
Inventor
李秀领
丁经伟
李言
鲁西
吕相蓉
蔡帅
孙国华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Jianzhu University
Original Assignee
Shandong Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Jianzhu University filed Critical Shandong Jianzhu University
Priority to CN201910596890.XA priority Critical patent/CN110318472B/en
Publication of CN110318472A publication Critical patent/CN110318472A/en
Application granted granted Critical
Publication of CN110318472B publication Critical patent/CN110318472B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/185Connections not covered by E04B1/21 and E04B1/2403, e.g. connections between structural parts of different material

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

The present invention discloses a kind of steel core concrete column and armored concrete Prefabricated beam connection structure and connection method, including armored concrete precast beam, partition, steel bushing, angle cleat and steel core concrete column;Reinforcing bar in armored concrete precast beam extends to the outside of prefabricated beam body, the end of reinforcing bar is connect with partition, first face of steel bushing is connect with steel core concrete column, it is cooperatively connected inside the steel bushing with partition and reinforcing bar, the steel bushing and partition and reinforcing bar are perfused with concrete in steel bushing inner space after being cooperatively connected, the angle cleat is used for joint steel pipe concrete column and steel bushing.The structure uses the site-assembled connection type of prefabricated components, farthest improves construction efficiency and easily controllable quality.

Description

Steel core concrete column and armored concrete Prefabricated beam connection structure and connection method
Technical field
The present invention relates to building engineering fields, and in particular to a kind of steel core concrete column is connect with armored concrete precast beam Structure and connection method.
Background technique
Bean column node is also referred to as joint cores, play the role of in the structure transmit load with connect beam column.In earthquake Structural damage mostly occurs on bean column node, or causes the collapsing of total by the destruction of bean column node.Therefore, beam The switching performance of Column border node plays conclusive effect to the stability and overall performance of total.
The connecting node of steel core concrete column and armored concrete precast beam composition is that building trade application is more extensive Connecting node, but reinforcing bar is passed through steel pipe column by traditional connecting node, forms perforation muscle, this structure be easy to steel pipe column by Power, which generates, weakens effect, brings difficulty when casting concrete in square steel tube, craftsmanship is poor.In addition node weld component is at the scene Heavy workload, welding quality require height, and processing is complicated, be easy to cause brittle break.
Summary of the invention
In view of the above problems, the present invention provides a kind of steel core concrete column and armored concrete Prefabricated beam connection structure and company Method is connect, which uses the site-assembled connection type of prefabricated components, farthest improves construction efficiency and is easy to Control quality.
Steel core concrete column and armored concrete Prefabricated beam connection structure, including armored concrete precast beam, partition, steel bushing Cylinder, angle cleat and steel core concrete column;
Reinforcing bar in the armored concrete precast beam extends to the outside of prefabricated beam body, and the end of the reinforcing bar and partition connect It connects, the steel bushing is the polyhedron of two sides opening, and two faces of opening are mutually perpendicular to, the first face of the steel bushing and steel pipe Concrete column connection, the steel bushing inside are cooperatively connected with partition and reinforcing bar, the steel bushing and partition and reinforcing bar cooperation company Concrete is perfused with after connecing in steel bushing inner space, the angle cleat is used for joint steel pipe concrete column and steel bushing Cylinder.
Further, symmetrical card is provided on opposed two sides vertical with the first face on the steel bushing Slot is additionally provided with snap-gauge on the opposed two sides of steel bushing, and the card slot is arranged in parallel with snap-gauge, the partition and card Slot is coupled, and the snap-gauge is coupled with reinforcing bar.
Further, the steel core concrete column is bolted with steel bushing, angle steel, the steel bushing and angle Steel is also by being bolted.
Further, the partition is connect with screw thread steel.
Invention additionally discloses a kind of connection methods of above structure, the specific steps are as follows:
Partition and reinforcing bar are coupled by step 1;
Steel bushing and steel core concrete column utilization are bolted securely by step 2;
Step 3, the armored concrete precast beam that will be equipped with partition and steel bushing are installed, and when installation, partition is inserted into card slot, are mixed The leading flank of solidifying soil precast beam is contacted with snap-gauge;
Step 4, the concrete perfusion into steel bushing;
Steel core concrete column and steel bushing are attached by step 5 with angle cleat.
Beneficial effects of the present invention:
1. being all made of bolt between each connecting component of the present invention to be attached, the end reinforcing bar and partition of armored concrete precast beam It is threadedly coupled, live welding, easy to operate, construction is simple.
2. rigidity at tie point is promoted, the principle of strong column and weak beam is strengthened in steel core concrete column outer cover steel loading sleeve, Plastic hinge can be made to occur except beam-to-column joint point.Steel bushing makes tie point not need to carry out formwork again when pouring simultaneously, just Fast, it saves tool to use, simplifies operating procedure.
3. inside setting card slot and snap-gauge, cooperate with partition and reinforcing bar, more convenient accurate when installing precast beam.
It is not outer when making casting concrete 4. form confined space after armored concrete precast beam and partition and steel bushing cooperation Stream.
5. sleeve inner concrete ensure that intensity and globality at node, the energy dissipation capacity of node is improved.
6. the connection structure tailored appearance, simple structure, reasonable stress, beam-ends are formed by casting concrete and steel bushing It is whole, pass through the bolt connection and moment of flexure between steel bushing, angle steel and steel core concrete column.
Detailed description of the invention
In order to illustrate the technical solutions in the embodiments of the present application or in the prior art more clearly, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of application for those of ordinary skill in the art without creative efforts, can be with It obtains other drawings based on these drawings.
Fig. 1 is schematic structural view of the invention
Fig. 2 is steel bushing schematic diagram
Fig. 3 is armored concrete precast beam and partition connection schematic diagram
Fig. 4 is angle cleat schematic diagram.
Specific embodiment
Below in conjunction with the attached drawing in the embodiment of the present application, technical solutions in the embodiments of the present application carries out clear, complete Whole description, it is clear that described embodiments are only a part of embodiments of the present application, instead of all the embodiments.It is based on Embodiments herein, every other reality obtained by those of ordinary skill in the art without making creative efforts Example is applied, shall fall in the protection scope of this application.
Fig. 1, steel core concrete column shown in Fig. 3 and armored concrete Prefabricated beam connection structure, armored concrete precast beam 2 Internal reinforcing bar extends to the outside of prefabricated beam body, extension elongation according to the sectional dimension calculating and setting of precast beam, reinforcing bar End processes screw thread, and partition 5 is drilled with through-hole, and reinforcing bar penetrates in the through-hole of partition 5, partition two sides respectively with nut by reinforcing bar with Partition is connected firmly.As shown in Fig. 2, steel bushing 3 be above with the hexahedron of front openings, steel bushing 3 below with steel pipe mix Solidifying earth pillar 1 is connected with, and is provided with symmetrical two card slots 6 and two snap-gauges 7, card slot in left and right sides inside steel bushing It is arranged in parallel with snap-gauge, the opening direction of card slot is oppositely arranged, and partition 5 and card slot 6 are coupled for Primary Location, snap-gauge 7 Be coupled with reinforcing bar and with precast beam body contact, for second step position.In steel core concrete column outer cover steel loading sleeve, Rigidity at tie point is promoted, the principle of strong column and weak beam is strengthened, plastic hinge can be made to occur except beam-to-column joint point.Steel bushing simultaneously Cylinder makes tie point not need to carry out formwork again when pouring, and convenient and efficient, saving tool uses, and simplifies operating procedure.Inside is set Card slot and snap-gauge are set, is cooperated with partition and reinforcing bar, it is more convenient accurate when precast beam is installed.
Steel bushing 3 and partition 5 and reinforcing bar are perfused with concrete in steel bushing inner space after being cooperatively connected, and ensure that The intensity and globality of node, improve the energy dissipation capacity of node.
Angle cleat 4 shown in Fig. 4 is connect with steel core concrete column 1 and steel bushing 3 respectively by bolt, connects institute herein It is high-strength bolt with bolt, is all made of bolt between each connecting component and is attached, the end of armored concrete precast beam Reinforcing bar is threadedly coupled with partition, live welding, easy to operate, construction is simple.
Invention additionally discloses a kind of connection methods of above structure, the specific steps are as follows:
Partition and reinforcing bar are coupled by step 1, are fastened in two sides of partition with nut;
Card slot and snap-gauge are welded on inside steel bushing by step 2, and steel bushing and steel core concrete column are connected using high-strength bolt It connects securely;
Step 3 lifts the armored concrete precast beam for being equipped with partition to installation at the tie point of steel core concrete column, installation When, partition is inserted into card slot, and the leading flank of concrete prefabricated beam is contacted with snap-gauge;
Concrete perfusion in step 4, the confined space formed to steel bushing;
Steel core concrete column and steel bushing are attached by step 5 with angle cleat.
The connection structure tailored appearance, simple structure, reasonable stress, beam-ends are formed by casting concrete with steel bushing whole Body passes through the bolt connection and moment of flexure between steel bushing, angle steel and steel core concrete column.
The foregoing description of the disclosed embodiments makes professional and technical personnel in the field can be realized or use the application. Various modifications to these embodiments will be readily apparent to those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the application.Therefore, the application It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest scope of cause.

Claims (5)

1. steel core concrete column and armored concrete Prefabricated beam connection structure, which is characterized in that including armored concrete precast beam, Partition, steel bushing, angle cleat and steel core concrete column;
Reinforcing bar in the armored concrete precast beam extends to the outside of prefabricated beam body, and the end of the reinforcing bar and partition connect It connects, the steel bushing is the polyhedron of two sides opening, and two faces of opening are mutually perpendicular to, the first face of the steel bushing and steel pipe Concrete column connection, the steel bushing inside are cooperatively connected with partition and reinforcing bar, the steel bushing and partition and reinforcing bar cooperation company Concrete is perfused with after connecing in steel bushing inner space, the angle cleat is used for joint steel pipe concrete column and steel bushing Cylinder.
2. steel core concrete column according to claim 1 and armored concrete Prefabricated beam connection structure, which is characterized in that institute It states and is provided with symmetrical card slot on opposed two sides vertical with the first face on steel bushing, the steel bushing is opposed Two sides on be additionally provided with snap-gauge, the card slot is arranged in parallel with snap-gauge, and the partition is coupled with card slot, the snap-gauge It is coupled with reinforcing bar.
3. steel core concrete column according to claim 1 and armored concrete Prefabricated beam connection structure, which is characterized in that institute It states steel core concrete column to be bolted with steel bushing, angle steel, the steel bushing and angle steel are also by being bolted.
4. steel core concrete column according to claim 3 and armored concrete Prefabricated beam connection structure, which is characterized in that institute Partition is stated to connect with screw thread steel.
5. a kind of power 1 is to the connection method of the power 4 any steel core concrete columns and armored concrete Prefabricated beam connection structures, It is characterized in that, steps are as follows:
Partition and reinforcing bar are coupled by step 1;
Steel bushing and steel core concrete column utilization are bolted securely by step 2;
Step 3, the armored concrete precast beam that will be equipped with partition and steel bushing are installed, and when installation, partition is inserted into card slot, are mixed The leading flank of solidifying soil precast beam is contacted with snap-gauge;
Step 4, the concrete perfusion into steel bushing;
Steel core concrete column and steel bushing are attached by step 5 with angle cleat.
CN201910596890.XA 2019-07-04 2019-07-04 Connecting structure and connecting method for steel pipe concrete column and reinforced concrete precast beam Active CN110318472B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910596890.XA CN110318472B (en) 2019-07-04 2019-07-04 Connecting structure and connecting method for steel pipe concrete column and reinforced concrete precast beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910596890.XA CN110318472B (en) 2019-07-04 2019-07-04 Connecting structure and connecting method for steel pipe concrete column and reinforced concrete precast beam

Publications (2)

Publication Number Publication Date
CN110318472A true CN110318472A (en) 2019-10-11
CN110318472B CN110318472B (en) 2021-02-02

Family

ID=68122526

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910596890.XA Active CN110318472B (en) 2019-07-04 2019-07-04 Connecting structure and connecting method for steel pipe concrete column and reinforced concrete precast beam

Country Status (1)

Country Link
CN (1) CN110318472B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113445625A (en) * 2021-08-31 2021-09-28 启东霓辉新材料科技有限公司 Prefabricated concrete pipe column steel rib concrete beam joint structure and construction method thereof
CN115467414A (en) * 2022-09-26 2022-12-13 中南大学 Mechanism and method for determining energy consumption of penetrating combined joint of concrete filled steel tubular column

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01122007A (en) * 1987-11-06 1989-05-15 Canon Electron Inc Magnetic head
EP2130984A2 (en) * 2008-06-04 2009-12-09 Industrieberatung Maier AG Load distribution body with profile carrier system
US9334642B1 (en) * 2015-04-14 2016-05-10 Senqcia Corporation Connection structure of column and beam, and reinforcing member
CN106522381A (en) * 2016-10-25 2017-03-22 华南理工大学 Joint connection of regeneration cubage concrete combination beam-column and construction method thereof
CN107574930A (en) * 2017-09-27 2018-01-12 华南理工大学 It is a kind of that H profile steel and the regeneration monolith connecting node of U-shaped steel are set
CN207160238U (en) * 2017-02-24 2018-03-30 新世界中国地产有限公司 Prefabricated construction system
KR20180109766A (en) * 2017-03-28 2018-10-08 (주)세진알앤에스 E-z connecting structure for beam and column wherein the end-moment and bending resistibility are reinforced
CN108678171A (en) * 2018-06-11 2018-10-19 沈阳建筑大学 Wooden frame column connection structure
CN108678167A (en) * 2018-08-04 2018-10-19 四川建安装配式工程科技股份有限公司 Shape for hat beam column connection part, beam column package assembly and installation method using the beam column connection part
CN108867889A (en) * 2018-07-04 2018-11-23 重庆大学 A kind of prefabricated reinforced concrete composite beam and steel pipe column connected node and its construction method
CN208396008U (en) * 2018-06-11 2019-01-18 上海通用建筑工程有限公司 A kind of connecting node of steel frame beam and reinforced concrete column
CN208899640U (en) * 2018-07-25 2019-05-24 上海生睿住宅工业有限公司 A kind of prefabricated post being easily installed
CN109811902A (en) * 2017-11-21 2019-05-28 王韬 A kind of steel core concrete column and steel beam connecting joint

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01122007A (en) * 1987-11-06 1989-05-15 Canon Electron Inc Magnetic head
EP2130984A2 (en) * 2008-06-04 2009-12-09 Industrieberatung Maier AG Load distribution body with profile carrier system
US9334642B1 (en) * 2015-04-14 2016-05-10 Senqcia Corporation Connection structure of column and beam, and reinforcing member
CN106522381A (en) * 2016-10-25 2017-03-22 华南理工大学 Joint connection of regeneration cubage concrete combination beam-column and construction method thereof
CN207160238U (en) * 2017-02-24 2018-03-30 新世界中国地产有限公司 Prefabricated construction system
KR20180109766A (en) * 2017-03-28 2018-10-08 (주)세진알앤에스 E-z connecting structure for beam and column wherein the end-moment and bending resistibility are reinforced
CN107574930A (en) * 2017-09-27 2018-01-12 华南理工大学 It is a kind of that H profile steel and the regeneration monolith connecting node of U-shaped steel are set
CN109811902A (en) * 2017-11-21 2019-05-28 王韬 A kind of steel core concrete column and steel beam connecting joint
CN108678171A (en) * 2018-06-11 2018-10-19 沈阳建筑大学 Wooden frame column connection structure
CN208396008U (en) * 2018-06-11 2019-01-18 上海通用建筑工程有限公司 A kind of connecting node of steel frame beam and reinforced concrete column
CN108867889A (en) * 2018-07-04 2018-11-23 重庆大学 A kind of prefabricated reinforced concrete composite beam and steel pipe column connected node and its construction method
CN208899640U (en) * 2018-07-25 2019-05-24 上海生睿住宅工业有限公司 A kind of prefabricated post being easily installed
CN108678167A (en) * 2018-08-04 2018-10-19 四川建安装配式工程科技股份有限公司 Shape for hat beam column connection part, beam column package assembly and installation method using the beam column connection part

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113445625A (en) * 2021-08-31 2021-09-28 启东霓辉新材料科技有限公司 Prefabricated concrete pipe column steel rib concrete beam joint structure and construction method thereof
CN113445625B (en) * 2021-08-31 2021-11-02 启东霓辉新材料科技有限公司 Prefabricated concrete pipe column steel rib concrete beam joint structure and construction method thereof
CN115467414A (en) * 2022-09-26 2022-12-13 中南大学 Mechanism and method for determining energy consumption of penetrating combined joint of concrete filled steel tubular column
CN115467414B (en) * 2022-09-26 2024-04-16 中南大学 Structure and method for determining penetrating type combined node energy consumption of concrete filled steel tube column

Also Published As

Publication number Publication date
CN110318472B (en) 2021-02-02

Similar Documents

Publication Publication Date Title
CN205776734U (en) A kind of assembly concrete connecting structure of beam column nodes
CN108193782A (en) Prefabricated modular frame node and assembling method thereof
CN207988220U (en) Combined steel plate shearing force wall
CN104912190A (en) Dry type joggle frame structure
CN102995756B (en) Concrete-filled rectangular steel tube column-box girder full-bolt connection node and construction method
CN207003652U (en) A kind of compound concrete-filled tubular column and steel tube concrete beam composite frame structure
CN105133791A (en) Construction method for prefabricated thick plate steel rib concrete column variable cross-section transformation node structure
CN207846687U (en) Prefabricated assembled modularization frame node
CN105064503A (en) Steel tube and core tube mixed structure
CN107023076A (en) A kind of assembly concrete pole steel beam connecting node and preparation method thereof
CN108894362A (en) Assembled grating type thin-walled steel plate regeneration concrete compound shear wall and assembly method
CN108316477A (en) Band steel pipe concrete column and section steel beam interior joint connection structure and construction method
CN109372129A (en) The novel full assembly concrete frame joint of one kind and its construction method
CN105239726B (en) The prefabricated combined special-shaped power consumption post of steel reinforced concrete
CN110318472A (en) Steel core concrete column and armored concrete Prefabricated beam connection structure and connection method
CN105696730A (en) Concrete-filled steel tube frame column-steel plate shear wall system and construction method
CN105507426A (en) Half-through bracket haunching type compound steel pipe concrete column-steel beam joint
CN106436926A (en) Square steel tube column-H-shaped steel beam end-plate connecting node
CN205688587U (en) A kind of to wearing rod iron and to wearing the perpendicular two-way rigid joint of board plug type beam column
CN208815676U (en) Band steel pipe concrete column and section steel beam interior joint connection structure
CN207714795U (en) A kind of novel reinforced concrete beam Column border node anti-seismic strengthening device
CN103628569B (en) A kind of draw-in groove assembly concrete-filled steel tube post-steel beam connecting joint
CN108222371B (en) Assembled steel pipe concrete composite column and splicing method
CN109339226A (en) A kind of prefabricated assembling type reinforced concrete beam-column connection structure
CN110284589A (en) Hub-type precast concrete beam column assembled Self-resetting system and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant