CN110306788A - Roof board post poured band bottom formwork erecting structure and its construction method - Google Patents

Roof board post poured band bottom formwork erecting structure and its construction method Download PDF

Info

Publication number
CN110306788A
CN110306788A CN201910580827.7A CN201910580827A CN110306788A CN 110306788 A CN110306788 A CN 110306788A CN 201910580827 A CN201910580827 A CN 201910580827A CN 110306788 A CN110306788 A CN 110306788A
Authority
CN
China
Prior art keywords
post
cast strip
main joist
layer board
support rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201910580827.7A
Other languages
Chinese (zh)
Inventor
葛立杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201910580827.7A priority Critical patent/CN110306788A/en
Publication of CN110306788A publication Critical patent/CN110306788A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • E04G11/483Supporting heads

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

It sets multi-layer board the present invention provides a kind of roof board post poured band bottom formwork erecting structure, on the downside of post-cast strip, is longitudinally equipped with secondary joist along post-cast strip under multi-layer board;It is equipped with main joist along post-cast strip cross-wise direction under secondary joist, multi-layer board is concordant with main joist side, their 500mms Chong Die with left side floor, other end 500mm Chong Die with right side floor;Support rod is set on the downside of main joist, additionally provide the construction method of above-mentioned roof board post poured band bottom formwork erecting structure, when roof plate template branch is set to post-cast strip position, formwork bracing system is trimmed at each 500mm in post-cast strip two sides, support rod is installed on the ground of post-cast strip two sides, main joist, secondary joist on main joist are placed on support rod, multi-layer board is placed on secondary joist, and it is concordant with surrounding floor face formwork elevation measuring to multi-layer board to adjust U support support rod height.The bed die of post-cast strip of the present invention is mutually separated with surrounding floor face die plate, can individually manage striking time, is not influenced on the other positions form removable time.

Description

Roof board post poured band bottom formwork erecting structure and its construction method
Technical field
The invention belongs to floor slab back casting belt construction technologies, and in particular to a kind of roof board post poured band bottom formwork erecting structure and its Construction method.
Background technique
Currently, post-cast strip will be arranged in the building body that length is more than 40m, post-cast strip concrete is not applied simultaneously with other top plate beams Work, but just can be carried out and pour after two months in two sides floor slab construction.In soffit formwork, after not distinguishing in the prior art Band position and other top plate beams are poured, but integrated template is installed.This results in waiting for that concrete roof test block is strong when roof bow template After degree reaches the dismounting of demoulding condition, because the later period also needs to construct to post-cast strip, then whole end template will be parked 2 months, material Material overstocks more, and turnover rate is low.
Summary of the invention
The present invention is to solve post-cast strip bottom in the prior art and other top plate beam bottoms portion one formwork, and material is caused to occupy Time is long, the low problem of turnover rate.
To solve the above problems, present invention provide the technical scheme that
A kind of roof board post poured band bottom formwork erecting structure, post-cast strip downside set multi-layer board, multi-layer board one end and left side floor It is overlapped 500mm, other end 500mm Chong Die with right side floor;Secondary joist is longitudinally equipped with along post-cast strip under multi-layer board;Secondary joist lower edge Post-cast strip cross-wise direction is equipped with main joist, and wide post-cast strip 500mm, right side width out go out post-cast strip 500mm on the left of main joist length;It is main Support rod is set on the downside of keel, support rod includes that scaffold tubes upright bar and U are held in the palm, in the U support that main joist fixes.
The connectionless relationship of the top plate lower template of this post-cast strip bottom formwork and side, without mutual stress, under other top plates It is individually left after form removable.The material of occupancy is few, improves the integral material turnover rate of engineering.
The present invention also provides the construction method of above-mentioned roof board post poured band bottom formwork erecting structure, follow these steps to carry out:
1) when roof plate template branch is set to post-cast strip position, formwork bracing system is cut at each 500mm in post-cast strip two sides Together, support rod is installed on the ground of post-cast strip two sides, support rod is symmetrical arranged in post-cast strip two sides;
2) main joist is placed on two symmetrical support rods, main joist is stuck in the U support of support bar top, and main joist is long Degree arranged on left and right sides on the basis of the width of post-cast strip respectively adds 500mm out;
3) along post-cast strip longitudinal direction, the secondary joist perpendicular to main joist is placed on main joist;
4) multi-layer board is placed on face in lifting for all secondary joists formation, wide post-cast strip 500 out on the left of multi-layer board, right side is wide Post-cast strip 500 out;
5) it adjusts U and holds in the palm support rod height, until multi-layer board is concordant with surrounding floor face formwork elevation measuring.
Although the bed die of post-cast strip of the present invention is concordant with floor face die plate around, but mutually separate, alter-pouring strips mould plate The structure of support top be it is independent, can individually manage striking time, other positions template is had no effect, the turnover of occupancy Material is less, is conducive to construction material turnover.
Detailed description of the invention
Fig. 1 is die structure figure in post-cast strip of the present invention;
Fig. 2 is supporting bar structure figure.
In figure, post-cast strip 1, multi-layer board 2, secondary joist 3, main joist 4, support rod 6, U support 6, nut 7.
Specific embodiment
The construction time of post-cast strip and the construction time of other floors are inconsistent, but when bed die installs in the prior art does not have Have and distinguish 1 position of post-cast strip and other floors, but be provided with the end template of one, design structure is unreasonable, and causing can not be right The independent management of different construction locations.The present invention designs to solve the above problems, avoid the valueless stop for a long time of most of template Individual post-cast strip bed die.
1-2 illustrates the present invention with reference to the accompanying drawing:
A kind of roof board post poured band bottom formwork erecting structure, sets multi-layer board 2 on the downside of the post-cast strip 1,2 one end of multi-layer board and left Side floor is overlapped 500mm, other end 500mm Chong Die with right side floor, and multi-layer board 2 has time longitudinally disposed along post-cast strip 1 Keel 3;Secondary joist 3 has the main joist 4 along the setting of 1 cross-wise direction of post-cast strip, and 4 length of main joist is greater than 1 width of post-cast strip 1000mm, left side width go out post-cast strip 500mm, and right side width goes out post-cast strip 500mm;Support rod 5, the support are set on the downside of main joist 4 Bar 5 includes scaffold tubes upright bar and U support 6, and main joist 4 fixes in U support.
U support is raised and lowered by the nut 7 on rotary supporting rod in the adjustable height of U support 6 at 5 top of support rod.
The present invention also provides the construction method of above-mentioned roof board post poured band bottom formwork erecting structure, follow these steps to carry out:
1) when roof plate template branch is set to post-cast strip position, formwork bracing system is cut at each 500mm in post-cast strip two sides Together, support rod is installed on the ground of post-cast strip two sides, support rod is symmetrical arranged in post-cast strip two sides;
2) main joist is placed on two symmetrical support rods, main joist is stuck in the U support of support bar top, and main joist is long Degree is that width both ends in post-cast strip add 500mm;
3) along post-cast strip longitudinal direction, the secondary joist perpendicular to main joist is placed on main joist;
4) multi-layer board is placed on face in lifting for all secondary joists formation, multi-layer board two sides are to be aligned with main joist both ends, The wide post-cast strip 500 out in its left side, the wide post-cast strip 500 out in right side;
5) it adjusts U and holds in the palm support rod height, until multi-layer board is concordant with surrounding floor face formwork elevation measuring.
The connectionless relationship of the top plate lower template of post-cast strip bottom provided by the invention formwork erecting structure and side, without mutually by Power can be removed normally after other positions reach demoulding requirement, the striking time of post-cast strip can individually be managed, to other positions mould Plate has no effect, and the material that the service life of occupancy is long is less, improves the integral material turnover rate of engineering.

Claims (2)

1. a kind of roof board post poured band bottom formwork erecting structure, it is characterized in that: multi-layer board is set on the downside of post-cast strip, multi-layer board one end and a left side Side floor is overlapped 500mm, other end 500mm Chong Die with right side floor;Secondary joist is longitudinally equipped with along post-cast strip under multi-layer board;Secondary dragon It is equipped with main joist along post-cast strip cross-wise direction under bone, wide post-cast strip 500mm, right side width out go out post-cast strip on the left of main joist length 500mm;Support rod is set on the downside of main joist, support rod includes that scaffold tubes upright bar and U are held in the palm, in the U support that main joist fixes.
2. the construction method of roof board post poured band as described in claim 1 bottom formwork erecting structure, follows these steps to carry out:
1) when roof plate template branch is set to post-cast strip position, formwork bracing system is trimmed at each 500mm in post-cast strip two sides, Support rod is installed, support rod is symmetrical arranged in post-cast strip two sides on the ground of post-cast strip two sides;
2) main joist is placed on two symmetrical support rods, main joist is stuck in the U support of support bar top, and main joist length exists Arranged on left and right sides respectively adds 500mm out on the basis of the width of post-cast strip;
3) along post-cast strip longitudinal direction, the secondary joist perpendicular to main joist is placed on main joist;
4) multi-layer board is placed on face in lifting for all secondary joists formation, wide post-cast strip 500 out on the left of multi-layer board, after right side width goes out Pour band 500;
5) it adjusts U and holds in the palm support rod height, until multi-layer board is concordant with surrounding floor face formwork elevation measuring.
CN201910580827.7A 2019-06-29 2019-06-29 Roof board post poured band bottom formwork erecting structure and its construction method Withdrawn CN110306788A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910580827.7A CN110306788A (en) 2019-06-29 2019-06-29 Roof board post poured band bottom formwork erecting structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910580827.7A CN110306788A (en) 2019-06-29 2019-06-29 Roof board post poured band bottom formwork erecting structure and its construction method

Publications (1)

Publication Number Publication Date
CN110306788A true CN110306788A (en) 2019-10-08

Family

ID=68078147

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910580827.7A Withdrawn CN110306788A (en) 2019-06-29 2019-06-29 Roof board post poured band bottom formwork erecting structure and its construction method

Country Status (1)

Country Link
CN (1) CN110306788A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110924678A (en) * 2019-11-27 2020-03-27 中国航天建设集团有限公司 Construction method and device for large-span variable-section haunch plate template
CN111550036A (en) * 2020-05-27 2020-08-18 北京天润建设有限公司 Aluminum-wood mixed template structure and construction method thereof
CN114856170A (en) * 2022-05-30 2022-08-05 北京城建集团有限责任公司 Roof formwork construction process
CN115387392A (en) * 2022-08-23 2022-11-25 中国五冶集团有限公司 Basement post-cast strip construction structure and method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000356041A (en) * 1999-06-17 2000-12-26 Nishimatsu Constr Co Ltd Method for placing concrete
CN201738575U (en) * 2010-06-25 2011-02-09 中天建设集团有限公司天津分公司 Beam-slab supporting system with post-cast strip
CN202530754U (en) * 2012-03-20 2012-11-14 叶小钗 Floor post-cast strip template structure
CN207048310U (en) * 2017-07-28 2018-02-27 北京城建七建设工程有限公司 A kind of alter-pouring strips mould plate support system
CN208039821U (en) * 2018-04-02 2018-11-02 中国建筑第二工程局有限公司 Floor slab back casting band shuttering supporting reinforcement system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000356041A (en) * 1999-06-17 2000-12-26 Nishimatsu Constr Co Ltd Method for placing concrete
CN201738575U (en) * 2010-06-25 2011-02-09 中天建设集团有限公司天津分公司 Beam-slab supporting system with post-cast strip
CN202530754U (en) * 2012-03-20 2012-11-14 叶小钗 Floor post-cast strip template structure
CN207048310U (en) * 2017-07-28 2018-02-27 北京城建七建设工程有限公司 A kind of alter-pouring strips mould plate support system
CN208039821U (en) * 2018-04-02 2018-11-02 中国建筑第二工程局有限公司 Floor slab back casting band shuttering supporting reinforcement system

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110924678A (en) * 2019-11-27 2020-03-27 中国航天建设集团有限公司 Construction method and device for large-span variable-section haunch plate template
CN111550036A (en) * 2020-05-27 2020-08-18 北京天润建设有限公司 Aluminum-wood mixed template structure and construction method thereof
CN114856170A (en) * 2022-05-30 2022-08-05 北京城建集团有限责任公司 Roof formwork construction process
CN114856170B (en) * 2022-05-30 2023-07-25 北京城建集团有限责任公司 Construction process of top plate template
CN115387392A (en) * 2022-08-23 2022-11-25 中国五冶集团有限公司 Basement post-cast strip construction structure and method
CN115387392B (en) * 2022-08-23 2023-12-15 中国五冶集团有限公司 Basement post-pouring strip construction structure and method

Similar Documents

Publication Publication Date Title
CN110306788A (en) Roof board post poured band bottom formwork erecting structure and its construction method
CN112342934B (en) Construction method of high-stability curve bridge plate
CN103161126A (en) Road bridge variable section hollow high pier slip-form construction method
CN108487630B (en) Concrete sill prefabricated assembly construction method
CN110409799B (en) Wind tunnel fair-faced concrete construction process
CN206607863U (en) A kind of post-cast strip temporary support structure
CN212689566U (en) Floor post-cast strip support system
CN110409319B (en) Bracket for large-span steel-concrete composite beam cast-in-place bridge deck and construction method
CN107090974A (en) A kind of top plate Quick Release support system and its construction method
CN208534025U (en) Floor slab back casting band separate support formwork erecting structure
CN106976157A (en) A kind of post stretching precast beam pedestal for being applicable different length and cross sectional shape
CN114770706B (en) Light T-beam prefabrication equipment and prefabrication installation construction method
CN219080981U (en) Non-support fixing device for post-pouring strip of superimposed sheet
US2966717A (en) Apparatus for casting concrete elements
CN110700490B (en) Transfer floor large-span steel reinforced concrete beam and construction method
CN210880205U (en) Movable common steel bar positioning device for prefabricated T-shaped beam and small box girder
CN111350348A (en) Positioning and reinforcing device for outer wall anti-seepage inverted beam template and construction method
CN209482350U (en) A kind of piping lane template integral support device
CN109235274B (en) Novel temporary backing beam system for pushing construction and construction method thereof
CN207048309U (en) A kind of top plate Quick Release support system
CN217734853U (en) Adjustable plate buckling template support frame for super-load small-clear-distance beam
CN109469100A (en) A kind of piping lane template integral support device
CN115338973A (en) Forward manufacturing equipment and manufacturing method for steel rib concrete upper flange plate
CN211074037U (en) Box girder template
CN209798958U (en) Pouring system for drainage ditch of bottom plate post-cast strip and shaping hanging die for drainage ditch

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20191008

WW01 Invention patent application withdrawn after publication