CN110306555A - Concrete dam abrupt slope foundation plane repeats surface grouting structure and its grouting method - Google Patents

Concrete dam abrupt slope foundation plane repeats surface grouting structure and its grouting method Download PDF

Info

Publication number
CN110306555A
CN110306555A CN201910623015.6A CN201910623015A CN110306555A CN 110306555 A CN110306555 A CN 110306555A CN 201910623015 A CN201910623015 A CN 201910623015A CN 110306555 A CN110306555 A CN 110306555A
Authority
CN
China
Prior art keywords
grouting
pipe
grout pipe
concrete dam
foundation plane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910623015.6A
Other languages
Chinese (zh)
Inventor
邓良军
杨宜文
张彩秀
李文杰
潘昌勇
杨世界
许晖
周钧
官忠瑞
黄金全
李青
李永明
林春兰
张琼芝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Kunming Engineering Corp Ltd
Original Assignee
PowerChina Kunming Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Kunming Engineering Corp Ltd filed Critical PowerChina Kunming Engineering Corp Ltd
Priority to CN201910623015.6A priority Critical patent/CN110306555A/en
Publication of CN110306555A publication Critical patent/CN110306555A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • E02B7/04Dams across valleys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

Concrete dam abrupt slope foundation plane repeats surface grouting structure and its grouting method, and especially a kind of concrete dam abrupt slope foundation plane for carrying out repeating supplementary grouting when the contact surface of concrete dam and foundation plane opens repeats surface grouting structure and its grouting method.Grouting structure setting of the invention is divided into several irrigated areas in concrete dam steep slope section, with vertical water flow direction;Arrange that two sets of grouting pipelines, every set grouting pipeline include a grout pipe in each irrigated area, grout pipe is in the U-tube being laterally arranged, and bottom nozzle is stock inlet, and upper orifice is overfall mouth;Grout pipe is inside and outside double-layer structure, and inside is pvc pipe, and slurry outlet is staggeredly equipped on pvc pipe, is elastic gum sleeve outside grout pipe, is staggeredly equipped with diffusion hole on gum sleeve.The present invention can carry out initial contact grouting construction when actual conditions reach design requirement at the scene and carry out supplementary grouting using same circuits when the contact surface of concrete dam and foundation plane opens again.

Description

Concrete dam abrupt slope foundation plane repeats surface grouting structure and its grouting method
Technical field
The present invention relates to hydraulic and hydroelectric engineering construction fields, especially a kind of not influence dam water storage task and engineering operation Target can carry out the concrete dam abrupt slope foundation plane weight for repeating supplementary grouting when the contact surface of concrete dam and foundation plane opens Multiple surface grouting structure and its grouting method.
Background technique
Concrete dam is current most wide one of the two kinds of dam types of use scope in the world.It builds and ran in concrete dam Cheng Dangzhong needs engineering construction or administrative staff to cause enough attention, wherein antiseepage and the dam body stability against sliding there are many aspect Even more two of them emphasis.As its name suggests, concrete dam is using concrete as main dam material, but due to concrete material Shrinkage character, at Dam Base Surface especially when the foundation plane gradient is steeper, contact face of the concrete dam with foundation plane It easily opens to form subtle gap because of the contraction of concrete, reduces the mechanics parameter of dam concrete and basement rock, part becomes collection Middle leakage passage, and the dam body stability against sliding degree of safety is reduced, to influence engineering safety and benefit.Therefore, designer is setting It need to usually consider to take surface grouting measure with blind during meter, reinforce the combination between dam concrete and foundation plane Density between ability and contact surface improves the dam body stability against sliding, and prevents from leaking.
In fact, the contraction distortion of concrete is a slow and permanent process, when dam concrete temperature reaches base It tends towards stability substantially when rock equilibrium temperature.But dam water storage task and engineering operation target have specific timing node to want It asks, is generally impermissible for carrying out surface grouting again after concrete shrinkage deformation reaches and stablizes on building time, but by item Mesh design side claims, and selects appropriate opportunity to be in the milk according to on-site actual situations and monitoring materials, receives in concrete Compression deformation carries out surface grouting construction after reaching a certain level.However, the routine that current design personnel are considered in design Surface grouting method, such as reserved grouting system grouting method, complement hole grouting method, tube drawing grouting method etc., usually there is only Can be carried out once grouting, can not re grouting the shortcomings that.With the sustainable development of concrete shrinkage deformation, especially dam water storage Concrete cooling is shunk afterwards, and contact surface and once opens there are still opening, need to take it after initial contact grouting His remedial measure such as punches supplementary irrigation, not only expends huge financial resource and material resource, and there is also grouting to be limited in scope, and grouting area is small, matter It is serious to measure biggish security risk, the consequence such as uncontrollable.
Summary of the invention
To be solved by this invention is exactly that existing concrete dam is easy to open because of concrete shrinkage at the foundation plane of abrupt slope, And there is a possibility that opening repeatedly after surface grouting, currently employed Conventional contact Grouting Design method is typically only capable to full Foot carry out a surface grouting the problem of, provide it is a kind of can the contact surface of concrete dam and foundation plane open when carry out repeat benefit The concrete dam abrupt slope foundation plane for charging slurry repeats surface grouting structure and its grouting method.
Concrete dam abrupt slope foundation plane of the invention repeats surface grouting structure, it is characterised in that the grouting structure setting exists Concrete dam steep slope section, each steep slope section are divided into several irrigated areas with vertical water flow direction, and each irrigated area area is to be not more than 2000m2;Two sets of grouting pipelines are arranged in each irrigated area, two sets of grout pipe roads, lower settings, every set grouting pipeline includes one A grout pipe, grout pipe are in the U-tube being laterally arranged, which is single circuit design, and bottom nozzle is stock inlet, upper tube Mouth is overfall mouth;Grout pipe is inside and outside double-layer structure, and inside is pvc pipe, is staggeredly equipped with slurry outlet on pvc pipe, outside grout pipe Portion is elastic gum sleeve, and gum sleeve hard-pressed bale is rolled in pvc pipe outer wall, is staggeredly equipped with diffusion hole on gum sleeve, Diffusion hole site is staggered with pulp hole site.
When surface grouting is constructed, under grouting pressure effect, slurries are emerged slurry outlet under pressure, and strut rubber Casing enters in the gap of contact surface into the gap between pvc pipe and gum sleeve, and then through diffusion hole;Grouting knot Shu Hou immediately cleans grouting pipeline with low pressure water, and the cement slurry in pipe is sucked out using vacuum tube and will with water by cleaning Grout pipe cleans up, and to prevent slurries residual between pvc pipe and gum sleeve from causing frozen plug, then rinses from inlet pipe direction 2min is with the unobstructed of pipeline that ensure to be in the milk;It is hydraulic with outer pulp in the elasticity of outer layer gum sleeve after not being in the milk or being in the milk Under power effect, gum sleeve is shunk by pressure, is fastened on pvc pipe, and then cover slurry outlet, is avoided slurries from flowing backwards and is entered pvc pipe.
The irrigated area is additionally provided with group stop, exhaust pipe and air discharge duct, and group stop setting is in irrigated area inner wall, by only starching Piece closes irrigated area surrounding, and air discharge duct is arranged in above the group stop at the top of irrigated area, and exhaust pipe passes vertically through air discharge duct setting.
Along the spacing about 3m of slope surface, each grouting pipeline between the grouting pipeline being arranged above and below in each irrigated area It is fixed on bedrock surface with the dowel of φ 6.
Concrete dam abrupt slope foundation plane repeats surface grouting method, it is characterised in that the grouting method is applied to above structure In, the specific steps are as follows:
(1) it on designed concrete dam, selects foundation plane to excavate the gradient suddenly in the monolith of 1:0.7, is flowed to and divided with vertical water For several irrigated areas, each irrigated area area is not more than 2000m2
(2) the grouting pipeline in each irrigated area uses pre-buried formation, is installed after grout pipe is clean, while to surface of bedrock It carries out smooth, cleans out;Than being laid with, strict demand must not on the overall slope of pipeline and attachment from overfall mouth to stock inlet by about 5% There is counter-slope, meets free-draining effect;
(3) after dam concrete is in the milk, is completely covered, consolidating, pipeline water flowing inspection of being in the milk, water flowing pressure is design grouting pressure 80%;
(4) after the minimum a set of grout pipe water flowing inspection in irrigated area is unimpeded, stock inlet or overfall mouth is closed, water-flowing amount is recorded;Wait be vented After slot return water, contact surface water flowing total amount V is calculated, Division area A is designed divided by irrigated area, calculates slit width W=V/A;By water flowing measuring and calculating Slit width is compared and analyzed with the slit width measured by crack gauge, selects the corresponding grouting ratio of mud and material on this basis,
(5) surface grouting
1) when reaching surface grouting condition, using being in the milk from bottom to top;After when bottom, grouting reaches ending standard, carry out Portion's grouting, when top, exhaust pipe plasma discharge pressure reaches specified value, entire 80% or more irrigated area grouting structure carries out grouting rear It can terminate the irrigated area cementing operations;
2) it is 0.6Mpa that the maximum grouting pressure of surface grouting, i.e. overfall mouth maximum, which control pressure,;In slurries by weight, water ash Than for 2:1,1:1 or 0.6:1, by it is dense to sorting be three than grade, selected according to the degree of coming to nothing or gap width;
3) when the pulp slurries of exhaust pipe reach most dense than grade, and exhaust pipe nozzle pressure reaches 0.2MPa, while injection rate is not Greater than 0.4L/min, then persistently, grouting 20min post-grouting terminates;
4) after being in the milk, grouting pipeline is cleaned with low pressure water immediately, cleaning uses vacuum tube by the cement slurry in pipe Be sucked out and simultaneously cleaned up grout pipe with water, to prevent between pvc pipe and gum sleeve slurries residual to cause frozen plug, then from into 2min is rinsed with the unobstructed of pipeline that ensure to be in the milk in slurry pipe direction, and last closed protective is to re grouting;
5) surface grouting construction is completed and through after the assay was approved, grout pipe is blocked closely knit using cement underflow.
After the grouting pipeline water flowing inspection or water flowing measuring and calculating, is successively used in wind clean stitched seam and managed by lowest part grout pipe After internal water accumulation, it can prepare to start surface grouting construction.
During the surface grouting, interrupt grouting more than 30min or when midge amount decrease beyond 50%, with clear water with Strong wind is in the milk again after rinsing grout pipe well.
In the step (4), when slit width is greater than 1.0mm, use the single ratio of mud for the ordinary portland cement of 0.6:1 Grouting;When slit width is less than 1.0mm and is greater than 0.5mm, the ordinary portland cement slurries that the perfusion ratio of mud is 2:1, to exhaust pipe After pulp, the slurries ratio of mud is changed to 1:1;When slit width is less than 0.5mm, using the levigate portland cement slurries of the 0.6:1 ratio of mud.
Concrete dam abrupt slope foundation plane of the invention repeats surface grouting structure and its grouting method, can be practical at the scene Situation can carry out initial contact grouting construction when reaching design requirement, not influence dam water storage task and engineering operation target, Supplementary grouting can be carried out using same circuits when the contact surface of concrete dam and foundation plane opens again again, avoided to adopt It takes other remedial measures and expends a large amount of manpower and material resources, improve dam foundation surface grouting quality, reduce the safety wind of engineering Danger.
Detailed description of the invention
Fig. 1 is invention grouting structural schematic diagram.
Fig. 2 is grouting pipeline normal configuration schematic diagram.
Fig. 3 is grouting pipeline working state structure schematic diagram.
Wherein, irrigated area 1, grout pipe 2, stock inlet 3, overfall mouth 4, pvc pipe 5, slurry outlet 6, gum sleeve 7, diffusion hole 8, Group stop 9, exhaust pipe 10, air discharge duct 11.
Specific embodiment
Embodiment 1: a kind of concrete dam abrupt slope foundation plane repeats surface grouting structure, and the grouting structure setting is in concrete Dam steep slope section, each steep slope section are divided into several irrigated areas 1 with vertical water flow direction, and each 1 area of irrigated area is to be not more than 2000m2;Often Two sets of 2 tunnels of grout pipe are arranged in a irrigated area 1, two sets of 2 roads of grout pipe, lower settings, every 2 tunnel of set grout pipe includes a grouting Pipe 2, grout pipe 2 are in the U-tube being laterally arranged, which is single circuit design, and bottom nozzle is stock inlet 3, and upper orifice is Overfall mouth 4;Grout pipe 2 is inside and outside double-layer structure, and inside is pvc pipe 5, is staggeredly equipped with slurry outlet 6, grout pipe 2 on pvc pipe 5 Outside is elastic gum sleeve 7, and 7 hard-pressed bale of gum sleeve is rolled in 5 outer wall of pvc pipe, is staggeredly equipped with expansion on gum sleeve 7 Hole 8 is dissipated, 8 position of diffusion hole is staggered with 6 position of slurry outlet.
When surface grouting is constructed, under grouting pressure effect, slurries are emerged slurry outlet 6 under pressure, and strut rubber Gum cover pipe 7 into the gap between pvc pipe 5 and gum sleeve 7, and then passes through diffusion hole 8 and enters in the gap of contact surface; After grouting, 2 tunnel of grout pipe is cleaned with low pressure water immediately, the cement slurry in pipe is sucked out simultaneously using vacuum tube for cleaning Grout pipe 2 is cleaned up with water, to prevent between pvc pipe 5 and gum sleeve 7 slurries residual to cause frozen plug, then from into slurry 2min is rinsed to ensure the unobstructed of 2 tunnel of grout pipe in pipe direction;After not being in the milk or being in the milk, in the elasticity of outer layer gum sleeve 7 Under outer pulp action of hydraulic force, gum sleeve 7 is shunk by pressure, is fastened on pvc pipe 5, and then cover slurry outlet 6, is avoided starching Liquid, which is flow backwards, enters pvc pipe 5.
Irrigated area 1 is additionally provided with group stop 9, exhaust pipe 10 and air discharge duct 11, and the setting of group stop 9 is in 1 inner wall of irrigated area, by only Lodicule 9 closes 1 surrounding of irrigated area, and 9 top of group stop at 1 top of irrigated area is arranged in air discharge duct 11, and exhaust pipe 10 passes vertically through exhaust Slot 11 is arranged.Along the spacing about 3m of slope surface between 2 tunnel of grout pipe being arranged above and below in each irrigated area 1, each 2 tunnel of grout pipe is used The dowel of φ 6 is fixed on bedrock surface.
Concrete dam abrupt slope foundation plane repeats surface grouting method, is applied in above structure, the specific steps are as follows:
(1) it on designed concrete dam, selects foundation plane to excavate the gradient suddenly in the monolith of 1:0.7, is flowed to and divided with vertical water For several irrigated areas 1, each 1 area of irrigated area is not more than 2000m2
(2) 2 tunnel of grout pipe in each irrigated area 1 uses pre-buried formation, is installed after grout pipe 2 is clean, while to basement rock Surface progress is smooth, cleans out;It is strictly wanted than being laid on the overall slope of pipeline and attachment from overfall mouth 4 to stock inlet 3 by about 5% It asks there is not allowed that counter-slope, meets free-draining effect;
(3) after dam concrete is in the milk, is completely covered, consolidating, 2 tunnel water flowing inspection of grout pipe, water flowing pressure is design grouting pressure The 80% of power;
(4) after minimum a set of 2 water flowing of the grout pipe inspection in irrigated area 1 is unimpeded, stock inlet 3 or overfall mouth 4 is closed, water-flowing amount is recorded;To After 11 return water of air discharge duct, contact surface water flowing total amount V is calculated, Division area A is designed divided by irrigated area 1, calculates slit width w=V/A;It will lead to Water measuring and calculating slit width compared and analyzed with the slit width measured by crack gauge, on this basis select accordingly be in the milk the ratio of mud and Material,
(5) surface grouting
1) when reaching surface grouting condition, using being in the milk from bottom to top;After when bottom, grouting reaches ending standard, carry out Portion's grouting, when exhaust pipe 10 plasma discharge pressure in top reaches specified value, entire 180% or more irrigated area grouting structure is in the milk After can terminate 1 cementing operations of irrigated area;
2) the maximum control pressure of the maximum grouting pressure of surface grouting, i.e. overfall mouth 4 is 0.6Mpa;In slurries by weight, water Gray scale is 2:1,1:1 or 0.6:1, by it is dense to sorting be three than grade, according to the degree of coming to nothing or gap width selection;
3) when the pulp slurries of exhaust pipe 10 reach most dense than grade, and 10 nozzle pressure of exhaust pipe reaches 0.2MPa, injects simultaneously Rate is not more than 0.4L/min, then persistently grouting 20min post-grouting terminates;
4) after being in the milk, 2 tunnel of grout pipe is cleaned with low pressure water immediately, cleaning uses vacuum tube by the cement slurry in pipe It is sucked out and is cleaned up grout pipe 2 with water, to prevent slurries residual between pvc pipe 5 and gum sleeve 7 from causing frozen plug, then 2min is rinsed to ensure the unobstructed of 2 tunnel of grout pipe from inlet pipe direction, and last closed protective is to re grouting;
5) surface grouting construction is completed and through after the assay was approved, grout pipe 2 is blocked closely knit using cement underflow.
After 2 tunnel water flowing inspection of grout pipe or water flowing measuring and calculating, by lowest part grout pipe 2 successively in wind clean stitched seam and pipe inner product After water, it can prepare to start surface grouting construction.
During surface grouting, grouting is interrupted more than 30min or when midge amount decrease beyond 50%, is rushed with clear water and strong wind It is in the milk again after wash clean grout pipe 2.
In step (4), when slit width is greater than 1.0mm, the single ratio of mud is used to be in the milk for the ordinary portland cement of 0.6:1; When slit width is less than 1.0mm and is greater than 0.5mm, the ordinary portland cement slurries that the perfusion ratio of mud is 2:1, to 10 pulp of exhaust pipe Afterwards, the slurries ratio of mud is changed to 1:1;When slit width is less than 0.5mm, using the levigate portland cement slurries of the 0.6:1 ratio of mud.

Claims (7)

1. a kind of concrete dam abrupt slope foundation plane repeats surface grouting structure, it is characterised in that the grouting structure setting is in concrete Dam steep slope section, each steep slope section are divided into several irrigated areas (1) with vertical water flow direction, and each irrigated area (1) area is to be not more than 2000m2;Two sets of grout pipe (2) roads, two sets of grout pipe (2) roads, lower settings, every set grout pipe are arranged in each irrigated area (1) (2) road includes a grout pipe (2), and grout pipe (2) is in the U-tube being laterally arranged, which is single circuit design, bottom Nozzle is stock inlet (4), and upper orifice is overfall mouth;Grout pipe (2) is inside and outside double-layer structure, and inside is pvc pipe (5), PVC It is staggeredly equipped with slurry outlet (6) on pipe (5), is outside grout pipe (2) elastic gum sleeve (7), gum sleeve (7) is tight It is wrapped in pvc pipe (5) outer wall, is staggeredly equipped with diffusion hole (8) on gum sleeve (7), diffusion hole (8) position and slurry outlet (6) Position is staggered.
2. concrete dam abrupt slope as described in claim 1 foundation plane repeats surface grouting structure, it is characterised in that the filling Area (1) is additionally provided with group stop (9), exhaust pipe (10) and air discharge duct (11), and group stop (9) is arranged in irrigated area (1) inner wall, passes through Group stop (9) closes irrigated area (1) surrounding, group stop (9) top that air discharge duct (11) is arranged at the top of irrigated area (1), exhaust pipe (10) air discharge duct (11) setting is passed vertically through.
3. concrete dam abrupt slope as described in claim 1 foundation plane repeats surface grouting structure, it is characterised in that described is every Along the spacing about 3m of slope surface between grout pipe (2) road being arranged above and below in a irrigated area (1), each grout pipe (2) road is with φ's 6 Dowel is fixed on bedrock surface.
4. a kind of repeat the method that surface grouting structure carries out repeating surface grouting, feature using concrete dam abrupt slope foundation plane It is that specific step is as follows for the grouting method:
(1) it on designed concrete dam, selects foundation plane to excavate the gradient suddenly in the monolith of 1:0.7, is flowed to and divided with vertical water For several irrigated areas (1), each irrigated area (1) area is not more than 2000m2
(2) grout pipe (2) road of each irrigated area (1) uses pre-buried formation, is installed after grout pipe (2) is clean, simultaneously It is smooth to surface of bedrock progress, it cleans out;The overall slope of pipeline and attachment from overfall mouth to stock inlet (4) by about 5% is than paving If being strict with there is not allowed that counter-slope, meets free-draining effect;
(3) after dam concrete is in the milk, is completely covered, consolidating, grout pipe (2) road water flowing inspection, water flowing pressure is design grouting The 80% of pressure;
(4) after irrigated area (1) minimum a set of grout pipe (2) water flowing inspection is unimpeded, stock inlet (4) or overfall mouth is closed, water flowing is recorded Amount;After air discharge duct (11) return water, calculate contact surface water flowing total amount V, divided by irrigated area (1) design Division area A, calculate slit width w= V/A;The slit width that water flowing is calculated is compared and analyzed with the slit width measured by crack gauge, selects corresponding grouting on this basis The ratio of mud and material,
(5) surface grouting
1) when reaching surface grouting condition, using being in the milk from bottom to top;After when bottom, grouting reaches ending standard, carry out Portion's grouting, when top exhaust pipe (10) plasma discharge pressure reaches specified value, entire (1) 80% or more irrigated area grouting structure is carried out It can terminate irrigated area (1) cementing operations after grouting;
2) it is 0.6Mpa that the maximum grouting pressure of surface grouting, i.e. overfall mouth maximum, which control pressure,;In slurries by weight, water ash Than for 2:1,1:1 or 0.6:1, by it is dense to sorting be three than grade, selected according to the degree of coming to nothing or gap width;
3) when the pulp slurries of exhaust pipe (10) reach most dense than grade, and exhaust pipe (10) nozzle pressure reaches 0.2MPa, simultaneously Injection rate is not more than 0.4L/min, then persistently grouting 20min post-grouting terminates;
4) after being in the milk, grout pipe (2) road is cleaned with low pressure water immediately, cleaning uses vacuum tube by the cement in pipe Slurry is sucked out and is cleaned up grout pipe (2) with water, to prevent slurries residual between pvc pipe (5) and gum sleeve (7) from causing to solidify Blocking, then 2min is rinsed from inlet pipe direction to ensure the unobstructed of grout pipe (2) road, last closed protective is to re grouting;
5) surface grouting construction is completed and through after the assay was approved, grout pipe (2) is blocked closely knit using cement underflow.
5. repeating surface grouting structure using concrete dam abrupt slope foundation plane as claimed in claim 4 to carry out repeating surface grouting Method, it is characterised in that described grout pipe (2) the road water flowing inspection or water flowing measuring and calculating after, successively by lowest part grout pipe (2) It is constructed with beginning surface grouting in wind clean stitched seam and after pipe internal water accumulation, can be prepared.
6. repeating surface grouting structure using concrete dam abrupt slope foundation plane as claimed in claim 4 to carry out repeating surface grouting Method, it is characterised in that during the surface grouting, interrupt grouting more than 30min or when midge amount decrease beyond 50%, It is in the milk again after rinsing grout pipe (2) well with clear water and strong wind.
7. repeating surface grouting structure using concrete dam abrupt slope foundation plane as claimed in claim 4 to carry out repeating surface grouting Method, it is characterised in that in the step (4), slit width be greater than 1.0mm when, use the single ratio of mud for the common of 0.6:1 Portland cement grouting;When slit width is less than 1.0mm and is greater than 0.5mm, the ordinary portland cement that the perfusion ratio of mud is 2:1 is starched Liquid, after exhaust pipe (10) pulp, the slurries ratio of mud is changed to 1:1;When slit width is less than 0.5mm, using the levigate of the 0.6:1 ratio of mud Portland cement slurries.
CN201910623015.6A 2019-07-11 2019-07-11 Concrete dam abrupt slope foundation plane repeats surface grouting structure and its grouting method Pending CN110306555A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910623015.6A CN110306555A (en) 2019-07-11 2019-07-11 Concrete dam abrupt slope foundation plane repeats surface grouting structure and its grouting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910623015.6A CN110306555A (en) 2019-07-11 2019-07-11 Concrete dam abrupt slope foundation plane repeats surface grouting structure and its grouting method

Publications (1)

Publication Number Publication Date
CN110306555A true CN110306555A (en) 2019-10-08

Family

ID=68081005

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910623015.6A Pending CN110306555A (en) 2019-07-11 2019-07-11 Concrete dam abrupt slope foundation plane repeats surface grouting structure and its grouting method

Country Status (1)

Country Link
CN (1) CN110306555A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114439034A (en) * 2020-10-30 2022-05-06 中国电建集团华东勘测设计研究院有限公司 Reserved grouting hole construction method for foundation treatment of embedded large-scale vibration equipment
CN116427413A (en) * 2023-02-17 2023-07-14 中国电建集团西北勘测设计研究院有限公司 Grouting system and method for improving contact grouting effect

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11107253A (en) * 1997-09-30 1999-04-20 Hazama Gumi Ltd Execution of rim grouting
CN204098037U (en) * 2014-09-18 2015-01-14 黄河勘测规划设计有限公司 Contact grouting one-way check grout box
CN108532557A (en) * 2018-06-05 2018-09-14 中国电建集团贵阳勘测设计研究院有限公司 A kind of Arch Dam Abutment foundation plane surface grouting system method for arranging

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11107253A (en) * 1997-09-30 1999-04-20 Hazama Gumi Ltd Execution of rim grouting
CN204098037U (en) * 2014-09-18 2015-01-14 黄河勘测规划设计有限公司 Contact grouting one-way check grout box
CN108532557A (en) * 2018-06-05 2018-09-14 中国电建集团贵阳勘测设计研究院有限公司 A kind of Arch Dam Abutment foundation plane surface grouting system method for arranging

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
周秋实: "三里坪双曲拱坝接触、接缝灌浆施工工艺", 《人民长江》 *
屈章彬等: "FUKO 管在小浪底引水发电压力钢管接触灌浆中的应用", 《华北水利水电学院学报》 *
陈胜: "大坝接缝灌浆施工方法", 《技术与市场》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114439034A (en) * 2020-10-30 2022-05-06 中国电建集团华东勘测设计研究院有限公司 Reserved grouting hole construction method for foundation treatment of embedded large-scale vibration equipment
CN116427413A (en) * 2023-02-17 2023-07-14 中国电建集团西北勘测设计研究院有限公司 Grouting system and method for improving contact grouting effect
CN116427413B (en) * 2023-02-17 2024-01-12 中国电建集团西北勘测设计研究院有限公司 Grouting system and method for improving contact grouting effect

Similar Documents

Publication Publication Date Title
CN106702952B (en) A kind of earth and rockfill dam landslide observed seepage behavior simulation test device and method
CN103410119B (en) A kind of seepage inside concrete waterproof of man grouting method
CN106759066B (en) A kind of method of mountain area side slope water conservancy diversion energy dissipating prevention and control geological disaster
CN105887886A (en) Strong karst development stratum curtain grouting construction method
CN110306555A (en) Concrete dam abrupt slope foundation plane repeats surface grouting structure and its grouting method
CN112761174B (en) Grouting plugging method suitable for large karst cave under high-flow-rate flowing water condition
CN107152294A (en) High hydraulic pressure big flow Karst Tunnel underground water seal blocking method
CN107386309A (en) The prominent water burst method for blocking of the mine big flow high flow rate pipeline crack type karst that is recessed
CN209603096U (en) A kind of small-sized earth and rockfill dam calvert below dam plugging device
CN107014729A (en) A kind of adrainage material water flowing performance testing device and test method for considering silting condition
CN206385495U (en) A kind of earth and rockfill dam landslide observed seepage behavior simulation test device
CN211948590U (en) Anti pressure relief device that floats of basement bottom plate
CN106761914B (en) A kind of routed water water damage prevention and controls of shallow buried coal seam mine raceway groove flood
CN106801414A (en) Dyke and dyke construction method of a kind of band from discharge structure
CN105970882B (en) Solve the structure and its building method of face dam construction time dam body reverse osmosis water problems
CN110359424A (en) A kind of dam blocking method
CN206554064U (en) A kind of dyke of band from discharge structure
CN107044131A (en) A kind of anti-seepage method of deep covering layer
CN110725717A (en) Water plugging structure for ore body roadway
CN114703878A (en) Plugging and draining device for dewatering well and construction method
CN100489202C (en) Construction method for matched backwashing in filtering layer of water purification building
CN209669901U (en) Foundation pit and Tunnel Base spring pump drainage plugging device
CN110243691A (en) A kind of test macro and method of antiseepage composite geo-membrane
CN208594095U (en) A kind of wetland structure combined using wetland technology and rainwater storage
CN206693206U (en) A kind of Tailings Dam bottom storehouse row oozes system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191008