CN110298504A CN201910564756.1A CN201910564756A CN110298504A CN 110298504 A CN110298504 A CN 110298504A CN 201910564756 A CN201910564756 A CN 201910564756A CN 110298504 A CN110298504 A CN 110298504A
Authority
CN
China
Prior art keywords
flood control
warning
information
forecasting
system construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910564756.1A
Other languages
Chinese (zh)
Inventor
刘超
刘怀利
马浩
方婧
王铭铭
马顺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Province (ministry Of Water Resources Huaihe Water Conservancy Committee) Water Conservancy Science Research Institute (anhui Water Conservancy Project Quality Inspection Center Station)
Original Assignee
Anhui Province (ministry Of Water Resources Huaihe Water Conservancy Committee) Water Conservancy Science Research Institute (anhui Water Conservancy Project Quality Inspection Center Station)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Province (ministry Of Water Resources Huaihe Water Conservancy Committee) Water Conservancy Science Research Institute (anhui Water Conservancy Project Quality Inspection Center Station) filed Critical Anhui Province (ministry Of Water Resources Huaihe Water Conservancy Committee) Water Conservancy Science Research Institute (anhui Water Conservancy Project Quality Inspection Center Station)
Priority to CN201910564756.1A priority Critical patent/CN110298504A/en
Publication of CN110298504A publication Critical patent/CN110298504A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/10Services
    • G06Q50/26Government or public services
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/40Controlling or monitoring, e.g. of flood or hurricane; Forecasting, e.g. risk assessment or mapping

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Human Resources & Organizations (AREA)
  • Tourism & Hospitality (AREA)
  • Economics (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • Development Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Educational Administration (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Game Theory and Decision Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Alarm Systems (AREA)

Abstract

The present invention relates to a kind of rural basic level flood control forecasting and warning System Construction methods precisely to grasp flood control key area, scientific and reasonable laying automatic monitor station point by preventing and treating flood investigation, the evaluation analysis in area;Automatic monitoring data, especially rain hydrologic regime data and research and appraisal achievement realize automatic storage, and supervise to the quality of data;Early warning platform completes the comprehensive analysis of monitoring result and evaluation result, according to the forecasting model of setting, Early-warning Model, realizes base's flood control forecasting and warning.It in such a way that platform and the programme end that releases news interconnect automatically, is oriented to danger zone and pushes forecast, warning information, realize live intuitive, timely, Dynamic Display flood control information.

Description

A kind of rural basic level flood control forecasting and warning System Construction method
Technical field
The present invention relates to a kind of rural basic level flood control forecasting and warning System Construction methods, belong to flood control forecasting and warning technology neck Domain.
Background technique
It since the harm of flood is big, needs to carry out rural basic level flood control forecasting and warning System Construction, makes great efforts to promote base Layer flood control and ability of preventing and reducing natural disasters.Guarantee the science and validity of rural basic level flood control forecasting and warning System Construction, It must have a set of technical method of the processes such as investigation, evaluation, acquisition, analysis, comparison, shared, publication.Currently, base's flood control There has been no the optimization methods proposed for rural basic level flood control forecasting and warning System Construction, lead to forecasting and warning System Construction process In there is automatic monitor station point and lay the problems such as publication of unreasonable, warning information cannot intuitively show basic staff so that Base's flood control forecasting and warning System Construction is unable to reach desired effect.
Summary of the invention
The purpose of the present invention is to provide a kind of rural basic level flood control forecasting and warning System Construction method, this method can be mentioned The science and validity of high rural basic level flood control forecasting and warning publication, reduce harm of the flood to life, ensure people's life And property safety;Specific technical solution is as follows:
A kind of rural basic level flood control forecasting and warning System Construction method, comprising the following steps:
Step 1: precisely grasping flood control key area, science by the investigation, the evaluation analysis that prevent and treat flood area Reasonable Arrangement automatic monitor station point;
Step 2: automatic monitoring data, realizes automatic storage for rain hydrologic regime data and research and appraisal achievement, and to data matter Amount is supervised;
Step 3: early warning platform completes the comprehensive analysis of monitoring result and evaluation result, according to the flood forecasting mould of setting Type, flood warning scheduling model realize base's flood control forecasting and warning;
Step 4: orienting and pushing to danger zone in such a way that early warning platform and release information programme end interconnect automatically Live intuitive, timely, Dynamic Display flood control information is realized in forecast, warning information.
As above-mentioned technical proposal to advanced optimize, the automatic monitor station point is automatic monitor station, such as gaging station, rain Measure one of station, video station, image station or several.
As above-mentioned technical proposal to advanced optimize, the early warning platform can also carry out information management or information inquiry is made Industry, and carry out the overall sharing of the hydrology, meteorology, territory data information.
As above-mentioned technical proposal to advanced optimize, the release information programme end is base's programme platform, video council One of quotient, cell phone application, short message are several.
As above-mentioned technical proposal to advanced optimize, the early warning platform further includes electronic map;When early warning platform is sent out When cloth warning information, internal warning information is sent from trend relevant staff by SMS, simultaneity factor is electronically The automatic display warning information of figure simultaneously generates sound prompting.
Beneficial effects of the present invention:
By the rural basic level flood control forecasting and warning System Construction method, rural basic level flood control forecasting and warning can be improved The science and validity of publication reduce harm of the flood to life, ensure people's life and property safety.
Detailed description of the invention
Fig. 1 is the process step figure of rural basic level flood control forecasting and warning System Construction method of the present invention.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and It is not used in the restriction present invention.
As shown in Figure 1, the rural basic level flood control forecasting and warning System Construction method, comprising the following steps:
A. flood investigation, evaluation analysis are carried out to base's flood prevention and treatment area, by field exploring, and to flood control Flood control key area is precisely grasped in the calculating such as service management relevant rudimentary information, historical data, engineering design data analysis, and Automatic monitor station, such as the related monitoring device of gaging station, precipitation station, video station, image station, structure are arranged according to investigation achievement science Data transmission network is built, watermark protocol data is acquired, improves the quantity, quality and transmission speed of collection of water and rainfall regime information.
B. according to unified standard and require, automatic monitoring data, especially rain hydrologic regime data and research and appraisal achievement from Dynamic storage provides basic data support for rural basic level Flood Control Practice application query, consultation and decision etc., and to the quality of data into Row supervision.
C. the monitoring result of flood control forecasting and warning and evaluation result are carried out by comprehensive analysis by early warning platform, according to setting Flood Forecasting Model, flood warning scheduling model, realize base's flood control early warning it is accurate, timely automatically generate.Lead to simultaneously Information management/information inquiry can also be carried out by crossing early warning platform, realize the overall sharing of the data informations such as the hydrology, meteorology, territory, To expand base's flood control information resources amount.
D. pass through the side such as application, such as base's programme platform, television consultation, cell phone application, short message of new technology, new product Formula is inquired and is shown to base work of flood prevention person and policymaker, to grasp flood control information at any time.By being after early warning generation System sends internal warning information from trend relevant staff by SMS, and simultaneity factor shows early warning automatically on map Information generates sound prompting.System can also issue external early warning, by base's programme platform, television consultation, cell phone application, short The media such as letter issue transfer instruction.Mitigation is combated a natural disaster for the people, evades and reduces the loss of flood bring, provide more more The approach and channel of modernization.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (5)

1. a kind of rural basic level flood control forecasting and warning System Construction method, it is characterised in that the following steps are included:
Step 1: flood control key area is precisely grasped by the investigation, the evaluation analysis that prevent and treat flood area, it is scientific and reasonable Lay automatic monitor station point;
Step 2: automatic monitoring data, rain hydrologic regime data and research and appraisal achievement are realized into automatic storage, and to the quality of data into Row supervision;
Step 3: early warning platform completes the comprehensive analysis of monitoring result and evaluation result, according to the Flood Forecasting Model of setting, flood Water early warning scheduling model realizes base's flood control forecasting and warning;
Step 4: forecast in such a way that early warning platform and release information programme end interconnect automatically to danger zone orientation push, Warning information realizes live intuitive, timely, Dynamic Display flood control information.
2. a kind of rural basic level flood control forecasting and warning System Construction method according to claim 1, it is characterised in that: described Automatic monitor station point is automatic monitor station, such as one of gaging station, precipitation station, video station, image station or several.
3. a kind of rural basic level flood control forecasting and warning System Construction method according to claim 1, it is characterised in that: described Early warning platform can also carry out information management or information inquiry job, and carry out the hydrology, meteorology, territory data information it is comprehensive altogether It enjoys.
4. a kind of rural basic level flood control forecasting and warning System Construction method according to claim 1, it is characterised in that: described Release information programme end is one of base's programme platform, television consultation, cell phone application, short message or several.
5. a kind of rural basic level flood control forecasting and warning System Construction method according to claim 1, it is characterised in that: described Early warning platform further includes electronic map;When early warning platform issues warning information, by SMS from trend related work people Member sends internal warning information, and simultaneity factor shows warning information in electronic map automatically and generates sound prompting.
CN201910564756.1A 2019-06-27 2019-06-27 A kind of rural basic level flood control forecasting and warning System Construction method Pending CN110298504A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910564756.1A CN110298504A (en) 2019-06-27 2019-06-27 A kind of rural basic level flood control forecasting and warning System Construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910564756.1A CN110298504A (en) 2019-06-27 2019-06-27 A kind of rural basic level flood control forecasting and warning System Construction method

Publications (1)

Publication Number Publication Date
CN110298504A true CN110298504A (en) 2019-10-01

Family

ID=68029002

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910564756.1A Pending CN110298504A (en) 2019-06-27 2019-06-27 A kind of rural basic level flood control forecasting and warning System Construction method

Country Status (1)

Country Link
CN (1) CN110298504A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111583587A (en) * 2020-04-20 2020-08-25 成都万江港利科技股份有限公司 Small watershed prediction system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104103153A (en) * 2014-07-01 2014-10-15 济南展飞物联网科技有限公司 Flood prevention rainwater information automatic monitoring central system and monitoring method thereof
CN106530626A (en) * 2016-11-07 2017-03-22 孙晓彤 Mountain flood disaster monitoring and early warning system and monitoring method
CN107195164A (en) * 2017-07-03 2017-09-22 长江水利委员会长江科学院 Mountain flood on-line monitoring identification method for early warning and its early warning system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104103153A (en) * 2014-07-01 2014-10-15 济南展飞物联网科技有限公司 Flood prevention rainwater information automatic monitoring central system and monitoring method thereof
CN106530626A (en) * 2016-11-07 2017-03-22 孙晓彤 Mountain flood disaster monitoring and early warning system and monitoring method
CN107195164A (en) * 2017-07-03 2017-09-22 长江水利委员会长江科学院 Mountain flood on-line monitoring identification method for early warning and its early warning system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
路广平: "辽宁省农村基层防汛预报预警体系建设", 《中国水利》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111583587A (en) * 2020-04-20 2020-08-25 成都万江港利科技股份有限公司 Small watershed prediction system

Similar Documents

Publication Publication Date Title
CN103116825B (en) Intelligent city management
CN106557855A (en) A kind of smart travel passenger flow total management system
CN108931970A (en) A kind of industrial park wisdom environment supervisory systems based on cloud platform technology
CN110197443A (en) A kind of intelligent safety helmet risk management and control system
CN109283897A (en) A kind of wisdom power plant comprehensively monitoring center intelligent monitoring implementation method
CN107992786A (en) A kind of people streams in public places amount statistical method and system based on face
CN108830457A (en) Operation of power networks monitoring and control panorama management system based on artificial intelligence
CN106982262A (en) Operation platform is concentrated in a kind of Internet of Things sewage disposal
CN206451017U (en) A kind of wisdom direct drinking business cloud platform
CN204549076U (en) Garbage disposal monitored control system
CN105809326A (en) Smart hotel background MGX information management system
CN108470386A (en) A kind of cable run intelligent inspection system based on GPS and cloud platform
CN107016082A (en) A kind of contamination accident identification and processing method and system
CN113284024A (en) Intelligent emergency management system for intensive personnel place
CN113822446A (en) Intelligent garbage transfer system
CN106314482A (en) Centralized management and control system and method for railway natural disasters and foreign matter invasion
CN110298504A (en) A kind of rural basic level flood control forecasting and warning System Construction method
CN106845780A (en) A kind of generating set operating condition analysis system and its analysis method
CN109272254A (en) A kind of in line comprehensive monitor system of sewage zero
CN106405036A (en) Intelligent water environment monitoring service system
CN111914780A (en) Wisdom street management platform
CN206431621U (en) A kind of intelligence community system based on big data Joint construction and sharing
WO2020037929A1 (en) Method and device for community management and electronic apparatus
CN109284986A (en) A kind of Property Management System based on big data
CN106791636A (en) A kind of key population monitoring system and method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191001

RJ01 Rejection of invention patent application after publication