CN110295925A - Red beds sand shale serious deformation paragraph construction method - Google Patents

Red beds sand shale serious deformation paragraph construction method Download PDF

Info

Publication number
CN110295925A
CN110295925A CN201810232753.3A CN201810232753A CN110295925A CN 110295925 A CN110295925 A CN 110295925A CN 201810232753 A CN201810232753 A CN 201810232753A CN 110295925 A CN110295925 A CN 110295925A
Authority
CN
China
Prior art keywords
deformation
inverted arch
top bar
paragraph
horizontal displacement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810232753.3A
Other languages
Chinese (zh)
Inventor
米涛
李井元
胡安华
何万阳
伍志华
迟学新
伍春晖
傅军
申冯
赖航
吴慧林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Second Courtyard (chengdu) Construction And Development Co Ltd
CREEC Chengdu Survey Design and Research Co Ltd
Original Assignee
China Railway Second Courtyard (chengdu) Construction And Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Second Courtyard (chengdu) Construction And Development Co Ltd filed Critical China Railway Second Courtyard (chengdu) Construction And Development Co Ltd
Priority to CN201810232753.3A priority Critical patent/CN110295925A/en
Publication of CN110295925A publication Critical patent/CN110295925A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

Red beds sand shale serious deformation paragraph construction method reduces construction delay risk effectively to avoid constructing tunnel from large deformation and landslide occur, improves construction efficiency.Carry out the test of large deformation section according to monitoring measurement situation and construction section deformation, increase deformation allowance, it adjusts supporting parameter and reinforces preliminary bracing, excavated section ratio of rise to span is adjusted according to vault sinking, horizontal displacement and inverted arch deformation, determines large deformation paragraph excavated section.Ratio of rise to span is adjusted to about 0.5, when horizontal displacement be worth larger and vault sinking value relative horizontal displacement value it is smaller, without inverted arch deformation when, large deformation paragraph excavated section is determined as semicircle;When vault sinking, horizontal displacement, inverted arch protuberance value are larger, large deformation paragraph excavated section is determined as circle.

Description

Red beds sand shale serious deformation paragraph construction method
Technical field
The present invention relates to tunnels, in particular to especially relate to the red beds sand shale for passing through the western regions of the Yunnan Province mud stone burning into sand rock of Hengduan mountain range Serious deformation paragraph construction method.
Background technique
Southwestern China area Hengduan mountain range complex formation, structure development, the wherein road the Jurassic system Ba Zhu group mud stone of the Mesozoic group Burning into sand rock, aubergine, light violet magenta, part press from both sides canescence quartz, gypsum, argillaceous texture, thin layer columnar structure.Rock mass is smashed to pieces, Stability is very poor, and rock mass is in dust shape and earthy, and rock stratum face is smooth, because it is based on red, is commonly called as " red beds ", and thickness is from hundred Rice is to upper km etc..
" red beds " based on mud stone and packsand, it is particular in that: mud stone matter is soft, and weatherability is weak, meets water Easily intensity is substantially reduced after softening, chance water, and inter-layer bonding force weakens, bad stability.If opening " red beds " time is long, will Loss of stability, chip off-falling are collapsed seriously, and the accidents such as large deformation, landslide easily occur for tunnel excavation, or even cause shutdown accident.
As the planning of China's Trans-Asia railway and Yunnan Province's western regions railway is built, the special geology of Hengduan mountain range is passed through Red bed in Wwest Yunnan tunnel will gradually increase.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of red beds sand shale serious deformation paragraph construction method, with It effectively avoids constructing tunnel from large deformation and landslide occur, reduces construction delay risk, improve construction efficiency.
The technical solution adopted by the present invention to solve the technical problems is as follows:
Red beds sand shale serious deformation paragraph construction method of the invention, includes the following steps:
(1) test of large deformation section is carried out according to monitoring measurement situation and construction section deformation, increases deformation allowance, Adjust supporting parameter reinforce preliminary bracing, according to vault sinking, horizontal displacement and inverted arch deformation adjust excavated section arrow across Than determining large deformation paragraph excavated section;
(2) arch advance support is applied, as support system is excavated, increases deformation allowance to discharge surrouding rock stress, so Afterwards using mechanical partial excavation top bar arc leading pit arch, top bar arc leading pit left side and top bar arc leading pit right side Portion reserves top bar Core Soil portion, applies top bar preliminary bracing and top bar lock foot device;
(3) the interim inverted arch of top bar is arranged in mechanical excavation top bar Core Soil portion;
(4) prestress anchorage cable is applied along top bar preliminary bracing is circumferentially-spaced;
(5) faulting of slab ends mechanical excavation is got out of a predicament or an embarrassing situation left side, right side of getting out of a predicament or an embarrassing situation, and applies preliminary bracing of getting out of a predicament or an embarrassing situation;
(6) inverted arch portion is excavated, inverted arch preliminary bracing and inverted arch and short abutment wall reinforced concrete lining layer are applied;
(7) inverted arch fill concrete is applied;
(8) arch wall reinforced concrete lining layer is applied.
In the step (1), excavated section ratio of rise to span is adjusted to about 0.5;When horizontal displacement is worth larger and vault sinking value Relative horizontal displacement value is smaller, without inverted arch deformation when, large deformation paragraph excavated section is determined as semicircle;When vault sinking, water When prosposition moves, inverted arch protuberance value is larger, large deformation paragraph excavated section is determined as circle.
The invention has the advantages that carrying out test, adjustment according to monitoring measurement situation and paragraph deformation of having constructed Excavated section ratio of rise to span is increased deformation allowance to discharge surrouding rock stress, is dropped using mechanical excavation to improve preliminary bracing stress Low to disturb to weak red bed in Wwest Yunnan country rock, remaining core soil in advance reduces face landslide risk;Using bucket step plus interim inverted arch, Top bar applies the control of prestress anchorage cable bout length in 10m or so to reduce prestress anchorage cable process circulation time, seals in time Cyclization is closed, the timely stress of prestress anchorage cable is avoided because of Stress relieving of surrounding rocks, and horizontal stress surge causes preliminary bracing seriously to become Shape improves construction efficiency to reduce construction delay risk, safe and smooth to pass through red bed in Wwest Yunnan sand shale serious deformation section It falls.
Detailed description of the invention
This specification includes such as five width attached drawings:
Fig. 1 is excavated section ratio of rise to span schematic diagram in red beds sand shale serious deformation paragraph construction method of the present invention;
Fig. 2 is excavated section ratio of rise to span schematic diagram in red beds sand shale serious deformation paragraph construction method of the present invention;
Fig. 3 is to add interim inverted arch to be arranged using bucket step in red beds sand shale serious deformation paragraph construction method of the present invention The working procedure cross-sectional view of prestress anchorage cable;
Fig. 4 is to add interim inverted arch to be arranged using bucket step in red beds sand shale serious deformation paragraph construction method of the present invention The working procedure skiagraph of prestress anchorage cable;
Fig. 5 is to add interim inverted arch to be arranged using bucket step in red beds sand shale serious deformation paragraph construction method of the present invention The working procedure plan view of prestress anchorage cable;
Component, toponym and corresponding label be shown in figure: arch advance support 1, top bar arc leading pit arch 2a, Top bar arc leading pit left side 2b, top bar arc leading pit right side 2c, top bar preliminary bracing 3, top bar lock foot device 3a, top bar Core Soil portion 4, the interim inverted arch 5 of top bar, prestress anchorage cable 6, the left side 7a that gets out of a predicament or an embarrassing situation, the right side 7b that gets out of a predicament or an embarrassing situation, Get out of a predicament or an embarrassing situation preliminary bracing 8, inverted arch portion 9, inverted arch preliminary bracing 10, inverted arch and short abutment wall reinforced concrete lining layer 11, inverted arch filling Concrete 12, arch wall reinforced concrete lining layer 13.
Specific embodiment
Present invention will be further explained below with reference to the attached drawings and examples.
Referring to figs. 1 to Fig. 5, red beds sand shale serious deformation paragraph construction method of the invention includes the following steps:
(1) test of large deformation section is carried out according to monitoring measurement situation and construction section deformation, increases deformation allowance, Adjust supporting parameter reinforce preliminary bracing, according to vault sinking, horizontal displacement and inverted arch deformation adjust excavated section arrow across Than determining large deformation paragraph excavated section;
(2) arch advance support 1 is applied, as support system is excavated, increases deformation allowance to discharge surrouding rock stress, so Afterwards using mechanical partial excavation top bar arc leading pit arch 2a, top bar arc leading pit left side 2b and top bar arc leading pit Right side 2c reserves top bar Core Soil portion 4, applies top bar preliminary bracing 3 and top bar lock foot device 3a;
(3) the interim inverted arch 5 of top bar is arranged in mechanical excavation top bar Core Soil portion 4;
(4) prestress anchorage cable 6 is applied along top bar preliminary bracing 3 is circumferentially-spaced;
(9) faulting of slab ends mechanical excavation get out of a predicament or an embarrassing situation left side 7a, get out of a predicament or an embarrassing situation right side 7b, apply preliminary bracing 8 of getting out of a predicament or an embarrassing situation;
(10) inverted arch portion 9 is excavated, inverted arch preliminary bracing 10 and inverted arch and short abutment wall reinforced concrete lining layer 11 are applied;
(11) inverted arch fill concrete 12 is applied;
(12) arch wall reinforced concrete lining layer 13 is applied.
In the step (1), excavated section ratio of rise to span is adjusted to about 0.5;When horizontal displacement is worth larger and vault sinking value Relative horizontal displacement value is smaller, without inverted arch deformation when, large deformation paragraph excavated section is determined as semicircle;When vault sinking, water When prosposition moves, inverted arch protuberance value is larger, large deformation paragraph excavated section is determined as circle.
The present invention improves preliminary bracing stress by adjusting excavated section ratio of rise to span, increases arch advance support prearrangement of deformation amount Amount is reduced using mechanical excavation and is disturbed to weak red bed in Wwest Yunnan country rock to discharge surrouding rock stress, and remaining core soil in advance reduces area Face landslide risk.Using bucket step plus interim inverted arch, top bar applies the control of prestress anchorage cable bout length in 10m or so to subtract Few prestress anchorage cable process circulation time, closing cyclization, the timely stress of prestress anchorage cable are avoided because of Stress relieving of surrounding rocks in time, Horizontal stress surge causes preliminary bracing severely deformed, to reduce construction delay risk, improves construction efficiency, safe and smooth logical Cross red bed in Wwest Yunnan sand shale serious deformation paragraph.

Claims (2)

1. red beds sand shale serious deformation paragraph construction method, includes the following steps:
(1) test of large deformation section is carried out according to monitoring measurement situation and construction section deformation, increases deformation allowance, adjustment Supporting parameter reinforces preliminary bracing, adjusts excavated section ratio of rise to span according to vault sinking, horizontal displacement and inverted arch deformation, really Determine large deformation paragraph excavated section;
(2) arch advance support (1) is applied, as support system is excavated, increases deformation allowance to discharge surrouding rock stress, then It is led using mechanical partial excavation top bar arc leading pit arch (2a), top bar arc leading pit left side (2b) and top bar arc It cheats right side (2c), reserves top bar Core Soil portion (4), apply top bar preliminary bracing (3) and top bar lock foot device (3a);
(3) mechanical excavation top bar Core Soil portion (4) is arranged the interim inverted arch of top bar (5);
(4) prestress anchorage cable (6) are applied along top bar preliminary bracing (3) is circumferentially-spaced;
(5) faulting of slab ends mechanical excavation is got out of a predicament or an embarrassing situation left side (7a), right side of getting out of a predicament or an embarrassing situation (7b), applies preliminary bracing of getting out of a predicament or an embarrassing situation (8);
(6) inverted arch portion (9) are excavated, applies inverted arch preliminary bracing (10) and inverted arch and short abutment wall reinforced concrete lining layer (11);
(7) inverted arch fill concrete (12) are applied;
(8) arch wall reinforced concrete lining layer (13) are applied.
2. red beds sand shale serious deformation paragraph construction method as described in claim 1, it is characterized in that: the step (1) In, excavated section ratio of rise to span is adjusted to about 0.5;When horizontal displacement be worth larger and vault sinking value relative horizontal displacement value it is smaller, When no inverted arch deforms, large deformation paragraph excavated section is determined as semicircle;When vault sinking, horizontal displacement, inverted arch protuberance value are equal When larger, large deformation paragraph excavated section is determined as circle.
CN201810232753.3A 2018-03-21 2018-03-21 Red beds sand shale serious deformation paragraph construction method Pending CN110295925A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810232753.3A CN110295925A (en) 2018-03-21 2018-03-21 Red beds sand shale serious deformation paragraph construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810232753.3A CN110295925A (en) 2018-03-21 2018-03-21 Red beds sand shale serious deformation paragraph construction method

Publications (1)

Publication Number Publication Date
CN110295925A true CN110295925A (en) 2019-10-01

Family

ID=68025261

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810232753.3A Pending CN110295925A (en) 2018-03-21 2018-03-21 Red beds sand shale serious deformation paragraph construction method

Country Status (1)

Country Link
CN (1) CN110295925A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2020253001A1 (en) * 2019-06-19 2020-12-24 中铁十九局集团第六工程有限公司 Two-step fast closed tunnel support structure having inverted arch and construction method therefor

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005256389A (en) * 2004-03-11 2005-09-22 Kajima Corp Intermediate unit with excavating mechanism and method for assembling excavator
CN102926757A (en) * 2012-09-07 2013-02-13 中铁五局(集团)有限公司 Construction method of two-sidestep and four-step excavation support of weak large-span tunnel of mountain ridge
CN204609900U (en) * 2015-05-15 2015-09-02 河北腾是达金属结构有限公司 A kind of corrugated steel preliminary bracing structure being applicable to benching tunnelling method excavation
CN105201532A (en) * 2015-09-11 2015-12-30 中铁九局集团第二工程有限公司 Ring excavation construction method for underground large-span spherical-cap-shaped dome under weak surrounding rock
CN205638495U (en) * 2016-05-25 2016-10-12 中铁十六局集团北京轨道交通工程建设有限公司 I -shaped supporting construction suitable for construction of CRD worker's method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005256389A (en) * 2004-03-11 2005-09-22 Kajima Corp Intermediate unit with excavating mechanism and method for assembling excavator
CN102926757A (en) * 2012-09-07 2013-02-13 中铁五局(集团)有限公司 Construction method of two-sidestep and four-step excavation support of weak large-span tunnel of mountain ridge
CN204609900U (en) * 2015-05-15 2015-09-02 河北腾是达金属结构有限公司 A kind of corrugated steel preliminary bracing structure being applicable to benching tunnelling method excavation
CN105201532A (en) * 2015-09-11 2015-12-30 中铁九局集团第二工程有限公司 Ring excavation construction method for underground large-span spherical-cap-shaped dome under weak surrounding rock
CN205638495U (en) * 2016-05-25 2016-10-12 中铁十六局集团北京轨道交通工程建设有限公司 I -shaped supporting construction suitable for construction of CRD worker's method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
汪耀等: "鹧鸪山高地应力软岩隧道大变形预测与施工技术研究", 《路基工程》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2020253001A1 (en) * 2019-06-19 2020-12-24 中铁十九局集团第六工程有限公司 Two-step fast closed tunnel support structure having inverted arch and construction method therefor
JP2022500579A (en) * 2019-06-19 2022-01-04 中鉄十九局集団第六工程有限公司China Railway 19Th Bureau Group Sixth Engineering Co., Ltd. Support structure of two-stage high-speed closed tunnel with reverse arch and its construction method
JP7125550B2 (en) 2019-06-19 2022-08-24 中鉄十九局集団第六工程有限公司 SUPPORT STRUCTURE AND CONSTRUCTION METHOD FOR TWO-STAGE HIGH-SPEED CLOSING TUNNEL WITH INVERTED ARCH

Similar Documents

Publication Publication Date Title
Yu et al. Field investigations of high stress soft surrounding rocks and deformation control
CN105370290B (en) A kind of correcting and then reinforcing method of shield tunnel
CN106499405B (en) Tunnel lining structure
Yu et al. Study on subgrade settlement characteristics after widening project of highway built on weak foundation
CN108842840A (en) Perforating causes the weak intercalated layer slip-casting lifting method of building settlement under a kind of compensation subway tunnel
CN110617067B (en) Low-risk construction method for full-section boundary advanced pipe shed of extremely-soft surrounding rock tunnel
CN110685714B (en) Micro-step reserved core soil construction structure and method for shallow-buried bias tunnel under phyllite geology
Wu et al. Sand-layer collapse treatment: An engineering example from Qingdao Metro subway tunnel
CN206319886U (en) Tunnel lining structure
CN106988750A (en) The embodiment at existing station is worn under a kind of large span running tunnel super close distance
CN102817621B (en) Comprehensive construction method applicable to controlling arch basement sedimentation for tunnel in unfavorable geological conditions
CN113062354A (en) Assembly method for prefabricated subway station of open-cut pile support system
CN108643940A (en) Large section Shallow-Buried Soft Rock tunnel groined type double side wall support system and method for tunnel construction
CN108797620A (en) A kind of OPT construction method of interlocking pile
CN104989419A (en) Tunnel early-stage support clearance-intrusion processing method and construction ancillary equipment of tunnel early-stage support clearance-intrusion processing method
CN110295925A (en) Red beds sand shale serious deformation paragraph construction method
CN111502697A (en) Drilling design method for grouting and reinforcing surrounding rock of vault of tunnel under urban road
CN108374674B (en) Six pilot tunnels, 12 step Underground Space Excavation method for protecting support
CN110043271A (en) A kind of hole Shallow-buried section spaces union supporting construction and its construction method
CN109355992A (en) A kind of karst region is anti-to collapse road structure and construction method suddenly
CN104018474A (en) Method for reconstructing construction adit into maintenance adit by virtue of back-filling
CN209260468U (en) A kind of karst region is anti-to collapse road structure suddenly
CN208073484U (en) One kind passing through fine sand layer tunnel structure
CN112963119A (en) Induced splitting grouting reinforcement method suitable for silt silty soil stratum
CN206127758U (en) Moderate -low speed magnetic levitation traffic engineering double -line excavation location detached pier column type support rail roof beam transition section structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191001

RJ01 Rejection of invention patent application after publication