CN110284419A CN201910716577.5A CN201910716577A CN110284419A CN 110284419 A CN110284419 A CN 110284419A CN 201910716577 A CN201910716577 A CN 201910716577A CN 110284419 A CN110284419 A CN 110284419A
Authority
CN
China
Prior art keywords
bridge pier
bent cap
pile body
notch
dissipating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201910716577.5A
Other languages
Chinese (zh)
Inventor
张延年
徐向新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Jianzhu University
Original Assignee
Shenyang Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Jianzhu University filed Critical Shenyang Jianzhu University
Priority to CN201910716577.5A priority Critical patent/CN110284419A/en
Publication of CN110284419A publication Critical patent/CN110284419A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to a kind of energy-dissipating and shock-absorbing nodes of assembled bridge pier, belong to technical field of bridge engineering.It mainly include bent cap and bridge pier, bent cap is arranged in bridge pier upper end, and the bottom of the bent cap is provided with the components such as bent cap notch, fixture block, high strong spring, and the bridge pier is provided with the components such as viscid fluid damper, pile body.First bridge pier is placed and is fixed, crane lifting and substantially aligns bent cap, slowly land and simultaneously adjusted in time by the case where observation fixture block, after fall completely afterwards viscid fluid damper is hinged at both ends, complete to install.Bearing capacity of the present invention is higher, constructs more convenient, is conducive to shorten the construction period, and can effectively solve the problems such as colliding with caused by previous methods installation contraposition is inaccurate, when earthquake occurs can maximum damping, ensure the traffic capacity of bridge.

Description

The energy-dissipating and shock-absorbing node of assembled bridge pier
Technical field
The invention belongs to technical field of bridge engineering, and in particular to a kind of energy-dissipating and shock-absorbing node of assembled bridge pier.
Background technique
Currently, Bridges in Our Country substructure mainly uses cast in situs construction method.Often construction is all for cast in situs construction Phase is long, and labo r usage is big, and construction quality is not easy to guarantee, and has larger impact to surrounding enviroment.To overcome these adverse effects, fill It comes into being with formula bridge pier form.Compared with the cast-in-place bridge pier of tradition, assembled bridge pier have short construction period, environment influence it is small, The advantages such as construction quality height meet the industrialized demand for development of China's building structure.As urban modernization and economic high speed are sent out Exhibition, urban construction are also required to the step immediately following the epoch.When the cast-in-place Bridge Pier Construction of bridge construction often to surrounding enviroment generate compared with Big adverse effect, the environmental pollution including generating noise and dust etc., the low-carbon advocated with city, environmental protection development are not inconsistent.Therefore, In the development of the following bridge construction, packaged type bridges will increasingly be taken seriously.
For general assembled bridge pier, whole bridge pier segments all use prefabrication, and it is existing then to transport construction Carry out assembled, it is weaker that this whole segments are all that the structural system of splicing relative to cast-in-place bridge pier embodies hysteretic energy ability Characteristic, anti-seismic performance is relatively weak, is mainly used in assembled bridge pier at this stage and non-provides fortification against earthquakes area or low antidetonation is set The bridge structure in defence area, it would be highly desirable to develop a kind of good node of damping energy consumption effect.
Summary of the invention
In order to solve above-mentioned technical problem, the present invention provides a kind of energy-dissipating and shock-absorbing node of assembled bridge pier, main It is higher in order to develop a kind of bearing capacity, it constructs more convenient, is conducive to shorten the construction period, can effectively solve previous methods installation The problems such as colliding with caused by contraposition is inaccurate, when earthquake occurs can maximum damping, ensure the consumption of the traffic capacity of bridge It can damping node.
The technical solution adopted by the present invention is as follows
A kind of energy-dissipating and shock-absorbing node of assembled bridge pier, including bent cap, bridge pier;Bent cap is arranged in bridge pier upper end;
The material of the bent cap is concrete, and in the bottom of bent cap, there are two bent cap notches, the bent cap notch to be arranged for setting Position is the position that bridge pier is placed, and the shape of the bent cap notch is truncated cone-shaped, and the circular diameter close to bottom end is greater than close to upper end Diameter of a circle, in the outside of bent cap notch, level is opened up there are four extendable room, the arrangement of the extendable room with it is coplanar Interior horizontal line and vertical line is all disposed with a high strong spring in the inside of each extendable room at degree angle, described each A high strong spring all connects a fixture block, and the fixture block is a wedge block, and the wedge-shaped inclination angle of the fixture block end is that degree is extremely spent, In the outside of bent cap notch, be disposed with four pairs of pre-buried set squares of bent cap, there are hole among the pre-buried set square of bent cap, stay with Carried out with viscid fluid damper hinged, the innermost end of the bent cap notch is provided with rubber pad, the shape of the rubber pad with The circle size of the innermost end of bent cap notch is identical;
The material of the bridge pier is concrete, and the shape of the pile body of bridge pier is cylinder, in pile body close to the position on top, setting There is pile body to expand disk, the shape that the pile body expands disk is also circle, expands on disk in pile body, is provided with four pairs of bridge piers pre-buried three Gusset is stayed there are hole among the pre-buried set square of bridge pier to carry out hinged, the top of the pile body with viscid fluid damper End is provided with pile cover, and the pile cover is truncated cone-shaped, and size is identical as the size of bent cap notch.
Further, the pile body, which expands, is arranged reinforcing bar in disk.
Further, the line of the pre-buried set square of the bent cap and the pre-buried set square of bridge pier and horizontal angle are 30 degree To 45 degree.
Further, pass through welded connecting between the high strong spring and fixture block.
Further, installation method are as follows: first bridge pier is installed and fixed, bent cap is lifted by crane, aligns and decline, declines process Effects of Viscous Fluid Damper both ends are respectively hinged at bent cap pre-buried three after it falls surely by the flexible situation of middle observation fixture block, adjustment On gusset and the pre-buried set square of bridge pier, installation is completed.
Beneficial effects of the present invention
Effect and advantage of the invention is that bearing capacity is higher, construct it is more convenient, be conducive to shorten the construction period, can effectively solve with Toward method installation contraposition it is inaccurate caused by collide with the problems such as, when earthquake occurs can maximum damping, ensure the logical of bridge Row ability.
Detailed description of the invention
Fig. 1 is bridge pier main view of the invention;
Fig. 2 is bridge pier top view of the invention;
Fig. 3 is the bottom view of bent cap of the invention;
Fig. 4 is the structural schematic diagram before bridge pier and bent cap installation of the invention;
Fig. 5 is the structural schematic diagram after bridge pier and bent cap installation of the invention;
Fig. 6 is the structural schematic diagram after installing;
In figure, 1 is bent cap, and 2 be bridge pier, and 1-1 is extendable room, and 1-2 is high strong spring, and 1-3 is fixture block, and 1-4 is that bent cap is pre-buried Set square, 1-5 are bent cap notch, and 1-6 is rubber pad, and 2-1 is pile body, and 2-2 is that pile body expands disk, and 2-3 is pile cover, and 2-4 is bridge The pre-buried set square of pier, 2-5 are Effects of Viscous Fluid Damper.
Specific embodiment
In order to further illustrate the present invention, the present invention is described in detail with reference to the accompanying drawings and embodiments, but not They can be interpreted as limiting the scope of the present invention.
As shown in fig. 6, the present invention is mainly made of bent cap 1,2 component of bridge pier;Bent cap 1 is arranged in 2 upper end of bridge pier;
As shown in Figures 3 to 5, the material of the bent cap 1 is concrete, and in the bottom of bent cap 1, there are two bent cap notch 1- for setting 5, the position that the bent cap notch 5 is arranged is the position that bridge pier 2 is placed, and the shape of the bent cap notch 1-5 is truncated cone-shaped, close The circular diameter of bottom end is greater than the diameter of a circle close to upper end, and in the outside of bent cap notch 1-5, level is opened up there are four extendable room 1-1's, the extendable room 1-1 arranges with coplanar interior horizontal line and vertical line in angle of 45 degrees, in each extendable room The inside of 1-1, is all disposed with strong spring 1-2 one high, the fixture block of each described high strong spring 1-2 connection one 1-3, described High strong spring 1-2 and fixture block 1-3 between by be welded to connect, the fixture block 1-3 be a wedge block, the end the fixture block 1-3 The wedge-shaped inclination angle in portion is 30 degree to 45 degree, in the outside of bent cap notch 1-5, is disposed with the pre-buried set square 1-4 of four pairs of bent caps, described There are hole among the pre-buried set square 1-4 of bent cap, stay to carry out hinged, the bent cap notch 1-5 with viscid fluid damper 2-5 Innermost end be provided with rubber pad 1-6, the shape of the rubber pad 1-6 is identical as the circle size of innermost end of bent cap notch 1-5;
As shown in Figure 1 and Figure 2, the material of the bridge pier 2 is concrete, and the body shape of the bridge pier 2 is cylinder, in column Close to the position on top, it is provided with pile body and expands disk 2-1, the shape that the pile body expands disk 2-1 is also circle, is expanded in pile body On disk 2-1, be provided with the pre-buried set square 2-4 of four pairs of bridge piers, there are hole among the pre-buried set square 2-4 of bridge pier, stay with Viscid fluid damper 2-5 is carried out hingedly, and the top of the bridge pier 2 is provided with pile cover 2-3, and the pile cover 2-3 is truncated cone-shaped, Size is identical as the size of bent cap notch 1-5.The pile body, which expands in disk 2-1, is also provided with reinforcing bar.The pre-buried set square of bent cap The line of 1-4 and the pre-buried set square 2-4 of bridge pier and horizontal angle are about 30 degree to 45 degree.
As shown in Figure 4, Figure 5, its installation method of the invention are as follows: first bridge pier 2 is installed and fixed, lifts by crane bent cap 1, greatly It causes to align and decline, the flexible situation of fixture block 1-3 is observed during declining, is adjusted in time, after it falls surely, viscous fluid is hindered The both ends Buddhist nun device 2-5 are respectively hinged on the pre-buried set square 1-4 of bent cap and the pre-buried set square 2-4 of bridge pier, complete installation.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered It is considered as protection scope of the present invention.

Claims (5)

1. a kind of energy-dissipating and shock-absorbing node of assembled bridge pier, it is characterised in that: including bent cap (1), bridge pier (2), bent cap (1) setting In bridge pier (2) upper end;
The material of the bent cap (1) is concrete, and in the bottom of bent cap (1), there are two bent cap notch (1-5), the lids for setting The position of beam notch (5) setting is the position that bridge pier (2) are placed, and the shape of the bent cap notch (1-5) is truncated cone-shaped, the bottom of close to The circular diameter at end is greater than the diameter of a circle close to upper end, and in the outside of bent cap notch (1-5), level is opened up there are four extendable room (1-1), the arrangement of the extendable room (1-1) in angle of 45 degrees, are stretched with coplanar interior horizontal line and vertical line each The inside in space (1-1), is all disposed with one high strong spring (1-2), each described high strong spring (1-2) connects a card Block (1-3), the fixture block (1-3) they are a wedge block, and the wedge-shaped inclination angle of fixture block (1-3) end is 30 degree to 45 degree, The outside of bent cap notch (1-5), is disposed with four pairs of pre-buried set squares of bent cap (1-4), and the pre-buried set square of bent cap (1-4) is intermediate There are hole, stay to be carried out hingedly with viscid fluid damper (2-5), the innermost end of the bent cap notch (1-5) is provided with rubber The shape of rubber mat (1-6), the rubber pad (1-6) is identical as the circle size of innermost end of bent cap notch (1-5);
The material of the bridge pier (2) is concrete, and the shape of the pile body (2-1) of bridge pier (2) is cylinder, is leaned in pile body (2-1) The position on nearly top is provided with pile body and expands disk (2-2), and the shape that the pile body expands disk (2-2) is also circle, expands in pile body On deep bid (2-2), four pairs of pre-buried set squares of bridge pier (2-4) are provided with, the pre-buried set square of bridge pier (2-4) is intermediate, and there are holes Hole is stayed to carry out hingedly with viscid fluid damper (2-5), and the top of the pile body (2-1) is provided with pile cover (2-3), described Pile cover (2-3) is truncated cone-shaped, and size is identical as the size of bent cap notch (1-5).
2. a kind of energy-dissipating and shock-absorbing node of assembled bridge pier according to claim 1, it is characterised in that: the pile body expands Reinforcing bar is set in disk (2-1).
3. a kind of energy-dissipating and shock-absorbing node of assembled bridge pier according to claim 1, it is characterised in that: the bent cap is pre-buried The line of set square (1-4) and the pre-buried set square of bridge pier (2-4) and horizontal angle are 30 degree to 45 degree.
4. a kind of energy-dissipating and shock-absorbing node of assembled bridge pier according to claim 1, it is characterised in that: the high-strength bullet Pass through welded connecting between spring (1-2) and fixture block (1-3).
5. a kind of energy-dissipating and shock-absorbing node of assembled bridge pier according to claim 1, installation method are as follows: first by bridge pier (2) it installs and fixes, lifts by crane bent cap (1), align and decline, the flexible situation of fixture block (1-3) is observed during decline, adjust It is whole, after it falls surely, the both ends Effects of Viscous Fluid Damper (2-5) are respectively hinged at the pre-buried set square of bent cap (1-4) and bridge pier is pre- It buries on set square (2-4), completes installation.
CN201910716577.5A 2019-08-05 2019-08-05 The energy-dissipating and shock-absorbing node of assembled bridge pier Withdrawn CN110284419A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910716577.5A CN110284419A (en) 2019-08-05 2019-08-05 The energy-dissipating and shock-absorbing node of assembled bridge pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910716577.5A CN110284419A (en) 2019-08-05 2019-08-05 The energy-dissipating and shock-absorbing node of assembled bridge pier

Publications (1)

Publication Number Publication Date
CN110284419A true CN110284419A (en) 2019-09-27

Family

ID=68024824

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910716577.5A Withdrawn CN110284419A (en) 2019-08-05 2019-08-05 The energy-dissipating and shock-absorbing node of assembled bridge pier

Country Status (1)

Country Link
CN (1) CN110284419A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111676804A (en) * 2020-06-23 2020-09-18 中铁二院工程集团有限责任公司 Frame-type pier transverse anti-seismic structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111676804A (en) * 2020-06-23 2020-09-18 中铁二院工程集团有限责任公司 Frame-type pier transverse anti-seismic structure

Similar Documents

Publication Publication Date Title
CN105672517A (en) Swing self-reset and self-standing type high-rise structure
SK286842B6 (en) Method of protecting buildings and objects from dynamic forces caused by acceleration foundation plate, for instance due to earthquake and apparatus for making the same
CN105780640A (en) Resettable shape memory alloy (SMA) multidimensional vibration isolating support
CN110359365B (en) Assembled bridge seat of moving away to avoid possible earthquakes
CN209194766U (en) A kind of building isolation structure
CN203320395U (en) X-shaped metal shock-absorbing device applicable to bridge structures and with limiting capability
CN110424255A (en) A kind of antishock device on pier column
CN110258315A (en) Antidetonation bridge and its method of construction across active breaking belt
CN106284056A (en) Longspan Bridge elastoplasticity shock mitigation system
CN110284419A (en) The energy-dissipating and shock-absorbing node of assembled bridge pier
CN215210496U (en) Public road bridge roof beam shock attenuation buffering support
CN214530165U (en) Anti-seismic device for highway bridge
CN109083001B (en) Improved structure of stop block for slowly reducing earthquake action and construction method thereof
Gimenez et al. Md. Seismic isolation of bridges: devices, common practices in Japan, and examples of application
CN207672442U (en) A kind of road and bridge crack easy to use ruggedized construction
CN102535499A (en) Lift-off type seismic isolation and reduction pile foundation structure
CN210482044U (en) Self-anchored suspension bridge tower shock absorption structure
CN209509000U (en) Building elastic vibration isolation earthquake-proof foundation equipped with Overthrow preventing device
Skinner et al. Seismic isolation in New Zealand
CN103806372A (en) Segment high pier bridge seismic reduction and isolation structure using inhaul cable supports arranged on double layers
RU2406804C2 (en) Universal seismic-insulating foundation
CN211735018U (en) Energy dissipation and shock absorption node of assembled pier
CN109235683B (en) Tensile device and method for seismic isolation building
CN210507103U (en) Shock absorber with BRB and sliding device connected in series
CN109235247A (en) A kind of vibration isolation type bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20190927