CN110259485A - A kind of loess tunnel support system and its installation method - Google Patents

A kind of loess tunnel support system and its installation method Download PDF

Info

Publication number
CN110259485A
CN110259485A CN201910654860.XA CN201910654860A CN110259485A CN 110259485 A CN110259485 A CN 110259485A CN 201910654860 A CN201910654860 A CN 201910654860A CN 110259485 A CN110259485 A CN 110259485A
Authority
CN
China
Prior art keywords
arch
bracket
hollow pipe
haunch
composite structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910654860.XA
Other languages
Chinese (zh)
Other versions
CN110259485B (en
Inventor
谢永利
王志超
来弘鹏
张梦泽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changan University
Original Assignee
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan University filed Critical Changan University
Priority to CN201910654860.XA priority Critical patent/CN110259485B/en
Publication of CN110259485A publication Critical patent/CN110259485A/en
Application granted granted Critical
Publication of CN110259485B publication Critical patent/CN110259485B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • E21D11/183Supporting means for arch members, not provided for in E21D11/22

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of loess tunnel support system and its installation methods, support system includes several compact arranged composite structure arches, each composite structure arch includes wing plate and hollow pipe, and hollow pipe is mounted on the inside of wing plate, and pipe inner concrete is perfused in hollow pipe;Form concrete is perfused between adjacent composite structure arch;Composite structure arch is circumferentially divided into bow supporter, haunch bracket, arch springing bracket and arch lower supporter, each bracket and uses bayonet joint, be completely embedded seamless.Composite structure arch, pipe inner concrete and form concrete three parts collective effect, improve the bearing capacity of Tunnel.The support system combines the advantages of steel and concrete, and the two can effectively be made to be combined into one, and being formed has higher rigidity and high-intensitive composite structure, and concrete is at three dimension stress state due to the package by steel, is more advantageous to the performance of intensity.

Description

A kind of loess tunnel support system and its installation method
Technical field
The invention belongs to tunnel support structure technical field more particularly to a kind of loess tunnel support system and its installation sides Method.
Background technique
Common preliminary bracing structure type is shaped steel arch and gunite concrete to loess tunnel at this stage, but when supporting The problem of can not quickly being provided there are still supporting intensity deficiency, supporting intensity.Therefore, all occur in many loess tunnels at home Arch distortion, fracture, gunite concrete cracking, the case where landslide in surface subsidence, hole.
This problem is mainly reflected in: (1) design reasons.Deep, shallow embedding boundary depth defines unclear;Just branch, two lining loads Allocation proportion is difficult to clear;(2) construction reason.Construction is complicated, process is various, and the processes such as excavation, stand, gunite concrete exist It interferes with each other, can not carry out simultaneously, supporting construction intensity forms slower, it is difficult to accomplish " strong supporting ", " fast cyclization ".Meanwhile it applying Working medium amount is also difficult to ensure that bolt is difficult to whole connections between arch, and gunite concrete connect bad adhesion with arch, especially one A little bad geological sections, gunite concrete are difficult to complete, and also are difficult to be formed even if completing intensity.
Therefore, high-strength supporting construction is very necessary for the safe construction of loess tunnel, is especially in anxious in loess tunnel Acute deformation stage, early to limit its deformation quantity particularly important for the control of large deformation, and prevent surrouding rock stress state from disliking The key of change.
Summary of the invention
The purpose of the present invention is to provide a kind of loess tunnel support system and its installation methods, solve loess tunnel morning The problem of phase supporting intensity is insufficient, supporting intensity can not be provided quickly.
The present invention is to be achieved through the following technical solutions:
A kind of loess tunnel support system, including several compact arranged composite structure arches, each composite structure arch Frame includes wing plate and hollow pipe, and hollow pipe is mounted on the inside of wing plate, and pipe inner concrete is perfused in hollow pipe;Adjacent group It closes and is perfused with form concrete between structure arch;
Injected hole is preset on hollow pipe.
Further, composite structure arch is circumferentially divided into bow supporter, haunch bracket, arch springing bracket and arch lower supporter;
Bow supporter and arch lower supporter are oppositely arranged, and haunch bracket is symmetrically disposed on bow supporter both ends, arch springing bracket pair Title is set to arch lower supporter both ends, and haunch bracket one end is connect with bow supporter, and the other end is connect with one end of arch springing bracket, arch The other end of foot support is connect with arch lower supporter;
Bow supporter and haunch bracket, haunch bracket and arch springing bracket and arch springing bracket and arch lower supporter are all made of spigot-and-socket Connection.
Further, bow supporter includes vault wing plate and vault hollow pipe, and vault hollow pipe is fixed on the inside of vault wing plate;
Haunch bracket includes haunch wing plate and haunch hollow pipe, and haunch hollow pipe is fixed on the inside of haunch wing plate;
Arch springing bracket includes arch springing wing plate and arch springing hollow pipe, and arch springing hollow pipe is fixed on the inside of arch springing wing plate;
Encircleing lower supporter includes arch bottom wing plate and arch bottom hollow pipe, and arch bottom hollow pipe is fixed on the inside of arch bottom wing plate.
Further, vault hollow pipe and haunch hollow pipe, haunch hollow pipe and arch springing hollow pipe and arch springing hollow pipe and arch Bottom hollow pipe passes through tube faucet and connects with pipe socket circumferential direction.
Further, vault hollow pipe both ends use tube faucet;Haunch hollow pipe and arch springing hollow pipe one end use tube faucet, The other end uses pipe socket;Encircle bottom hollow pipe both ends and uses pipe socket.
Further, injected hole is preset on arch springing hollow pipe.
Further, gas vent is preset on vault wing plate.
Further, hollow pipe uses rectangular tube, rectangular tube or polygonal tube.
The invention also discloses the installation methods of the loess tunnel support system, comprising the following steps:
1) after the completion of soil excavation, by multiple composite structure arch close-packed arrays and chamber is installed on tunneling direction It is interior;
2) slip casting is carried out by injected hole, completes pouring for pipe inner concrete;
3) place template on the outside of every two adjacent hollow pipe, template and hollow tubular at space in coagulation is perfused Soil completes pouring for form concrete.
Further, composite structure arch is circumferentially divided into bow supporter, haunch bracket, arch springing bracket and arch lower supporter;
In step 1), the installation steps of composite structure arch specifically:
1.1) haunch bracket is installed in chamber two sides first, completes the installation of haunch bracket;
1.2) bow supporter is installed among two haunch brackets, the installation of bow supporter is completed on circumferential direction;
1.3) an arch springing bracket is connected in one end of each haunch bracket, the installation of arch springing bracket is completed on circumferential direction;
1.4) the installation arch lower supporter between two arch springing brackets, the installation of arch lower supporter is completed on circumferential direction, completes first The installation of a composite structure arch;
1.5) step 1.1)~1.4 are repeated), complete next composite structure arch.
Compared with prior art, the invention has the following beneficial technical effects:
A kind of loess tunnel support system disclosed by the invention, including composite structure arch, pipe inner concrete and mould build it is mixed Solidifying soil three parts, are closed using composite structure arch and excavate space, and the first floor supporting construction of support system is formed, and carrying, which is excavated, to be produced Raw country rock load, composite structure arch is as arch bearing bed;Hollow combination structure includes wing plate and hollow pipe, by sky Intrusion pipe inner concrete keeps hollow combination structure arch closely knit in heart pipe, forms concrete filled steel tube skeleton structure, undertakes timeliness change The country rock load of change, pipe inner concrete is as reinforcing carcass bearing bed;Space between each skeleton, mould are filled using form concrete Concrete is built as internal filling bearing bed, three bearing beds form complete preliminary bracing bearing bed.The support system combines The advantages of steel and concrete, both can effectively make to be combined into one, and being formed has higher rigidity and high-intensitive combination Structure, concrete are at three dimension stress state due to the package by steel, are more advantageous to the performance of intensity.Using mould The gap between the mode closed gantry of concrete is built, using the skeleton structure of the composite structure arch set up as template branch Frame forms it into the concrete layer of bigger thickness, and support rigidity is improved, also, the mode that mould is built is more advantageous to concrete Maintenance, guarantee the quality of concrete construction.
Further, tunnel excavation is partial excavation, and not tunneling boring is constructed, and composite structure arch is circumferentially divided into arch Ceiling hold, haunch bracket, arch springing bracket and arch four part of lower supporter, are connected using branch, can match tunnel after arch segmentation Construction method, meanwhile, segmentation also facilitates arch and is conveyed into hole.
Further, connection is completed by tube faucet and pipe socket between each bracket, does not need additional bolt and nut and carries out Connection, installation is easier, realizes the circumferential connection between bracket, guarantees the compactness of entire support system structure connection.
Further, injected hole is preset on arch springing hollow pipe, from bottom to up concrete perfusion, so that slip casting is more evenly.
Further, it is prefabricated with gas vent on vault wing plate, additional air in hollow pipe can be discharged in slip casting operation And dross, guarantee slip casting operation quality.
The invention also discloses the installation method of loess tunnel support system, first installation composite structure arch, combination knots After structure arch is set up, country rock can be closed immediately, can quickly propel face, quickly cyclization;In the case where guaranteeing safe enabled condition, The construction of concrete perfusion and form concrete is more flexible in managing, and it can be carried out simultaneously with the propulsion of face, accomplish respectively to apply The zero interference of work process.Composite structure arch can complete the closing to circumferential country rock after being installed, offer earlier is radial Stress makes country rock be in advantageous triaxial stress state, reduces the extension of plastic zone.It can be become according to practice of construction condition and country rock Shape situation is adjusted flexibly the time for injecting of steel pipe concrete filled and just lining concrete mould is built opportunity, improves construction efficiency.Combination Structure arch is installed the good section of rear supporting effect, and face can push ahead, the primary pipe completed in number cyclic advance Interior slip casting and just lining concrete mould build work, and simplified process flow accelerates construction progress.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of support system of the invention;
Fig. 2 is the structural schematic diagram of composite structure arch;
Fig. 3 is the structural schematic diagram of bow supporter;
Fig. 4 is the structural schematic diagram of haunch bracket;
Fig. 5 is the structural schematic diagram of arch springing bracket;
Fig. 6 is the structural schematic diagram for encircleing lower supporter;
Fig. 7 is support system construction technology floor map of the invention.
Wherein, 1 is pipe inner concrete, and 2 be form concrete, and 1-1 is bow supporter, and 1-2 is haunch bracket, and 1-3 is arch Foot support, 1-4 are arch lower supporter, and 3 be wing plate, and 3-1 is vault wing plate, and 3-2 is haunch wing plate, and 3-3 is arch springing wing plate, and 3-4 is Encircle bottom wing plate, 4 be hollow pipe, and 4-1 is vault hollow pipe, and 4-2 is haunch hollow pipe, and 4-3 is arch springing hollow pipe, and 4-4 is arch bottom Hollow pipe, 5 be tube faucet, and 6 be pipe socket, and 7 be gas vent, and 8 be injected hole.
Specific embodiment
Below with reference to specific embodiment, the present invention is described in further detail, it is described be explanation of the invention and It is not to limit.
As shown in Figure 1, a kind of loess tunnel support system of the invention, including composite structure arch, 1 and of pipe inner concrete 2 three parts of form concrete, composite structure arch is by wing plate 3 and hollow pipe 4 is prefabricated forms, and hollow pipe 4 is mounted in wing plate 3 Side is perfused with pipe inner concrete 1 in hollow pipe 4, is perfused with form concrete 2 between adjacent composite structure arch.
As shown in Fig. 2, composite structure arch is divided into bow supporter 1-1, haunch bracket 1-2, arch springing bracket 1-3 and arch bottom branch Frame 1-4, bow supporter 1-1 and arch lower supporter 1-4 are oppositely arranged, and haunch bracket 1-2 is symmetrically disposed on the both ends bow supporter 1-1, Arch springing bracket 1-3 is symmetrically disposed on the arch both ends lower supporter 1-4, and haunch one end bracket 1-2 is connect with bow supporter 1-1, the other end It is connect with one end of arch springing bracket 1-3, the other end of arch springing bracket 1-3 is connect with arch lower supporter 1-4;Bow supporter 1-1, haunch The circumferential connection of bracket 1-2, arch springing bracket 1-3 and arch lower supporter 1-4 are connected by tube faucet 5 with 6 socket joint of pipe socket.
As shown in figure 3, bow supporter 1-1 includes vault wing plate 3-1 and vault hollow pipe 4-1, the circumferential direction of bow supporter 1-1 Interconnecting piece uses tube faucet 5.There is prefabricated gas vent 7 at the top of bow supporter 1-1, is discharged in slip casting operation more in hollow pipe 4 Remaining air and dross guarantee slip casting operation quality.
As shown in figure 4, haunch bracket 1-2 includes haunch wing plate 3-2 and haunch hollow pipe 4-2, wherein haunch bracket 1-2 ring It is pipe socket 6 to connection top, lower part is tube faucet 5.
As shown in figure 5, arch springing bracket 1-3 includes arch springing wing plate 3-3 and arch springing hollow pipe 4-3, wherein arch springing bracket 1-3 ring It is pipe socket 6 to connection top, lower part is tube faucet 5.Arch springing bracket 1-3 side surface part has prefabricated injected hole 8, after closing cyclization Slip casting operation is carried out by injected hole 8, pipe inner concrete 1 is completed and pours.
As shown in fig. 6, arch lower supporter 1-4 includes arch bottom wing plate 3-4 and arch bottom hollow pipe 4-4, encircle the circumferential direction of lower supporter 1-4 Interconnecting piece is all made of pipe socket 6.
Bow supporter 1-1 is also possible to both ends and uses 6 structure of pipe socket, and the arch both ends lower supporter 1-4 use 5 knot of tube faucet Structure;Or four portion support be all one end using 5 structure of tube faucet, the other end uses 6 structure of pipe socket.As long as by adjacent two Portion support links together.
More preferably, rectangular tube, rectangular tube or polygonal tube can be used in hollow pipe 4.
The construction technology of composite structure support system specifically:
1) after the completion of soil excavation, by multiple composite structure arch close-packed arrays and chamber is installed on tunneling direction It is interior;
When for benching tunnelling method construction, the specific installation process of composite structure arch are as follows:
1.1) haunch bracket 1-2 is installed in chamber two sides first, completes the installation of haunch bracket 1-2;
1.2) bow supporter 1-1 is placed between two haunch bracket 1-2, by bow supporter 1-1 and haunch branch on circumferential direction Frame 1-2 is aligned with pipe socket 6 by tube faucet 5 and is fixedly connected, and the installation of bow supporter 1-1 is completed;
1.3) an arch springing bracket 1-3 is connected in one end of each haunch bracket 1-2, by haunch bracket 1-2 on circumferential direction It is aligned and is fixedly connected with pipe socket 6 by tube faucet 5 with arch springing bracket 1-3, complete the installation of arch springing bracket 1-3;
1.4) arch lower supporter 1-4 is placed between two arch springing bracket 1-3, by arch springing bracket 1-3 and arch bottom branch on circumferential direction Frame 1-4 is aligned with pipe socket 6 by tube faucet 5 and is fixedly connected, and the installation of arch lower supporter 1-4 is completed, and so far completes first group Close the installation of structure arch;
1.5) step 1.1)~1.4 are repeated), complete next composite structure arch.It is adjacent bow supporter 1-1, adjacent Haunch bracket 1-2, adjacent arch springing bracket 1-3 and adjacent arch lower supporter 1-4 be in the longitudinal direction only tight on tunneling direction It gets together, not additional connection structure, along tunneling direction, multiple composite structure arches is successively installed.
2) after composite structure arch closing cyclization, carry out slip casting operation from injected hole 8, until in gas vent 7 without air and Dross overflows, and completes pouring for pipe inner concrete 1.
3) after completing composite structure arch and 1 operation of pipe inner concrete, mould is placed on the outside of every two adjacent hollow pipe 4 Plate, the concrete perfusion in the space that template and hollow pipe 4 are formed, completes 2 operation of form concrete, encircles it with composite structure Composite structure support system is collectively formed in frame and pipe inner concrete 1.
4) it is laid with splash guard in 2 inner surface of form concrete, and applies secondary lining in time.Preliminary bracing surfacing, Convenient-laying waterproof layer makes integral waterproofing effect promoting.
Support system of the invention has the advantage that
(1) increase support rigidity and intensity: be on the one hand embodied in steel-concrete combined structure have stronger resistance to compression, anti-torsion, Bending resistance;On the other hand bigger thickness can be accomplished by being embodied in form concrete layer, overcome gunite concrete linked network The limitation of thickness and the big problem of springback capacity.
(2) change the rigidity ratio of preliminary bracing, secondary lining: using preliminary bracing as the arrying main body of loess tunnel, Improve loess surrouding rock stress condition by the preliminary bracing of " high-strength, early strong ".
(3) the offer supporting intensity of timesharing branch: on the basis of hollow arch quick closure country rock, by being perfused in pipe Concrete, form concrete are to adapt to loess pressure from surrounding rock gradual change propagation process.
(4) improve arch frame structure stability: skeleton structure use concrete filled steel tube, cross sectional shape be rectangle, it is rectangular or The inhomogeneities of polygon, strong and weak axis bending stiffness substantially reduces, and compares more original shaped steel arch, and Outside-plate stabilizing performance is able to It is promoted.
(5) biggish supporting intensity can be provided immediately after the stand of composite structure arch, and due to composite structure arch and Form concrete layer changes the rigidity ratio of just branch and two linings, can provide biggish supporting earlier as preliminary bracing Counter-force plays positive effect for the generation of the extension of limitation plastic zone of surrounding rock, reduction loose load.It is dependent on this, it can be to two The thickness of secondary lining cutting suitably reduces, to guarantee constant excavated section and controllable construction cost.

Claims (10)

1. a kind of loess tunnel support system, which is characterized in that including several compact arranged composite structure arches, each group Closing structure arch includes wing plate (3) and hollow pipe (4), and hollow pipe (4) is mounted on the inside of wing plate (3), is filled in hollow pipe (4) It is marked with pipe inner concrete (1);Form concrete (2) are perfused between adjacent composite structure arch;
Injected hole (8) are preset on hollow pipe (4).
2. loess tunnel support system according to claim 1, which is characterized in that composite structure arch is circumferentially divided into arch Ceiling hold (1-1), haunch bracket (1-2), arch springing bracket (1-3) and arch lower supporter (1-4);
Bow supporter (1-1) and arch lower supporter (1-4) are oppositely arranged, and haunch bracket (1-2) is symmetrically disposed on bow supporter (1-1) Both ends, arch springing bracket (1-3) are symmetrically disposed on arch both ends lower supporter (1-4), haunch bracket one end (1-2) and bow supporter (1- 1) it connects, the other end is connect with the one end of arch springing bracket (1-3), and the other end and arch lower supporter (1-4) of arch springing bracket (1-3) are even It connects;
Bow supporter (1-1) and haunch bracket (1-2), haunch bracket (1-2) and arch springing bracket (1-3) and arch springing bracket (1-3) Bayonet joint is all made of with arch lower supporter (1-4).
3. loess tunnel support system according to claim 2, which is characterized in that bow supporter (1-1) includes the vault wing Plate (3-1) and vault hollow pipe (4-1), vault hollow pipe (4-1) are fixed on the inside of vault wing plate (3-1);
Haunch bracket (1-2) includes haunch wing plate (3-2) and haunch hollow pipe (4-2), and haunch hollow pipe (4-2) is fixed on haunch On the inside of wing plate (3-2);
Arch springing bracket (1-3) includes arch springing wing plate (3-3) and arch springing hollow pipe (4-3), and arch springing hollow pipe (4-3) is fixed on arch springing On the inside of wing plate (3-3);
Encircleing lower supporter (1-4) includes arch bottom wing plate (3-4) and arch bottom hollow pipe (4-4), and arch bottom hollow pipe (4-4) is fixed on arch bottom On the inside of wing plate (3-4).
4. loess tunnel support system according to claim 3, which is characterized in that vault hollow pipe (4-1) and haunch are empty Heart pipe (4-2), haunch hollow pipe (4-2) and arch springing hollow pipe (4-3) and arch springing hollow pipe (4-3) and arch bottom hollow pipe (4-4) Pass through tube faucet (5) and the circumferential connection of pipe socket (6).
5. loess tunnel support system according to claim 4, which is characterized in that the vault hollow pipe both ends (4-1) use Tube faucet (5);Haunch hollow pipe (4-2) and arch springing hollow pipe one end (4-3) use tube faucet (5), and the other end uses pipe socket (6);Encircle the bottom hollow pipe both ends (4-4) and uses pipe socket (6).
6. loess tunnel support system according to claim 2, which is characterized in that it is hollow that injected hole (8) is preset in arch springing It manages on (4-3).
7. loess tunnel support system according to claim 2, which is characterized in that be preset on vault wing plate (3-1) Gas vent (7).
8. loess tunnel support system according to claim 1, which is characterized in that hollow pipe (4) is using rectangular tube, rectangular Pipe or polygonal tube.
9. the installation method of loess tunnel support system described in claim 1~8 any one, which is characterized in that including following Step:
1) it after the completion of soil excavation, by multiple composite structure arch close-packed arrays and is installed in chamber on tunneling direction;
2) slip casting is carried out by injected hole (8), completes pouring for pipe inner concrete (1);
3) template is placed on the outside of every two adjacent hollow pipe (4), perfusion is mixed in the space that template and hollow pipe (4) are formed Solidifying soil, completes pouring for form concrete (2).
10. the installation method of loess tunnel support system according to claim 9, which is characterized in that composite structure arch Circumferentially it is divided into bow supporter (1-1), haunch bracket (1-2), arch springing bracket (1-3) and arch lower supporter (1-4);
In step 1), the installation steps of composite structure arch specifically:
1.1) haunch bracket (1-2) is installed in chamber two sides first, completes the installation of haunch bracket (1-2);
1.2) bow supporter (1-1) is installed among two haunch brackets (1-2), the peace of bow supporter (1-1) is completed on circumferential direction Dress;
1.3) an arch springing bracket (1-3) is connected in one end of each haunch bracket (1-2), arch springing bracket is completed on circumferential direction The installation of (1-3);
1.4) installation arch lower supporter (1-4) between two arch springing brackets (1-3), completes the peace of arch lower supporter (1-4) on circumferential direction Dress, completes the installation of first composite structure arch;
1.5) step 1.1)~1.4 are repeated), complete next composite structure arch.
CN201910654860.XA 2019-07-19 2019-07-19 Loess tunnel support system and installation method thereof Active CN110259485B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910654860.XA CN110259485B (en) 2019-07-19 2019-07-19 Loess tunnel support system and installation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910654860.XA CN110259485B (en) 2019-07-19 2019-07-19 Loess tunnel support system and installation method thereof

Publications (2)

Publication Number Publication Date
CN110259485A true CN110259485A (en) 2019-09-20
CN110259485B CN110259485B (en) 2024-06-25

Family

ID=67927299

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910654860.XA Active CN110259485B (en) 2019-07-19 2019-07-19 Loess tunnel support system and installation method thereof

Country Status (1)

Country Link
CN (1) CN110259485B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111022084A (en) * 2019-11-19 2020-04-17 长安大学 Large-section loess tunnel excavation primary support arch frame single truss and method
CN111219200A (en) * 2020-03-18 2020-06-02 长安大学 Buckling-restrained assembled tunnel combined structure supporting system and construction method thereof
CN112832825A (en) * 2021-01-19 2021-05-25 华北理工大学 Assembled hollow sandwich concrete filled steel tube arch center and construction method thereof
CN112832817A (en) * 2021-01-27 2021-05-25 兖州中材建设有限公司 Underground chamber ore bin supporting structure and construction process thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205206838U (en) * 2015-12-17 2016-05-04 长安大学 Collapsible loess tunnel supporting construction
CN205503146U (en) * 2016-04-11 2016-08-24 长安大学 Novel supporting construction of shallow tunnel suitable for city sensitizing range
CN205532619U (en) * 2016-04-19 2016-08-31 长安大学 Loess tunnel support system
US20180291736A1 (en) * 2016-07-08 2018-10-11 Shandong University High-strength confined concrete support system for underground tunnel
CN108798722A (en) * 2018-06-04 2018-11-13 郑州工程技术学院 A kind of roadway support concrete steel pipe support frame device and method for supporting
CN108915727A (en) * 2018-06-27 2018-11-30 昆明理工大学 It is a kind of using concrete filled steel tube as the tunnel lining structure of skeleton and slding form operation method
WO2019056794A1 (en) * 2017-09-20 2019-03-28 中铁十四局集团有限公司 Method for constructing cavity behind tunnel lining, and composite lining structure formed after construction
CN210217774U (en) * 2019-07-19 2020-03-31 长安大学 Loess tunnel supporting system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205206838U (en) * 2015-12-17 2016-05-04 长安大学 Collapsible loess tunnel supporting construction
CN205503146U (en) * 2016-04-11 2016-08-24 长安大学 Novel supporting construction of shallow tunnel suitable for city sensitizing range
CN205532619U (en) * 2016-04-19 2016-08-31 长安大学 Loess tunnel support system
US20180291736A1 (en) * 2016-07-08 2018-10-11 Shandong University High-strength confined concrete support system for underground tunnel
WO2019056794A1 (en) * 2017-09-20 2019-03-28 中铁十四局集团有限公司 Method for constructing cavity behind tunnel lining, and composite lining structure formed after construction
CN108798722A (en) * 2018-06-04 2018-11-13 郑州工程技术学院 A kind of roadway support concrete steel pipe support frame device and method for supporting
CN108915727A (en) * 2018-06-27 2018-11-30 昆明理工大学 It is a kind of using concrete filled steel tube as the tunnel lining structure of skeleton and slding form operation method
CN210217774U (en) * 2019-07-19 2020-03-31 长安大学 Loess tunnel supporting system

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111022084A (en) * 2019-11-19 2020-04-17 长安大学 Large-section loess tunnel excavation primary support arch frame single truss and method
CN111022084B (en) * 2019-11-19 2024-04-26 长安大学 Single arch truss of primary support for excavating large-section loess tunnel and method
CN111219200A (en) * 2020-03-18 2020-06-02 长安大学 Buckling-restrained assembled tunnel combined structure supporting system and construction method thereof
CN111219200B (en) * 2020-03-18 2024-04-26 长安大学 Buckling-restrained assembled tunnel combined structure supporting system and construction method thereof
CN112832825A (en) * 2021-01-19 2021-05-25 华北理工大学 Assembled hollow sandwich concrete filled steel tube arch center and construction method thereof
CN112832825B (en) * 2021-01-19 2022-04-12 华北理工大学 Assembled hollow sandwich concrete filled steel tube arch center and construction method thereof
CN112832817A (en) * 2021-01-27 2021-05-25 兖州中材建设有限公司 Underground chamber ore bin supporting structure and construction process thereof

Also Published As

Publication number Publication date
CN110259485B (en) 2024-06-25

Similar Documents

Publication Publication Date Title
CN110259485A (en) A kind of loess tunnel support system and its installation method
CN104863614B (en) Method for primary support with corrugated steel plate and concrete combined structure taking place of steel grating
CN104818991B (en) A kind of construction method in Shallow-buried residual soil slope tunnel
CN106337686B (en) Three layers of subway station canopy structure of rocky stratum tunneling and construction method
CN104405399B (en) One kind passes through drift sand stratum tunnel excavation support body engineering method
CN102953739B (en) Bidirectional punching method for underground excavation of subway station
CN106351670B (en) A kind of closed pre support tunnel structure
CN106761778B (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN106930777B (en) The construction method that Bored Section of Metro main track assembled two serves as a contrast
CN107100653A (en) A kind of flat top wall pipe curtain structure builds the construction method of super Shallow Covered Metro Station
CN105781574A (en) Fabricated tunnel support system and construction method thereof
CN205503146U (en) Novel supporting construction of shallow tunnel suitable for city sensitizing range
CN102226399A (en) Soft rock four-line large-span tunnel three-bench cable-bracing excavation construction method
CN108868778A (en) A kind of Large Underground Structure no-dig technique construction method
CN104405411B (en) Oversized variable cross section tunnel supporting structure
CN211038657U (en) Cover encircles based deeply buries loess tunnel deformation control construction structures
CN110318776A (en) Method for tunnel construction based on inverted arch and inverted arch filled layer substitution steel-concrete combined structure
CN103256060A (en) Moisture rich and weak mylonite large section tunnel surrounding rock consolidation and excavation method
CN107044288A (en) Prefabricated support lining structure and construction method for large-deformation tunnel in soft rock
CN103670446B (en) Circular diversion tunnel 2/3 circle concrete-liner construction method
CN106894830B (en) A kind of double curvature arch supporting construction and construction method for underground engineering
CN110005435A (en) A kind of construction technology of tunnel trunk preliminary bracing
CN107806349A (en) A kind of steel FRP complex waves card tunnel secondary liner structure and its apply method
CN108561156A (en) Separate tunnel changes arch supporting construction and its construction method
CN205532619U (en) Loess tunnel support system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant