CN110258563A - A kind of pinpoint device of foot-operated drill rod drilling pile point, production method and application method - Google Patents
A kind of pinpoint device of foot-operated drill rod drilling pile point, production method and application method Download PDFInfo
- Publication number
- CN110258563A CN110258563A CN201910637600.1A CN201910637600A CN110258563A CN 110258563 A CN110258563 A CN 110258563A CN 201910637600 A CN201910637600 A CN 201910637600A CN 110258563 A CN110258563 A CN 110258563A
- Authority
- CN
- China
- Prior art keywords
- filling
- pricker
- pricker body
- cylinder
- drill rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000005553 drilling Methods 0.000 title claims abstract description 21
- 238000000034 method Methods 0.000 title claims abstract description 12
- 238000004519 manufacturing process Methods 0.000 title claims abstract description 11
- 239000002689 soil Substances 0.000 claims abstract description 21
- 235000008733 Citrus aurantifolia Nutrition 0.000 claims abstract description 12
- 235000011941 Tilia x europaea Nutrition 0.000 claims abstract description 12
- 239000004571 lime Substances 0.000 claims abstract description 12
- 229910000831 Steel Inorganic materials 0.000 claims description 19
- 239000010959 steel Substances 0.000 claims description 19
- 230000003014 reinforcing effect Effects 0.000 claims description 7
- 239000000284 extract Substances 0.000 claims description 6
- 239000003292 glue Substances 0.000 claims description 3
- 238000005498 polishing Methods 0.000 claims description 3
- 238000000605 extraction Methods 0.000 claims description 2
- 238000010276 construction Methods 0.000 description 8
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 6
- 239000004744 fabric Substances 0.000 description 3
- 229910052742 iron Inorganic materials 0.000 description 3
- 241001536352 Fraxinus americana Species 0.000 description 1
- 208000027418 Wounds and injury Diseases 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 230000006378 damage Effects 0.000 description 1
- 208000014674 injury Diseases 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000010412 perfusion Effects 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 230000001360 synchronised effect Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D13/00—Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02F—DREDGING; SOIL-SHIFTING
- E02F5/00—Dredgers or soil-shifting machines for special purposes
- E02F5/16—Machines for digging other holes in the soil
- E02F5/20—Machines for digging other holes in the soil for vertical holes
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The present invention provides a kind of pinpoint device of foot-operated drill rod drilling pile point, production method and application method, device includes drill rod, fills grey cylinder and funnel, the drill rod includes pricker body, bore bit, pedal and level, the bore bit is located at pricker body lower end and is conical, the pedal is located at pricker body lower part, and the level is located at the top of pricker body;The grey cylinder of the filling includes hollow stack shell and the filling ash cylinder handle above stack shell, and the stack shell is set in the pricker and the stack shell inner wall is bonded the pricker body outer wall, and the barrel length is less than the bore bit to the distance of the pedal;Funnel lower end outer diameter is less than the barrel diameter, and lime can be filled into soil to 20cm to 50cm, rather than be only sprinkling upon native surface, the anchor point cover type of label will be closed on when operation around, overburden soil can be rooted out, slightly label point can be exposed by rooting out some soil more, and eyelet is small, it is few to fill ash, accurate positioning, is not easy sideslip, easily looks for and sees original anchor point, it is time saving and energy saving, it is convenient and efficient.
Description
Technical field
The invention belongs to technical field of building construction, step on the pinpoint dress of drill rod drilling pile point more particularly, to one kind
It sets.
Background technique
Nowadays construction pile foundation engineering is widely used to technical field of construction, stake point location is pile foundation engineering construction
Primary step beat, whether stake heart position deviation, the construction quality of pile foundation engineering will be directly affected.The side of traditional stake point location
Method is lime directly to be sprinkled on this position, or insert after finding a heart position accurately with total station or other instruments, steel ruler etc.
Enter the objects such as the attached red cloth of reinforcing bar, timber, iron nail, with the position of this marking pile heart.There are the easy sideslips in stake heart position for such method, or
Mud or soil covering close on marked point when bore operation, bring inconvenience to construction:
It is big to spread lime range, mark position deviation is larger, easily causes pile position deviation beyond regulating scope.
The objects such as reinforcing bar are inserted into, be easy to cause reinforcing bar to deviate when squeezing surrounding soil, and cause personnel, machine-walking not
Just, pedestrian is easily tripped, injury to personnel is caused.When machine, which positions, prepares drilling, also needs to extract reinforcing bar, easily cause pile position deviation
Greatly.
Using timber positioning since timber intensity is low, construction site is easy to be destroyed by vehicle etc., and using timber existing
Field cannot start apparent mark.Using the method for the attached red cloth of iron nail, although apparent mark can be played the role of using red cloth,
Iron nail is insecure, is easy to happen offset, and it is lower to bury native depth, is easily destroyed.
When two neighbor distances are closer, the stake of first pore-forming easily covers the marked good stake of surrounding after soil or mud outflow
Point position, causes resetting, labor intensive, material resources.
Summary of the invention
The present invention has made improvements in view of the above-mentioned problems of the prior art, i.e., the present invention provides a kind of foot-operated drill rod pore-forming
Pinpoint device is put in stake, and the present apparatus is easy to operate, production, convenient for disassembly and assembly, raising construction efficiency, saving cost of labor, dress
Set versatile, stake point is not easy to be destroyed.
In order to solve the above technical problem, the present invention provides a kind of pinpoint device of foot-operated drill rod drilling pile point, packets
It includes drill rod, fill grey cylinder and funnel, wherein
The drill rod includes pricker body, bore bit, pedal and level, and the bore bit is located at pricker body lower end and to be conical, institute
It states pedal and is located at pricker body lower part, the level is located at the top of pricker body;
The grey cylinder of the filling includes hollow stack shell and the filling ash cylinder handle above stack shell, and the stack shell is set in described
With pricker and the stack shell inner wall is bonded the pricker body outer wall, the barrel length be less than the bore bit to the pedal away from
From;
Funnel lower end outer diameter is less than the barrel diameter.
Preferably, the pricker body is equipped with handle.
Preferably, the length of the stack shell is 20cm to 50cm.
The present invention also announces a kind of production method for making a kind of pinpoint device of foot-operated drill rod drilling pile point,
Comprising steps of
Step 1: lower end polishing is conical to be used as bore bit, using φ using φ 12mm round steel as pricker body lower half portion
Half part with 14mm round steel or the round steel of larger diameter production pricker, centre are welded to connect, and use building glue at the top of the pricker body
Paste level, intercept 30cm-50cm diameter be φ 20mm screw-thread steel or larger diameter reinforcing bar as the pricker with
Handle and pedal, the handle is parallel with pedal and is vertically welded in the pricker;
Step 2: the diameter for intercepting 30cm-50cm is φ 1mm using φ 14mm steel pipe as the stack shell for filling grey cylinder
Screw-thread steel is vertically welded on the stack shell as grey cylinder handle, the grey cylinder handle of the filling is filled.
Preferably, the barrel length is 40cm.
The present invention also announces a kind of application method of the pinpoint device of foot-operated drill rod drilling pile point, including step
It is rapid:
Step 1: determining engineering pile centerline by surveying setting-out;
It is withstood below the pedal Step 2: covering the grey cylinder of the filling in pricker body lower end to the grey cylinder handle of the filling;
Step 3: bore bit is directed at engineering pile centerline, the pricker body is adjusted by the level held with the pricker and is protected
It is vertical to hold, hand steered handle, foot pedal, by part under pricker body and be set in part under pricker body filling ash cylinder be pressed into ground down toward
Grey cylinder handle is filled close to ground;
Step 4: extracting pricker body vertically, funnel lower end is deeply filled in grey cylinder, lime is filled into grey cylinder by funnel,
Vertical extract fills grey cylinder.
Preferably, in step 4, with funnel to when filling perfusion lime in grey cylinder, note is smash using pricker body and fills grey cylinder, so that white
Ash is filled closely knit.
Preferably, it in step 4, when vertical extraction fills grey cylinder, is fixed temporarily to grey cylinder two sides soil layer is filled, it is slow, steady
Surely lift the grey cylinder of filling, prevent from filling when grey cylinder extracts soil layer and destroy stake point hole.
Through the above technical solutions, lime can be filled into soil to 20cm to 50cm, rather than it is only sprinkling upon native surface, works as surrounding
The anchor point cover type that label will be closed on when operation, can root out overburden soil, and slightly label point can be exposed by rooting out some soil more.Hole
Eye is small, fills ash less, accurate positioning is not easy sideslip.It easily looks for and sees original anchor point, whether direct stake machine drills or checks in place
Point, it is time saving and energy saving, it is convenient and efficient.
Detailed description of the invention
Fig. 1 is a kind of filling ash barrel structure signal of the pinpoint device of foot-operated drill rod drilling pile point of the embodiment of the present invention
Figure;
Fig. 2 is a kind of drill rod structural representation of the pinpoint device of foot-operated drill rod drilling pile point of the embodiment of the present invention
Figure;
Fig. 3 is a kind of funnel structure signal of the pinpoint device of foot-operated drill rod drilling pile point of the embodiment of the present invention
Figure;
Fig. 4 is the drill rod and the grey cylinder group of filling of a kind of pinpoint device of foot-operated drill rod drilling pile point of the embodiment of the present invention
Close figure;
Fig. 5 is the funnel and the grey cylinder group of filling of a kind of pinpoint device of foot-operated drill rod drilling pile point of the embodiment of the present invention
Close figure;
In figure:
1, stack shell 2, the grey cylinder handle 3 of filling, level
4, pricker body 5, handle 6, pedal
7, bore bit 8, funnel
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description.Obviously, described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that term " center ", "upper", "lower", "left", "right", "vertical",
The orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" be based on the orientation or positional relationship shown in the drawings, merely to
Convenient for description the present invention and simplify description, rather than the device or element of indication or suggestion meaning must have a particular orientation,
It is constructed and operated in a specific orientation, therefore is not considered as limiting the invention.
As shown in Figures 1 to 5, the present invention provides a kind of foot-operated drill rod drilling pile point pinpoint device, including drill rod,
Fill grey cylinder and funnel, wherein
Drill rod includes pricker body 4, bore bit 7, pedal 6 and level 3, and bore bit 7 is located at 4 lower end of pricker body and to be conical, pedal 6
Positioned at 4 lower part of pricker body, level 3 is located at 4 top of pricker body;
Filling grey cylinder includes hollow stack shell 1 and the filling ash cylinder handle 2 above stack shell 1, and stack shell 1 is set on pricker body 4
And 1 inner wall of stack shell is bonded 4 outer wall of pricker body, 1 length of stack shell is less than the distance that bore bit 7 arrives pedal 6;
8 lower end outer diameter of funnel is less than 1 internal diameter of stack shell.
A kind of preferred scheme, 4 top of pricker body are equipped with handle 5.
A kind of preferred scheme, the length of stack shell 1 are 20cm to 50cm.
The present invention also announces a kind of production method for making a kind of pinpoint device of foot-operated drill rod drilling pile point, including
Step:
Step 1: lower end polishing is conical to be used as bore bit 7 using φ 12mm round steel as 4 lower half portion of pricker body, use
φ 14mm round steel or the round steel of larger diameter make 4 top half of pricker body, and centre is welded to connect, and use building glue at the top of pricker body 4
Level 3 is pasted, intercepting the diameter of 30cm-50cm is φ 20mm screw-thread steel or the reinforcing bar of larger diameter as the handle with pricker
5 and pedal 6, handle 5 is parallel with pedal 6 and is vertically welded on pricker body 4;
Step 2: the diameter for intercepting 30cm-50cm is φ 1mm screw thread using φ 14mm steel pipe as the stack shell 1 for filling grey cylinder
Steel fills grey cylinder handle 2 and is vertically welded on stack shell 1 as grey cylinder handle 2 is filled.
A kind of preferred scheme, 1 length of stack shell are 40cm.
The present invention also announces a kind of application method of the pinpoint device of foot-operated drill rod drilling pile point, comprising steps of
Step 1: determining engineering pile centerline by surveying setting-out;
It is withstood below pedal 6 in 4 lower end of pricker body to grey cylinder handle 2 is filled Step 2: grey cylinder will be filled and covered;
Step, three, bore bit 7 is directed at engineering pile centerline, pricker body 4 is adjusted by the level 3 of 4 upper end of pricker body and keeps perpendicular
Directly, hand steered handle 5, foot pedal 6, by the lower part of pricker body 4 and be set in part under pricker body 4 filling ash cylinder be pressed into ground down toward
Grey cylinder handle 2 is filled close to ground;
Step 4: extracting pricker body 4 vertically, 8 lower end of funnel is deeply filled in grey cylinder, lime is filled into ash by funnel 8
Cylinder, vertical extract fill grey cylinder.
A kind of preferred scheme, in step 4, with funnel 8 to fill lime is perfused in grey cylinder when, smash note using pricker body 4 and fill ash
Cylinder, so that lime filling is closely knit.
A kind of preferred scheme, it is vertical to extract when filling grey cylinder in step 4, to fill grey cylinder two sides soil layer carry out it is temporarily solid
It is fixed, slowly, steadily lift the grey cylinder of filling, prevents from filling when grey cylinder extracts soil layer and destroy stake point hole;It is further preferred that can be used
Weight is pressed in above the soil layer for filling grey cylinder two sides and carries out provisional fixation to soil layer;Still more preferably, lifting the grey cylinder of filling
During synchronous rotary fill grey cylinder.
Through the above technical solutions, lime can be filled into soil to 20cm to 50cm, rather than it is only sprinkling upon native surface, works as surrounding
The anchor point cover type that label will be closed on when operation, can root out overburden soil, and slightly label point can be exposed by rooting out some soil more.Hole
Eye is small, fills ash less, accurate positioning is not easy sideslip.It easily looks for and sees original anchor point, whether direct stake machine drills or checks in place
Point, it is time saving and energy saving, it is convenient and efficient.
The device can deepen the length of embedment of stake point according to local soil property situation, and stake point indwelling time is long, device operation
Simply, production, convenient for disassembly and assembly, raising construction efficiency, saving cost of labor.Device is versatile, and the stake point engineering being related to is equal
The present apparatus can be used.
The embodiments of the present invention have been described in detail above, but content is only the preferred embodiment of the present invention,
It should not be considered as limiting the scope of the invention.Any changes and modifications in accordance with the scope of the present application,
It should still be within the scope of the patent of the present invention.
Claims (8)
1. a kind of pinpoint device of foot-operated drill rod drilling pile point, which is characterized in that including drill rod, grey cylinder and funnel are filled,
In,
The drill rod includes pricker body, bore bit, pedal and level, and the bore bit is located at pricker body lower end and to be conical, described to step on
Plate is located at pricker body lower part, and the level is located at the top of pricker body;
The grey cylinder of the filling includes that hollow stack shell and the filling ash cylinder handle above stack shell, the stack shell are set in the pricker body
The upper and described stack shell inner wall is bonded the pricker body outer wall, and the barrel length is less than the bore bit to the distance of the pedal;
Funnel lower end outer diameter is less than the barrel diameter.
2. a kind of pinpoint device of foot-operated drill rod drilling pile point according to claim 1, which is characterized in that the pricker
Body is equipped with handle.
3. a kind of pinpoint device of foot-operated drill rod drilling pile point according to claim 2, which is characterized in that the cylinder
The length of body is 20cm to 50cm.
4. a kind of, to make a kind of foot-operated drill rod drilling pile point described in any one of claims 1 to 3 claim pinpoint
The production method of device, comprising steps of
Step 1: lower end polishing is conical to be used as bore bit, using φ 14mm using φ 12mm round steel as pricker body lower half portion
Half part with round steel or the round steel of larger diameter production pricker, centre is welded to connect, is pasted at the top of the pricker body with building glue
Level, intercepting the diameter of 30cm-50cm is φ 20mm screw-thread steel or the reinforcing bar of larger diameter as the handle with the pricker
And pedal, the handle is parallel with pedal and is vertically welded in the pricker;
Step 2: the diameter for intercepting 30cm-50cm is φ 1mm screw thread using φ 14mm steel pipe as the stack shell for filling grey cylinder
Steel is vertically welded on the stack shell as grey cylinder handle, the grey cylinder handle of the filling is filled.
5. production method according to claim 4, which is characterized in that the barrel length is 40cm.
6. the pinpoint device of a kind of foot-operated drill rod drilling pile point described in a kind of any one of claims 1 to 3 claim
Application method, which is characterized in that comprising steps of
Step 1: determining engineering pile centerline by surveying setting-out;
It is withstood below the pedal Step 2: covering the grey cylinder of the filling in pricker body lower end to the grey cylinder handle of the filling;
Step 3: bore bit is directed at engineering pile centerline, the pricker body is adjusted by the level held with the pricker and keeps perpendicular
Directly, part under pricker body and the filling ash cylinder for being set in part under pricker body are pressed into ground down toward filling ash by hand steered handle, foot pedal
Cylinder handle is close to ground;
Step 4: extracting pricker body vertically, funnel lower end is deeply filled in grey cylinder, lime is filled into grey cylinder by funnel, vertically
It extracts and fills grey cylinder.
7. application method according to claim 6, which is characterized in that in step 4, be perfused with funnel into the grey cylinder of filling white
When grey, note is smash using pricker body and fills grey cylinder, so that lime filling is closely knit.
8. application method according to claim 7, which is characterized in that in step 4, when vertical extraction fills grey cylinder, to filling ash
Cylinder two sides soil layer is fixed temporarily, and the grey cylinder of filling slowly, is steadily lifted, and is prevented from filling when grey cylinder extracts soil layer and is destroyed stake spot hole
Hole.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910637600.1A CN110258563A (en) | 2019-07-15 | 2019-07-15 | A kind of pinpoint device of foot-operated drill rod drilling pile point, production method and application method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910637600.1A CN110258563A (en) | 2019-07-15 | 2019-07-15 | A kind of pinpoint device of foot-operated drill rod drilling pile point, production method and application method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110258563A true CN110258563A (en) | 2019-09-20 |
Family
ID=67926302
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910637600.1A Pending CN110258563A (en) | 2019-07-15 | 2019-07-15 | A kind of pinpoint device of foot-operated drill rod drilling pile point, production method and application method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110258563A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111719558A (en) * | 2020-06-29 | 2020-09-29 | 中能建西北城市建设有限公司 | CFG pile composite foundation construction process |
CN113882379A (en) * | 2021-11-05 | 2022-01-04 | 中国十七冶集团有限公司 | Tubular pile construction positioning and paying-off device and construction method |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10240801A1 (en) * | 2002-08-30 | 2004-03-18 | Ritter Gmbh | Applicator for masonry plug into cellular brick has a pump action dispenser to position porous plug while injecting two component bonder into plug |
CN103850255A (en) * | 2014-02-25 | 2014-06-11 | 中国建筑第六工程局有限公司 | Planar surveying, positioning and marking method of engineering pile |
CN104806279A (en) * | 2015-05-12 | 2015-07-29 | 蒲长晏 | Combined anchor rod |
CN105133614A (en) * | 2014-05-30 | 2015-12-09 | 中国二十冶集团有限公司 | Tool and method for marking underground pile position of engineering site |
CN206090649U (en) * | 2016-08-30 | 2017-04-12 | 中铁三局集团有限公司 | Pile foundation construction is with device of layouting |
CN206495206U (en) * | 2017-02-18 | 2017-09-15 | 北京东地岩土工程有限公司 | A kind of soil nailing |
CN208486266U (en) * | 2018-06-29 | 2019-02-12 | 五冶集团上海有限公司 | Pile foundation telltale mark point tool |
CN109518683A (en) * | 2018-11-26 | 2019-03-26 | 五冶集团上海有限公司 | A kind of stake heart localization method of artificial digging pile |
CN208701663U (en) * | 2018-08-08 | 2019-04-05 | 湖北金扬建设工程有限责任公司 | Convenient for positioning the casing at pore-creating center |
CN109680687A (en) * | 2019-01-17 | 2019-04-26 | 江西联保工程咨询有限公司 | A kind of integrally formed construction technology of platform |
CN210459214U (en) * | 2019-07-15 | 2020-05-05 | 中冶天工集团有限公司 | Device for accurately positioning hole-forming pile points of pedal steel drill |
-
2019
- 2019-07-15 CN CN201910637600.1A patent/CN110258563A/en active Pending
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10240801A1 (en) * | 2002-08-30 | 2004-03-18 | Ritter Gmbh | Applicator for masonry plug into cellular brick has a pump action dispenser to position porous plug while injecting two component bonder into plug |
CN103850255A (en) * | 2014-02-25 | 2014-06-11 | 中国建筑第六工程局有限公司 | Planar surveying, positioning and marking method of engineering pile |
CN105133614A (en) * | 2014-05-30 | 2015-12-09 | 中国二十冶集团有限公司 | Tool and method for marking underground pile position of engineering site |
CN104806279A (en) * | 2015-05-12 | 2015-07-29 | 蒲长晏 | Combined anchor rod |
CN206090649U (en) * | 2016-08-30 | 2017-04-12 | 中铁三局集团有限公司 | Pile foundation construction is with device of layouting |
CN206495206U (en) * | 2017-02-18 | 2017-09-15 | 北京东地岩土工程有限公司 | A kind of soil nailing |
CN208486266U (en) * | 2018-06-29 | 2019-02-12 | 五冶集团上海有限公司 | Pile foundation telltale mark point tool |
CN208701663U (en) * | 2018-08-08 | 2019-04-05 | 湖北金扬建设工程有限责任公司 | Convenient for positioning the casing at pore-creating center |
CN109518683A (en) * | 2018-11-26 | 2019-03-26 | 五冶集团上海有限公司 | A kind of stake heart localization method of artificial digging pile |
CN109680687A (en) * | 2019-01-17 | 2019-04-26 | 江西联保工程咨询有限公司 | A kind of integrally formed construction technology of platform |
CN210459214U (en) * | 2019-07-15 | 2020-05-05 | 中冶天工集团有限公司 | Device for accurately positioning hole-forming pile points of pedal steel drill |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111719558A (en) * | 2020-06-29 | 2020-09-29 | 中能建西北城市建设有限公司 | CFG pile composite foundation construction process |
CN111719558B (en) * | 2020-06-29 | 2021-09-21 | 中能建西北城市建设有限公司 | CFG pile composite foundation construction process |
CN113882379A (en) * | 2021-11-05 | 2022-01-04 | 中国十七冶集团有限公司 | Tubular pile construction positioning and paying-off device and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105604070B (en) | Canal in Loess Area side slope vegetation planting guarantee masonry structure system and its construction method | |
CN110258563A (en) | A kind of pinpoint device of foot-operated drill rod drilling pile point, production method and application method | |
CN204199335U (en) | A kind of pressure release well reducing PHC tube pile construction soil compaction effect | |
CN110258538A (en) | A kind of soil nailing reinforces buffer-type artificial digging pile and its construction method | |
CN109853538A (en) | Cast-in-place concrete pile pile foundation reinforcing structure and its construction method | |
CN207525758U (en) | A kind of reinforced Structure About Soldier Pile | |
CN208472592U (en) | Close to the steel pipe pile reinforced construction of deep basal pit bridge friction pile | |
CN212405086U (en) | Disposal and detection structure for karst cave under rock-socketed pile base | |
CN110872839B (en) | Construction method of conical pile tip tubular pile capable of post-grouting | |
CN107476319A (en) | Mountain area steep slope region Road Bridge Pile Foundation construction method | |
CN205116207U (en) | Offshore wind farm fan combined type embedded rock pile basis | |
CN104088292A (en) | Axis single-pile multi-tripod foundation and construction method thereof | |
CN106403996A (en) | Production method of forced centering observation mark stake for precision engineering measurement | |
CN203583501U (en) | Deep-layer shear resistant device capable of preventing rock sliding | |
CN207881706U (en) | A kind of measurement mark | |
CN206220114U (en) | A kind of eight High-Rise Pile Cap Foundations | |
CN203160222U (en) | Ground settlement monitoring point device | |
JPS55159024A (en) | Construction method for structure foundation | |
CN210459214U (en) | Device for accurately positioning hole-forming pile points of pedal steel drill | |
CN209230632U (en) | A kind of measurement and positioning and the fixed control stake of elevation | |
CN207211213U (en) | One kind enters lithotype anti-floating anchor rod structure | |
CN207812477U (en) | Composite screw anchor foundation | |
CN207295465U (en) | Open cut rock anchor combination foundation | |
CN205224070U (en) | Compound foundation stabilization structure of drill bit anchor pile | |
CN209227542U (en) | A kind of Concrete Core Mixing Pile supporting construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |