CN110219391A - A kind of fabricated shear wall and construction method - Google Patents

A kind of fabricated shear wall and construction method Download PDF

Info

Publication number
CN110219391A
CN110219391A CN201910543002.8A CN201910543002A CN110219391A CN 110219391 A CN110219391 A CN 110219391A CN 201910543002 A CN201910543002 A CN 201910543002A CN 110219391 A CN110219391 A CN 110219391A
Authority
CN
China
Prior art keywords
wall
connector
hole
steel plate
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910543002.8A
Other languages
Chinese (zh)
Inventor
蔡健
杨正宁
巫博璘
陈庆军
罗翼锋
马平川
朱东烽
张伟生
陈祺荣
江幸莲
邓皓匀
黄小芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Jing Hong Construction Co Ltd
Guangdong Yuncheng Architectural Technology Co Ltd
South China University of Technology SCUT
Original Assignee
Guangdong Jing Hong Construction Co Ltd
Guangdong Yuncheng Architectural Technology Co Ltd
South China University of Technology SCUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Jing Hong Construction Co Ltd, Guangdong Yuncheng Architectural Technology Co Ltd, South China University of Technology SCUT filed Critical Guangdong Jing Hong Construction Co Ltd
Priority to CN201910543002.8A priority Critical patent/CN110219391A/en
Publication of CN110219391A publication Critical patent/CN110219391A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The present invention discloses a kind of fabricated shear wall and construction method, the fabricated shear wall includes the first wall and the second wall mutually assembled, at least one connector and nut, first wall and the second wall are respectively double-layer plate, fill concrete in double-layer plate, the assembly side of first wall is equipped at least one slot, the assembly side of second wall is equipped at least one bolt, bolt is inserted into slot, through setting fixation hole on bolt, first wall corresponds to fixation hole through the first mounting hole of setting, first mounting hole runs through slot, connector is fixed by nuts after passing through the first mounting hole and fixation hole.The modes such as fabricated shear wall of the invention, the first wall and the second wall can be produced in batches in factory, and connection is spliced by scene, bolt is fixed are completed, and welding or cast-in-place connecting band are not needed, and have the features such as environmentally protective, high construction efficiency, high financial profit.

Description

A kind of fabricated shear wall and construction method
Technical field
The present invention relates to technical field of structural engineering, in particular to a kind of fabricated shear wall and construction method.
Background technique
The general type of steel plate-concrete combined shear wall, which has in embedded steel plate, unilateral steel plate and double-layer plate, fills out coagulation The forms such as soil.Wherein double-layer plate concrete filled performance is the most superior, and the outside plate construction stage can also serve as concrete mould Plate, construction are rapid.Assembling steel plate-combined concrete shear wall is on the basis of above structure feature, using " prefabrication The build model of main member, on-site consolidation, welding or cast-in-place connecting band " has and improves production efficiency, energy saving, development The features such as Green environmental-protection building.
According to the loading characteristic of shear wall, the fabricated shear wall of the type junction to guarantee good bearing capacity and Deformability.For dry construction, assembling steel plate-combined concrete shear wall common at present adds steel often through outside Plate site welding or split bolt connect upper lower steel plate.Under this connection type, when structure is by horizontal loading, bolt Biggish shearing is suffered from weld seam, so that overall structure bearing capacity is far below requirement in advance.It is therefore desirable to develop one Proper form of the kind for the horizontal piece of formula steel plate-concrete combined shear wall that is linked and packed.
Summary of the invention
It is an object of the invention to overcome the deficiencies of the prior art and provide a kind of fabricated shear walls, by bolt and insert The assembly of shear wall can be completed in slot, does not need welding or cast-in-place connecting band, high construction efficiency are environmentally protective.
Another object of the present invention is to provide a kind of construction methods of fabricated shear wall.
The technical solution of the present invention is as follows: a kind of fabricated shear wall, including the first wall mutually assembled and the second wall, At least one connector and nut, first wall and the second wall are respectively double-layer plate, fill coagulation in double-layer plate Soil, the assembly side of the first wall are equipped at least one slot, and the assembly side of the second wall is equipped at least one bolt, bolt insertion In slot, through setting fixation hole on bolt, the first wall corresponds to fixation hole through the first mounting hole of setting, and the first mounting hole passes through Interspersed slot, connector are fixed by nuts after passing through the first mounting hole and fixation hole.By using the connection type of bolt and slot, When the first wall and the second wall are by horizontal loading, steel plate and concrete synergistic effect at bolt and slot are held jointly Horizontal shear is carried on a shoulder pole, stress performance is good, and quality of connection is high, and bolt is fixed in wall by connector, improves anti-between wall Pull out ability.
Further, viscoplasticity Energy dissipating material is filled between the bolt and slot, viscoplasticity Energy dissipating material is rubber, latex Or epoxy resin, viscoplasticity Energy dissipating material play energy-absorbing damping, mitigate the damage of the disasters brings such as earthquake.
Further, the width of the slot and depth are slightly larger than the width and depth of bolt, it is ensured that the first wall and second After wall assembly, it is not displaced mutually between the first wall and the second wall, while ensuring at the first wall and the second wall assembly Gap it is sufficiently small, enhance whole structural strength.
Further, the fabricated shear wall further includes muti-piece junction steel plate, and muti-piece junction steel plate is located at the first wall Two sides at body and the second wall assembly, the both ends of junction steel plate are separately connected the first wall and the second wall.By connecting steel Plate connects the first wall and the second wall, further increases the breakout capacity between the first wall and the second wall, connects simultaneously Steel plate can shared horizontal shear, improve overall structural strength.
Further, second wall is equipped with the second mounting hole, corresponding first mounting hole of junction steel plate and the second installation Hole is equipped with connecting hole, and connector includes the first connector and the second connector, and the first connector sequentially passes through connecting hole, the first peace Hole and fixation hole are filled, the second connector sequentially passes through connecting hole and the second mounting hole, the first connector and the second connector difference Junction steel plate is fixed on by nut.The first connector and the second connector are fixed by junction steel plate, further mentioned Breakout capacity and shear resistance between high first wall and the second wall, while entire assembling process is without welding or cast-in-place company The advantages that tape splicing has high construction efficiency, environmentally protective, high financial profit.
Further, first connector and the first wall body vertical, the second connector and the second wall body vertical.
Further, the assembled wall further includes Horizontal concrete component, and the Horizontal concrete component is respectively with One wall and the second wall body vertical, the first connector and the second connector are threaded reinforcing bar, Horizontal concrete component cladding First connector, the second connector and junction steel plate.When there is the Horizontal concrete component with the first wall and the second wall body vertical When across the first wall and the second wall, such as crossbeam, Horizontal concrete component is coated at the first wall and the second wall assembly Gap, junction steel plate, the first connector and the second connector, enhance integrally-built stability, while making junction steel plate and dress Gap with place is not exposed.
The present invention also provides another technical solution, a kind of construction method of fabricated shear wall, including what is mutually assembled First wall and the second wall, at least one connector and nut, first wall and the second wall are respectively double-layer plate, Fill concrete in double-layer plate, the assembly side of the first wall are equipped at least one slot, and the assembly side of the second wall is equipped with extremely A few bolt, through setting fixation hole on bolt, the first wall correspond to fixation hole and installs through the first mounting hole of setting, first Slot is run through in hole;First bolt is inserted into slot, then connector is passed through into the first mounting hole and fixation hole, is finally secured with nuts Connector.
It further, further include muti-piece junction steel plate, muti-piece junction steel plate is located at the first wall and the assembly of the second wall The two sides at place, the both ends of junction steel plate are separately connected the first wall and the second wall, and the second wall is equipped with the second mounting hole, even It connecing corresponding first mounting hole of steel plate and the second mounting hole is equipped with connecting hole, connector includes the first connector and the second connector, First connector sequentially passes through connecting hole, the first mounting hole and fixation hole, and the second connector sequentially passes through connecting hole and the second peace Hole is filled, the first connector and the second connector pass through nut respectively and be fixed on junction steel plate.It is connected by junction steel plate to first Part and the second connector are fixed, and further increase breakout capacity and shear resistance between the first wall and the second wall, The advantages that entire assembling process has high construction efficiency without welding or cast-in-place connecting band simultaneously, environmentally protective, high financial profit.
Further, viscoplasticity Energy dissipating material is filled between the bolt and slot, viscoplasticity Energy dissipating material is rubber, latex Or epoxy resin, viscoplasticity Energy dissipating material play energy-absorbing damping, mitigate the damage of the disasters brings such as earthquake.
The construction method of above-mentioned fabricated shear wall is as follows, and the bolt of the second wall is first inserted into the slot of the first wall It is interior, then the first connector is sequentially passed through into connecting hole, the first mounting hole and fixation hole, the second connector sequentially pass through connecting hole and First connector and the second connector are fixed on junction steel plate finally by nut by the second mounting hole.
The present invention compared with the existing technology, has the advantages that
Fabricated shear wall of the invention, the first wall and the second wall can be produced in batches in factory, and connection passes through existing The modes such as field is spliced, bolt is fixed are completed, and welding or cast-in-place connecting band are not needed, and have environmentally protective, high construction efficiency, economical to imitate The features such as benefit is high.
Fabricated shear wall of the invention, by using the connection type of bolt and slot, when shear wall structure is by water When flat load, steel plate and concrete synergistic effect at bolt and slot, shared horizontal shear, stress performance is good, even Connect quality height.
Detailed description of the invention
Fig. 1 is the stereogram exploded view of fabricated shear wall of the invention.
Fig. 2 is the front view of fabricated shear wall of the invention.
Fig. 3 is the side view of fabricated shear wall of the invention.
Fig. 4 is cross-sectional view of the Fig. 2 along AA line.
Fig. 5 is cross-sectional view of the Fig. 2 along BB line.
Fig. 6 is the perspective view of the fabricated shear wall in embodiment 2.
Specific embodiment
Below with reference to embodiment, the present invention is described in further detail, and embodiments of the present invention are not limited thereto.
Embodiment 1
As depicted in figs. 1 and 2, the present embodiment provides a kind of fabricated shear walls, including 1 He of the first wall mutually assembled Second wall 2, at least one connector, at least one junction steel plate 3 and nut 4.
As shown in Figure 1, Figure 4 and Figure 5, the first wall and the second wall are respectively double-layer plate, and filling is mixed in double-layer plate Solidifying soil, the assembly side of the first wall are equipped at least one slot 5, and the assembly side of the second wall is equipped at least one bolt 6, slot Width and depth be slightly larger than the width and depth of bolt, in the present embodiment, the quantity of slot and bolt is respectively six, six A slot is equally spaced respectively in the assembly side of the first wall, and six bolts are equally spaced respectively in the assembly side of the second wall, Fixation hole 7 is provided through on bolt, the first wall corresponds to fixation hole through the first mounting hole 8 of setting, and the second wall is equipped with Second mounting hole 9.
As shown in Figure 1, Figure 2 and Figure 3, in the present embodiment, the quantity of junction steel plate shares 12 pieces, 12 pieces of junction steel plates The two sides being equally spaced at the first wall and the second wall assembly, corresponding first mounting hole of junction steel plate and the second mounting hole are set There is connecting hole 10, connector includes the first connector 11 and the second connector 12, and the first connector and the second connector are screw rod, First connector and the first wall body vertical, the second connector and the second wall body vertical, the first connector sequentially pass through connecting hole, One mounting hole and fixation hole, the second connector sequentially pass through connecting hole and the second mounting hole, the first connector and the second connector Junction steel plate (as shown in Figure 5) is fixed on by nut respectively.
As shown in figure 4, filling viscoplasticity Energy dissipating material 13 between bolt and slot, viscoplasticity Energy dissipating material is rubber, cream Glue or epoxy resin, viscoplasticity Energy dissipating material play energy-absorbing damping, mitigate the damage of the disasters brings such as earthquake.
The construction method of above-mentioned fabricated shear wall is as follows, and the bolt of the second wall is first inserted into the slot of the first wall It is interior, then the first connector is sequentially passed through into connecting hole, the first mounting hole and fixation hole, the second connector sequentially pass through connecting hole and First connector and the second connector are fixed on junction steel plate finally by nut by the second mounting hole.
Embodiment 2
The present embodiment the difference from embodiment 1 is that, fabricated shear wall further includes Horizontal concrete component, horizontal coagulation For native component respectively with the first wall and the second wall body vertical, the first connector and the second connector are threaded reinforcing bar (such as Fig. 6 It is shown), Horizontal concrete component coats the first connector, the second connector and junction steel plate.When having and the first wall and second When the Horizontal concrete component (such as crossbeam) of wall body vertical passes through the first wall and the second wall, Horizontal concrete component cladding the Gap, junction steel plate, the first connector and the second connector at one wall and the second wall assembly enhance integrally-built steady It is qualitative, while keeping the gap at junction steel plate and assembly not exposed.
As described above, the present invention can be better realized, above-described embodiment is only presently preferred embodiments of the present invention, is not used To limit practical range of the invention;It is i.e. all according to equivalent changes and modifications made by the content of present invention, all wanted for right of the present invention Range claimed is asked to be covered.

Claims (10)

1. a kind of fabricated shear wall, which is characterized in that including the first wall mutually assembled and the second wall, at least one company Fitting and nut, first wall and the second wall are respectively double-layer plate, fill concrete in double-layer plate, the first wall Assembly side be equipped at least one slot, the assembly side of the second wall is equipped at least one bolt, and bolt is inserted into slot, bolt Upper to run through setting fixation hole, the first wall corresponds to fixation hole through the first mounting hole of setting, and the first mounting hole runs through slot, connects Part is fixed by nuts after passing through the first mounting hole and fixation hole.
2. fabricated shear wall according to claim 1, which is characterized in that fill viscoplasticity between the bolt and slot Energy dissipating material.
3. fabricated shear wall according to claim 1, which is characterized in that the width and depth of the slot are slightly larger than slotting The width and depth of pin.
4. fabricated shear wall according to claim 1, which is characterized in that further include muti-piece junction steel plate, muti-piece connection Steel plate is located at the two sides at the first wall and the second wall assembly, and the both ends of junction steel plate are separately connected the first wall and Two walls.
5. fabricated shear wall according to claim 4, which is characterized in that second wall is equipped with the second installation Hole, corresponding first mounting hole of junction steel plate and the second mounting hole are equipped with connecting hole, and connector includes that the first connector and second connect Fitting, the first connector sequentially pass through connecting hole, the first mounting hole and fixation hole, and the second connector sequentially passes through connecting hole and Two mounting holes, the first connector and the second connector pass through nut respectively and are fixed on junction steel plate.
6. fabricated shear wall according to claim 5, which is characterized in that first connector and the first wall hang down Directly, the second connector and the second wall body vertical.
7. fabricated shear wall according to claim 5, which is characterized in that further include Horizontal concrete component, the water For flat concrete component respectively with the first wall and the second wall body vertical, the first connector and the second connector are threaded steel Muscle, Horizontal concrete component coat the first connector, the second connector and junction steel plate.
8. a kind of construction method of fabricated shear wall, which is characterized in that including the first wall mutually assembled and the second wall, At least one connector and nut, first wall and the second wall are respectively double-layer plate, fill coagulation in double-layer plate Soil, the assembly side of the first wall are equipped at least one slot, and the assembly side of the second wall is equipped at least one bolt, passes through on bolt It wears and sets fixation hole, the first wall corresponds to fixation hole through the first mounting hole of setting, and the first mounting hole runs through slot;
First bolt is inserted into slot, then connector is passed through into the first mounting hole and fixation hole, connector is finally secured with nuts.
9. the construction method of fabricated shear wall according to claim 8, which is characterized in that further include muti-piece connection steel Plate, muti-piece junction steel plate are located at the two sides at the first wall and the second wall assembly, and the both ends of junction steel plate are separately connected First wall and the second wall, the second wall are equipped with the second mounting hole, corresponding first mounting hole of junction steel plate and the second installation Hole is equipped with connecting hole, and connector includes the first connector and the second connector, and the first connector sequentially passes through connecting hole, the first peace Hole and fixation hole are filled, the second connector sequentially passes through connecting hole and the second mounting hole, the first connector and the second connector difference Junction steel plate is fixed on by nut.
10. the construction method of fabricated shear wall according to claim 8, which is characterized in that the bolt and slot it Between fill viscoplasticity Energy dissipating material.
CN201910543002.8A 2019-06-21 2019-06-21 A kind of fabricated shear wall and construction method Pending CN110219391A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910543002.8A CN110219391A (en) 2019-06-21 2019-06-21 A kind of fabricated shear wall and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910543002.8A CN110219391A (en) 2019-06-21 2019-06-21 A kind of fabricated shear wall and construction method

Publications (1)

Publication Number Publication Date
CN110219391A true CN110219391A (en) 2019-09-10

Family

ID=67814251

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910543002.8A Pending CN110219391A (en) 2019-06-21 2019-06-21 A kind of fabricated shear wall and construction method

Country Status (1)

Country Link
CN (1) CN110219391A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110700441A (en) * 2019-10-30 2020-01-17 上海应用技术大学 Prefabricated assembled concrete shear force wall tenon formula steel node connection structure
CN113863756A (en) * 2021-11-15 2021-12-31 东莞理工学院 Three-phase adjacent structure damping control system suitable for building compact area
CN116856584A (en) * 2023-08-18 2023-10-10 河北陆星建设集团有限公司 Energy-saving multifunctional building outer wall body

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000170285A (en) * 1998-12-08 2000-06-20 Kajima Corp Connecting method for steel sheet concrete structural wall and junction structure
CN107299699A (en) * 2017-06-26 2017-10-27 东南大学 Assembled cavity shear wall horizontal joint Alveolus type dry type attachment structure
CN207277570U (en) * 2017-09-26 2018-04-27 华南理工大学 A kind of assembled steel plate concrete combined shear wall concave-convex piecing connection structure
CN108360710A (en) * 2018-01-31 2018-08-03 广州大学 A kind of assembled damping wall of building structure
CN109440973A (en) * 2018-12-20 2019-03-08 沈阳建筑大学 A kind of fabricated shear wall vertically connects energy-dissipation structure and its construction method
CN208650328U (en) * 2018-04-03 2019-03-26 山东科技大学 Connecting node between a kind of assembling steel plate-Combined concrete wall wall
CN109577518A (en) * 2018-12-05 2019-04-05 谢建林 A kind of fabricated shear wall horizontal connection structure and construction method
CN109898667A (en) * 2019-03-22 2019-06-18 中南大学 A kind of the assembled RC shear wall structure and its construction method of dry type connection
CN210597740U (en) * 2019-06-21 2020-05-22 华南理工大学 Assembled shear force wall

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000170285A (en) * 1998-12-08 2000-06-20 Kajima Corp Connecting method for steel sheet concrete structural wall and junction structure
CN107299699A (en) * 2017-06-26 2017-10-27 东南大学 Assembled cavity shear wall horizontal joint Alveolus type dry type attachment structure
CN207277570U (en) * 2017-09-26 2018-04-27 华南理工大学 A kind of assembled steel plate concrete combined shear wall concave-convex piecing connection structure
CN108360710A (en) * 2018-01-31 2018-08-03 广州大学 A kind of assembled damping wall of building structure
CN208650328U (en) * 2018-04-03 2019-03-26 山东科技大学 Connecting node between a kind of assembling steel plate-Combined concrete wall wall
CN109577518A (en) * 2018-12-05 2019-04-05 谢建林 A kind of fabricated shear wall horizontal connection structure and construction method
CN109440973A (en) * 2018-12-20 2019-03-08 沈阳建筑大学 A kind of fabricated shear wall vertically connects energy-dissipation structure and its construction method
CN109898667A (en) * 2019-03-22 2019-06-18 中南大学 A kind of the assembled RC shear wall structure and its construction method of dry type connection
CN210597740U (en) * 2019-06-21 2020-05-22 华南理工大学 Assembled shear force wall

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110700441A (en) * 2019-10-30 2020-01-17 上海应用技术大学 Prefabricated assembled concrete shear force wall tenon formula steel node connection structure
CN113863756A (en) * 2021-11-15 2021-12-31 东莞理工学院 Three-phase adjacent structure damping control system suitable for building compact area
CN113863756B (en) * 2021-11-15 2022-09-13 东莞理工学院 Three-phase adjacent structure damping control system suitable for building compact area
CN116856584A (en) * 2023-08-18 2023-10-10 河北陆星建设集团有限公司 Energy-saving multifunctional building outer wall body
CN116856584B (en) * 2023-08-18 2023-12-08 河北陆星建设集团有限公司 Energy-saving multifunctional building outer wall body

Similar Documents

Publication Publication Date Title
CN110219391A (en) A kind of fabricated shear wall and construction method
CN102995756A (en) Concrete-filled rectangular steel tube column-box girder full-bolt connection node and construction method
CN208981820U (en) It is a kind of that rod structure is connect based on former the newly-increased of reinforced column top
CN107732668A (en) A kind of new glass fibre reinforced plastic lightning rod
CN107119851A (en) A kind of assembly concrete post plug-in type bolt splicing node and making construction method
RU2374402C2 (en) Nodal connection of wooden and glue-wood rod elements of low-pitched net domes
CN207998925U (en) Full-prefabricated assembled concrete frame
CN109610654A (en) Prefabricated assembled double steel plate concrete shear force wall connection component and its application method
CN205557838U (en) Assembled antidetonation honeycomb girder steel - shear force wall connection structure
CN110284725B (en) Reinforced concrete frame node beam hogging moment assembly steel structure and reinforcing method thereof
CN210597740U (en) Assembled shear force wall
CN104989010B (en) A kind of connection method for bamboo and wood prefabricated panel
CN108661224B (en) But height-adjusting's assembled concrete coincide floor
CN208815980U (en) A kind of steel plate concrete assembled wall board anti-side energy-consuming device for modular architectural
CN208136920U (en) A kind of triangle prestressing force foundation pit supporting pile and its connection structure
CN206800624U (en) With the Multicarity concrete filled steel tube pole steel beam face outer bolt assembled connecting node to wearing screw rod
CN109403489A (en) A kind of fabricated shear wall vertical abutment joint friction energy-dissipating attachment device
CN208183955U (en) A kind of assembling type node structure
CN107630509A (en) A kind of compound orthogonal-diagonal lattice space steel lattice boxlike tube-in-tube structure of assembled
CN204457044U (en) A kind of column foot node combining angle cross section for electric power pylon without fill plate four
CN209082694U (en) A kind of connecting node of assembly concrete frame beam column
CN206681150U (en) A kind of exterior formula connecting node of multi-cavity steel tube concrete pole steel beam plane used to wearing rod iron
CN206800740U (en) A kind of prefabricated assembled composite floor
CN205976051U (en) Assembly type structure shock -absorbing structure
CN206784655U (en) A kind of fabricated damping wall

Legal Events