CN110206135A - A kind of stone masonry house foundation ruggedized construction and method - Google Patents

A kind of stone masonry house foundation ruggedized construction and method Download PDF

Info

Publication number
CN110206135A
CN110206135A CN201910422830.6A CN201910422830A CN110206135A CN 110206135 A CN110206135 A CN 110206135A CN 201910422830 A CN201910422830 A CN 201910422830A CN 110206135 A CN110206135 A CN 110206135A
Authority
CN
China
Prior art keywords
foundation
stone
wall
basis
steel bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910422830.6A
Other languages
Chinese (zh)
Other versions
CN110206135B (en
Inventor
林上顺
薛玲
林长庚
王文平
林永捷
叶世集
林玉莲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian University Of Science And Technology
Fuzhou Peiyan Engineering Technology Co ltd
Original Assignee
Fujian Qianye Construction Engineering Co Ltd
Fuzhou Peiyan Engineering Technology Co Ltd
Fujian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Qianye Construction Engineering Co Ltd, Fuzhou Peiyan Engineering Technology Co Ltd, Fujian University of Technology filed Critical Fujian Qianye Construction Engineering Co Ltd
Priority to CN201910422830.6A priority Critical patent/CN110206135B/en
Publication of CN110206135A publication Critical patent/CN110206135A/en
Application granted granted Critical
Publication of CN110206135B publication Critical patent/CN110206135B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/48Foundations inserted underneath existing buildings or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0007Base structures; Cellars
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/24Structural elements or technologies for improving thermal insulation
    • Y02A30/244Structural elements or technologies for improving thermal insulation using natural or recycled building materials, e.g. straw, wool, clay or used tires

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Foundations (AREA)

Abstract

The present invention relates to building strengthening technical fields, and in particular to a kind of stone masonry house foundation ruggedized construction, the stone masonry house foundation include wall and stone basis, including anchor pole, steel tie, foundation beam and exposed steel bar.Stone masonry house foundation ruggedized construction provided by the invention, soil excavation amount is smaller in work progress, even without large-scale excavation equipment;The anchor pole squeezed into the side grooves of stone basis has greatly reinforced foundation capability, increases the forced area on stone basis;The setting of foundation beam has dispersed force path, and total contact area of stone basis and ground is increased after reinforcing, and the common stress of foundation beam and stone basis significantly reduces the pressure from wall of stone basis receiving;By steel tie connection that the connection of two sides foundation beam is integral, the globality of stone basis and foundation beam is enhanced, and loose stone basis is avoided to be deformed because bearing excessive stresses.

Description

A kind of stone masonry house foundation ruggedized construction and method
Technical field
The present invention relates to building strengthening technical fields, and in particular to a kind of stone masonry house foundation ruggedized construction and method.
Background technique
Widely using rock material as house foundation in the old-fashioned masonry structure building in China's Coastal Areas, and old-fashioned room The rubble-mound foundation in room is mostly that rubble is mixed with ordinary mortar or other low intensive cementitious materials, due to its material is loose, The extremely low feature of globality poor, shear resistance is affected by geology hydrological environment around, geology caused by the decline of underground water Differential settlement may cause wall crazing.In addition, the use function change in house or house carry out lotus caused by add-story reconstruction It carries and increases.When shearing resistance resistance to compression when rubble-mound foundation is not able to satisfy requirement, it is often necessary to carry out strengthening reconstruction to rubble-mound foundation.
Traditional strengthening reconstruction mode carries out the reinforcing on basis often through the mode that Hou Bu reinforced concrete fortifield village covers, this Reforming mode not only excavation and filling heavy workload, and it is complex to construct.
Add that enclose set processed as patent of invention that domestic applications number are CN104674680A discloses a kind of stone foundation Journey, including former stone structure wall are made of coagulation fortifield village set, stirrup, column angle siffener angle, ground beam, the rectangular slab of stone and concrete cushion, It is characterized in that: original structure is brick foundation, presentation quality is poor, should increase a underpinning on cleaning original structure member base Operational procedure, conventional method are that reinforced concrete fortifield village set is added in original basis, should be arranged by design requirement in coagulation fortifield village set Stirrup and suspension column siffener angle, coagulation fortifield village set should be formed using the concrete cast-in-situ not less than C20.The invention is attached for basis The soil excavated volume of part is larger, and operational procedure is complicated, and coagulation fortifield village set and the globality on basis are poor, after causing reinforcing The not high problem of underlying reli-ability.
Summary of the invention
The technical problems to be solved by the present invention are: it is small to provide a kind of excavation and filling workload, form of construction work is simple and globality Preferable barnacle body house wall ruggedized construction and method.
In order to solve the above-mentioned technical problem, a kind of the technical solution adopted by the present invention are as follows: stone masonry house foundation reinforcing knot Structure, including wall and stone basis, the stone basis are set in the soil body on ground, and the wall body vertical is fixedly arranged on stone-based The top surface of plinth further includes anchor pole, steel tie, foundation beam and exposed steel bar;
Multiple anchor poles are vertically arranged in the soil body of stone basis two sides and perpendicular to horizontal plane;
The steel tie includes wall steel bar and reinforcement foundation, and the wall steel bar level is arranged in the lower part of wall, The reinforcement foundation level is arranged in the top on stone basis, the wall steel bar and reinforcement foundation and corresponds in vertical direction Setting, the wall steel bar on same vertical direction are fixedly connected with reinforcement foundation;Two foundation beams are respectively arranged at The two sides on stone basis, the upper end of the anchor pole, the both ends of wall steel bar, reinforcement foundation both ends protrude into foundation beam inside and It is fixedly connected with foundation beam;
The exposed steel bar is set to the junction of wall Yu stone basis, the exposed steel bar and the fixed company of wall steel bar It connects.
Wherein, the anchor pole branch of stone basis two sides is with quincuncial pile formula arrangement.
Wherein, the reinforcement foundation is welded with the anchor pole close to stone basis.
Wherein, the foundation beam is internally provided with steel reinforcement cage, and the steel reinforcement cage is made of four vertical muscle and several stirrups.
Wherein, the wall steel bar and wall are fixedly connected by concrete grouting, the reinforcement foundation and stone Basis is fixedly connected by concrete grouting.
Wherein, the exposed steel bar is fixedly connected with wall steel bar by welding manner.
The construction method of above-mentioned stone masonry house foundation ruggedized construction, includes the following steps:
Step 1, excavating a sliver transvers section respectively according to the profile of foundation beam in stone basis two sides is rectangular groove, Anchor pole is squeezed into vertically in the form of quincuncial pile in trench bottom surfaces;
Multiple first preformed holes are arranged in the lower horizontal of wall in step 2, are horizontally disposed with the on the top on stone basis Two preformed holes, the first preformed hole and the second preformed hole correspond in the vertical direction, and wall steel bar is arranged in first and is reserved Reinforcement foundation is arranged in the second preformed hole by hole, carries out slip casting to the first preformed hole and the second preformed hole, it is ensured that wall steel bar with Wall, reinforcement foundation and stone basis are firmly bonded, with one section of reinforcing bar by reinforcement foundation corresponding on vertical direction and wall steel Muscle is welded, and reinforcement foundation and the anchor pole close to stone basis are welded;
The steel reinforcement cage being made of four vertical muscle and several stirrups is put into groove by step 3 after the completion of ground is tied up, Then the concrete perfusion into groove, so that concrete cladding reinforcing steel bar cage, the top of anchor pole, reinforcement foundation and the wall steel of perfusion The exposed one end of muscle is to basis of formation beam;
Step 4 backfills the soil body into groove, then carry out the reinforcing of surface of wall after the concrete consolidation in groove, Wall steel bar net can be connect with exposed steel bar.
Seen from the above description, the beneficial effects of the present invention are: stone masonry house foundation provided by the invention reinforces knot Structure, soil excavation amount is smaller in work progress, even without large-scale excavation equipment;The anchor pole squeezed into the side grooves of stone basis Foundation capability has been greatly reinforced, the forced area on stone basis is increased;The setting of foundation beam has dispersed force path, and Total contact area of stone basis and ground is increased after reinforcing, and the common stress of foundation beam and stone basis significantly reduces The pressure from wall that stone basis is born;Two sides foundation beam is linked to integral, stone basis by steel tie connection Enhanced with the globality of foundation beam, loose stone basis is avoided to be deformed because bearing excessive stresses.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the stone masonry house foundation ruggedized construction of the specific embodiment of the invention;
Fig. 2 is the top view of the stone masonry house foundation ruggedized construction of the specific embodiment of the invention;
Fig. 3 is the top view of the steel reinforcement cage of the stone masonry house foundation ruggedized construction of the specific embodiment of the invention;
Fig. 4 is the side view of the foundation beam of the stone masonry house foundation ruggedized construction of the specific embodiment of the invention;
Label declaration:
1, wall;2, stone basis;3, anchor pole;4, steel tie;41, wall steel bar;42, reinforcement foundation;5, foundation beam; 51, steel reinforcement cage;6, exposed steel bar;7, groove.
Specific embodiment
To explain the technical content, the achieved purpose and the effect of the present invention in detail, below in conjunction with embodiment and cooperate attached Figure is explained.
The most critical design of the present invention is: wall steel bar is arranged on wall, reinforcement foundation is set on the basis of stone, Anchor pole is set in the trench, is connected on stone basis with above structure by concrete perfusion integral.
It please refers to shown in Fig. 1 and Fig. 2, stone masonry house foundation ruggedized construction provided by the invention, including wall 1 and stone Head basis 2, the stone basis 2 is set in the soil body on ground, and the wall 1 is vertically located in the top surface on stone basis 2, also Including anchor pole 3, steel tie 4, foundation beam 5 and exposed steel bar 6;
Multiple anchor poles 3 are vertically arranged in the soil body of basic 2 two sides of stone and perpendicular to horizontal plane;
The steel tie 4 includes wall steel bar 41 and reinforcement foundation 42, and 41 level of wall steel bar is arranged in wall 1 Lower part, 42 level of reinforcement foundation is arranged in the top on stone basis 2, the wall steel bar 41 and reinforcement foundation 42 perpendicular Histogram corresponds upwards, and the wall steel bar 41 on same vertical direction is fixedly connected with reinforcement foundation 42;
Two foundation beams 5 are respectively arranged at the two sides on stone basis 2, the upper end of the anchor pole 3, wall steel bar 41 Both ends, reinforcement foundation 42 both ends protrude into the inside of foundation beam 5 and be fixedly connected with foundation beam 5;
The exposed steel bar 6 is set to the junction of wall 1 Yu stone basis 2, the exposed steel bar 6 and wall steel bar 41 It is fixedly connected.
Seen from the above description, the beneficial effects of the present invention are: stone masonry house foundation provided by the invention reinforces knot Structure, soil excavation amount is smaller in work progress, even without large-scale excavation equipment;The anchor pole squeezed into the side grooves of stone basis Foundation capability has been greatly reinforced, the forced area on stone basis is increased;The setting of foundation beam has dispersed force path, and Total contact area of stone basis and ground is increased after reinforcing, and the common stress of foundation beam and stone basis significantly reduces The pressure from wall that stone basis is born;Two sides foundation beam is linked to integral, stone basis by steel tie connection Enhanced with the globality of foundation beam, loose stone basis is avoided to be deformed because bearing excessive stresses.
Further, 3 branch of anchor pole of basic 2 two sides of the stone is with quincuncial pile formula arrangement.
Further, the reinforcement foundation 42 is welded with the anchor pole 3 close to stone basis 2.
Further, the foundation beam 5 is internally provided with steel reinforcement cage 51, and the reinforcing bar is by four vertical muscle and several stirrup groups At.Steel reinforcement cage 51 is the necessary component that armored concrete bears pulling force, and reinforced concrete member must have steel reinforcement cage 51, stirrup spacing The shearing according to basis is needed to design, muscle is indulged and stirrup thickness is all undetermined, and the function of steel reinforcement cage 51 is for anchor pole, drawknot Reinforcing bar is independent, the position of the adjustment of 51 stirrup spacing of steel reinforcement cage, the adjustment of each reinforcing bar thickness all with anchor pole and steel tie It is unrelated.
Seen from the above description, by the setting of steel reinforcement cage, the pulling force ability to bear of foundation beam can be improved.
Further, the wall steel bar 41 is fixedly connected with wall 1 by concrete grouting, the reinforcement foundation 42 are fixedly connected with stone basis 2 by concrete grouting.
Further, the exposed steel bar 6 is fixedly connected with wall steel bar 41 by welding manner.
The construction method of above-mentioned stone masonry house foundation ruggedized construction, includes the following steps:
Step 1, excavating a sliver transvers section respectively according to the profile of foundation beam 5 in basic 2 two sides of stone is rectangular groove 7, anchor pole 3 is squeezed into vertically in the form of quincuncial pile in 7 bottom surface of groove;
Multiple first preformed holes are arranged in the lower horizontal of wall 1 in step 2, and the top on stone basis 2 is horizontally disposed Second preformed hole, the first preformed hole and the second preformed hole correspond in the vertical direction, and wall steel bar 41 is arranged in first Reinforcement foundation 42 is arranged in the second preformed hole by preformed hole, carries out slip casting to the first preformed hole and the second preformed hole, it is ensured that wall Reinforcing bar 41 is firmly bonded with wall 1, reinforcement foundation 42 and stone basis 2, with one section of reinforcing bar by basis corresponding on vertical direction Reinforcing bar 42 and wall steel bar 41 are welded, and reinforcement foundation 42 and the anchor pole 3 close to stone basis 2 are welded;
The steel reinforcement cage 51 being made of four vertical muscle and several stirrups is put into groove by step 3 after the completion of ground is tied up It is interior, the then concrete perfusion into groove 7, so that the concrete cladding reinforcing steel bar cage 51 of perfusion, the top of anchor pole 3, reinforcement foundation 42 and the exposed one end of wall steel bar 41 to basis of formation beam 5;
Step 4 backfills the soil body into groove 7 after the concrete consolidation in groove 7, then carries out adding for 1 surface of wall Gu 41 net of wall steel bar can be connect with exposed steel bar 6.
Please refer to figs. 1 to 4, the embodiment of the present invention one:
A kind of stone masonry house foundation ruggedized construction, including wall 1 and stone basis 2, the stone basis 2 are set to ground In the soil body in face, the wall 1 is vertically located in the top surface on stone basis 2, further includes anchor pole 3, steel tie 4,5 and of foundation beam Exposed steel bar 6;
Multiple anchor poles 3 are vertically arranged in the soil body of basic 2 two sides of stone and perpendicular to horizontal plane;
The steel tie 4 includes wall steel bar 41 and reinforcement foundation 42, and 41 level of wall steel bar is arranged in wall 1 Lower part, 42 level of reinforcement foundation is arranged in the top on stone basis 2, the wall steel bar 41 and reinforcement foundation 42 perpendicular Histogram corresponds upwards, and the wall steel bar 41 on same vertical direction is fixedly connected with reinforcement foundation 42;
Two foundation beams 5 are respectively arranged at the two sides on stone basis 2, the upper end of the anchor pole 3, wall steel bar 41 Both ends, reinforcement foundation 42 both ends protrude into the inside of foundation beam 5 and be fixedly connected with foundation beam 5;
The exposed steel bar 6 is set to the junction of wall 1 Yu stone basis 2, the exposed steel bar 6 and wall steel bar 41 It is fixedly connected;
3 branch of anchor pole of basic 2 two sides of the stone is with quincuncial pile formula arrangement;
The reinforcement foundation 42 is welded with the anchor pole 3 close to stone basis 2;
The foundation beam 5 is internally provided with steel reinforcement cage 51, and the reinforcing bar is made of four vertical muscle and several stirrups;
The wall steel bar 41 is fixedly connected with wall 1 by concrete grouting, the reinforcement foundation 42 and stone Basis 2 is fixedly connected by concrete grouting;
The exposed steel bar 6 is fixedly connected with wall steel bar 41 by welding manner.
The construction method of above-mentioned stone masonry house foundation ruggedized construction, includes the following steps:
Step 1, excavating a sliver transvers section respectively according to the profile of foundation beam 5 in basic 2 two sides of stone is rectangular groove 7, anchor pole 3 is squeezed into vertically in the form of quincuncial pile in 7 bottom surface of groove;
Multiple first preformed holes are arranged in the lower horizontal of wall 1 in step 2, and the top on stone basis 2 is horizontally disposed Second preformed hole, the first preformed hole and the second preformed hole correspond in the vertical direction, and wall steel bar 41 is arranged in first Reinforcement foundation 42 is arranged in the second preformed hole by preformed hole, carries out slip casting to the first preformed hole and the second preformed hole, it is ensured that wall Reinforcing bar 41 is firmly bonded with wall 1, reinforcement foundation 42 and stone basis 2, with one section of reinforcing bar by basis corresponding on vertical direction Reinforcing bar 42 and wall steel bar 41 are welded, and reinforcement foundation 42 and the anchor pole 3 close to stone basis 2 are welded;
The steel reinforcement cage 51 being made of four vertical muscle and several stirrups is put into groove by step 3 after the completion of ground is tied up It is interior, the then concrete perfusion into groove 7, so that the concrete cladding reinforcing steel bar cage 51 of perfusion, the top of anchor pole 3, reinforcement foundation 42 and the exposed one end of wall steel bar 41 to basis of formation beam 5;
Step 4 backfills the soil body into groove 7 after the concrete consolidation in groove 7, then carries out adding for 1 surface of wall Gu 41 net of wall steel bar can be connect with exposed steel bar 6.
In conclusion stone masonry house foundation ruggedized construction provided by the invention, soil excavation amount is smaller in work progress, Even without large-scale excavation equipment;The anchor pole squeezed into the side grooves of stone basis has greatly reinforced foundation capability, increases The forced area on stone basis;The setting of foundation beam has dispersed force path, and stone basis and ground always connect after reinforcing Contacting surface product is increased, and the common stress of foundation beam and stone basis significantly reduces the pressure from wall of stone basis receiving Power;By steel tie connection that the connection of two sides foundation beam is integral, the globality of stone basis and foundation beam is enhanced, and is kept away Exempt from loose stone basis to be deformed because bearing excessive stresses;
By the setting of steel reinforcement cage, the pulling force ability to bear of foundation beam can be improved.
The above description is only an embodiment of the present invention, is not intended to limit the scope of the invention, all to utilize this hair Equivalents made by bright specification and accompanying drawing content are applied directly or indirectly in relevant technical field, similarly include In scope of patent protection of the invention.

Claims (7)

1. a kind of stone masonry house foundation ruggedized construction, the stone basis is set in the soil body on ground, the wall body vertical It is fixedly arranged on the top surface on stone basis, which is characterized in that further include anchor pole, steel tie, foundation beam and exposed steel bar;
Multiple anchor poles are vertically arranged in the soil body of stone basis two sides and perpendicular to horizontal plane;
The steel tie includes wall steel bar and reinforcement foundation, and the wall steel bar level is arranged in the lower part of wall, described Reinforcement foundation level is arranged in the top on stone basis, the wall steel bar and reinforcement foundation and sets in vertical direction one-to-one correspondence It sets, the wall steel bar on same vertical direction is fixedly connected with reinforcement foundation;
Two foundation beams are respectively arranged at the two sides on stone basis, the upper end of the anchor pole, the both ends of wall steel bar, basis The both ends of reinforcing bar are protruded into the inside of foundation beam and are fixedly connected with foundation beam;
The exposed steel bar is set to the junction of wall Yu stone basis, and the exposed steel bar is fixedly connected with wall steel bar.
2. stone masonry house foundation ruggedized construction according to claim 1, which is characterized in that stone basis two sides Anchor pole branch is with quincuncial pile formula arrangement.
3. stone masonry house foundation ruggedized construction according to claim 2, which is characterized in that the reinforcement foundation with it is close The anchor pole on stone basis is welded.
4. stone masonry house foundation ruggedized construction according to claim 1, which is characterized in that setting inside the foundation beam There is steel reinforcement cage, the reinforcing bar is made of four vertical muscle and several stirrups;
Seen from the above description, by the setting of steel reinforcement cage, the pulling force ability to bear of foundation beam can be improved.
5. stone masonry house foundation ruggedized construction according to claim 1, which is characterized in that the wall steel bar and wall It is fixedly connected by concrete grouting, the reinforcement foundation is fixedly connected with stone basis by concrete grouting.
6. stone masonry house foundation ruggedized construction according to claim 1, which is characterized in that the exposed steel bar and wall Reinforcing bar is fixedly connected by welding manner.
7. according to claim 1 to the construction method of stone masonry house foundation ruggedized construction described in 6 any one, feature exists In including the following steps:
Step 1, excavating a sliver transvers section respectively according to the profile of foundation beam in stone basis two sides is rectangular groove, in ditch Groove bottom squeezes into anchor pole vertically in the form of quincuncial pile;
Step 2, is arranged multiple first preformed holes in the lower horizontal of wall, and it is pre- to be horizontally disposed with second on the top on stone basis It boxes out, the first preformed hole and the second preformed hole correspond in the vertical direction, and wall steel bar is arranged in the first preformed hole, will Reinforcement foundation is arranged in the second preformed hole, carries out slip casting to the first preformed hole and the second preformed hole, it is ensured that wall steel bar and wall, Reinforcement foundation is firmly bonded with stone basis, is carried out reinforcement foundation corresponding on vertical direction and wall steel bar with one section of reinforcing bar Welding, and reinforcement foundation and the anchor pole close to stone basis are welded;
The steel reinforcement cage being made of four vertical muscle and several stirrups is put into groove, then by step 3 after the completion of ground is tied up The concrete perfusion into groove, so that outside the concrete cladding reinforcing steel bar cage of perfusion, the top of anchor pole, reinforcement foundation and wall steel bar One end of dew is to basis of formation beam;
Step 4 backfills the soil body into groove, then carry out the reinforcing of surface of wall, wall after the concrete consolidation in groove Steel mesh can be connect with exposed steel bar.
CN201910422830.6A 2019-05-21 2019-05-21 Stone masonry house foundation reinforcing structure and method Active CN110206135B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910422830.6A CN110206135B (en) 2019-05-21 2019-05-21 Stone masonry house foundation reinforcing structure and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910422830.6A CN110206135B (en) 2019-05-21 2019-05-21 Stone masonry house foundation reinforcing structure and method

Publications (2)

Publication Number Publication Date
CN110206135A true CN110206135A (en) 2019-09-06
CN110206135B CN110206135B (en) 2024-01-12

Family

ID=67787927

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910422830.6A Active CN110206135B (en) 2019-05-21 2019-05-21 Stone masonry house foundation reinforcing structure and method

Country Status (1)

Country Link
CN (1) CN110206135B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111456080A (en) * 2020-03-12 2020-07-28 浙江大学城市学院 Steel pipe underpinning construction method under existing building foundation
CN112267557A (en) * 2020-10-20 2021-01-26 中国十九冶集团有限公司 Construction method of underground baffle plate supporting structure

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100846094B1 (en) * 2007-01-29 2008-07-14 (주)내경엔지니어링 Abutment structure and the construction method of this for mountains area installation with slope
CN101250886A (en) * 2008-04-09 2008-08-27 武汉大学 Method for reinforcing masonry structure building base
KR20100009802A (en) * 2008-07-21 2010-01-29 강남건영(주) All precast concrete prefabricated water storage tank using precast concrete panel for retaining wall
CN202689240U (en) * 2012-07-05 2013-01-23 西安建筑科技大学 Stone wall body
CN103498572A (en) * 2013-10-12 2014-01-08 北京筑福国际工程技术有限责任公司 Stone-structure externally-added clamping plate beam and clamping plate column reinforced structure and construction method thereof
CN103498571A (en) * 2013-10-12 2014-01-08 北京筑福国际工程技术有限责任公司 Reinforcing stone structure utilizing through-wall reinforcement cages with externally-arranged wire meshes and construction method of reinforcing stone structure
CN103912028A (en) * 2013-01-04 2014-07-09 上海建工二建集团有限公司 Construction protection ultra-deep foundation beam underpinning joint device and usage method thereof
CN108086343A (en) * 2017-12-12 2018-05-29 上海建工建集团有限公司 Overhanging type unilateral side wall mixed reinforcement and replacing structure and its construction method
CN109024662A (en) * 2018-07-19 2018-12-18 深圳市工勘岩土集团有限公司 Method of the anchor pile underpinning without basement building underground space increasing layer
CN210507766U (en) * 2019-05-21 2020-05-12 福建工程学院 Stone masonry house foundation reinforcing structure

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100846094B1 (en) * 2007-01-29 2008-07-14 (주)내경엔지니어링 Abutment structure and the construction method of this for mountains area installation with slope
CN101250886A (en) * 2008-04-09 2008-08-27 武汉大学 Method for reinforcing masonry structure building base
KR20100009802A (en) * 2008-07-21 2010-01-29 강남건영(주) All precast concrete prefabricated water storage tank using precast concrete panel for retaining wall
CN202689240U (en) * 2012-07-05 2013-01-23 西安建筑科技大学 Stone wall body
CN103912028A (en) * 2013-01-04 2014-07-09 上海建工二建集团有限公司 Construction protection ultra-deep foundation beam underpinning joint device and usage method thereof
CN103498572A (en) * 2013-10-12 2014-01-08 北京筑福国际工程技术有限责任公司 Stone-structure externally-added clamping plate beam and clamping plate column reinforced structure and construction method thereof
CN103498571A (en) * 2013-10-12 2014-01-08 北京筑福国际工程技术有限责任公司 Reinforcing stone structure utilizing through-wall reinforcement cages with externally-arranged wire meshes and construction method of reinforcing stone structure
CN108086343A (en) * 2017-12-12 2018-05-29 上海建工建集团有限公司 Overhanging type unilateral side wall mixed reinforcement and replacing structure and its construction method
CN109024662A (en) * 2018-07-19 2018-12-18 深圳市工勘岩土集团有限公司 Method of the anchor pile underpinning without basement building underground space increasing layer
CN210507766U (en) * 2019-05-21 2020-05-12 福建工程学院 Stone masonry house foundation reinforcing structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111456080A (en) * 2020-03-12 2020-07-28 浙江大学城市学院 Steel pipe underpinning construction method under existing building foundation
CN112267557A (en) * 2020-10-20 2021-01-26 中国十九冶集团有限公司 Construction method of underground baffle plate supporting structure
CN112267557B (en) * 2020-10-20 2022-08-09 中国十九冶集团有限公司 Construction method of underground baffle plate supporting structure

Also Published As

Publication number Publication date
CN110206135B (en) 2024-01-12

Similar Documents

Publication Publication Date Title
CN103711135B (en) Anti-slide pile of jointed arch structure
CN110820763A (en) Truss type cast-in-situ bored pile supporting method for mucky soil deep foundation pit
CN206941608U (en) A kind of diaphram wall foundation pit supporting construction
CN206706772U (en) A kind of double steel sheet pile supporting construction
CN207092107U (en) A kind of anti-subsidence structure using diaphram wall
CN204590038U (en) A kind of permanent foundation pit supporting construction
CN110241828A (en) The outer sealing construction method for supporting of anchor in a kind of row's grating tubular pole grouting behind shaft or drift lining
CN110206038A (en) Supporting construction and construction method at a kind of concave foundation pit external corner
CN107059882A (en) Arch anchor net and Anchor-Pile Retaining Structure structure
CN112301887A (en) Suspension bridge main cable anchoring system under bedrock deep-buried condition and construction method
CN110206135A (en) A kind of stone masonry house foundation ruggedized construction and method
CN201801843U (en) Overwater gravity type earth-retaining structure with anchoring structure
CN107165173A (en) A kind of foundation pit supporting system and its construction method
CN109881683A (en) A kind of more sublevel retaining structures and its construction method for combining artificial earth fill's grouting reinforcement technique
CN211285725U (en) Basin hills abrupt slope area high-rise building synthesizes earthquake-resistant structure
CN101793027A (en) Core-grouted static pressure anchor rod pile
CN207582471U (en) A kind of Retaining Structure with Double-row Piles equipped with deep layer prestress anchorage cable
CN212129160U (en) Oblique-pulling foundation pit supporting structure for pile top
CN209243910U (en) A kind of side slope building structure
CN101298779B (en) Method for enhancing frame construction building shock strength
CN206337566U (en) Foundation ditch vertical prestressing anchor pole supporting construction
CN108005086B (en) A kind of high buttress counter pull type inclined support structure for pattern foundation pit supporting structure
CN210507766U (en) Stone masonry house foundation reinforcing structure
CN108589738A (en) Half gravity dam formula foundation pit enclosure structure and its construction method
CN201232189Y (en) Composite soil nail wall supporting construction for adding piers

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: No.3, Xueyuan Road, new campus of Fuzhou University, Shangjie Town, Minhou County, Fuzhou City, Fujian Province

Applicant after: Fujian University of Science and Technology

Applicant after: Fujian Qianye Construction Engineering Co.,Ltd.

Applicant after: Fuzhou Peiyan Engineering Technology Co.,Ltd.

Address before: No.3, Xueyuan Road, new campus of Fuzhou University, Shangjie Town, Minhou County, Fuzhou City, Fujian Province

Applicant before: FUJIAN University OF TECHNOLOGY

Applicant before: Fujian Qianye Construction Engineering Co.,Ltd.

Applicant before: Fuzhou Peiyan Engineering Technology Co.,Ltd.

CB02 Change of applicant information
CB03 Change of inventor or designer information

Inventor after: Lin Shangshun

Inventor after: Lin Changgeng

Inventor after: Wang Wenping

Inventor after: Lin Yongjie

Inventor after: Ye Shiji

Inventor after: Lin Yulian

Inventor before: Lin Shangshun

Inventor before: Xue Ling

Inventor before: Lin Changgeng

Inventor before: Wang Wenping

Inventor before: Lin Yongjie

Inventor before: Ye Shiji

Inventor before: Lin Yulian

CB03 Change of inventor or designer information
TA01 Transfer of patent application right

Effective date of registration: 20231207

Address after: No.3, Xueyuan Road, new campus of Fuzhou University, Shangjie Town, Minhou County, Fuzhou City, Fujian Province

Applicant after: Fujian University of Science and Technology

Applicant after: Fuzhou Peiyan Engineering Technology Co.,Ltd.

Address before: No.3, Xueyuan Road, new campus of Fuzhou University, Shangjie Town, Minhou County, Fuzhou City, Fujian Province

Applicant before: Fujian University of Science and Technology

Applicant before: Fujian Qianye Construction Engineering Co.,Ltd.

Applicant before: Fuzhou Peiyan Engineering Technology Co.,Ltd.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant