CN110202300A - Wind power tower door frame welding platform - Google Patents

Wind power tower door frame welding platform Download PDF

Info

Publication number
CN110202300A
CN110202300A CN201910553077.4A CN201910553077A CN110202300A CN 110202300 A CN110202300 A CN 110202300A CN 201910553077 A CN201910553077 A CN 201910553077A CN 110202300 A CN110202300 A CN 110202300A
Authority
CN
China
Prior art keywords
ladder
door frame
platform
power tower
wind power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910553077.4A
Other languages
Chinese (zh)
Other versions
CN110202300B (en
Inventor
张威
张浩然
周化锦
张萍
段鹏凯
廖承桂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Hydropower Fourth Bureau (yangjiang) Marine Equipment Co Ltd
Original Assignee
China Hydropower Fourth Bureau (yangjiang) Marine Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Hydropower Fourth Bureau (yangjiang) Marine Equipment Co Ltd filed Critical China Hydropower Fourth Bureau (yangjiang) Marine Equipment Co Ltd
Priority to CN201910553077.4A priority Critical patent/CN110202300B/en
Priority claimed from CN201910553077.4A external-priority patent/CN110202300B/en
Publication of CN110202300A publication Critical patent/CN110202300A/en
Application granted granted Critical
Publication of CN110202300B publication Critical patent/CN110202300B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K37/00Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K37/00Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups
    • B23K37/04Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups for holding or positioning work
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K37/00Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups
    • B23K37/04Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups for holding or positioning work
    • B23K37/0461Welding tables

Landscapes

  • Physics & Mathematics (AREA)
  • Optics & Photonics (AREA)
  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Wind Motors (AREA)

Abstract

The present invention discloses a kind of wind power tower door frame welding platform, including portal frame, travelling platform, ladder, hoist engine, traction piece, fixed pulley and free bearing.The fixed pulley is installed on the crossbeam of the portal frame, the hoist engine is located at the corresponding lower section of the fixed pulley, the travelling platform is located at the front of the crossbeam, the free bearing is located at the back lower place of the travelling platform, the ladder is located at the front of the crossbeam, the bottom end of the ladder and the free bearing are hinged, the top of the ladder is fixed with the travelling platform, one end of the traction piece is installed on the travelling platform or ladder, the other end of the traction piece is installed on the hoist engine, the traction piece is also around in the fixed pulley from the rear of the crossbeam.Wind power tower door frame welding platform of the invention has the advantages that operate conveniently, improves production efficiency, reduces occupied space and at low cost.

Description

Wind power tower door frame welding platform
Technical field
The present invention relates to the equipment used in wind-power tower manufacturing process more particularly to a kind of welding of wind power tower door frame are flat Platform.
Background technique
Wind-power tower is the capital equipment for supporting high altitude wind power generator group, and offshore wind farm tower height is generally 85 meters of left sides The right side is divided into 4 sections, bottom section diameter about 7-7.5m.Every set tower is provided with tower door in bottom section, when tower doorframe is installed, tower (shape is cylindrical body) puts to be horizontal, and doorframe needs operator to tower outer surface by manual gas shield welding after being installed Carry out outer seam welding.In actual production, since the bottom section tower of offshore wind farm tower is relatively large in diameter, doorframe out-seam welding position Higher, operator is easy to slide from barrel, it is necessary to platform be arranged and protected.
The Platform Designing that conventional land wind power tower door frame welding is used is only protective platform and necessary supporting member, Cooperate aluminium alloy ladder to use, needs to carry out using workshop crane tool to be hoisted to tower surface, while also being drawn It is fixed.And for offshore wind farm tower, platform, aluminium alloy ladder feature dimension are larger, compare occupied space, and necessary Using lifting equipment handling and fixation, therefore, the cost time is long and there are unhandy defects, meanwhile, have an effect on production effect Rate;In addition, there is also at high cost, installing and dismountings often and the defect of stability difference.
Therefore, it is badly in need of wanting a kind of stable structure, at low cost, the wind tower tube door that operates conveniently and reduce installing and dismounting number Frame welding platform overcomes drawbacks described above.
Summary of the invention
The purpose of the present invention is to provide a kind of stable structure, it is at low cost, operate conveniently and reduce installing and dismounting number Wind power tower door frame welding platform.
To achieve the above object, wind power tower door frame welding platform of the invention include portal frame, travelling platform, ladder, Hoist engine, traction piece, fixed pulley and free bearing.The fixed pulley is installed on the crossbeam of the portal frame, and the hoist engine is located at The corresponding lower section of the fixed pulley, the travelling platform are located at the front of the crossbeam, and the free bearing is located at the travelling platform The back lower place, the ladder is located at the front of the crossbeam, and the bottom end of the ladder and the free bearing are hinged, the top of the ladder End is fixed with the travelling platform, and one end of the traction piece is installed on the travelling platform or ladder, the traction piece The other end is installed on the hoist engine, and the traction piece is also around in the fixed pulley from the rear of the crossbeam.
Preferably, the free bearing is located at the front of the hoist engine.
Preferably, the ladder is in the arranged spaced apart of the first from left right side on the travelling platform, each ladder Bottom end it is each side hinged with a free bearing.
Preferably, the fixed pulley is located at the surface of the hoist engine, the fixed pulley also exceeds the travelling platform Or the position for being installed with the traction piece of ladder.
Preferably, the centre of the travelling platform penetratingly offers operation hole.
Preferably, the bottom of the travelling platform has supporting leg, the supporting leg is distributed in the bottom of the travelling platform Everywhere in portion.
Preferably, the bottom of the supporting leg is equipped with neonychium flexible.
Preferably, the neonychium is rubber pad or silicagel pad.
Preferably, being equipped with guardrail on the travelling platform and ladder.
Preferably, the traction piece is wirerope.
Compared with prior art, since fixed pulley is installed on the crossbeam of portal frame, it is corresponding that hoist engine is located at fixed pulley Lower section, travelling platform are located at the front of crossbeam, and free bearing is located at the back lower place of travelling platform, and ladder is located at the front of crossbeam, ladder Bottom end and free bearing it is hinged, top and the travelling platform of ladder are fixed, and one end of traction piece is installed on travelling platform or ladder, The other end of traction piece is installed on hoist engine, and traction piece is also around in fixed pulley from the rear of crossbeam, therefore in the door to wind-power tower When frame is welded, traction piece traction travelling platform is passed downwardly through together with ladder around ladder in leading for fixed pulley by hoist engine Hinged place between free bearing lift or decline pivot pendulum so that travelling platform be affixed on fast and reliablely wind-power tower or It is lifted from wind-power tower, on the one hand makes the welding of doorframe easy to operate;On the other hand, since travelling platform is together with climbing The pivot pendulum that hinged place of the ladder together between ladder and free bearing is lifted or declined, i.e., the height of adjustable travelling platform and position It sets, to match the door frame welding of different wind-power towers, therefore does not need using lifting equipment, it being capable of effectively save place and reduction Installing and dismounting number;Furthermore by the hinged of the bottom end and free bearing of fixed pulley and ladder, on the one hand make the cloth of hoist engine It sets more convenient, on the other hand makes the stabilized structure of wind power tower door frame welding platform of the invention and at low cost.
Detailed description of the invention
Fig. 1 is schematic perspective view when wind power tower door frame welding platform of the invention is affixed on tower.
Fig. 2 is wind power tower door frame welding platform shown in FIG. 1 in the planar structure signal projected along arrow D direction Figure.
Fig. 3 is wind power tower door frame welding platform shown in FIG. 1 in the planar structure projected along arrow A meaning opposite direction Schematic diagram.
Specific embodiment
For the technology contents that the present invention will be described in detail, construction feature, below in conjunction with embodiment and cooperate attached drawing make into One step explanation.
It please refers to Fig.1 to Fig.3, wind power tower door frame welding platform 100 of the invention is applied to the horizontal wind tower put The door frame welding of cylinder 200, in order to which door frame welding of the operator to wind-power tower 200 operates.Wherein, wind tower of the invention Tube door frame welding platform 100 include portal frame 10, travelling platform 20, ladder 30, hoist engine 40, traction piece 50, fixed pulley 60 and Free bearing 70.Fixed pulley 60 is installed on the crossbeam 11 of portal frame 10, for changing traction Impact direction;It is preferably fixed pulley 60 are located at the middle part of crossbeam 11, and the column 12 of portal frame 10 is fixed on ground, to ensure the solid and reliable property of portal frame 10, but It is without being limited thereto.Hoist engine 40 is located at the corresponding lower section of fixed pulley 60, is preferably, hoist engine 40 be located at fixed pulley 60 just under Side, it may also be said to, fixed pulley 60 is located at the surface of hoist engine 40, consequently facilitating hoist engine 40 is fixed on ground, facilitates peace Dress and later maintenance;Meanwhile more conducively hoist engine 40 carries out draw operations to the traction piece 50 for being around in fixed pulley 60, but is not limited to This.Travelling platform 20 is located at the front of crossbeam 11, and free bearing 70 is located at the back lower place of travelling platform 20, is preferably, free bearing 70 is also Positioned at the front of hoist engine 40, to ensure so that 30 top of ladder turns forward and the sweptback arrangement in bottom end, state is shown in Shown in Fig. 2, for example, free bearing 70 is affixed on ground, but not limited to this.Ladder 30 is located at the front of crossbeam 11, ladder 30 bottom end and free bearing 70 are hinged, so that ladder 30 and free bearing 70 form a hinged center line C;The top of ladder 30 and walking are flat Platform 20 is fixed, and such as, but not limited to this is welded and fixed or is threadedly coupled fixation;Specifically, ladder 30 is on travelling platform 20 Right arranged spaced apart of one the first from left, the bottom end of each ladder 30 it is each side hinged with a free bearing 70, in order to operate Travelling platform 20 is fallen on personnel, is preferably, left and right directions (i.e. arrow D direction and opposite of the ladder 30 along portal frame 10 Direction) it is mutually aligned, to ensure that each ladder 30 is overlapped with the hinged center line C of free bearing 70, but not limited to this.Traction piece 50 One end is installed on travelling platform 20, and the other end of traction piece 50 is installed on hoist engine 40, and traction piece 50 is also from the rear of crossbeam 11 It is around in fixed pulley 60, i.e. position of the traction piece 50 between its both ends is around in fixed pulley 60, is preferably, traction piece 50 is steel Cord, to improve 50 bearing capacity of traction piece, and fixed pulley 60 also exceed travelling platform 20 for being installed with traction piece 50 Position 21, the purpose designed in this way are to increase traction piece 50 to the stabilizing power of travelling platform 20;For example, position 21 is one Pull ring structure, so that traction piece 50 is fixed by canoe and travelling platform 20, increase traction piece 50 and travelling platform 20 it Between assembly and disassembly operations convenience, be preferably that between two ladders 30 in institute's clip space, design, which can avoid, in this way is climbed at position 21 Terraced 30 pairs of traction pieces 50 cause to interfere, and further improve the reliability of the work of traction piece 50, but not limited to this.It is intelligible It is that according to actual needs, traction piece 50 can be assemblied at ladder 30, as long as ensuring hoist engine 40 in the guiding of fixed pulley 60 The pivot that ladder 30 lifts or declines around hinged center line C is drawn by traction piece 50 down to put.More specifically, as follows:
It as shown in Figure 1, the centre of travelling platform 20 penetratingly offers operation hole 22, is preferably that operation hole 22 is side Shape hole, it is ensured that there are enough working spaces.Specifically, the bottom of travelling platform 20 has supporting leg 23, and supporting leg 23 is distributed Everywhere in the bottom of travelling platform 20, more excellent four corners in the bottom for being distributed across travelling platform 20, and be symmetrical set, For guaranteeing that the wall surface of travelling platform 20 and wind-power tower 200 is steadily contacted, so that supporting leg 23 plays support travelling platform 20 Effect;It more specifically, the bottom of supporting leg 23 is equipped with neonychium 24 flexible, is preferably that neonychium 24 is rubber pad Or silicagel pad, the wall surface that can be effectively protected wind-power tower 200 is not supported the scratch of leg 23, while increasing travelling platform 20 and wind The frictional force of the wall surface of pylon cylinder 200 enhances stability, but not limited to this.In order to increase the intensity of travelling platform 20, walking is flat Platform 20 is welded to form by fashioned iron (such as, but not limited to this I-steel), and the top surface of travelling platform 20 can be laid with checkered steel plate, side Just the movement of operator.For the safety of effective guarantee operator, therefore travelling platform 20 and ladder 30 are equipped with guardrail 80.
In conjunction with attached drawing, the working principle of wind power tower door frame welding platform of the invention is illustrated: when lifting downwards When playing travelling platform 20, winding traction piece 50 is done by hoist engine 40 at this time and is moved, is located at hoist engine 40 so as to shorten traction piece 50 With the length between travelling platform 20, thus by traction piece 50 pull travelling platform 20 together with ladder 30 around hinged center line C is lifted up;When to put down travelling platform 20 downwards, the scroll movement unclamped to traction piece 50 is done by hoist engine 40 at this time, To increase length of the traction piece 50 between hoist engine 40 and travelling platform 20, thus is unclamped by traction piece 50 and walking is put down The pulling of platform 20 and ladder 30, and under the self weight of travelling platform 20 and ladder 30, so that travelling platform 20 is together with ladder 30 1 It rises and declines downwards around hinged center line C.
Compared with prior art, since fixed pulley 60 is installed on the crossbeam 11 of portal frame 10, hoist engine 40 is located at fixed sliding 60 corresponding lower sections are taken turns, travelling platform 20 is located at the front of crossbeam 11, and free bearing 70 is located at the back lower place of travelling platform 20, ladder 30 Positioned at the front of crossbeam 11, the bottom end of ladder 30 and free bearing 70 are hinged, and the top of ladder 30 and travelling platform 20 are fixed, traction piece 50 one end is installed on travelling platform 20 or ladder 30, and the other end of traction piece 50 is installed on hoist engine 40, and traction piece 50 is also It is around in fixed pulley 60 from the rear of crossbeam 11, therefore when the doorframe to wind-power tower 200 welds, cunning is being determined by hoist engine 40 Wheel 60 leads the hinge for passing downwardly through the traction travelling platform 20 of traction piece 50 together with ladder 30 between ladder 30 and free bearing 70 The pivot pendulum that the place of connecing (i.e. hinged center line C) lifts or declines, so that travelling platform 20 is affixed on wind tower fast and reliablely Cylinder 200 lifts from wind-power tower 200, on the one hand makes the welding of doorframe easy to operate;On the other hand, due to walking The pivot pendulum that platform 20 lifts or declines together with hinged place of the ladder 20 between ladder 30 and free bearing 70 can match not The door frame welding of same wind-power tower 200, therefore assembly and disassembly operations again is not needed, therefore reduce installing and dismounting number;Furthermore by fixed The bottom end of pulley 60 and ladder 30 is hinged with free bearing 70, on the one hand makes the arrangement of hoist engine 40 more convenient, on the other hand So that the stabilized structure of wind power tower door frame welding platform 100 of the invention and at low cost.
It should be noted that the direction of the arrow A meaning in figure is the direction of portal frame 10 back to front, arrow B is signified Direction be the direction of portal frame 10 from the bottom to top, the direction of arrow D meaning is the direction of portal frame 10 from left to right;And from figure Find out, the axial direction of wind-power tower 200 is exactly the left and right directions of portal frame 10, and but not limited to this.
The above disclosure is only a preferred example of the present invention, and the scope of the invention cannot be limited thereby, Therefore equivalent changes made in accordance with the claims of the present invention belong to the range that the present invention is covered.

Claims (10)

1. a kind of wind power tower door frame welding platform, which is characterized in that including portal frame, travelling platform, ladder, hoist engine, lead Draw part, fixed pulley and free bearing, the fixed pulley is installed on the crossbeam of the portal frame, and the hoist engine is located at the fixed pulley Corresponding lower section, the travelling platform are located at the front of the crossbeam, and the free bearing is located at the back lower place of the travelling platform, institute The front that ladder is located at the crossbeam is stated, the bottom end of the ladder and the free bearing are hinged, the top of the ladder and the row It walks platform to fix, one end of the traction piece is installed on the travelling platform or ladder, the other end installation of the traction piece In the hoist engine, the traction piece is also around in the fixed pulley from the rear of the crossbeam.
2. wind power tower door frame welding platform according to claim 1, which is characterized in that the free bearing is located at the elevator The front of machine.
3. wind power tower door frame welding platform according to claim 1, which is characterized in that the ladder is flat in the walking In right arranged spaced apart of a first from left on platform, the bottom end of each ladder it is each side hinged with a free bearing.
4. wind power tower door frame welding platform according to claim 1, which is characterized in that the fixed pulley is located at the volume The surface of machine is raised, the fixed pulley also exceeds the position for installing with the traction piece of the travelling platform or ladder.
5. wind power tower door frame welding platform according to claim 1, which is characterized in that the centre of the travelling platform is passed through Offer operation hole with wearing.
6. wind power tower door frame welding platform according to claim 1, which is characterized in that the bottom of the travelling platform has There is supporting leg, the supporting leg is distributed in everywhere in the bottom of the travelling platform.
7. wind power tower door frame welding platform according to claim 6, which is characterized in that install the bottom of the supporting leg Flexible neonychium.
8. wind power tower door frame welding platform according to claim 7, which is characterized in that the neonychium be rubber pad or Silicagel pad.
9. wind power tower door frame welding platform according to claim 1, which is characterized in that on the travelling platform and ladder It is equipped with guardrail.
10. wind power tower door frame welding platform according to claim 1, which is characterized in that the traction piece is wirerope.
CN201910553077.4A 2019-06-24 Welding platform for wind power tower cylinder door frame Active CN110202300B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910553077.4A CN110202300B (en) 2019-06-24 Welding platform for wind power tower cylinder door frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910553077.4A CN110202300B (en) 2019-06-24 Welding platform for wind power tower cylinder door frame

Publications (2)

Publication Number Publication Date
CN110202300A true CN110202300A (en) 2019-09-06
CN110202300B CN110202300B (en) 2024-07-09

Family

ID=

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112643265A (en) * 2020-12-04 2021-04-13 武汉华电工程装备有限公司 Anti-falling cantilever type wind power tower cylinder welding platform
CN116921941A (en) * 2023-09-14 2023-10-24 中广核(兴安盟)新能源有限公司 Welding platform for wind power tower cylinder door frame

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080093176A1 (en) * 2006-09-28 2008-04-24 Rosenthal Harry J Lifting apparatus and method for transporting people and objects
US7424932B1 (en) * 2004-09-02 2008-09-16 Patrick Arthur Murphy Lifting hoist assembly
CN202155668U (en) * 2011-06-28 2012-03-07 中国水电四局(酒泉)新能源装备有限公司 Multifunctional welding machine frame for welding soldering seam outside barrel body of wind power generation tower barrel
CN203612826U (en) * 2013-12-09 2014-05-28 天津天易海上工程有限公司 Gunwale fixing gantry crane
CN204474085U (en) * 2014-08-01 2015-07-15 广州市京龙工程机械有限公司 A kind of elevator high-altitude maintenance job platform
CN205464746U (en) * 2016-01-14 2016-08-17 新疆天山恒合能源装备有限责任公司 Wind power tower cylinder outer wall welding seam welding platform truck
CN205684924U (en) * 2016-06-07 2016-11-16 中国水电四局(酒泉)新能源装备有限公司 A kind of novel wind power tower door frame welding protecting platform
CN206784865U (en) * 2017-03-20 2017-12-22 中铁四局集团电气化工程有限公司 A kind of detachable adjustable for height subway tunnel section construction operation platform
CN210209147U (en) * 2019-06-24 2020-03-31 中国水电四局(阳江)海工装备有限公司 Wind power tower cylinder door frame welding platform

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7424932B1 (en) * 2004-09-02 2008-09-16 Patrick Arthur Murphy Lifting hoist assembly
US20080093176A1 (en) * 2006-09-28 2008-04-24 Rosenthal Harry J Lifting apparatus and method for transporting people and objects
CN202155668U (en) * 2011-06-28 2012-03-07 中国水电四局(酒泉)新能源装备有限公司 Multifunctional welding machine frame for welding soldering seam outside barrel body of wind power generation tower barrel
CN203612826U (en) * 2013-12-09 2014-05-28 天津天易海上工程有限公司 Gunwale fixing gantry crane
CN204474085U (en) * 2014-08-01 2015-07-15 广州市京龙工程机械有限公司 A kind of elevator high-altitude maintenance job platform
CN205464746U (en) * 2016-01-14 2016-08-17 新疆天山恒合能源装备有限责任公司 Wind power tower cylinder outer wall welding seam welding platform truck
CN205684924U (en) * 2016-06-07 2016-11-16 中国水电四局(酒泉)新能源装备有限公司 A kind of novel wind power tower door frame welding protecting platform
CN206784865U (en) * 2017-03-20 2017-12-22 中铁四局集团电气化工程有限公司 A kind of detachable adjustable for height subway tunnel section construction operation platform
CN210209147U (en) * 2019-06-24 2020-03-31 中国水电四局(阳江)海工装备有限公司 Wind power tower cylinder door frame welding platform

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112643265A (en) * 2020-12-04 2021-04-13 武汉华电工程装备有限公司 Anti-falling cantilever type wind power tower cylinder welding platform
CN116921941A (en) * 2023-09-14 2023-10-24 中广核(兴安盟)新能源有限公司 Welding platform for wind power tower cylinder door frame
CN116921941B (en) * 2023-09-14 2023-12-15 中广核(兴安盟)新能源有限公司 Welding platform for wind power tower cylinder door frame

Similar Documents

Publication Publication Date Title
EP3517776B1 (en) Method and equipment for replacing wind turbine components
CN205294665U (en) Jack -up tower crane based on engineering mechanics
CN103274315B (en) Installing and hoisting device for side plate and upright of gas chamber
CN103352559A (en) Hanging type movable working platform for storage tank maintenance
CN204629404U (en) Gear-driven navigational lighting aid tower fragile stem jacking system
CN203269405U (en) Hoisting device for mounting side plates and upright columns of gas cabinet
CN204629405U (en) Navigational lighting aid tower fragile stem jacking system
JP5584674B2 (en) Steel tower repair system
CN101649684B (en) Installing method of roof mast
CN204170002U (en) A kind of artificial digging pile safety apparatus
CN210825200U (en) Lifting device for large-scale power equipment installation
CN110202300A (en) Wind power tower door frame welding platform
CN104847283B (en) Cluster well drilling module drilling rod ramp, ocean
CN208249734U (en) One kind is built the road gantry crane
CN110712718A (en) Device and method for boarding offshore wind power platform
CN213039199U (en) Movable anti-falling ladder stand
CN210852816U (en) Offshore wind power platform boarding device
CN210209147U (en) Wind power tower cylinder door frame welding platform
CN210886924U (en) Maintenance platform in retractable double-cable-plane cable-stayed bridge tower stay cable area
KR20150053449A (en) Jack up rig having a retractable platform of escape chute
CN110202300B (en) Welding platform for wind power tower cylinder door frame
CN106672804A (en) Travelling hoist rope changing auxiliary device
CN208401377U (en) A kind of inspection platform for power station high voltage switchyard
CN205603179U (en) Prevent electric power engineering work platform that falls
CN216190876U (en) Leveling system for working bucket of aerial working platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant