CN110163562A - A kind of mine business backlog processing method - Google Patents

A kind of mine business backlog processing method Download PDF

Info

Publication number
CN110163562A
CN110163562A CN201910345602.3A CN201910345602A CN110163562A CN 110163562 A CN110163562 A CN 110163562A CN 201910345602 A CN201910345602 A CN 201910345602A CN 110163562 A CN110163562 A CN 110163562A
Authority
CN
China
Prior art keywords
business
mine
software
operation flow
platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910345602.3A
Other languages
Chinese (zh)
Inventor
毛杜
王晋淼
汤其旺
毕林
王李管
张炬
任助理
钟德云
陈鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha Di Mai Numeral Science And Technology Inc Co
Original Assignee
Changsha Di Mai Numeral Science And Technology Inc Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha Di Mai Numeral Science And Technology Inc Co filed Critical Changsha Di Mai Numeral Science And Technology Inc Co
Priority to CN201910345602.3A priority Critical patent/CN110163562A/en
Publication of CN110163562A publication Critical patent/CN110163562A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/109Time management, e.g. calendars, reminders, meetings or time accounting
    • G06Q10/1093Calendar-based scheduling for persons or groups
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/02Agriculture; Fishing; Forestry; Mining

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Quality & Reliability (AREA)
  • Data Mining & Analysis (AREA)
  • Operations Research (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Agronomy & Crop Science (AREA)
  • Animal Husbandry (AREA)
  • Marine Sciences & Fisheries (AREA)
  • Mining & Mineral Resources (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

A kind of mine business backlog processing method disclosed by the invention, comprising steps of creating business form and initiating operation flow;Backlog and business form are signed for and checked to login techniques collaborative platform;Click-to-call service software link starts business software;Business software downloads associated traffic data from the central database;The traffic engineered teacher in mine completes the vocational work by business software;Attachment page is uploaded to central database;It submits business form and automatically goes to downstream node according to business process flow;Downstream node receives the pending prompting of mine business, examines whether upper process node traffic work meets the requirements, and does not meet, rejects, meet, continues;Business process in mine circulates to downstream node, and so on, until operation flow terminates.The present invention realizes the unitized of mine Life cycle business, orderly management, work compound and realizes data sharing, avoids loss of data and inconsistent, raising mine vocational work efficiency and quality.

Description

A kind of mine business backlog processing method
Technical field
The present invention relates to Mine digitalization intelligent construction fields, more particularly, to a kind of mine business backlog Processing method.
Background technique
During Mine digitalization intelligent construction, it is related to exploration, planning, design, plan, production management, measurement are tested Each Service Period such as receive, and the vocational work for each profession such as geology, measurement, mining are further related in Service Period, each business The vocational work of stage and each profession is closely linked by business information data again.However existing mine respectively participates in Side, each post, information interchange is still and is transmitted with drawing between each technical professional, and information data was asked for Cheng Zhongxu across participant, it is trans-departmental, across personnel, the exchange transmitting of information data hinders inevitable, and information data was transmitted It inevitably occasions a delay in journey, defect and loss.In addition, each service software system often mutually isolates, establishes one's own system, thereby increases and it is possible to From different production firms, and the industry of this participant, this department and this profession is only considered when business information data processing Business demand, message data content and format often can not meet subsequent business demand, then need to repeat typing, cause Information Number It according to redundancy, waste and can not share, and lead to vocational work complicated, low efficiency and of low quality.
For above-mentioned phenomenon, need a kind of based on the processing of the mine business backlog of business process in mine and business form Method.
Summary of the invention
The purpose of the present invention is to provide a kind of mine business backlog processing methods, realize mine Life cycle industry The unitized of process of being engaged in, orderly management and work compound, it is total across participant, trans-departmental and information data across personnel It enjoys, guarantees that all business datums are effectively organized and tracked, guarantee do not occur information data in the transmittance process of information data It loses, reduces the ambiguity and inconsistent, raising work quality and efficiency of information data.
To reach above-mentioned technical purpose, technical scheme is as follows:
A kind of mine business backlog processing method, this method provide a technology synergy platform, one or more business Software and a central database, the technology synergy platform include Business Process Management module, user management module, data-interface And business software interface;
The Business Process Management module is matched for defining and creating mine Life cycle operation flow by internet Standardization operation flow is set, initiates, handles and examines, the filing of operation flow achievement and business are completed to remind, operation flow pipe Reason module is also used to create business form;The user management module is matched for the affiliated organizational structure management of user, user role It sets, the technology synergy platform feature of role and operating location configure, role corresponding business software uses and matches with function privilege Set, the management of user login information and for user log in obtain backlog notice and prompting message;The data-interface For carrying out data interaction with central database and business software, the business software interface is used for technology synergy platform and business Software carries out data interaction;The business software is used to work for traffic engineered teacher's processing business;The central database is used for Storage service data and for business software downloading service data;
The mine business backlog processing method includes the following steps:
S1. Business Process Management module is standardized according to the business schedule requirement under target job place, definition with creation Operation flow, and according to the business form under the specific business in establishing business process mine target job place, the traffic table Single includes Business Name, operating location, business software link, operation flow examination & approval option (agree to or reject) and explanation, industry Workflow history of being engaged in and attachment page, the operation flow contain at least one flow nodes, and flow nodes are traffic engineered containing correspondence The user information and business software of teacher links;First send business form to first flow nodes traffic engineered teacher, with Initiate the operation flow;
S2. traffic engineered teacher inputs its user information login techniques collaborative platform in user management module, signs for and checks Backlog and business form;
S3. the business software link carried on traffic engineered teacher's click-to-call service list, technology synergy platform receive feedback letter Breath, by Business Process Management module by business software interface start under traffic engineered teacher's claim corresponding to all business it is soft Part;
S4. correlation needed for business software downloads the vocational work of the flow nodes by data-interface from the central database Business datum;
S5. traffic engineered teacher completes the business under its job duty using business software based on associated traffic data Work, and newly generated business datum achievement is submitted and is saved in central database;
S6. traffic engineered teacher increases by user management module login techniques collaborative platform, and in the attachment page of business form Add the attachment content formed during the business handling, and attachment content is uploaded to centre data inventory by technology synergy platform Storage, while traffic engineered teacher submits its business form to technology synergy platform, Business Process Management module according to it is defined with match The operation flow set by business form, be responsible for by the business of automatic flow to downstream node in a manner of backlog reminding People;
S7. business responsible person is by user management module login techniques collaborative platform, receive backlog reminding and its Business form executes step S2~S4, to examine whether the vocational work of a upper flow nodes meets the requirements, if not meeting, leads to It crosses business form to be rejected, executes step S2~S6;If meeting, S5~S6 is continued to execute, completes the business of the flow nodes Work, and submit business form;
S8. business process flow goes to downstream node, executes step S7, and so on, until the operation flow terminates, Then the operation flow is marked as being completed, and achievement filing is carried out by Business Process Management module.
Further, in the step S1, when creating business form, Business Process Management module is obtained from user management module Take the corresponding user role information of each flow nodes, the technology synergy platform feature of role corresponding with operating location information, role Business software use and function privilege information be added in business form.
Further, in the step S1, the initiation of operation flow includes initiating and automatically initiating manually;Manually initiate be Business process in mine promoter is according to the business schedule requirement under operating location, by inputting its user's account in user management module Number and password login adopt technology synergy platform, create the business form under the specific business in mine target job place and simultaneously initiate the industry Business process, and automatically initiate, by voluntarily initiating the operation flow after Business Process Management module creation business form.
Further, mine business include probing design, probing design, drilling is edited and recorded, tunnel is edited and recorded, GEOLOGICAL INTERPRETATION, Matter modeling, the termination of ore body, reserves valuation and calculating, underground control measurement, surface control measurement, construction lofting, well lane engineering are surveyed Amount, dead zone measurement, mine amount make an inventory, topographic survey, expropriation of land measurement, exploit study, adopt and cut design, explosion design, filling design, adopt Dig planning, mine ventilation resolves and optimization and production management.
Preferably, the technology synergy platform supports web terminal, C/S client and mobile terminal, user that can pass through web terminal, C/ S client and mobile terminal login techniques collaborative platform.
Further, in the step S3, traffic engineered teacher passes through the business carried on WEB client side click-to-call service list The URL of software link is parsed the URL of business software link using operating system, finds related service software installation position, Start business software, and the parameter in URL is passed into business software, realizes the single-sign-on of business software;The URL packet Include Workflow messages, user information and authority information, target job location information.
Further, in the step S3, traffic engineered teacher finds the business software by the script in C/S client Installation site starts business software, and parameter is passed to business software by script, realizes that the single-point of business software is stepped on Record, the parameter includes Workflow messages, user information and authority information, target job location information.
Further, the content of the backlog reminding includes business form entrance, business process map, operation flow name Title, process promoter, process initiate date, operation flow type, current business process node and operation flow urgency level;Industry Business flow chart includes business game place, business information, operation flow circulation history and attachment page;The content of the attachment page Including document, map file and the vocational work explanation formed during business handling.
Further, in the step S7, if the vocational work of a upper flow nodes meets the requirements, and the flow nodes are Approval process node directly submits business form after addition examination & approval attachment explanation.
Further, in the step S8, business process flow goes to downstream node, if the downstream node is knot The operation flow then is labeled as being completed, and filed by beam flow nodes;If there are also its subsequent processes for the downstream node Node, when the business responsible person of the downstream node has found that the performance data of a upper flow nodes does not meet its vocational work When, then it is rejected.
After adopting the above scheme, technical effect of the invention are as follows:
One, present invention definition and standardization operation flow of the creation based on mine Life cycle, according to standardization business Process creates business form, is successively circulated by business form to each flow nodes, enables to standardize operation flow orderly It executes, realizes the unitized of mine Life cycle operation flow, orderly management and work compound;
Two, the present invention and utilize technology synergy platform associated services software and central database, solve across participant, across The problems such as department, the information data exchange across personnel are transmitted not smooth, delay, defect and lost, also solves information data It redundancy, waste and the problems such as can not share, realize shared across participant, trans-departmental and information data across personnel, guarantee Information data is effectively organized and is tracked, and is guaranteed the loss for not occurring information data in the transmittance process of information data, is reduced letter Cease the ambiguity and inconsistent, raising work quality and efficiency of data.
Detailed description of the invention
Fig. 1 is transaction processing system structure chart in mine provided in an embodiment of the present invention;
Fig. 2 is mine business backlog processing method flow chart provided in an embodiment of the present invention;
Fig. 3 well lane engineering provided in an embodiment of the present invention measures business backlog processing method flow chart;
Fig. 4 mine ventilation business backlog processing method flow chart provided in an embodiment of the present invention.
Specific embodiment
In the following description, numerous specific details are set forth in order to facilitate a full understanding of the present invention.But the present invention can be with Much it is different from other way described herein to implement, those skilled in the art can be without prejudice to intension of the present invention the case where Under do similar improvement, therefore the present invention is not limited to the specific embodiments disclosed below.
In the description of the present invention, it should be noted that term " center ", "upper", "lower", "left", "right", "vertical", The orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" be based on the orientation or positional relationship shown in the drawings, merely to Convenient for description the present invention and simplify description, rather than the device or element of indication or suggestion meaning must have a particular orientation, It is constructed and operated in a specific orientation, therefore is not considered as limiting the invention.In addition, term " first ", " second ", " third " is used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance.
Unless otherwise defined, all technical and scientific terms used herein and belong to technical field of the invention The normally understood meaning of technical staff is identical.Term as used herein in the specification of the present invention is intended merely to description tool The purpose of the embodiment of body, it is not intended that in the limitation present invention.
As shown in Figure 1, a kind of mine business backlog processing method that the embodiment of the present invention discloses, this method is by mine Mountain transaction processing system realizes that the system includes technology synergy platform 100, business software 200 and central database 300, institute Stating technology synergy platform 100 includes that Business Process Management module 101, user management module 102, data-interface 103 and business are soft Part interface 104, and technology synergy platform 100 supports web terminal, C/S client and mobile terminal, user can pass through web terminal, C/S visitor Family end and mobile terminal login techniques collaborative platform 100;
Above-mentioned Business Process Management module 101 passes through interconnection for defining and creating mine Life cycle operation flow Net configures, initiates, handles and examines standardization operation flow, and the filing of operation flow achievement and business are completed to remind, Business Stream Thread management module 101 is also used to create business form;The user management module 102 for the affiliated organizational structure management of user, User role configuration, role 100 function of technology synergy platform and operating location configure, the corresponding business software 200 of role makes It is logged in the management of configuration, user login information with function privilege and for user to obtain backlog notice and remind and believe Breath;The data-interface 103 is used to carry out data interaction, the business software interface with central database and business software 200 104 carry out data interaction for technology synergy platform 100 and business software 200;The business software 200 is used for for traffic engineered The work of teacher's processing business;The central database is for storage service data and for 200 downloading service data of business software;This reality Applying mine business involved in example includes that probing designs, probing design, drilling is edited and recorded, tunnel is edited and recorded, GEOLOGICAL INTERPRETATION, geology are built Mould, the termination of ore body, reserves valuation and calculating, underground control measurement, surface control measurement, construction lofting, well lane engineering measurement, sky Region measurement, mine amount make an inventory, topographic survey, expropriation of land measurement, exploit study, adopt and cut design, explosion design, filling design, digging meter Draw establishment, mine ventilation resolves and optimization and production management.
As shown in Fig. 2, above-mentioned mine business backlog processing method includes the following steps:
S1. Business Process Management module 101 is standardized according to the business schedule requirement under target job place, definition with creation The operation flow of change, and according to the business form under the specific business in establishing business process mine target job place, the business List include Business Name, operating location, business software link, operation flow examination & approval option (agree to or reject) and explanation, Operation flow circulates history and attachment page, and when creating business form, Business Process Management module 101 is from user management module The corresponding user role information of 102 each flow nodes of acquisition, 100 function of technology synergy platform of role and operating location information, Corresponding 200 use of business software of role is added in business form with function privilege information;
Above-mentioned operation flow contain at least one flow nodes, the user information of flow nodes traffic engineered teacher containing correspondence and Business software link;Business form is sent first to the traffic engineered teacher of first flow nodes, to initiate the operation flow;Industry The initiation for process of being engaged in can use and initiate or automatically initiate manually;Manually initiate be business process in mine promoter according to operation Business schedule requirement under point, it is flat by adopting technology synergy in its user account of input of user management module 102 and password login Platform 100, create the specific business in mine target job place under business form and initiate the operation flow, and automatically initiate then by Business Process Management module 101 voluntarily initiates the operation flow after creating business form;
S2. traffic engineered teacher inputs its user information login techniques collaborative platform 100 in user management module 102, signs for And check backlog and business form;
S3. the business software link carried on traffic engineered teacher's click-to-call service list, technology synergy platform 100 receive feedback Information is then started by Business Process Management module by business software interface 104 corresponding under traffic engineered teacher's claim All business softwares 200;
S4. business software 200 is downloaded needed for the vocational work of the flow nodes from the central database by data-interface 103 Associated traffic data;By taking the technology synergy platform based on WEB terminal as an example, traffic engineered teacher passes through web browser click-to-call service The URL of the business software link carried on list, the URL of business software link is parsed using operating system, finds correlation 200 installation site of business software, starts business software 200, and by parameter (including the Workflow messages, Yong Huxin in URL Breath and authority information, target job location information) business software 200 is passed to, realize the single-sign-on of business software 200;When So, it since the technology of the present invention collaborative platform 100 supports C/S client, can also be searched by the script in C/S client To 200 installation site of business software, start business software 200, and by script by parameter (including Workflow messages, User information and authority information, target job location information) business software 200 is passed to, realize that the single-point of business software 200 is stepped on Record;
S5. traffic engineered teacher completes the industry under its job duty using business software 200 based on associated traffic data It works work, and newly generated business datum achievement is submitted and is saved in central database;
S6. traffic engineered teacher passes through 102 login techniques collaborative platform 100 of user management module, specific traffic engineered teacher Its user information can be inputted in user management module 102 by web terminal (web browser), C/S client and mobile terminal log in skill Then art collaborative platform 100 increases the attachment content formed during the business handling in the attachment page of business form, and by skill Art collaborative platform 100 uploads attachment content to central database and stores;Traffic engineered teacher also mentions after login techniques collaborative platform 100 Hand over its business form to technology synergy platform 100, Business Process Management module 101 is according to defined and configured operation flow By business form in a manner of backlog reminding automatic flow to downstream node business responsible person;The backlog The content of prompting includes business form entrance, business process map, operation flow title, process promoter, process initiation date, industry Business flow type, current business process node and operation flow urgency level;Operation flow list includes business game place, industry Business information, operation flow circulation history and attachment page;The content of the attachment page include the document formed during business handling, Map file and vocational work explanation.
S7. the business responsible person of downstream node is connect by 102 login techniques collaborative platform 100 of user management module Receive backlog reminding and its business form, execute step S2~S4, with examine a upper flow nodes vocational work whether It meets the requirements, if not meeting, is rejected by business form, execute step S2~S6;If meeting, S5~S6 is continued to execute, The vocational work of the flow nodes is completed, and submits business form;In addition, if the vocational work of a upper flow nodes conforms to It asks, and the flow nodes are approval process node, after addition examination & approval attachment explanation, directly submits business form;
S8. business process flow goes to downstream node, executes step S7, and so on, until the operation flow terminates, Then the operation flow is marked as being completed, and achievement filing is carried out by Business Process Management module 101.
In above-mentioned steps S8, business process flow goes to downstream node, if the downstream node is to terminate process The operation flow then is labeled as being completed, and filed by node;If the downstream node there are also its subsequent flow nodes, When the performance data of the upper flow nodes of the business responsible person of downstream node discovery does not meet its vocational work, then will It is rejected.
At a kind of mine business backlog based on business process in mine and business form provided in an embodiment of the present invention Reason method is successively circulated by business form on the one hand according to standardization establishing business process business form to each process section Point enables standardization operation flow orderly to execute, realizes the unitized of mine Life cycle operation flow, orderly management And work compound, promote working efficiency;On the other hand it solves across participant, trans-departmental information data exchange across personnel The problems such as transmitting not smooth, delay, defect and losing also solves information data redundancy, waste and the difficulties such as can not share Topic realizes and shares across participant, trans-departmental and information data across personnel that guarantee information data is effectively organized and tracking, Guarantee do not occur the loss of information data in the transmittance process of information data, reduces the ambiguity and inconsistent, raising of information data Work quality.
Fig. 3 shows well lane engineering measurement operation flow, and detailed step includes:
A1: being the construction speed of " middle two middle section 0# stope 1# route of area ", unit in charge of construction's survey engineering according to operating location Teacher passes through the user account and password login technology synergy platform of oneself, is using Business Process Management module creation operating location Business form under the well lane engineering measurement operation flow of " middle two middle section 0# stope 1# route of area ", and initiate well lane engineering survey Measure operation flow;
A2: the unit in charge of construction's survey engineer for being responsible for operating location roadway measurement business passes through WEB terminal, C/S client End or mobile phone terminal login techniques collaborative platform receive the pending prompting of business, and the unit in charge of construction for being responsible for roadway measurement business surveys Amount engineer signs for and checks that backlog and roadway measure business form;
A3: unit in charge of construction's survey engineer clicks the well lane engineering software chain on roadway measurement business form by WEB terminal It connects, or by the script of C/S client, technology synergy platform starts the well lane engineering software under engineer's permission automatically, Well lane engineering software is with the user account of technology synergy platform and password automated log on, without repeat logon;
A4: corresponding well lane engineering software is according to pending business automatically from mine under unit in charge of construction's survey engineer permission Central database downloads the roadway control point and measuring point that the operating location has been examined;
A5: unit in charge of construction's survey engineer is based on roadway control point and measuring point, and " leading by well lane engineering software Enter measuring point function " import measuring point data measured by the operating location underground survey, and " connecting automatically using well lane engineering software Line " draw " gradeline " and " roadway center line ", and roadway cross-sectional area, perimeter and supporting information are set, then " gradeline " and " roadway center line " that will just draw saves and is committed to central database;
A6: unit in charge of construction's survey engineer, which logs on to, adopts technology synergy platform, on well lane engineering measurement business form The attachment content that attachment page uploads the formation of the business is uploaded to central database;Unit in charge of construction's survey engineer is submitted simultaneously should Roadway measures business form, and well lane engineering measurement business process flow goes to the unit in charge of construction person in charge of the technology aspect of downstream node;
A7: the unit in charge of construction person in charge of the technology aspect for being responsible for the operating location business passes through WEB terminal, C/S client or hand Generator terminal login techniques collaborative platform receives the pending prompting of business, executes step A2~A4, examines that construction survey engineer is drawn Roadway cross-sectional area, perimeter and supporting letter are drawn as required and be arranged to " gradeline " and " roadway center line " of system whether Breath, if not meeting, login techniques collaborative platform is rejected by well lane engineering measurement business form and gives construction survey engineer, again Execute step A2~A6;If meeting, because the job duty of unit in charge of construction person in charge of the technology aspect is examination & approval, then login techniques collaborative platform Business form is measured by well lane engineering and executes examination & approval " agreement ", and well lane engineering is submitted to measure business form;
A8: well lane engineering measurement business process flow goes to the supervising engineer of downstream node, is responsible for the operating location The supervising engineer of business receives that business is pending to be mentioned by WEB terminal, C/S client or mobile phone terminal login techniques collaborative platform It wakes up, executes step A7, if not meeting, login techniques collaborative platform measures business form by well lane engineering and rejects to construction survey Engineer re-execute the steps A2~A7;If meeting, because the job duty of supervising engineer is examination & approval, then login techniques are cooperateed with Platform measures business form by well lane engineering and executes examination & approval " agreement ", and well lane engineering is submitted to measure business form.
A9: well lane engineering measurement business process flow goes to mine side's survey engineer of downstream node, is responsible for the operation Mine side's survey engineer login techniques collaborative platform of the place business receives the pending prompting of business, step A7 is executed, if not Meet, login techniques collaborative platform is rejected by well lane engineering measurement business form and gives construction survey engineer, and step is re-executed Rapid A2~A8;If meeting, " gradeline " and " roadway center that mine side's survey engineer is drawn with construction survey engineer Based on line " and setting roadway cross-sectional area, perimeter and supporting information, modeled using the well lane engineering in well lane engineering software Formation function " well lane engineering Model Measured ", saves and is committed to central database, then login techniques collaborative platform passes through well Lane engineering survey business form executes examination & approval " agreement ", and well lane engineering is submitted to measure business form;
A10: well lane engineering measurement business process flow goes to mine side's measurement responsible person of downstream node, is responsible for the operation Mine side's survey engineer of the place business is received by WEB terminal, C/S client or mobile phone terminal login techniques collaborative platform The pending prompting of business executes step A2~A4, whether examines " well lane engineering Model Measured " constructed by mine side's survey engineer It constructs as required, if not meeting, login techniques collaborative platform is rejected by well lane engineering measurement business form and measures work to mine side Cheng Shi re-execute the steps A9;If meeting, because the job duty of mine side's measurement responsible person is examination & approval, then login techniques collaboration is flat Platform measures business form by well lane engineering and executes examination & approval " agreement ", and well lane engineering is submitted to measure business form;
A11: well lane engineering measurement business process flow goes to the mine side supervisor secondary chief of a pit of downstream node, is responsible for the operation The mine side supervisor secondary chief of a pit of the place business receives industry by WEB terminal, client or mobile phone terminal login techniques collaborative platform It is engaged in pending prompting, executes step A2~A4, examine whether " well lane engineering Model Measured " constructed by mine side's survey engineer presses It is required that building, if not meeting, login techniques collaborative platform is rejected by well lane engineering measurement business form and gives mine side's survey engineering Teacher re-execute the steps A9~A10;If meeting, because mine side is responsible for the job duty of the secondary chief of a pit as examination & approval, then login techniques are cooperateed with Platform measures business form by well lane engineering and executes examination & approval " agreement ", and well lane engineering is submitted to measure business form;
A12: well lane engineering measurement operation flow is finished, by well lane engineering measurement operation flow labeled as complete At, and file.
Fig. 4 shows mine ventilation operation flow, and detailed step includes:
B1: being the construction speed of " middle two middle section 0# stope 1# route of area " according to operating location, and mine ventilation engineer is logical The user account and password login technology synergy platform for crossing oneself, using Business Process Management module creation operating location be " in Business form under the mine ventilation operation flow of two middle section 0# stope 1# route of area ", and initiate the operation flow.
B2: the mine ventilation engineer for being responsible for the operating location business is logged in by WEB terminal, client or mobile phone terminal Technology synergy platform receives the pending prompting of business, the mine ventilation engineer for being responsible for the business sign for and check backlog with Mine ventilation business form.
B3: the mine ventilation resolving that mine ventilation engineer clicks on mine ventilation business form is linked with optimization software, Technology synergy platform starts mine ventilation resolving and optimization software under engineer's permission automatically, and mine ventilation resolves and optimization Software is with the user account of technology synergy platform and password automated log on, without repeat logon;
B4: corresponding mine ventilation resolving and optimization software are automatic according to pending business under mine ventilation engineer's permission From mine central database downloading well lane engineering practical measuring examples in operating location be " middle two middle section 0# stope 1# route of area " The well lane engineering center line of examination & approval;
B5: mine ventilation engineer passes through the " logical of mine ventilation resolving and optimization software based on roadway center line Roadway center line is converted to the ventilation network line number evidence of mine ventilation resolving and optimization software by wind network switching function ", and is made It is connected to adjacent airway with " interrupting " function with " mobile to replicate " of optimization software with mine ventilation resolving, transfer The section information of roadway center line and supporting information are directly copied to the ventilation network after conversion during changing, and according to branch Resistance coefficient, then " ventilation network are assigned to the ventilation network in the resistance coefficient library for protecting information and mine ventilation resolving and optimization software Check ", ventilation network check it is correct after Ventilation Network Solution again, and be compared and meet the requirements with practical wind value of surveying, save Mine ventilation network model resolves report and surveys wind report, and is committed to central database;
B6: mine ventilation engineer logs in and adopts technology synergy platform, and the attachment page on mine ventilation business form uploads The attachment content of the formation of the business is uploaded to central database;Mine ventilation engineer submits the mine ventilation traffic table simultaneously For list to technology synergy platform, mine ventilation business process flow goes to the An Huan section ventilation responsible person of downstream node;
B7: the An Huan section ventilation responsible person for being responsible for the operating location business is stepped on by WEB terminal, client or mobile phone terminal Record technology synergy platform receives the pending prompting of business, executes step B2~B4, examine and increase " middle two middle section 0# stope 1# of area into Whether the air quantity of the operating location, the air quantity of wind speed and entire ventilation network and wind speed meet the requirements behind road ", if not meeting, Login techniques collaborative platform is rejected by mine ventilation business form and gives mine ventilation engineer, and B2~B6 is re-execute the steps; If meeting, the job duty of Yin An ring section ventilation responsible person is examination & approval, then login techniques collaborative platform passes through mine ventilation business List executes examination & approval " agreement ", and submits mine ventilation business form;
B8: mine ventilation business process flow goes to the supervisor secondary chief of a pit, and the supervisor for being responsible for the operating location business passes through WEB End, C/S client or mobile phone terminal login techniques collaborative platform receive the pending prompting of business, execute step B7, if not meeting, Login techniques collaborative platform is rejected by mine ventilation business form and gives mine ventilation engineer, and B2~B7 is re-execute the steps; If meeting, because the job duty of the supervisor secondary chief of a pit is examination & approval, then login techniques collaborative platform is held by mine ventilation business form Row examination & approval " agreement ", and submit mine ventilation business form;
B9: mine ventilation business process flow goes to production technology portion person in charge, is responsible for the life of the operating location business It produces technology department person in charge and receives that business is pending to be mentioned by WEB terminal, C/S client or mobile phone terminal login techniques collaborative platform It wakes up, executes step B7, if not meeting, login techniques collaborative platform is rejected by mine ventilation business form and gives mine ventilation engineering Teacher re-execute the steps B2~B8;If meeting, because the job duty of production technology portion person in charge is examination & approval, then login techniques Collaborative platform executes examination & approval " agreement " by mine ventilation business form, and submits mine ventilation business form;
B10: mine ventilation business process flow goes to safety and environmental protection portion person in charge, is responsible for the production technology portion master of the business Pipe leader receives the pending prompting of business by WEB terminal, C/S client or mobile phone terminal login techniques collaborative platform, executes step Rapid B7, if not meeting, login techniques collaborative platform is rejected by mine ventilation business form and gives mine ventilation engineer, is held again Row step B2~B9;If meeting, because the job duty of safety and environmental protection portion person in charge is examination & approval, then login techniques collaborative platform is logical It crosses mine ventilation business form and executes examination & approval " agreement ", and submit mine ventilation business form;
B11: mine ventilation business process flow goes to chief engineer, and the chief engineer for being responsible for the business passes through WEB terminal, C/S Client or mobile phone terminal login techniques collaborative platform receive the pending prompting of business, execute step B7, if not meeting, log in skill Art collaborative platform is rejected by mine ventilation business form and gives mine ventilation engineer, and B2~B10 is re-execute the steps;If symbol It closes, because the job duty of chief engineer is examination & approval, then login techniques collaborative platform executes examination & approval by mine ventilation business form " agreement ", and submit mine ventilation business form;
B12: mine ventilation operation flow is finished, which is labeled as being completed, and file.
Each technical characteristic of embodiment described above can be combined arbitrarily, for simplicity of description, not to above-mentioned reality It applies all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited In contradiction, all should be considered as described in this specification.
The embodiments described above only express several embodiments of the present invention, and the description thereof is more specific and detailed, but simultaneously It cannot therefore be construed as limiting the scope of the patent.It should be pointed out that coming for those of ordinary skill in the art It says, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to protection of the invention Range.Therefore, the scope of protection of the patent of the invention shall be subject to the appended claims.

Claims (10)

1. a kind of mine business backlog processing method, which is characterized in that the method need to provide a technology synergy platform, one A or multiple business softwares and a central database, the technology synergy platform include Business Process Management module, user management Module, data-interface and business software interface;
The Business Process Management module is used to defining and creating mine Life cycle operation flow, configured by internet, Standardization operation flow is initiated, handles and examines, the filing of operation flow achievement and business are completed to remind, Business Process Management mould Block is also used to create business form;The user management module is for the affiliated organizational structure management of user, user role configuration, angle The technology synergy platform feature of color and operating location configure, the corresponding business software of role uses configuration with function privilege, use The management of family log-on message and for user log in obtain backlog notice and prompting message;The data-interface be used for Central database and business software carry out data interaction, the business software interface for technology synergy platform and business software into Row data interaction;The business software is used to work for traffic engineered teacher's processing business;The central database is for storing industry It is engaged in data and for business software downloading service data;
The mine business backlog processing method includes the following steps:
S1. Business Process Management module is according to the business schedule requirement under target job place, the industry of definition and creation standardization Business process, and according to the business form under the specific business in establishing business process mine target job place, the business form packet Include Business Name, operating location, business software link, operation flow examination & approval option and explanation, operation flow circulate history and attached Part page, the operation flow contain at least one flow nodes, the user information and industry of flow nodes traffic engineered teacher containing correspondence Business software link;Business form is sent first to the traffic engineered teacher of first flow nodes, to initiate operation flow;
S2. traffic engineered teacher inputs its user information login techniques collaborative platform in user management module, signs for and checks pending Item and business form;
S3. the business software link carried on traffic engineered teacher's click-to-call service list, technology synergy platform receive feedback information, by Business Process Management module starts all business softwares corresponding under traffic engineered teacher's claim by business software interface;
S4. related service needed for business software downloads the vocational work of the flow nodes by data-interface from the central database Data;
S5. traffic engineered teacher completes the vocational work under its job duty using business software based on associated traffic data, And newly generated business datum achievement is submitted and is saved in central database;
S6. traffic engineered teacher is by user management module login techniques collaborative platform, and increasing in the attachment page of business form should The attachment content formed during business handling, and attachment content to central database is uploaded by technology synergy platform and is stored, together When traffic engineered teacher submit its business form to technology synergy platform, Business Process Management module according to it is defined with it is configured Operation flow by business form in a manner of backlog reminding automatic flow to downstream node business responsible person;
S7. business responsible person receives backlog reminding and its business by user management module login techniques collaborative platform List executes step S2~S4, to examine whether the vocational work of a upper flow nodes meets the requirements, if not meeting, passes through industry Business list is rejected, and step S2~S6 is executed;If meeting, S5~S6 is continued to execute, completes the vocational work of the flow nodes, And submit business form;
S8. business process flow goes to downstream node, executes step S7, and so on, until the operation flow terminates, then will The operation flow is marked as being completed, and carries out achievement filing by Business Process Management module.
2. a kind of mine business backlog processing method as described in claim 1, it is characterised in that: in the step S1, When creating business form, Business Process Management module obtains the corresponding user role letter of each flow nodes from user management module The corresponding business software use of breath, technology synergy platform feature and the operating location information of role, role and function privilege information It is added in business form.
3. a kind of mine business backlog processing method as described in claim 1, it is characterised in that: in the step S1, The initiation of operation flow includes initiating and automatically initiating manually;It initiates to be business process in mine promoter according to operating location manually Under business schedule requirement, by inputting its user account in user management module and password login adopts technology synergy platform, wound The business form built under the specific business in mine target job place simultaneously initiates the operation flow, and automatically initiates then by operation flow The operation flow is voluntarily initiated after management module creation business form.
4. a kind of mine business backlog processing method as described in claim 1, it is characterised in that: mine business includes hole Visit design, probing design, drilling is edited and recorded, tunnel is edited and recorded, GEOLOGICAL INTERPRETATION, Geologic modeling, the termination of ore body, reserves valuation with calculating, Underground control measurement, surface control measurement, construction lofting, well lane engineering measurement, dead zone measures, mine amount is made an inventory, topographic survey, sign Ground measurement, exploit study, adopt cut design, explosion design, filling design, schedule of extraction and development establishment, mine ventilation resolve with optimization and Production management.
5. a kind of mine business backlog processing method as described in claim 1, it is characterised in that: the technology synergy is flat Platform supports web terminal, C/S client and mobile terminal, and user can be cooperateed with flat by web terminal, C/S client and mobile terminal login techniques Platform.
6. a kind of mine business backlog processing method as claimed in claim 5, it is characterised in that: in the step S3, Traffic engineered teacher is parsed by the URL of the business software link carried on WEB client side click-to-call service list using operating system The URL of business software link, finds related service software installation position, starts business software, and by the parameter in URL Business software is passed to, realizes the single-sign-on of business software;The URL includes Workflow messages, user information and permission Information, target job location information.
7. a kind of mine business backlog processing method as claimed in claim 5, it is characterised in that: in the step S3, Traffic engineered teacher finds the business software installation site by the script in C/S client, starts business software, and pass through Parameter is passed to business software by script, realizes that the single-sign-on of business software, the parameter include Workflow messages, user Information and authority information, target job location information.
8. a kind of mine business backlog processing method as described in claim 1, it is characterised in that: the backlog mentions Awake content includes business form entrance, business process map, operation flow title, process promoter, process initiation date, business Flow type, current business process node and operation flow urgency level;Operation flow list includes business game place, business Information, operation flow circulation history and attachment page;The content of the attachment page includes document, the figure of formation during business handling Shelves and vocational work explanation.
9. a kind of mine business backlog processing method as described in claim 1, it is characterised in that: in the step S7, If the vocational work of a upper flow nodes meets the requirements, and the flow nodes are approval process node, are said in addition examination & approval attachment After bright, business form is directly submitted.
10. a kind of mine business backlog processing method as described in claim 1, it is characterised in that: in the step S8, Business process flow goes to downstream node, if the downstream node is to terminate flow nodes, which is marked To be completed, and file;If there are also its subsequent flow nodes for the downstream node, when the business of the downstream node is negative When duty people has found that the performance data of a upper flow nodes does not meet its vocational work, then rejected.
CN201910345602.3A 2019-04-26 2019-04-26 A kind of mine business backlog processing method Pending CN110163562A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910345602.3A CN110163562A (en) 2019-04-26 2019-04-26 A kind of mine business backlog processing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910345602.3A CN110163562A (en) 2019-04-26 2019-04-26 A kind of mine business backlog processing method

Publications (1)

Publication Number Publication Date
CN110163562A true CN110163562A (en) 2019-08-23

Family

ID=67640158

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910345602.3A Pending CN110163562A (en) 2019-04-26 2019-04-26 A kind of mine business backlog processing method

Country Status (1)

Country Link
CN (1) CN110163562A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110796432A (en) * 2019-10-22 2020-02-14 南京华盾电力信息安全测评有限公司 Group enterprise business auditing process management method and system
CN111192004A (en) * 2019-12-12 2020-05-22 北京城乡建设集团有限责任公司 Method for displaying current to-do task and subsequent to-do workflow
CN112433794A (en) * 2020-11-20 2021-03-02 金蝶云科技有限公司 Method for controlling service progress of ERP system and related equipment
CN113344520A (en) * 2021-05-31 2021-09-03 珠海大横琴科技发展有限公司 Investigation management method and device of project management system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW200813865A (en) * 2006-09-15 2008-03-16 Hon Hai Prec Ind Co Ltd System and method for processing a workflow form
CN105117896A (en) * 2015-08-14 2015-12-02 安徽新华博信息技术股份有限公司 An office automation method
CN105260858A (en) * 2015-11-16 2016-01-20 苏州天地微易智能科技有限公司 Oa intelligent office system and management method thereof
CN106779613A (en) * 2016-12-28 2017-05-31 北京奇鱼时代科技有限公司 A kind of method and apparatus for examining configuration
CN107705020A (en) * 2017-10-12 2018-02-16 山东联诚工程建设监理有限公司 A kind of overall process intelligence engineering supervisory information managing and control system
CN109460970A (en) * 2018-10-26 2019-03-12 北京神州海泰克科技有限公司 It is a kind of based on the autonomous controllable office automation system of Domestic Database safety

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW200813865A (en) * 2006-09-15 2008-03-16 Hon Hai Prec Ind Co Ltd System and method for processing a workflow form
CN105117896A (en) * 2015-08-14 2015-12-02 安徽新华博信息技术股份有限公司 An office automation method
CN105260858A (en) * 2015-11-16 2016-01-20 苏州天地微易智能科技有限公司 Oa intelligent office system and management method thereof
CN106779613A (en) * 2016-12-28 2017-05-31 北京奇鱼时代科技有限公司 A kind of method and apparatus for examining configuration
CN107705020A (en) * 2017-10-12 2018-02-16 山东联诚工程建设监理有限公司 A kind of overall process intelligence engineering supervisory information managing and control system
CN109460970A (en) * 2018-10-26 2019-03-12 北京神州海泰克科技有限公司 It is a kind of based on the autonomous controllable office automation system of Domestic Database safety

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110796432A (en) * 2019-10-22 2020-02-14 南京华盾电力信息安全测评有限公司 Group enterprise business auditing process management method and system
CN111192004A (en) * 2019-12-12 2020-05-22 北京城乡建设集团有限责任公司 Method for displaying current to-do task and subsequent to-do workflow
CN112433794A (en) * 2020-11-20 2021-03-02 金蝶云科技有限公司 Method for controlling service progress of ERP system and related equipment
CN113344520A (en) * 2021-05-31 2021-09-03 珠海大横琴科技发展有限公司 Investigation management method and device of project management system

Similar Documents

Publication Publication Date Title
CN110163562A (en) A kind of mine business backlog processing method
CN107038259B (en) Operation method and system for constructing traffic network data
Van Reijswoud Appropriate ICT as a tool to increase effectiveness in ICT4D: Theoretical considerations and illustrating cases
CN111369158A (en) BIM-based informatization quality management method and system
CN107784088A (en) The knowledge mapping construction method of knowledge based point annexation
CN109472390B (en) Intelligent planning scheme generation method and system based on machine learning
Wahab et al. An integrative framework of COBIT and TOGAF for designing IT governance in local government
CN105989443A (en) Intelligent-mobile-terminal-based communication line inspection system
CN109145100A (en) A kind of the Task customer service robot system and its working method of customizable process
CN109145445A (en) A kind of hydroelectric project intelligent construction management system
Yu et al. RIOMS: An intelligent system for operation and maintenance of urban roads using spatio-temporal data in smart cities
CN102208064A (en) Administrative collaborative approval system and approval method
CN110069479A (en) A kind of public security big data administering method
CN104899401A (en) Aircraft research & development process and adjoint acknowledge combined method
CN113326028A (en) Micro-service decomposition method based on domain-driven design and service panoramic event storm
Matu et al. Stakeholder participation in project initiation: a foundation to completion of Urban road transport infrastructure projects, Kenya
Aleksandrova et al. Methods of digital transformation of management systems
CN110599041A (en) Enterprise target management method, cloud and system based on artificial intelligence technology
CN106599216A (en) Computer based training courseware publishing system
CN117829754A (en) Intelligent engineering construction whole process number management method and platform based on BIM and GIS
CN107590601A (en) Communication scheme produces accessory system
CN110490321A (en) Railway traffic engineering Safety Supervision method for early warning and monitoring system
CN114254160A (en) Construction method of data navigation map for power grid company
CN110175813A (en) A kind of coordinated operation system based on mine Life cycle operation flow
Blair et al. A comparative study of methodologies for designing IDSSs

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190823