CN110159309A - A kind of construction method using foam concrete backfill Tunneling by mining method - Google Patents

A kind of construction method using foam concrete backfill Tunneling by mining method Download PDF

Info

Publication number
CN110159309A
CN110159309A CN201910446070.2A CN201910446070A CN110159309A CN 110159309 A CN110159309 A CN 110159309A CN 201910446070 A CN201910446070 A CN 201910446070A CN 110159309 A CN110159309 A CN 110159309A
Authority
CN
China
Prior art keywords
foam concrete
backfill
feedhole
construction method
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910446070.2A
Other languages
Chinese (zh)
Other versions
CN110159309B (en
Inventor
颜锐
伍浩
符子钊
常彦博
曾绍军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 8 Co Ltd
Original Assignee
Sinohydro Bureau 8 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 8 Co Ltd filed Critical Sinohydro Bureau 8 Co Ltd
Priority to CN201910446070.2A priority Critical patent/CN110159309B/en
Publication of CN110159309A publication Critical patent/CN110159309A/en
Application granted granted Critical
Publication of CN110159309B publication Critical patent/CN110159309B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of construction methods using foam concrete backfill Tunneling by mining method, the following steps are included: lower section block wall is built, lower section backfills foam concrete, remove gib, upper section block wall is built, upper section backfills foam concrete, and the present invention has easy to operate, the low advantage of construction cost.

Description

A kind of construction method using foam concrete backfill Tunneling by mining method
Technical field
Construction field is backfilled the present invention relates to Tunneling by mining method more particularly to a kind of using foam concrete backfill Mining Method The construction method in tunnel.
Background technique
Currently, there are following problems for Tunneling by mining method backfill construction: (1) tunnel cross-section is difficult to backfill closely knit, after easily causing Continuous shield driving cutterhead discontinuity;(2) it commonly uses backfill material or intensity is excessively high, increase shield cutter abrasion or intensity is too low, It causes face that can not provide enough counter-forces, then leads to pipe sheet assembling leakiness;(3) backfill operation is by external influence factor Greatly, the easy the phenomenon that supply of backfill material occur not in time, and backfill efficiency is slow, causes the raising of cost of labor;(4) material is backfilled Expect with high costs.According to current same type condition of construction, the above problem can not be all properly settled, majority is using backfill concrete, backfill The techniques such as beans gravel, backfill and backfill mountain flour slag, wherein backfill concrete material is at high cost, and intensity is higher, later period shield driving Cutterhead serious wear, and backfill beans gravel, soil or mountain flour slag and be then difficult to backfill closely knit, and mechanization degree is low, and backfill effect is slow Slowly, high labor cost, backfill surface intensity is low, exists because of counter-pressure deficiency, section of jurisdiction is caused to splice uncompacted situation.
Summary of the invention
The technical problem to be solved by the present invention is to overcome the deficiencies in the prior art, provide a kind of easy to operate, construction cost The low construction method using foam concrete backfill Tunneling by mining method.
In order to solve the above technical problems, the invention adopts the following technical scheme:
A kind of construction method using foam concrete backfill Tunneling by mining method, comprising the following steps:
S1: determining the section length of tunnel single backfill, completely builds block wall in the lower section of Tunneling by mining method, blocks coping It is reserved to return slurry hole, the first feedhole is reserved in gib;
S2: being delivered to section under the first feedhole backfill tunnel for foam concrete, when returning slurry hole and returning slurry, then stops lower section Slurry hole is returned in backfill, closure;
S3: abolishing the gib that section under tunnel has backfilled overlying regions, increases block wall to tunnel top, block wall top It is reserved to return slurry hole and the second feedhole;
S4: by foam concrete be delivered to the second feedhole backfill tunnel on section, when return slurry hole return slurry when, then stop backfilling, Slurry hole and the second feedhole are returned in closure;
S5: circulation step S1-S4 carries out the backfill of next section length, until backfill is completed.
As further improvement to above-mentioned technical proposal:
Described return in slurry hole is provided with slurry recovering tube.
In the step S3, the slurry hole of returning is located above the second feedhole.
The foam concrete is prepared and is conveyed by foam concrete automation preparation system, and the foam concrete is certainly Dynamicization preparation system includes the hopper being sequentially communicated, blender, foaming machine and feed pipe.
The foam concrete specifically includes following preparation step: using cement and water as foam concrete raw material, being placed in material It send after being mixed in bucket and is stirred evenly into blender, be subsequently sent to foam in foaming machine, obtain foam concrete.
The foam concrete raw material further includes hydrophober.
The foam concrete automation preparation system further includes multiple conveying pipelines, and the conveying pipeline is connected to hopper and stirs It mixes between machine between blender and foaming machine.
Compared with the prior art, the advantages of the present invention are as follows:
1. operation of the present invention is simple, construction quickly, can apply to the backfill of various tunnel cross-sections, and backfill is closely knit, can be sufficiently Tunnel cross-section is filled, while guaranteeing that shield duct piece is normally assembled, it is ensured that shield can speedy drivage, cutterhead uniform force, Since foam concrete intensity is lower, convenient for shield speedy drivage and shield cutter abrasion condition is reduced.And construction of the invention Method material consumption is low, and the artificial used time is few, and cost is greatly saved compared to traditional backfilling process, therefore has significant economic benefit And social benefit.
2. foam concrete automation preparation may be implemented in foam concrete preparation system of the invention, when backfill according to From the bottom to top, horizontal fragmentation, vertical layered principle are backfilled, and are separated between each segmentation using block wall, and backfill is quick and constructs Quality is high.
Detailed description of the invention
Fig. 1 is flow chart of the invention.
Fig. 2 is that foam concrete automates preparation system schematic diagram.
Fig. 3 is that lower section backfills schematic diagram.
Fig. 4 is gib dismounting schematic diagram in tunnel after the backfill of lower section.
Fig. 5 is that upper section backfills schematic diagram.
Fig. 6 is line A-A sectional view in Fig. 3.
Fig. 7 is line B-B sectional view in Fig. 5.
Marginal data:
1, foam concrete automates preparation system;11, hopper;12, blender;13, foaming machine;14, feed pipe;15, conveying Pipe;21, Mining Method just props up;22, gib;23, the first feedhole;24, block wall;25, slurry hole is returned;26, foam concrete; 27, the second feedhole;28, slurry recovering tube.
Specific embodiment
The present invention is described in further details below with reference to Figure of description and specific embodiment.Except no special theory Bright, following material and instrument are commercially available.
As shown in Fig. 1 to 7, a kind of construction method using foam concrete backfill Tunneling by mining method of the invention, construction Process are as follows: the lower masonry of section block wall 24 → lower section backfill foam concrete 26 → dismounting gib 22 → upper section blocks The masonry of wall 24 → upper section backfills foam concrete 26, specifically includes the following steps:
S1: determining the section length of tunnel single backfill, completely build block wall 24 in the lower section of Tunneling by mining method, block wall 24 Top is reserved to return slurry hole 25, and the first feedhole 23 is reserved in gib 22;
S2: by foam concrete 26 be delivered to the first feedhole 23 backfill tunnel under section, when return slurry hole 25 return slurry when, then stop Slurry hole 25 is returned in lower section backfill, closure;
S3: abolishing the gib 22 that section under tunnel has backfilled overlying regions, increases block wall 24 to tunnel top, block wall 24 tops are reserved to return slurry hole 25 and the second feedhole 27;
S4: by foam concrete 26 be delivered to the second feedhole 27 backfill tunnel on section, when return slurry hole 25 return slurry when, then stop Slurry hole 25 and the second feedhole 27 are returned in backfill, closure;
S5: circulation step S1-S4 carries out the backfill of next section length, until backfill is completed.
It returns in slurry hole 25 and is provided with slurry recovering tube 28, for judging whether the backfill of 24 back side of block wall is closely knit.
In step S3, returns slurry hole 25 and be located at 27 top of the second feedhole.
Foam concrete 26 automates the preparation of preparation system 1 by foam concrete and conveys, foam concrete automation Preparation system 1 includes hopper 11, blender 12, foaming machine 13 and the feed pipe 14 being sequentially communicated.Of the invention, foam concrete The automation preparation of foam concrete 26 may be implemented in automation preparation system 1, and the foam concrete 26 after the completion of preparing is by sending Expects pipe is delivered in Tunneling by mining method by high-pressure pump and is backfilled, and is set according to tunnel sectional area, single set equipment daily work load and quasi- investment Standby quantity calculates, and the present embodiment section length is 20m.
Foam concrete 26 specifically includes following preparation step: using cement and water as foam concrete raw material, being placed in hopper It send after being mixed in 11 into blender 12 and stirs evenly, be subsequently sent to foam in foaming machine 13, obtain foam concrete 26.
In the present embodiment, foam concrete raw material further includes hydrophober.
Foam concrete automation preparation system 1 further includes multiple conveying pipelines 15, and conveying pipeline 15 is connected to hopper 11 and stirs It mixes between machine 12 between blender 12 and foaming machine 13.
In the present embodiment, according to actual needs, design foam concrete 26 is matched, and cement and water are mixed by 1.52 ratio of muds It is sent into blender 12 after conjunction to be stirred, and mixes hydrophober according to the 1.2% of cement consumption in whipping process, it is ensured that foam is mixed Solidifying soil finished product has certain waterproofness.
In the present embodiment, foaming agent is made 13 built in air compressor (not shown) of foaming machine, air compressor Foam, and mixed in cement slurry according to default specific volume and bubble containing ratio 74.5%, bubble dosage 7kg/m are made automatically3Foam Concrete 26, and through 14 force feed of feed pipe to corresponding backfill position.
In the present embodiment, feeding pipe diameter 50mm, material is rubber tube.
In the present embodiment, single foam concrete automation preparation system odd-numbered day workload that covers is 150 m3~300 m3, vertically Effective delivery head is 120m, and horizontal effectively conveying distance is 300m.According to construction tunnel sectional area and equipment investment amount, planning Single backfills length, really completes the segmentation in report Mining Method tunnel segment gib 22 dismounting one day after and backfills operation.
In the present embodiment, block wall 24 is with a thickness of 400mm, using 200 × 200 × 600mm foam brick masonry.
In the present embodiment, after the completion of lower section block wall 24 is built, using reserving the of 100mm diameter in gib 22 The downward section conveying foam concrete 26 of one feedhole 23 backfills.
That two diameter 60mm are reserved in the present embodiment, at the top of lower section block wall 24 returns slurry hole 25, and places slurry recovering tube 28, foam concrete 26 returns out through slurry recovering tube 28 can stop conveying.Gap is blocked with mortar between slurry recovering tube 28 and block wall 24 Tightly.
In the present embodiment, 28 diameter of slurry recovering tube is 50mm, and material is pvc pipe.
In the present embodiment, the insertion backfill of slurry recovering tube 28 segment length L is 200mm.
In the present embodiment, tunnel vault, Mining Method, which just prop up, sets plastic cement hook (not shown) on 21, links up with for hanging Feed pipe 14 is hung, upper section is backfilled using feed pipe 14, and 14 end range segment separating end distance M of feed pipe is not more than 500mm。
In the present embodiment, needed at the top of upper section block wall 24 point about reserve diameter 60mm hole, hole center spacing is not Greater than 100mm.Bottom hole pierced feed pipe 14, and top hole is for placing slurry recovering tube 28.
In the present embodiment, after upper section slurry recovering tube 28 has foam concrete 26 to return out, the feed pipe of insertion backfill section is cut off 14, and feed pipe 14 and slurry recovering tube 28 are blocked, complete the backfill of this circulation.
Although the present invention has been disclosed as a preferred embodiment, however, it is not intended to limit the invention.It is any to be familiar with ability The technical staff in domain, without deviating from the scope of the technical scheme of the present invention, all using the technology contents pair of the disclosure above Technical solution of the present invention makes many possible changes and modifications or equivalent example modified to equivalent change.Therefore, all Without departing from the content of technical solution of the present invention, according to the present invention technical spirit any simple modification made to the above embodiment, Equivalent variations and modification, all shall fall within the protection scope of the technical scheme of the invention.

Claims (7)

1. a kind of construction method using foam concrete backfill Tunneling by mining method, it is characterised in that: the following steps are included:
S1: it determines the section length of tunnel single backfill, completely builds block wall (24), block wall in the lower section of Tunneling by mining method (24) top is reserved to return slurry hole (25), reserves the first feedhole (23) on gib (22);
S2: by foam concrete (26) be delivered to the first feedhole (23) backfill tunnel under section, when return slurry hole (25) return slurry when, Then stop lower section backfill, slurry hole (25) is returned in closure;
S3: abolishing the gib (22) that section under tunnel has backfilled overlying regions, increases block wall (24) to tunnel top, envelope It is reserved at the top of wall (24) to return slurry hole (25) and the second feedhole (27);
S4: by foam concrete (26) be delivered to the second feedhole (27) backfill tunnel on section, when return slurry hole (25) return slurry when, Then stop backfilling, slurry hole (25) and the second feedhole (27) are returned in closure;
S5: circulation step S1-S4 carries out the backfill of next section length, until backfill is completed.
2. construction method according to claim 1, it is characterised in that: described return in slurry hole (25) is provided with slurry recovering tube (28).
3. construction method according to claim 2, it is characterised in that: in the step S3, slurry hole (25) that returns is located at Above second feedhole (27).
4. construction method according to any one of claim 1 to 3, it is characterised in that: the foam concrete (26) is logical Foam concrete automation preparation system (1) is crossed to prepare and convey, foam concrete automation preparation system (1) include according to Hopper (11), blender (12), foaming machine (13) and the feed pipe (14) of secondary connection.
5. construction method according to claim 4, it is characterised in that: the foam concrete (26) specifically includes following system Standby step: it using cement and water as foam concrete raw material, is placed in hopper (11) after mixing and send into blender (12) stirring equal It is even, it is subsequently sent to foam in foaming machine (13), obtains foam concrete (26).
6. construction method according to claim 5, it is characterised in that: the foam concrete raw material further includes hydrophober.
7. construction method according to claim 5, it is characterised in that: the foam concrete automates preparation system (1) It further include multiple conveying pipelines (15), the conveying pipeline (15) is connected between hopper (11) and blender (12) and blender (12) Between foaming machine (13).
CN201910446070.2A 2019-05-27 2019-05-27 Construction method for backfilling mine method tunnel with foam concrete Active CN110159309B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910446070.2A CN110159309B (en) 2019-05-27 2019-05-27 Construction method for backfilling mine method tunnel with foam concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910446070.2A CN110159309B (en) 2019-05-27 2019-05-27 Construction method for backfilling mine method tunnel with foam concrete

Publications (2)

Publication Number Publication Date
CN110159309A true CN110159309A (en) 2019-08-23
CN110159309B CN110159309B (en) 2021-03-23

Family

ID=67629192

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910446070.2A Active CN110159309B (en) 2019-05-27 2019-05-27 Construction method for backfilling mine method tunnel with foam concrete

Country Status (1)

Country Link
CN (1) CN110159309B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112343603A (en) * 2020-09-30 2021-02-09 中交第二公路勘察设计研究院有限公司 Comprehensive construction method suitable for tunneling of shield tunnel with ultra-large section

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1902197A2 (en) * 2005-07-09 2008-03-26 Skumtech AS Construction of superstructures and infrastructures
CN103899325A (en) * 2014-04-23 2014-07-02 上海隧道工程股份有限公司 Construction method for shield machine to enter hole to receive concrete box
CN105036789A (en) * 2015-06-29 2015-11-11 河南华泰建材开发有限公司 Light foamed soil applied to backfill of subway station foundation pit
CN105804770A (en) * 2016-04-11 2016-07-27 刘文涛 Method for backfilling of tunnel construction through TBM method and equipment for method
CN106499410A (en) * 2016-11-13 2017-03-15 中铁十局集团第工程有限公司 Tunnel-liner side wall concrete is by window placement layer by layer method
CN108103871A (en) * 2017-12-19 2018-06-01 浙江大学城市学院 A kind of construction method of the roadbed foam concrete fill placement technique of neighbouring existing Subway Facilities
CN108590680A (en) * 2018-05-04 2018-09-28 北京市政建设集团有限责任公司 A kind of construction method that launching shaft foundation pit vertical section pours
CN108708743A (en) * 2018-05-14 2018-10-26 中水电第十工程局(郑州)有限公司 A method of using grouting treatment Tunnel Collapse
CN108775244A (en) * 2018-05-28 2018-11-09 中铁十六局集团有限公司 A kind of Mining Method receives shield machine and shield sky pushes away construction method
CN208236434U (en) * 2018-04-13 2018-12-14 中国水利水电第十四工程局有限公司 Inverted arch fill concrete continuous placing plate device

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1902197A2 (en) * 2005-07-09 2008-03-26 Skumtech AS Construction of superstructures and infrastructures
CN103899325A (en) * 2014-04-23 2014-07-02 上海隧道工程股份有限公司 Construction method for shield machine to enter hole to receive concrete box
CN105036789A (en) * 2015-06-29 2015-11-11 河南华泰建材开发有限公司 Light foamed soil applied to backfill of subway station foundation pit
CN105804770A (en) * 2016-04-11 2016-07-27 刘文涛 Method for backfilling of tunnel construction through TBM method and equipment for method
CN106499410A (en) * 2016-11-13 2017-03-15 中铁十局集团第工程有限公司 Tunnel-liner side wall concrete is by window placement layer by layer method
CN108103871A (en) * 2017-12-19 2018-06-01 浙江大学城市学院 A kind of construction method of the roadbed foam concrete fill placement technique of neighbouring existing Subway Facilities
CN208236434U (en) * 2018-04-13 2018-12-14 中国水利水电第十四工程局有限公司 Inverted arch fill concrete continuous placing plate device
CN108590680A (en) * 2018-05-04 2018-09-28 北京市政建设集团有限责任公司 A kind of construction method that launching shaft foundation pit vertical section pours
CN108708743A (en) * 2018-05-14 2018-10-26 中水电第十工程局(郑州)有限公司 A method of using grouting treatment Tunnel Collapse
CN108775244A (en) * 2018-05-28 2018-11-09 中铁十六局集团有限公司 A kind of Mining Method receives shield machine and shield sky pushes away construction method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
廖志钻: "泡沫混凝土的填筑应用", 《建筑施工》 *
蒋明: "泡沫混凝土在盾构进洞过程中的应用", 《建筑科技》 *
霍元盛: "土压平衡盾构机通过地铁隧道矿山法段的回填掘进施工技术", 《铁道标准设计》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112343603A (en) * 2020-09-30 2021-02-09 中交第二公路勘察设计研究院有限公司 Comprehensive construction method suitable for tunneling of shield tunnel with ultra-large section

Also Published As

Publication number Publication date
CN110159309B (en) 2021-03-23

Similar Documents

Publication Publication Date Title
CN110630321B (en) Goaf aboveground filling equipment and goaf aboveground filling method
CN209323523U (en) A kind of deep drilled shaft concrete pours device
CN104632252A (en) Automatic grouting system
CN101603427A (en) Shield synchronization slip casting construction technology
CN106761837A (en) Slip casting structure and supporting grouting method in tunnel excavating process
CN106065782A (en) A kind of big flow high concentration structure stream full tail sand cemented filling technique
CN107218078A (en) Filled for underground coal goaf and abandoned workings, the new technology of grouting filling
CN110159309A (en) A kind of construction method using foam concrete backfill Tunneling by mining method
CN105464701B (en) Super-capacity stable continuous filling system
CN108487921A (en) One kind being used for underground coal mine large-section underground continuous concrete device and its casting method
CN108191365A (en) A kind of method using ardealite material cementing fill metal mine
CN103352722B (en) Cemented filling close to back processing technology for goaf at barren rock filling background
CN207480896U (en) A kind of device for continuously stirring supply slurries
CN110005432A (en) Double-shielded TBM development machine passes through the synchronous grouting construction method of fractured weak zone
CN212614799U (en) Device for accurately filling anchoring agent
CN111173537B (en) Large-scale supplementary grouting method between duct piece and surrounding rock for tunnel construction by TBM method
CN209585433U (en) A kind of prefabricated components
CN212641364U (en) Underwater leakage blocking structure system for concrete faced rockfill dam
CN207740011U (en) Novel slurry filling system for effectively controlling surface subsidence
CN203655350U (en) Device for ensuring working surfaces to pass through open-off cut
CN103362522B (en) A kind of dry-type synchronization slip casting construction technology
CN110424982B (en) Method for reinforcing rock clamping of proximity laminated tunnel
CN209162837U (en) A kind of device reducing subsider range and settling amount
CN206034936U (en) Mortar cloth fill
CN108060931A (en) For effectively controlling the novel slurry filling system of surface subsidence and grouting process

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant