CN110145110A - One discharge plate buckle type scaffold - Google Patents

One discharge plate buckle type scaffold Download PDF

Info

Publication number
CN110145110A
CN110145110A CN201910390087.0A CN201910390087A CN110145110A CN 110145110 A CN110145110 A CN 110145110A CN 201910390087 A CN201910390087 A CN 201910390087A CN 110145110 A CN110145110 A CN 110145110A
Authority
CN
China
Prior art keywords
expression lobes
upright bar
connecting rod
fastener
bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201910390087.0A
Other languages
Chinese (zh)
Inventor
栗亮
吴丽颖
李东生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Third Metallurgical Group Co Ltd
Original Assignee
China Third Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Third Metallurgical Group Co Ltd filed Critical China Third Metallurgical Group Co Ltd
Priority to CN201910390087.0A priority Critical patent/CN110145110A/en
Publication of CN110145110A publication Critical patent/CN110145110A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/30Scaffolding bars or members with non-detachably fixed coupling elements
    • E04G7/301Scaffolding bars or members with non-detachably fixed coupling elements for connecting bars or members which are parallel or in end-to-end relation

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

The present invention relates to Architectural Equipment technical fields, and disclose a discharge plate buckle type scaffold, including upright bar and it is welded on the connecting rod of upright bar one end, the upright bar is equipped with No.1 expression lobes, adjustment tank and No.1 fastener hole far from the side of connecting rod, and No.1 expression lobes are located at the inner sidewall of upright bar, the side wall of connecting rod position corresponding with No.1 expression lobes, adjustment tank and No.1 fastener hole is respectively equipped with No. two expression lobes, adjusting hole and No. two fastener holes.The disk buckle type scaffold, by the extruding of No. two expression lobes of No.1 expression lobes, the influence in gap between upright bar and connecting rod is eliminated, reduces the opposite shaking between upright bar and connecting rod, so that the alignment of upright bar is more preferable in build process, the bearing capacity for improving scaffold reduces the use of cross bar and brace, simultaneously, operability is more preferable, reduce installation so that error, reduces operator's workload, reduces engineering manpower's cost and time cost.

Description

One discharge plate buckle type scaffold
Technical field
The present invention relates to Architectural Equipment technical fields, specially a discharge plate buckle type scaffold.
Background technique
Referring to Fig. 1, disk buckle type scaffold is high because of its bearing capacity, component is few and combination is simply becoming increasingly popular, The connection of upright bar is fixed by being socketed blending bolt, and upright bar and the connection of cross bar are connected by being welded on the fixed disk of upright bar.
When upright bar is socketed, there is certain gap between two upright bars, there may be a slight shaking, and foot hand The height that frame is built is usually very high, and the shaking of lower layer's scaffold can be amplified to upper layer, and there are security risks, on the other hand, Vibration caused by gap can cause metal fatigue, reduce the bulk life time of scaffold.
Secondly, gap can make the axis of upper and lower upright bar not be overlapped, on the one hand, may be such that the verticality of upright bar not It is enough, the overall stability of scaffold is influenced, on the other hand, the axis difference of scaffold can reduce whole bearing capacity, need More dense brace is just able to satisfy the bearing requirements of scaffold, improves the use cost of scaffold.
Further, when scaffold is built it is higher-height when, the requirement of the levelness of verticality and cross bar to upright bar It is very high, it is calibrated when building with horizontal ruler during building, gap when due to pull rod socket increases error, makes to build The undesirable situation of the verticality of upright bar is more easier to occur in journey, and operator needs to spend more volume time adjustment vertical Bar increases workload and improves human cost, while tying down the progress of building, and is unfavorable for the cost control and progress control of engineering System.
Summary of the invention
For the deficiency of above-mentioned background technique, the present invention provides a discharge plate buckle type scaffold, has and shake small, carrying height With build quick advantage, solve the problems, such as background technique proposition.
The invention provides the following technical scheme: a discharge plate buckle type scaffold,
One discharge plate buckle type scaffold including upright bar and is welded on the connecting rod of upright bar one end, and the upright bar is far from connecting rod Side be equipped with No.1 expression lobes, adjustment tank and No.1 fastener hole, and No.1 expression lobes are located at the inner sidewall of upright bar, described The side wall of connecting rod position corresponding with No.1 expression lobes, adjustment tank and No.1 fastener hole be respectively equipped with No. two expression lobes, Adjusting hole and No. two fastener holes, the upright bar and connecting rod are connected with adjustment bar by adjusting slot and adjusting hole, described vertical Bar and connecting rod are connected with fastener by No.1 fastener hole and No. two fastener holes.
Preferably, the No.1 expression lobes and No. two expression lobes are the cylinder that section is arc, and the No.1 squeezes Mean breadth of the sum of the thickness of protrusion and No. two expression lobes slightly larger than gap between upright bar and connecting rod.
Preferably, the adjustment tank is the notch vertical with upright bar axis, and the length of the adjustment tank is squeezed greater than No.1 The sum of the cross-sectional axis of protrusion and No. two expression lobes.
Preferably, the side of the adjustment bar is equipped with screw thread and connects the connecting rod of crowbar pipe.
Preferably, the two sides up and down of the No.1 fastener hole and No. two fastener holes are equipped with No.1 expression lobes and No. two are squeezed Belling rises.
Preferably, the fastener is that side is equipped with bolt smooth among screw thread, and the fastener has screw thread side Diameter be less than intermediate diameter.
The present invention have it is following the utility model has the advantages that
1, the disk buckle type scaffold eliminates upright bar and connection by the extruding of No. two expression lobes of No.1 expression lobes The influence in gap between bar, increases the tightness between upright bar and connecting rod, reduces opposite between upright bar and connecting rod It shakes, improves the safety that scaffold uses, meanwhile, phase mutual friction is reduced between upright bar and connecting rod, improves upright bar and connection The service life of bar.
2, the disk buckle type scaffold, since upright bar and connecting rod are adjacent to, so that the alignment of upright bar is more preferable in build process, Reducing the inclination angle of upright bar, scaffold is built more neat, the stability of scaffold is improved, on the other hand, alignment The more regular uniform of the effect dispersion of power can more preferably be made, improve the bearing capacity of scaffold, scaffold builds design can To use less brace and cross bar, the human cost and material cost built are reduced.
3, the disk buckle type scaffold, rotation has been adjacent to No.1 expression lobes and No. two expression lobes mutual extrusions when installation At the socket of two upright bars, operability is more preferable, reduces installation so that error, carries out vertical principal and adjustment and installation to upright bar Time it is less, to reduce operator's workload, reduce engineering manpower's cost and time cost, convenient for engineering at This control and progress monitoring.
Detailed description of the invention
Fig. 1 is existing structure schematic diagram;
Fig. 2 is schematic structural view of the invention;
Fig. 3 is the diagrammatic cross-section of AA in Fig. 2 of the present invention;
Fig. 4 is the stereoscopic schematic diagram of upright bar and connecting rod in the present invention;
Fig. 5 is upright bar partial schematic diagram in the present invention;
Fig. 6 is the schematic diagram that bar is adjusted in the present invention;
Fig. 7 is to adjust schematic diagram after being socketed in the present invention.
In figure: 1, upright bar;2, connecting rod;3, No.1 expression lobes;4, No. two expression lobes;5, adjustment tank;6, adjusting hole; 7, fastener;8, bar is adjusted;9, No.1 fastener hole;10, No. two fastener holes.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Please refer to Fig. 2-7, a discharge plate buckle type scaffold, including upright bar 1 and the connecting rod 2 for being welded on 1 one end of upright bar, upright bar 1 side far from connecting rod 2 is equipped with No.1 expression lobes 3, adjustment tank 5 and No.1 fastener hole 9, and No.1 expression lobes 3 are located at The inner sidewall of upright bar 1, the side wall of connecting rod 2 position difference corresponding with No.1 expression lobes 3, adjustment tank 5 and No.1 fastener hole 9 It is living by adjusting slot 5 and adjusting hole 6 equipped with No. two expression lobes 4, adjusting hole 6 and No. two fastener holes 10, upright bar 1 and connecting rod 2 Dynamic to be connected with adjustment bar 8, adjustment bar 8 passes through adjustment tank 5 and adjusting hole 6, and adjustment bar 8 moves in adjustment tank 5, makes to adjust bar 8 Connecting rod 2 is driven to rotate, upright bar 1 and 2 relative rotation of connecting rod push against No.1 expression lobes 3 and No. two expression lobes 4 mutually, The influence for eliminating gap between upright bar 1 and connecting rod 2 keeps its alignment more preferable, while making No.1 fastener hole 9 and No. two fastener holes 10 alignment, upright bar 1 and connecting rod 2 are connected with fastener 7 by No.1 fastener hole 9 and No. two fastener holes 10, and fastener 7 is worn No.1 fastener hole 9 and No. two fastener holes 10 are crossed, nut, the position of fixed No.1 expression lobes 3 and No. two expression lobes 4 are screwed on.
Wherein, No.1 expression lobes 3 and No. two expression lobes 4 are the cylinder that section is arc, are convenient for No.1 expression lobes 3 With being mutually shifted until pushing against for No. two expression lobes 4, the sum of thickness of No.1 expression lobes 3 and No. two expression lobes 4 is bigger The mean breadth in gap between upright bar 1 and connecting rod 2 guarantees that No.1 expression lobes 3 and No. two expression lobes 4 can mutually offset Tightly.
Wherein, adjustment tank 5 is the notch vertical with 1 axis of upright bar, facilitates the movement of adjustment bar 8, and adjusting hole 6 is and adjustment The through-hole that bar 8 is adapted to, adjustment bar 8 promote adjusting hole 6 to rotate when moving in adjustment tank 5, and the length of adjustment tank 5 is squeezed greater than No.1 Belling plays the sum of the cross-sectional axis of 3 and No. two expression lobes 4, it is ensured that the movement of adjustment bar 8 can make No.1 expression lobes 3 and two Number expression lobes 4 are mutually adjacent to.
Wherein, the side for adjusting bar 8 is equipped with screw thread and connects the connecting rod of crowbar pipe, convenient for connection crowbar pipe, is conveniently adjusted The realization of 8 function of bar, while screwing on the function that nut realizes fastening.
Wherein, No.1 expression lobes 3 and No. two expression lobes 4 are provided with multiple groups, No.1 fastener hole 9 and No. two fastener holes 10 Two sides up and down be equipped with No.1 expression lobes 3 and No. two expression lobes 4, the fastening effect of No.1 fastener hole 9 is more balanced, mentions High No.1 expression lobes 3 and No. two expression lobes 4 are adjacent to effect.
Wherein, due to the effect of No.1 expression lobes 3 and No. two expression lobes 4, No.1 fastener hole 9 and No. two fastener holes 10 And be misaligned, fastener 7 is that side is equipped with smooth bolt among screw thread, and fastener 7 has during the diameter of screw thread side is less than Between diameter, convenient for the installation of fastener 7.
The installation process of the disk buckle type scaffold:
Adjustable setting is installed according to setting-out size, installs starting bar, adjustment adjustable nut is adjusted to substantially water It is flat, by being inserted in the connecting rod 2 of starting bar for another upright bar 1, by No.1 expression lobes 3 and No. two expression lobes 4 when being inserted in It is staggered, by adjusting slot 5 and the insertion adjustment bar 8 of adjusting hole 6, connects crowbar pipe by adjusting the crowbar connecting rod of bar 8, agitate adjustment Bar 8 makes upright bar 1 and 2 relative rotation of connecting rod makes No.1 expression lobes 3 and No. two expression lobes 4 mutually offset, while No.1 is tight Solid hole 9 and No. two fastener holes 10 are aligned, and fastener 7 are installed by No.1 fastener hole 9 and No. two fastener holes 10, after finally installing The screw thread of bar 8 is adjusted, the installation of a section upright bar 1 is completed, repeats the installation that step completes scaffold, when disassembly first unscrews fastener 7 and adjustment bar 8 nut, buttress upright bar 1 and rotate be convenient for fastener 7 removal.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment Intrinsic element.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (6)

1. a discharge plate buckle type scaffold, including upright bar (1) and it is welded on the connecting rod (2) of upright bar (1) one end, it is characterised in that: The upright bar (1) is equipped with No.1 expression lobes (3), adjustment tank (5) and No.1 fastener hole (9) far from the side of connecting rod (2), and No.1 expression lobes (3) are located at the inner sidewall of upright bar (1), the side wall of the connecting rod (2) and No.1 expression lobes (3), adjustment Slot (5) and the corresponding position of No.1 fastener hole (9) are respectively equipped with No. two expression lobes (4), adjusting hole (6) and No. two fastener holes (10), the upright bar (1) and connecting rod (2) are connected with by adjusting slot (5) and adjusting hole (6) adjusts bar (8), described vertical Bar (1) and connecting rod (2) pass through No.1 fastener hole (9) and No. two fastener holes (10) are connected with fastener (7).
2. discharge plate buckle type scaffold according to claim 1, it is characterised in that: the No.1 expression lobes (3) and two Number expression lobes (4) are the cylinder that section is arc, the thickness of the No.1 expression lobes (3) and No. two expression lobes (4) it And the mean breadth slightly larger than gap between upright bar (1) and connecting rod (2).
3. discharge plate buckle type scaffold according to claim 1, it is characterised in that: the adjustment tank (5) be and upright bar (1) The vertical notch of axis, the length of the adjustment tank (5) are greater than the section of No.1 expression lobes (3) and No. two expression lobes (4) The sum of axis.
4. discharge plate buckle type scaffold according to claim 1, it is characterised in that: the side of adjustment bar (8) is equipped with The connecting rod of screw thread and connection crowbar pipe.
5. discharge plate buckle type scaffold according to claim 1, it is characterised in that: the No.1 fastener hole (9) and No. two The two sides up and down of fastener hole (10) are equipped with No.1 expression lobes (3) and No. two expression lobes (4).
6. discharge plate buckle type scaffold according to claim 1, it is characterised in that: the fastener (7) is equipped with for side Smooth bolt among screw thread, and the fastener (7) has the diameter of screw thread side to be less than intermediate diameter.
CN201910390087.0A 2019-05-10 2019-05-10 One discharge plate buckle type scaffold Withdrawn CN110145110A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910390087.0A CN110145110A (en) 2019-05-10 2019-05-10 One discharge plate buckle type scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910390087.0A CN110145110A (en) 2019-05-10 2019-05-10 One discharge plate buckle type scaffold

Publications (1)

Publication Number Publication Date
CN110145110A true CN110145110A (en) 2019-08-20

Family

ID=67595156

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910390087.0A Withdrawn CN110145110A (en) 2019-05-10 2019-05-10 One discharge plate buckle type scaffold

Country Status (1)

Country Link
CN (1) CN110145110A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112609958A (en) * 2020-12-21 2021-04-06 浙江欣捷建设有限公司 High-efficiency disc buckling frame support and construction method thereof
CN114059759A (en) * 2021-11-15 2022-02-18 中建二局第三建筑工程有限公司 Adjustable elevation dish of using little bump technique is buckled a circle dish
CN115506573A (en) * 2022-11-01 2022-12-23 浙江星辰建筑科技有限公司 Firm type scaffold frame

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB330123A (en) * 1929-05-23 1930-06-05 Scaffolding Great Britain Ltd Improvements in or connected with connecting tubes together
JPS56105054U (en) * 1980-01-16 1981-08-17
CN1202590A (en) * 1997-06-12 1998-12-23 日钢计划株式会社 Pipe connecting joint
EP2314797A1 (en) * 2009-10-22 2011-04-27 Gierre S.r.L. Moving scaffold
CN203701570U (en) * 2014-02-24 2014-07-09 吕立明 Safety roof for building
CN105408561A (en) * 2013-08-02 2016-03-16 Peri有限公司 Scaffolding tube of scaffolding, and scaffolding element
CN205875687U (en) * 2016-07-12 2017-01-11 上海宏金设备工程有限公司 A pole setting coupling assembling for coiling detain formula scaffold frame
JP2018003544A (en) * 2016-07-07 2018-01-11 株式会社Osk Pipe joint
CN207988479U (en) * 2017-09-08 2018-10-19 天津市莎烽科技有限公司 New type scaffold pipe fitting

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB330123A (en) * 1929-05-23 1930-06-05 Scaffolding Great Britain Ltd Improvements in or connected with connecting tubes together
JPS56105054U (en) * 1980-01-16 1981-08-17
CN1202590A (en) * 1997-06-12 1998-12-23 日钢计划株式会社 Pipe connecting joint
EP2314797A1 (en) * 2009-10-22 2011-04-27 Gierre S.r.L. Moving scaffold
CN105408561A (en) * 2013-08-02 2016-03-16 Peri有限公司 Scaffolding tube of scaffolding, and scaffolding element
CN203701570U (en) * 2014-02-24 2014-07-09 吕立明 Safety roof for building
JP2018003544A (en) * 2016-07-07 2018-01-11 株式会社Osk Pipe joint
CN205875687U (en) * 2016-07-12 2017-01-11 上海宏金设备工程有限公司 A pole setting coupling assembling for coiling detain formula scaffold frame
CN207988479U (en) * 2017-09-08 2018-10-19 天津市莎烽科技有限公司 New type scaffold pipe fitting

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112609958A (en) * 2020-12-21 2021-04-06 浙江欣捷建设有限公司 High-efficiency disc buckling frame support and construction method thereof
CN114059759A (en) * 2021-11-15 2022-02-18 中建二局第三建筑工程有限公司 Adjustable elevation dish of using little bump technique is buckled a circle dish
CN115506573A (en) * 2022-11-01 2022-12-23 浙江星辰建筑科技有限公司 Firm type scaffold frame

Similar Documents

Publication Publication Date Title
CN110145110A (en) One discharge plate buckle type scaffold
CN108756241B (en) Device is established to shear force wall outside floor template of encorbelmenting
CN208777675U (en) A kind of overhanging scaffold erection structure
CN108894315A (en) System is built in a kind of modular building structure
CN208251619U (en) A kind of assembling truss floor support plate support
CN109025233A (en) Overhanging support and its construction method
CN109252436B (en) Floor tile structure convenient to install fast
CN201731234U (en) Base installing and fixing structure
CN207277630U (en) A kind of stone curtain wall that can be mounted and dismounted from outside
CN208618810U (en) A kind of concrete board wall plank sheathing unilateral side support device
CN210939209U (en) Prefabricated wallboard piling bin
CN212743560U (en) Novel anti-toppling support device for installation of angle steel tower
CN202228880U (en) Mounting and fixing structure of LCD display wall
CN106836942A (en) A kind of electric tower Anti-inclining pedestal
CN210827850U (en) Quick detachable temporary building fixed knot constructs
CN210263827U (en) Scaffold for building construction
CN207974524U (en) The outer drawknot fixture of column cap beam forms
CN110206162A (en) A kind of assembling type steel structure building connector and its construction method
CN220888334U (en) Cylinder platform bracket and construction platform
CN211873427U (en) Assembled steel construction outer wall
CN211246908U (en) Firm sealing part easy to install for material conveying
CN210395873U (en) A tile spare antiskid device that falls for modern building heavy grade roofing
CN218117242U (en) Flexible back edge connector
CN218597805U (en) Building wall adds solid coupling mechanism
CN220267203U (en) Frame column reinforcing device for house building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20190820