CN110130648A - A kind of structure and method of steel pipe column side-wall hole casting concrete - Google Patents

A kind of structure and method of steel pipe column side-wall hole casting concrete Download PDF

Info

Publication number
CN110130648A
CN110130648A CN201910482520.3A CN201910482520A CN110130648A CN 110130648 A CN110130648 A CN 110130648A CN 201910482520 A CN201910482520 A CN 201910482520A CN 110130648 A CN110130648 A CN 110130648A
Authority
CN
China
Prior art keywords
steel pipe
pipe column
hole
pouring
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910482520.3A
Other languages
Chinese (zh)
Inventor
潘樱桃
谢景亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
China Construction Fourth Engineering Division South China Construction Co Ltd
Original Assignee
China Construction Fourth Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Engineering Division Corp Ltd filed Critical China Construction Fourth Engineering Division Corp Ltd
Priority to CN201910482520.3A priority Critical patent/CN110130648A/en
Publication of CN110130648A publication Critical patent/CN110130648A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/24Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/14Railings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses the structure and method of a kind of steel pipe column side-wall hole casting concrete, the present invention is pouring hole (3) to be arranged in steel pipe column (1) side wall, and drain hole (4) are arranged in steel pipe column (1) side wall below pouring hole (3);Pump line is protruded into from pouring hole (3) and completes pouring for steel pipe column interior concrete in steel pipe column (1);After the completion of concreting, pouring hole (3) and drain hole (4) are blocked.The present invention improves construction safety coefficient, shortens the construction period, plays the role of to saving labour and construction cost good.The present invention has the characteristics that structure is simple, construction safety is convenient, time saving and energy saving.

Description

A kind of structure and method of steel pipe column side-wall hole casting concrete
Technical field
The present invention relates to the structures and method of a kind of steel pipe column side-wall hole casting concrete, belong to building construction technology neck Domain.
Background technique
The dual Lateral Resistant System structure of steel core concrete column-Reinforced Concrete Core Walls Structure is that current Super High is common A kind of structure type, this kind of structure type outline border are typically designed to horizontal steel construction+steel core concrete column.Due to inner cylinder and outline border Using the material of different performance, Reinforced Concrete Core Walls Structure is difficult to synchronous with outline border Construction of Steel Structure, and Core Walls Structure is constructed in advance, is led Steel pipe column interior concrete is caused to pour difficulty.
Summary of the invention
The object of the present invention is to provide the structures and method of a kind of steel pipe column side-wall hole casting concrete, in steel After tubing string is continuously installed, concreting is carried out in floor, can be reduced and be faced idle job, and ensure construction quality and construction Progress, thus overcome the deficiencies in the prior art.
To achieve the above object, the present invention adopts the following technical scheme:
A kind of structure of steel pipe column side-wall hole casting concrete of the invention;Including steel pipe column, it is equipped on steel pipe column side wall The pouring hole of pump line can be protruded into, and is equipped with drain hole on the steel pipe column side wall below pouring hole.
In above structure, the inner wall of steel pipe column at the pouring hole is equipped with reinforcing ring, and reinforcing ring is equipped with grout hole;Reinforcing ring Center line be overlapped with the center line of pouring hole;Reinforcing ring outer diameter is greater than pouring hole aperture, and reinforcement annular aperture is less than pouring hole hole Diameter;The radian of inner wall of steel pipe column of contact surface and steel pipe column of reinforcing ring is corresponding;Reinforcing ring surrounding and inner wall of steel pipe column are welded.
A kind of steel pipe column side-wall hole casting concrete method of the invention for above structure;This method is in steel pipe Pouring hole is preset on column side wall, and drain hole is set on the steel pipe column side wall below pouring hole;By pump line from pouring hole It protrudes into and completes pouring for steel pipe column interior concrete in steel pipe column;After the completion of concreting, pouring hole and drain hole are blocked.
In preceding method, the center line of the pouring hole is located at the above 800mm~1200mm of absolute altitude of floor girder steel top surface.
In preceding method, the floor girder steel at the pouring hole is equipped with operating platform;It is equipped with around operating platform and faces side Guardrail.
In preceding method, the pump line includes the vertical pump line of one group of head and the tail connection;Vertical pump line is through bracket and floor steel Beam connection.
In preceding method, the vertical pump line both ends are equipped with connecting flange;Remove the vertical pump of one section be located at pouring hole Pipe, the vertical pump line top of lower section is connect with quarter bend pump line one end;The quarter bend pump line other end protrudes into steel pipe column and through even Acting flange is connect with eyesight elbow;The outlet end of eyesight elbow is bent downwardly and is overlapped with the center line of steel pipe column.
In preceding method, quarter bend pump line bottom is equipped with support, support and operating platform or faces side guardrail and connect.
In preceding method, the pouring hole and drain hole are cut using cutting technique, and what is cut down pours Hole raw steel plate is for blocking pouring hole after the completion of concreting;The drain hole raw steel plate cut down is used for concrete Drain hole is blocked after the completion of pouring.
It in preceding method, when carrying out concreting, is vibrated using layering, layer height is not more than 1 meter;Layering rests When, it is put in steel pipe column and is vibrated from pouring hole using intermediate frequency vibrating spear;The artificial mallet of steel pipe column fit on simultaneously taps, root Judge whether concrete is closely knit according to sound.
In preceding method, pouring for same root steel pipe column should be carried out continuously, and the midfeather time is no more than concrete Presetting period;When concrete cannot be in time for that at once, should take intermittent pumping mode.
By adopting the above-described technical solution, compared with prior art, the present invention the present invention improves construction safety coefficient, The construction period is shortened, is played the role of to saving labour and construction cost good.The present invention is simple with structure, constructs Safe ready, time saving and energy saving feature.
Detailed description of the invention
Fig. 1 is method schematic diagram of the invention;
Fig. 2 is the structural schematic diagram of reinforcing ring;
Fig. 3 is to cut down spare pouring hole raw steel plate;
Fig. 4 is to cut down spare drain hole raw steel plate.
The label in accompanying drawing is: 1- steel pipe column, 2- floor girder steel, 3- pouring hole, 4- drain hole, 5- drain hole raw steel plate, 6- reinforcing ring, 7- support, 8- grout hole, 9- inner wall of steel pipe column, 10- pouring hole raw steel plate, 11- operating platform, 12- face side shield Column, 13- eyesight elbow, 14- bracket, 15- connecting flange, 16- quarter bend pump line, the vertical pump line of 17-, 18- contact surface.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawings and examples.
A kind of structure of steel pipe column side-wall hole casting concrete of the invention, as depicted in figs. 1 and 2, including steel pipe column 1, the pouring hole 3 that can protrude into pump line is equipped on 1 side wall of steel pipe column, and be equipped on the side wall of the steel pipe column 1 below pouring hole 3 Drain hole 4.
In said structure, 1 inner wall of steel pipe column at pouring hole 3 is equipped with reinforcing ring 6, and reinforcing ring 6 is as shown in Fig. 2, mend Strong ring 6 is equipped with grout hole 8;The center line of reinforcing ring 6 is overlapped with the center line of pouring hole 3;6 outer diameter of reinforcing ring is greater than pouring hole 3 Aperture, 6 aperture of reinforcing ring are less than 3 aperture of pouring hole;The radian of the inner wall of steel pipe column 9 of the contact surface 18 and steel pipe column 1 of reinforcing ring 6 It is corresponding;6 surrounding of reinforcing ring and inner wall of steel pipe column 9 are welded, and weld seam grade is level-one.
A kind of method of steel pipe column side-wall hole casting concrete of the invention for above structure;As shown in Figure 1, should Method is pouring hole 3 to be preset on 1 side wall of steel pipe column, and drain hole is arranged on 1 side wall of steel pipe column below pouring hole 3 4;Pump line is protruded into from pouring hole 3 and completes pouring for steel pipe column interior concrete in steel pipe column 1;After the completion of concreting, it will pour It builds hole 3 and drain hole 4 blocks.
The center line of pouring hole 3 is located at the 2 above 800mm~1200mm of top surface absolute altitude of floor girder steel.Building at pouring hole 3 Layer girder steel 2 is equipped with operating platform 11;It is equipped with around operating platform 11 and faces side guardrail 12.Pump line includes the perpendicular of one group of head and the tail connection To pump line 17;Vertical pump line 17 is connect through bracket 14 with floor girder steel 2.Vertical 17 both ends of pump line are equipped with connecting flange 15;It removes Vertical 17 top of pump line of lower section is connect by one section of vertical pump line 17 at pouring hole 3 with 16 one end of quarter bend pump line;Right angle Curved 16 other end of pump line is protruded into steel pipe column 1 and is connect through connecting flange 15 with eyesight elbow 13;The outlet end of eyesight elbow 13 is downward It is bent and is overlapped with the center line of steel pipe column 1.16 bottom of quarter bend pump line is equipped with support 7, support 7 and operating platform 11 or faces side Guardrail 12 connects.
Pouring hole 3 and drain hole 4 are cut using cutting technique, and the pouring hole raw steel plate 10(cut down is shown in Fig. 3) for being blocked after the completion of concreting to pouring hole 3;The drain hole raw steel plate 5(cut down is shown in Fig. 4) it is used for Drain hole 4 is blocked after the completion of concreting.
It when carrying out concreting, is vibrated using layering, layer height is not more than 1 meter;When layering rests, using intermediate frequency Vibrating spear is put in steel pipe column 1 from pouring hole 3 to vibrate;The artificial mallet of 1 fit on of steel pipe column simultaneously taps, and is sentenced according to sound Whether disconnected concrete is closely knit.Pouring for same root steel pipe column 1 should be carried out continuously, and the midfeather time is first no more than concrete The solidifying time;When concrete cannot be in time for that at once, should take intermittent pumping mode.
Embodiment
It as shown in Figure 1: include the pouring hole 3 that 1 side wall of steel pipe column is opened, pouring hole 3 is poured as the concrete of lower layer's steel pipe column That builds pump line puts in hole.Pouring hole 3 is located at the 2 above 800mm~1200mm of top surface absolute altitude of floor girder steel, the height position of pouring hole 3 Casting concrete should be convenient for by setting.One drain hole 4 is set down apart from 3 center line of pouring hole, drain hole 4 is for draining and controlling The absolute altitude of concreting.When Specific construction, at the pouring hole 3 in inner wall of steel pipe column 9 paste a reinforcement with a thickness of 25mm Ring 6, for reinforcing ring 6 as shown in Fig. 2, reinforcing ring 6 is equipped with grout hole 8, the axis of grout hole 8 is consistent with the axis of pouring hole 3.It pours Build hole 3 and drain hole 4 be all made of cutting technique and cut, the pouring hole raw steel plate 10(cut down is shown in Fig. 3) it is used for Pouring hole 3 is blocked after the completion of concreting;The drain hole raw steel plate 5(cut down is shown in Fig. 4) it is poured for concrete Drain hole 4 is blocked after the completion of building.When closure, copes with pouring hole 3 and pouring hole raw steel plate 10 and drain hole 4 and sluice Hole raw steel plate 5 is polished, and pouring hole raw steel plate 10 and 5 surrounding of drain hole raw steel plate is polished groove, then in groove Surrounding weld all around is completed, weld seam answers full bubble-free.Weld seam grade is first-order weld.6 outer arc of reinforcing ring should be with 9 arc of inner wall of steel pipe column It spends identical, it is ensured that 6 outer arc of reinforcing ring is fitted closely with steel pipe column inner arc.Fitting uses the weld all around of angle fillet surrounding.
The present invention constructs according to the following steps:
1, the cutting of pouring hole 3 and drain hole 4 on steel pipe column 1 is completed according to drawing in professional chemical plant;What is cut down pours Hole raw steel plate 10 and drain hole raw steel plate 5 retain spare.And the production of reinforcing ring 6 is completed according to drawing in professional chemical plant, and Reinforcing ring 6 is welded in the inner wall of steel pipe column 9 of 3 corresponding position of pouring hole;
2, steel pipe column 1 is end to end, complete the installation of steel pipe column 1;It is completed at the same time the connection of steel pipe column 1 Yu floor girder steel;
3, operating platform 11 is set up outside the pouring hole 3 of steel pipe column 1;And it is set up at 11 edge of operating platform and faces side guardrail 12;
4, vertical pump line 17 is laid using operating platform 11, vertical pump line 17 is connected using connecting flange 15, and vertical pump line 17 is logical Bracket 14 is crossed to connect with floor girder steel 2;
5, one section of vertical pump line 17 being located at outside pouring hole 3 is removed, and in next section of 17 top of vertical pump line connection quarter bend pump Pipe 16,16 other end of quarter bend pump line are protruded into steel pipe column 1 and are connect through connecting flange 15 with eyesight elbow 13;Eyesight elbow 13 goes out Mouth end is bent downwardly and is overlapped with the center line of steel pipe column 1;
6, in 16 bottom of quarter bend pump line setting support 7, support 7 and operating platform 11 or face side guardrail 12 and connect.
7, concreting is carried out;Concreting is vibrated using layering, and layer height is not more than 1 meter, when layering rests Between, it is put in steel pipe column 1 and is vibrated from pouring hole 3 using intermediate frequency vibrating spear.The artificial mallet of 1 fit on of steel pipe column strikes simultaneously It hits, judges whether concrete is closely knit according to sound.The pumping dynamics that pump truck should be controlled when pouring enables concrete hang down in cavity It is straight to fall, the self-compaction of concrete is reached using the kinetic energy that concrete whereabouts generates.And controlled using drain hole 4, it pours Build to drain hole 4 overflow concrete grout when, that is, stop pour.Concreting forming surface in lower section steel pipe column 1 is away from drain hole 4 Distance cannot be less than 500mm.
8, after the completion of a layer concrete pours, pouring hole raw steel plate 10 is carried out before concreting after carrying out upper layer and is let out Water hole raw steel plate 5 blocks welding, and weld seam grade is first-order weld.It must be strictly controlled welding sequence when welding, after the completion of welding It needs to carry out carrying out flaw detection qualification, guarantees quality.
When carrying out pouring hole raw steel plate 10 and drain hole raw steel plate 5 and blocking welding, it should be ensured that 1 concrete is not in steel pipe column It can be impaired because welding.Same root steel pipe column 1 should be carried out continuously when pouring, initial set of the midfeather time no more than concrete Time.When concrete cannot be in time for that at once, should take intermittent pumping mode.
Concreting process carries out from the bottom to top, repeats step 5~8 until completing pouring for whole steel pipe column 1.
The present invention improves construction safety coefficient, shortens the construction period, plays to saving labour and construction cost Good effect.The present invention has the characteristics that structure is simple, construction safety is convenient, time saving and energy saving.

Claims (10)

1. a kind of structure of steel pipe column side-wall hole casting concrete, including steel pipe column (1), it is characterised in that: in steel pipe column (1) Side wall is equipped with the pouring hole (3) that can protrude into pump line, and drain hole is equipped on steel pipe column (1) side wall below pouring hole (3) (4).
2. the structure of steel pipe column side-wall hole casting concrete according to claim 1, it is characterised in that: the pouring hole (3) steel pipe column (1) inner wall at is equipped with reinforcing ring (6), and reinforcing ring (6) is equipped with grout hole (8);The center line of reinforcing ring (6) with The center line of pouring hole (3) is overlapped;Reinforcing ring (6) outer diameter is greater than pouring hole (3) aperture, and reinforcing ring (6) aperture is less than pouring hole (3) aperture;The contact surface (18) of reinforcing ring (6) and the radian of inner wall of steel pipe column (9) of steel pipe column (1) are corresponding;Reinforcing ring (6) four Week welds with inner wall of steel pipe column (9).
3. a kind of method of steel pipe column side-wall hole casting concrete;It is characterized by: this method is on steel pipe column (1) side wall It presets pouring hole (3), and drain hole (4) is set on steel pipe column (1) side wall below pouring hole (3);By pump line from pouring It builds hole (3) and protrudes into pouring for the interior completion steel pipe column interior concrete of steel pipe column (1);After the completion of concreting, by pouring hole (3) and Drain hole (4) blocks.
4. the method for steel pipe column side-wall hole casting concrete according to claim 3, it is characterised in that: the pouring hole (3) center line is located at the above 800mm~1200mm of absolute altitude of floor girder steel (2) top surface.
5. the method for steel pipe column side-wall hole casting concrete according to claim 3, it is characterised in that: the pouring hole (3) the floor girder steel (2) at is equipped with operating platform (11);It is equipped with around operating platform (11) and faces side guardrail (12).
6. the method for steel pipe column side-wall hole casting concrete according to claim 3, it is characterised in that: the pump line includes The vertical pump line (17) of one group of head and the tail connection;Vertical pump line (17) is connect through bracket (14) with floor girder steel (2).
7. the method for steel pipe column side-wall hole casting concrete according to claim 6, it is characterised in that: the vertical pump line (17) both ends are equipped with connecting flange (15);One section of vertical pump line (17) being located at pouring hole (3) is removed, by the vertical pump line of lower section (17) top is connect with quarter bend pump line (16) one end;Quarter bend pump line (16) other end protrudes into steel pipe column (1) and through connecting Flange (15) is connect with eyesight elbow (13);The outlet end of eyesight elbow (13) is bent downwardly and is overlapped with the center line of steel pipe column (1).
8. the method for steel pipe column side-wall hole casting concrete according to claim 7, it is characterised in that: the quarter bend pump It manages (16) bottom and is equipped with support (7), support (7) and operating platform (11) or face side guardrail (12) and connect.
9. the method for steel pipe column side-wall hole casting concrete according to claim 3, it is characterised in that: the pouring hole (3) it is cut with drain hole (4) using cutting technique, the pouring hole raw steel plate (10) cut down is poured for concrete Pouring hole (3) is blocked after the completion of building;The drain hole raw steel plate (5) cut down for after the completion of concreting to letting out Water hole (4) is blocked.
10. the method for steel pipe column side-wall hole casting concrete according to claim 3, it is characterised in that: carrying out coagulation It when soil pours, is vibrated using layering, layer height is not more than 1 meter;Layering is when resting, using intermediate frequency vibrating spear from pouring hole (3) It puts in steel pipe column (1) and vibrates;The artificial mallet of steel pipe column (1) fit on simultaneously taps, and judges that concrete is according to sound It is no closely knit;Pouring for same root steel pipe column (1) should be carried out continuously, presetting period of the midfeather time no more than concrete; When concrete cannot be in time for that at once, should take intermittent pumping mode.
CN201910482520.3A 2019-06-04 2019-06-04 A kind of structure and method of steel pipe column side-wall hole casting concrete Pending CN110130648A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910482520.3A CN110130648A (en) 2019-06-04 2019-06-04 A kind of structure and method of steel pipe column side-wall hole casting concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910482520.3A CN110130648A (en) 2019-06-04 2019-06-04 A kind of structure and method of steel pipe column side-wall hole casting concrete

Publications (1)

Publication Number Publication Date
CN110130648A true CN110130648A (en) 2019-08-16

Family

ID=67580247

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910482520.3A Pending CN110130648A (en) 2019-06-04 2019-06-04 A kind of structure and method of steel pipe column side-wall hole casting concrete

Country Status (1)

Country Link
CN (1) CN110130648A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115405047A (en) * 2022-10-12 2022-11-29 中建八局第四建设有限公司 Method for pouring concrete in steel pipe

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10110530A (en) * 1996-10-04 1998-04-28 Nkk Corp Draining method and device in steel pipe concrete column
CN203066355U (en) * 2012-12-06 2013-07-17 中建钢构有限公司 Concrete-filled steel tube column and subassembly thereof
CN103510702A (en) * 2013-09-29 2014-01-15 广州建筑股份有限公司 Concrete-filled steel tube column needle type concrete pouring construction method
CN104131704A (en) * 2014-05-16 2014-11-05 中国建筑第四工程局有限公司 Steel pipe column concrete lateral pouring method and steel pipe column structure used in method
CN206071063U (en) * 2016-10-13 2017-04-05 中国建筑一局(集团)有限公司 High-pressure pump pipe jacking and pouring system for post-repair construction of super high-rise building
CN210563437U (en) * 2019-06-04 2020-05-19 中建四局华南建设有限公司 Structure for pouring concrete through opening in side wall of steel pipe column

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10110530A (en) * 1996-10-04 1998-04-28 Nkk Corp Draining method and device in steel pipe concrete column
CN203066355U (en) * 2012-12-06 2013-07-17 中建钢构有限公司 Concrete-filled steel tube column and subassembly thereof
CN103510702A (en) * 2013-09-29 2014-01-15 广州建筑股份有限公司 Concrete-filled steel tube column needle type concrete pouring construction method
CN104131704A (en) * 2014-05-16 2014-11-05 中国建筑第四工程局有限公司 Steel pipe column concrete lateral pouring method and steel pipe column structure used in method
CN206071063U (en) * 2016-10-13 2017-04-05 中国建筑一局(集团)有限公司 High-pressure pump pipe jacking and pouring system for post-repair construction of super high-rise building
CN210563437U (en) * 2019-06-04 2020-05-19 中建四局华南建设有限公司 Structure for pouring concrete through opening in side wall of steel pipe column

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115405047A (en) * 2022-10-12 2022-11-29 中建八局第四建设有限公司 Method for pouring concrete in steel pipe

Similar Documents

Publication Publication Date Title
CN103526929B (en) A kind of super high-rise steel pipe column interior concrete pouring construction method
CN103821280A (en) Construction method for steel tube confined concrete composite columns
CN105275209A (en) Special-shaped spatial curved surface water concrete construction method
CN1978838A (en) Construction method for combined V-shape steel pipe concrete pile
CN101487293A (en) Concrete pouring method for beam-column joints with different strength grades
CN102296570B (en) Construction method of large cast-in-place reinforced concrete water inlet channel
CN104131704A (en) Steel pipe column concrete lateral pouring method and steel pipe column structure used in method
CN106760502A (en) Shear wall end cylinder construction method
CN110103326A (en) A kind of prefabricated panel pylon preformed hole and device for hoisting
CN110130648A (en) A kind of structure and method of steel pipe column side-wall hole casting concrete
CN104612697A (en) Construction method for subway station track upwind way
CN210563437U (en) Structure for pouring concrete through opening in side wall of steel pipe column
CN106049704B (en) Prefabrication cast-in-place combined type fair-faced concrete outer wall structure and construction method
CN110017023A (en) Collar tie beam construction method based on tool-type regularization concrete collar tie beam formwork erecting structure
CN102425110A (en) Cast-in-situ concrete construction method for full section of urban overpass box girder
CN108582426A (en) A kind of producing device and production method of stiffened column
CN110761562A (en) Auxiliary tool for pouring concrete and using method
CN115506272A (en) Installation and construction method for regular octagonal steel ladle concrete cable tower
CN108331343A (en) The construction method of Cantilever Beams and aluminum alloy mould plate lap-joint
CN210562268U (en) Portable grouting groove structure in fan anchor bolt foundation secondary grouting
CN111236075B (en) External prestressed reinforcement bundle mounting structure of concrete box bridge
CN208163928U (en) A kind of producing device of stiffened column
CN210738077U (en) Waterproof reverse-edge aluminum alloy hanging die
CN204001713U (en) V-type cylinder oblique line section concrete is built mould
CN114083641A (en) Vibrator combined structure in precast T-beam concrete pouring process and use method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20200116

Address after: 510700 room 702, building a, room 701, building a, No. 18, science Avenue, Huangpu District, Guangzhou City, Guangdong Province

Applicant after: South China Construction Co., Ltd. of China Construction Fourth Engineering Bureau

Applicant after: China Construction Fourth Engineering Bureau Ltd.

Address before: 510665 Guangzhou, Guangdong, Guangzhou, Tianhe District, 16 Guangzhou Road, B 4 block.

Applicant before: China Construction Fourth Engineering Bureau Ltd.