A kind of structure and method of steel pipe column side-wall hole casting concrete
Technical field
The present invention relates to the structures and method of a kind of steel pipe column side-wall hole casting concrete, belong to building construction technology neck
Domain.
Background technique
The dual Lateral Resistant System structure of steel core concrete column-Reinforced Concrete Core Walls Structure is that current Super High is common
A kind of structure type, this kind of structure type outline border are typically designed to horizontal steel construction+steel core concrete column.Due to inner cylinder and outline border
Using the material of different performance, Reinforced Concrete Core Walls Structure is difficult to synchronous with outline border Construction of Steel Structure, and Core Walls Structure is constructed in advance, is led
Steel pipe column interior concrete is caused to pour difficulty.
Summary of the invention
The object of the present invention is to provide the structures and method of a kind of steel pipe column side-wall hole casting concrete, in steel
After tubing string is continuously installed, concreting is carried out in floor, can be reduced and be faced idle job, and ensure construction quality and construction
Progress, thus overcome the deficiencies in the prior art.
To achieve the above object, the present invention adopts the following technical scheme:
A kind of structure of steel pipe column side-wall hole casting concrete of the invention;Including steel pipe column, it is equipped on steel pipe column side wall
The pouring hole of pump line can be protruded into, and is equipped with drain hole on the steel pipe column side wall below pouring hole.
In above structure, the inner wall of steel pipe column at the pouring hole is equipped with reinforcing ring, and reinforcing ring is equipped with grout hole;Reinforcing ring
Center line be overlapped with the center line of pouring hole;Reinforcing ring outer diameter is greater than pouring hole aperture, and reinforcement annular aperture is less than pouring hole hole
Diameter;The radian of inner wall of steel pipe column of contact surface and steel pipe column of reinforcing ring is corresponding;Reinforcing ring surrounding and inner wall of steel pipe column are welded.
A kind of steel pipe column side-wall hole casting concrete method of the invention for above structure;This method is in steel pipe
Pouring hole is preset on column side wall, and drain hole is set on the steel pipe column side wall below pouring hole;By pump line from pouring hole
It protrudes into and completes pouring for steel pipe column interior concrete in steel pipe column;After the completion of concreting, pouring hole and drain hole are blocked.
In preceding method, the center line of the pouring hole is located at the above 800mm~1200mm of absolute altitude of floor girder steel top surface.
In preceding method, the floor girder steel at the pouring hole is equipped with operating platform;It is equipped with around operating platform and faces side
Guardrail.
In preceding method, the pump line includes the vertical pump line of one group of head and the tail connection;Vertical pump line is through bracket and floor steel
Beam connection.
In preceding method, the vertical pump line both ends are equipped with connecting flange;Remove the vertical pump of one section be located at pouring hole
Pipe, the vertical pump line top of lower section is connect with quarter bend pump line one end;The quarter bend pump line other end protrudes into steel pipe column and through even
Acting flange is connect with eyesight elbow;The outlet end of eyesight elbow is bent downwardly and is overlapped with the center line of steel pipe column.
In preceding method, quarter bend pump line bottom is equipped with support, support and operating platform or faces side guardrail and connect.
In preceding method, the pouring hole and drain hole are cut using cutting technique, and what is cut down pours
Hole raw steel plate is for blocking pouring hole after the completion of concreting;The drain hole raw steel plate cut down is used for concrete
Drain hole is blocked after the completion of pouring.
It in preceding method, when carrying out concreting, is vibrated using layering, layer height is not more than 1 meter;Layering rests
When, it is put in steel pipe column and is vibrated from pouring hole using intermediate frequency vibrating spear;The artificial mallet of steel pipe column fit on simultaneously taps, root
Judge whether concrete is closely knit according to sound.
In preceding method, pouring for same root steel pipe column should be carried out continuously, and the midfeather time is no more than concrete
Presetting period;When concrete cannot be in time for that at once, should take intermittent pumping mode.
By adopting the above-described technical solution, compared with prior art, the present invention the present invention improves construction safety coefficient,
The construction period is shortened, is played the role of to saving labour and construction cost good.The present invention is simple with structure, constructs
Safe ready, time saving and energy saving feature.
Detailed description of the invention
Fig. 1 is method schematic diagram of the invention;
Fig. 2 is the structural schematic diagram of reinforcing ring;
Fig. 3 is to cut down spare pouring hole raw steel plate;
Fig. 4 is to cut down spare drain hole raw steel plate.
The label in accompanying drawing is: 1- steel pipe column, 2- floor girder steel, 3- pouring hole, 4- drain hole, 5- drain hole raw steel plate,
6- reinforcing ring, 7- support, 8- grout hole, 9- inner wall of steel pipe column, 10- pouring hole raw steel plate, 11- operating platform, 12- face side shield
Column, 13- eyesight elbow, 14- bracket, 15- connecting flange, 16- quarter bend pump line, the vertical pump line of 17-, 18- contact surface.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawings and examples.
A kind of structure of steel pipe column side-wall hole casting concrete of the invention, as depicted in figs. 1 and 2, including steel pipe column
1, the pouring hole 3 that can protrude into pump line is equipped on 1 side wall of steel pipe column, and be equipped on the side wall of the steel pipe column 1 below pouring hole 3
Drain hole 4.
In said structure, 1 inner wall of steel pipe column at pouring hole 3 is equipped with reinforcing ring 6, and reinforcing ring 6 is as shown in Fig. 2, mend
Strong ring 6 is equipped with grout hole 8;The center line of reinforcing ring 6 is overlapped with the center line of pouring hole 3;6 outer diameter of reinforcing ring is greater than pouring hole 3
Aperture, 6 aperture of reinforcing ring are less than 3 aperture of pouring hole;The radian of the inner wall of steel pipe column 9 of the contact surface 18 and steel pipe column 1 of reinforcing ring 6
It is corresponding;6 surrounding of reinforcing ring and inner wall of steel pipe column 9 are welded, and weld seam grade is level-one.
A kind of method of steel pipe column side-wall hole casting concrete of the invention for above structure;As shown in Figure 1, should
Method is pouring hole 3 to be preset on 1 side wall of steel pipe column, and drain hole is arranged on 1 side wall of steel pipe column below pouring hole 3
4;Pump line is protruded into from pouring hole 3 and completes pouring for steel pipe column interior concrete in steel pipe column 1;After the completion of concreting, it will pour
It builds hole 3 and drain hole 4 blocks.
The center line of pouring hole 3 is located at the 2 above 800mm~1200mm of top surface absolute altitude of floor girder steel.Building at pouring hole 3
Layer girder steel 2 is equipped with operating platform 11;It is equipped with around operating platform 11 and faces side guardrail 12.Pump line includes the perpendicular of one group of head and the tail connection
To pump line 17;Vertical pump line 17 is connect through bracket 14 with floor girder steel 2.Vertical 17 both ends of pump line are equipped with connecting flange 15;It removes
Vertical 17 top of pump line of lower section is connect by one section of vertical pump line 17 at pouring hole 3 with 16 one end of quarter bend pump line;Right angle
Curved 16 other end of pump line is protruded into steel pipe column 1 and is connect through connecting flange 15 with eyesight elbow 13;The outlet end of eyesight elbow 13 is downward
It is bent and is overlapped with the center line of steel pipe column 1.16 bottom of quarter bend pump line is equipped with support 7, support 7 and operating platform 11 or faces side
Guardrail 12 connects.
Pouring hole 3 and drain hole 4 are cut using cutting technique, and the pouring hole raw steel plate 10(cut down is shown in
Fig. 3) for being blocked after the completion of concreting to pouring hole 3;The drain hole raw steel plate 5(cut down is shown in Fig. 4) it is used for
Drain hole 4 is blocked after the completion of concreting.
It when carrying out concreting, is vibrated using layering, layer height is not more than 1 meter;When layering rests, using intermediate frequency
Vibrating spear is put in steel pipe column 1 from pouring hole 3 to vibrate;The artificial mallet of 1 fit on of steel pipe column simultaneously taps, and is sentenced according to sound
Whether disconnected concrete is closely knit.Pouring for same root steel pipe column 1 should be carried out continuously, and the midfeather time is first no more than concrete
The solidifying time;When concrete cannot be in time for that at once, should take intermittent pumping mode.
Embodiment
It as shown in Figure 1: include the pouring hole 3 that 1 side wall of steel pipe column is opened, pouring hole 3 is poured as the concrete of lower layer's steel pipe column
That builds pump line puts in hole.Pouring hole 3 is located at the 2 above 800mm~1200mm of top surface absolute altitude of floor girder steel, the height position of pouring hole 3
Casting concrete should be convenient for by setting.One drain hole 4 is set down apart from 3 center line of pouring hole, drain hole 4 is for draining and controlling
The absolute altitude of concreting.When Specific construction, at the pouring hole 3 in inner wall of steel pipe column 9 paste a reinforcement with a thickness of 25mm
Ring 6, for reinforcing ring 6 as shown in Fig. 2, reinforcing ring 6 is equipped with grout hole 8, the axis of grout hole 8 is consistent with the axis of pouring hole 3.It pours
Build hole 3 and drain hole 4 be all made of cutting technique and cut, the pouring hole raw steel plate 10(cut down is shown in Fig. 3) it is used for
Pouring hole 3 is blocked after the completion of concreting;The drain hole raw steel plate 5(cut down is shown in Fig. 4) it is poured for concrete
Drain hole 4 is blocked after the completion of building.When closure, copes with pouring hole 3 and pouring hole raw steel plate 10 and drain hole 4 and sluice
Hole raw steel plate 5 is polished, and pouring hole raw steel plate 10 and 5 surrounding of drain hole raw steel plate is polished groove, then in groove
Surrounding weld all around is completed, weld seam answers full bubble-free.Weld seam grade is first-order weld.6 outer arc of reinforcing ring should be with 9 arc of inner wall of steel pipe column
It spends identical, it is ensured that 6 outer arc of reinforcing ring is fitted closely with steel pipe column inner arc.Fitting uses the weld all around of angle fillet surrounding.
The present invention constructs according to the following steps:
1, the cutting of pouring hole 3 and drain hole 4 on steel pipe column 1 is completed according to drawing in professional chemical plant;What is cut down pours
Hole raw steel plate 10 and drain hole raw steel plate 5 retain spare.And the production of reinforcing ring 6 is completed according to drawing in professional chemical plant, and
Reinforcing ring 6 is welded in the inner wall of steel pipe column 9 of 3 corresponding position of pouring hole;
2, steel pipe column 1 is end to end, complete the installation of steel pipe column 1;It is completed at the same time the connection of steel pipe column 1 Yu floor girder steel;
3, operating platform 11 is set up outside the pouring hole 3 of steel pipe column 1;And it is set up at 11 edge of operating platform and faces side guardrail 12;
4, vertical pump line 17 is laid using operating platform 11, vertical pump line 17 is connected using connecting flange 15, and vertical pump line 17 is logical
Bracket 14 is crossed to connect with floor girder steel 2;
5, one section of vertical pump line 17 being located at outside pouring hole 3 is removed, and in next section of 17 top of vertical pump line connection quarter bend pump
Pipe 16,16 other end of quarter bend pump line are protruded into steel pipe column 1 and are connect through connecting flange 15 with eyesight elbow 13;Eyesight elbow 13 goes out
Mouth end is bent downwardly and is overlapped with the center line of steel pipe column 1;
6, in 16 bottom of quarter bend pump line setting support 7, support 7 and operating platform 11 or face side guardrail 12 and connect.
7, concreting is carried out;Concreting is vibrated using layering, and layer height is not more than 1 meter, when layering rests
Between, it is put in steel pipe column 1 and is vibrated from pouring hole 3 using intermediate frequency vibrating spear.The artificial mallet of 1 fit on of steel pipe column strikes simultaneously
It hits, judges whether concrete is closely knit according to sound.The pumping dynamics that pump truck should be controlled when pouring enables concrete hang down in cavity
It is straight to fall, the self-compaction of concrete is reached using the kinetic energy that concrete whereabouts generates.And controlled using drain hole 4, it pours
Build to drain hole 4 overflow concrete grout when, that is, stop pour.Concreting forming surface in lower section steel pipe column 1 is away from drain hole 4
Distance cannot be less than 500mm.
8, after the completion of a layer concrete pours, pouring hole raw steel plate 10 is carried out before concreting after carrying out upper layer and is let out
Water hole raw steel plate 5 blocks welding, and weld seam grade is first-order weld.It must be strictly controlled welding sequence when welding, after the completion of welding
It needs to carry out carrying out flaw detection qualification, guarantees quality.
When carrying out pouring hole raw steel plate 10 and drain hole raw steel plate 5 and blocking welding, it should be ensured that 1 concrete is not in steel pipe column
It can be impaired because welding.Same root steel pipe column 1 should be carried out continuously when pouring, initial set of the midfeather time no more than concrete
Time.When concrete cannot be in time for that at once, should take intermittent pumping mode.
Concreting process carries out from the bottom to top, repeats step 5~8 until completing pouring for whole steel pipe column 1.
The present invention improves construction safety coefficient, shortens the construction period, plays to saving labour and construction cost
Good effect.The present invention has the characteristics that structure is simple, construction safety is convenient, time saving and energy saving.