CN110130347A - Intelligent positioning guiding device, method, project management method for pile foundation construction - Google Patents

Intelligent positioning guiding device, method, project management method for pile foundation construction Download PDF

Info

Publication number
CN110130347A
CN110130347A CN201910358497.7A CN201910358497A CN110130347A CN 110130347 A CN110130347 A CN 110130347A CN 201910358497 A CN201910358497 A CN 201910358497A CN 110130347 A CN110130347 A CN 110130347A
Authority
CN
China
Prior art keywords
layer casing
internal layer
pile foundation
positioning
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910358497.7A
Other languages
Chinese (zh)
Other versions
CN110130347B (en
Inventor
王巧艺
黄金星
陈金龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Lugang (group) Co Ltd
Original Assignee
Fujian Lugang (group) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Lugang (group) Co Ltd filed Critical Fujian Lugang (group) Co Ltd
Priority to CN201910358497.7A priority Critical patent/CN110130347B/en
Publication of CN110130347A publication Critical patent/CN110130347A/en
Application granted granted Critical
Publication of CN110130347B publication Critical patent/CN110130347B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/04Guide devices; Guide frames
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L67/00Network arrangements or protocols for supporting network services or applications
    • H04L67/01Protocols
    • H04L67/02Protocols based on web technology, e.g. hypertext transfer protocol [HTTP]
    • H04L67/025Protocols based on web technology, e.g. hypertext transfer protocol [HTTP] for remote control or remote monitoring of applications
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L67/00Network arrangements or protocols for supporting network services or applications
    • H04L67/01Protocols
    • H04L67/12Protocols specially adapted for proprietary or special-purpose networking environments, e.g. medical networks, sensor networks, networks in vehicles or remote metering networks
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L67/00Network arrangements or protocols for supporting network services or applications
    • H04L67/50Network services
    • H04L67/52Network services specially adapted for the location of the user terminal

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Signal Processing (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • Health & Medical Sciences (AREA)
  • Computing Systems (AREA)
  • Medical Informatics (AREA)
  • General Health & Medical Sciences (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention belongs to foundation construction technical fields, and in particular to kind is used for intelligent positioning guiding device, method, the project management method of pile foundation construction.The intelligent positioning guiding device for pile foundation construction, including outer layer casing, internal layer casing, position adjusting mechanism, positioning mechanism, the position data of internal layer casing is obtained by positioning mechanism, and the adjustment movement of position adjusting mechanism is controlled by the position data, realize the positioning in the accurate positionin and steel reinforcement cage hole of pile foundation guiding, it improves filling pile construction and transfers vertical precision into brill precision and reinforcing bar cage hoisting, solve conventional filling pile construction because ground layer soil body it is soft or hard it is uneven caused by hole scattering, pile body out of plumb and steel reinforcement cage lowered position are not allowed to cause pile body deflection, the security risks such as unbalance stress, guarantee construction quality, improve the efficiency of management.

Description

Intelligent positioning guiding device, method, project management method for pile foundation construction
Technical field
The invention belongs to foundation construction technical fields, and in particular to a kind of intelligent positioning guiding dress for pile foundation construction It sets, method, project management method.
Background technique
The filling column that drills is a kind of pile-type most-often used in engineering construction, it is generated by the contact surface of pile body and ground Collateral resistance and stake end and ground the end resistance that generates of contact surface, effective bearing capacity is formed, by engineering pile by capital load Pass to the ground of a side and stake bottom, thus make building or structures firmly stand on the basis of, with various regions urbanization into The quickening of journey and the development of auto industry, Basement pit supporting increasingly become the key technology of construction project, and bored concrete pile is made It is the primary structural member of pattern foundation pit supporting structure for support pile, is also increasingly valued by people.
In the installation and process of construction of bored concrete pile, there is biggish relationship with the geological environment of construction location, for difference Geological environment often there is also different, especially extensive use of the bored concrete pile in bridge pier construction, bridges in construction method Pile foundation be generally in complex formation it is changeable, it is soft or hard it is uneven etc. under the conditions of, conventional steel pile casting construction is soft or hard uneven in the soil body In the case of, easily there is hole scattering, pile body out of plumb and steel reinforcement cage lowered position and is not allowed to cause pile body deflection, unbalance stress etc. Security hidden trouble.
Summary of the invention
In order to solve above-mentioned conventional steel pile casting construction, in the soft or hard uneven situation of the soil body, easily there is hole scattering, stake Body out of plumb and steel reinforcement cage lowered position are not allowed to cause the security hidden troubles such as pile body deflection, unbalance stress, and the present invention provides one Kind is used for intelligent positioning guiding device, method, the project management method of pile foundation construction.
To achieve the above object, the technical scheme adopted by the invention is that: a kind of intelligent positioning for pile foundation construction is led To device, including outer layer casing, internal layer casing, position adjusting mechanism, positioning mechanism, the internal layer casing is sheathed on outer layer casing There are adjustment gap between interior and internal layer casing set and outer layer casing, the position adjusting mechanism connect with internal layer casing and is used for The relative position of internal layer casing and outer layer casing is adjusted, the positioning mechanism is used to obtain the position data of internal layer casing, And it is acted by the adjustment that position data controls position adjusting mechanism.
Further, positioning mechanism includes multiple, and multiple positioning mechanisms are uniformly arranged in internal layer casing top.
Further, positioning mechanism is GPS laser locator, and the GPS laser locator obtains the internal layer casing Geographic location data message, the in real time station-keeping data between acquisition internal layer casing and outer layer casing.
Further, position adjusting mechanism includes multiple groups, and every group of position adjusting mechanism is believed with a positioning mechanism respectively Number connection.
Further, every group of position adjusting mechanism includes at least two pushers, and multiple pushers with group are vertical It is arranged on the side wall of outer layer casing, the pusher has the push rod extended into adjustment gap, and the push rod and internal layer protect Cylinder is fixedly connected.
It further, further include data terminal, the positioning mechanism is docked with data terminal data, for it will acquire in The position data of layer casing is uploaded to data terminal.
A kind of positioning and guiding method for pile foundation construction is oriented to dress using the above-mentioned intelligent positioning for pile foundation construction It sets, method is as follows:
Operation platform is arranged, guiding installation pit is excavated, intelligent positioning guiding device is installed to the installation pit, utilize The outer layer casing is fixed in soil body backfill;
It carries out note mud off operation, progress pile body construction operation or bored concrete pile bore operation, steel reinforcement cage and work is precisely installed Industry,
When operation, the position data of the synchronous detection internal layer casing of positioning mechanism, and will test data and be processed into control The control instruction of positioning mechanism, position adjusting mechanism adjust position of the internal layer casing relative to outer layer casing according to control instruction, The verticality and levelness for guaranteeing internal layer casing meet construction requirement, until operation is completed.
Further, before intelligent positioning guiding device being installed to the installation pit, intelligence is obtained by positioning mechanism Locating guide device installs precise mounting position information extremely.
Further, after positional relationship of the position adjusting mechanism according to control instruction adjustment internal layer casing, positioning mechanism is again The location information of secondary detection internal layer casing, until internal layer casing meets preset construction requirement.
A kind of pile foundation job engineering management method, using the above-mentioned intelligent positioning guiding device for pile foundation construction,
It obtains in work progress, the position data for the detection synchronous with construction that positioning mechanism obtains is uploaded to cloud data Library;
Position data is arranged, pile foundation work data is converted into;
The positional relationship variation in work progress is obtained by pile foundation work data, and then pipe is carried out to pile foundation job engineering Reason.
The present invention provides a kind of intelligent positioning guiding device for pile foundation construction, by opening in pile foundation construction job platform Outer layer casing, internal layer casing, position adjusting mechanism, positioning mechanism is arranged in the guiding installation pit of digging, realizes the accurate of pile foundation guiding Positioning in positioning and steel reinforcement cage hole improves filling pile construction into precision and reinforcing bar cage hoisting decentralization vertical precision is bored, solves normal Rule filling pile construction because ground layer soil body it is soft or hard it is uneven caused by hole scattering, pile body out of plumb and steel reinforcement cage lowered position be not allowed to make At security risks such as pile body deflection, unbalance stress, guarantee construction quality, improves the efficiency of management.
Detailed description of the invention
Fig. 1 is the structural schematic diagram before the use of intelligent positioning guiding device;
Fig. 2 is structural schematic diagram when intelligent positioning guiding device uses;
Fig. 3 is the top view of the intelligent positioning guiding device for pile foundation construction;
Fig. 4 is the flow chart of the intelligent positioning guidance method for pile foundation construction;
Fig. 5 is the flow chart of pile foundation job engineering management method.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, is clearly and completely retouched to the technical solution in the present invention It states, it is clear that the described embodiments are merely a part of the embodiments of the present invention, instead of all the embodiments.
As shown in Figure 1-3, a kind of intelligent positioning guiding device for pile foundation construction, including outer layer casing 1, internal layer casing 2, position adjusting mechanism 3, positioning mechanism 4, internal layer casing 2 is the adjustable steel pile casting of internal layer in the present embodiment, and outer layer casing 1 is outer layer Fixed steel pile casting, the internal layer casing 2 be sheathed in outer layer casing 1 and 2 sets of internal layer casing there are tune between outer layer casing 1 Whole gap, the position adjusting mechanism 3 connect the opposite position for adjusting internal layer casing 2 Yu outer layer casing 1 with internal layer casing 2 It sets, the positioning mechanism 4 is used to obtain the position data of internal layer casing, and controls position adjustment by position data The adjustment of mechanism acts, and realizes the positioning in the accurate positionin and steel reinforcement cage hole of pile foundation guiding, improves filling pile construction into brill essence Degree and reinforcing bar cage hoisting transfer vertical precision, guarantee construction quality, improve the efficiency of management, effectively solve conventional filling pile construction because Ground layer soil body is soft or hard unevenly cause hole scattering, pile body out of plumb and steel reinforcement cage lowered position be not allowed to cause pile body deflection, by The unequal security risk of power.
For positioning mechanism 4 including multiple, multiple positioning mechanisms are uniformly arranged in internal layer casing top, positioning mechanism GPS Laser locator, the GPS laser locator obtain the geographic location data message of the internal layer casing, acquire internal layer shield in real time Station-keeping data between cylinder and outer layer casing, GPS laser locator includes four in the present embodiment, is symmetrically set in described Layer casing top, and the GPS laser locator analyzes the position data of acquisition, handles, Dynamic Display, realizes to internal layer Adjustable steel pile casting position adjustment guides, manages and early warning;
Position adjusting mechanism 3 includes multiple groups, and every group of position adjusting mechanism is connect with a positioning mechanism signal respectively.Often Group position adjusting mechanism includes at least two pushers, and multiple pushers with group are arranged vertically within the side wall of outer layer casing On, the pusher has the push rod extended into adjustment gap, and the push rod is fixedly connected with internal layer casing;In the present embodiment Pusher is intelligent hydraulic pusher, is respectively symmetrically set to internal layer casing top and bottom end, i.e. the top of internal layer casing is set There are four pusher, be symmetrically set in internal layer casing low side also there are four;The intelligent hydraulic pusher working principle is to be swashed according to GPS After the position data of light-seeking device acquisition is handled, converted, it is transmitted to intelligent hydraulic pusher, intelligent hydraulic pusher is according to place Data carry out primary positioning to internal layer adjustable steel casing plane and vertical position and adjust after reason, and then GPS laser locator is again Data are acquired, above-mentioned adjusting is carried out, until the adjustable steel pile casting of internal layer is adjusted to predeterminated position, realize the accurate positionin of pile foundation guiding With the positioning in steel reinforcement cage hole, filling pile construction is improved into brill precision and reinforcing bar cage hoisting and transfers vertical precision;
The present embodiment further includes data terminal, and the positioning mechanism is docked with data terminal data, for it will acquire in The position data of layer casing is uploaded to data terminal, i.e. GPS laser locator can retain initial data in the construction process, and Data are uploaded to wisdom construction management platform, construction management, quality tracing and the optimization design for composite foundation processing provide Decision support.
As shown in figure 4, a kind of positioning and guiding method for pile foundation construction, uses the above-mentioned intelligence for pile foundation construction Locating guide device, method are as follows:
S1: arranging operation platform, excavates guiding installation pit, intelligent positioning guiding device is installed to the installation pit, It is backfilled using the soil body and fixes the outer layer casing;
Before intelligent positioning guiding device is installed to the installation pit, intelligent positioning guiding dress is obtained by positioning mechanism Set the precise mounting position information of installation extremely;
S2: note mud off operation, progress pile body construction operation or bored concrete pile bore operation, steel reinforcement cage are carried out and is precisely installed Operation;
S3: when operation, the position data of the synchronous detection internal layer casing of positioning mechanism, and will test data and be processed into control The control instruction of positioning mechanism processed, position adjusting mechanism adjust position of the internal layer casing relative to outer layer casing according to control instruction It sets, guarantees that the verticality of internal layer casing and levelness meet construction requirement, until operation is completed;
After i.e. position adjusting mechanism adjusts the positional relationship of internal layer casing according to control instruction, in positioning mechanism detects again The location information of layer casing, until internal layer casing meets preset construction requirement;
The adjustable steel pile casting position data of internal layer is namely acquired by GPS laser locator in real time, and to the position data It analyzed, handled, Dynamic Display, and internal layer adjustable steel casing position adjustment is guided, is managed and early warning;Position After data are handled, are converted, then by eight intelligent hydraulic pushers to internal layer adjustable steel casing plane and vertical position progress Primary positioning is adjusted, and then GPS laser locator acquires data again, carries out above-mentioned adjusting, until the adjustable steel pile casting tune of internal layer Positioning in the whole accurate positionin and steel reinforcement cage hole being oriented to predeterminated position, realization pile foundation improves filling pile construction into brill precision And reinforcing bar cage hoisting transfers vertical precision;
Then mud off to be infused, and pile body construction operation is monitored, pile body construction operation drills to pile body, Internal layer is adjustable, and steel pile casting synchronizes detection pile body location information, completes until pile body drills;Steel reinforcement cage, internal layer are installed after the completion of drilling Adjustable steel pile casting carries out guiding confirmation to reinforcing bar cage location, i.e., irradiates laser net by GPS laser locator and realize steel reinforcement cage peace The accurate guiding of dress controls plan-position and the verticality of pile body and steel reinforcement cage, realizes the control of stake point position real-time oversight, pile body Verticality accurately controls, and manipulator is guided accurately to construct, and guarantees construction quality, improves the efficiency of management.
As shown in figure 5, a kind of pile foundation job engineering management method, is led using the above-mentioned intelligent positioning for pile foundation construction To device, management method is as follows:
S101: obtaining in work progress, and the position data for the detection synchronous with construction that positioning mechanism obtains is uploaded to cloud Client database;
I.e. GPS laser locator obtain the adjustable steel pile casting of internal layer position data and acquisition carry out note mud off operation, Position data when pile body construction operation or the accurate installation exercise of bored concrete pile bore operation, steel reinforcement cage is carried out, and these are original Data are uploaded to wisdom construction management platform, and construction management, quality tracing and the optimization design for composite foundation processing provide certainly Plan support;
S102: position data is arranged, and is converted into pile foundation work data;
The position data that will acquire is classified, is arranged, and pile foundation work data is converted into, and is stored in wisdom construction pipe Platform;
S103: the positional relationship in work progress is obtained by pile foundation work data and is changed, and then to pile foundation job engineering It is managed.
I.e. when carrying out work progress, by the pile foundation work data stored in wisdom construction management platform, constructed Positional relationship variation in the process, the construction management for facilitating construction personnel to handle composite foundation, while being the matter of work progress Amount is traced to the source and optimization design is provided decision support.
The present invention is by pile foundation construction installing intelligent positioning guiding device, intelligent positioning guiding device application GPS Laser locator acquires the adjustable steel pile casting position data of internal layer in real time, and is analyzed the position data, handled, dynamic exhibition Show, internal layer adjustable steel casing position adjustment is guided, is managed and early warning;After the position data is handled, converted, pass Intelligent hydraulic pusher is transported to, intelligent hydraulic pusher is according to data after processing to internal layer adjustable steel casing plane and vertical position It carries out primary positioning to adjust, then GPS laser locator acquires data again, above-mentioned adjusting is carried out, until internal layer adjustable steel protects Cylinder is adjusted to predeterminated position, realizes the precise positioning to steel pile casting position, be conducive to it is subsequent drill and install to pile body steel reinforcement cage into The accurate guidance of row improves filling pile construction into brill precision and reinforcing bar cage hoisting and transfers vertical precision, effectively solves conventional bored concrete pile Pile body deflection caused by construction is not allowed because of the soft or hard uneven hole scattering pile body out of plumb of ground layer soil body and steel reinforcement cage lowered position, by The unequal security risk of power.
It above are only preferred embodiment of the invention, but the design concept of the present invention is not limited to this, all benefits It is made a non-material change to the present invention, should all be belonged to behavior that violates the scope of protection of the present invention with this design.

Claims (10)

1. a kind of intelligent positioning guiding device for pile foundation construction, it is characterised in that: including outer layer casing, internal layer casing, position Adjustment mechanism, positioning mechanism are set, the internal layer casing is sheathed in outer layer casing and stays between internal layer casing set and outer layer casing There is adjustment gap, the position adjusting mechanism connect the opposite position for adjusting internal layer casing Yu outer layer casing with internal layer casing It sets, the positioning mechanism is used to obtain the position data of internal layer casing, and controls position adjustment by position data The adjustment of mechanism acts.
2. the intelligent positioning guiding device according to claim 1 for pile foundation construction, it is characterised in that: the localization machine Structure include it is multiple, multiple positioning mechanisms are uniformly arranged in internal layer casing top.
3. the intelligent positioning guiding device according to claim 2 for pile foundation construction, it is characterised in that: the localization machine Structure is GPS laser locator, and the GPS laser locator obtains the geographic location data message of the internal layer casing, adopts in real time Collect the station-keeping data between internal layer casing and outer layer casing.
4. the intelligent positioning guiding device according to claim 2 for pile foundation construction, it is characterised in that: the position tune Complete machine structure includes multiple groups, and every group of position adjusting mechanism is connect with a positioning mechanism signal respectively.
5. the intelligent positioning guiding device according to claim 4 for pile foundation construction, it is characterised in that: every group of position Setting adjustment mechanism includes at least two pushers, and multiple pushers with group are arranged vertically on the side wall of outer layer casing, The pusher has the push rod extended into adjustment gap, and the push rod is fixedly connected with internal layer casing.
6. the intelligent positioning guiding device according to claim 1 for pile foundation construction, it is characterised in that: further include data Terminal, the positioning mechanism are docked with data terminal data, and the position data of the internal layer casing for will acquire is uploaded to data Terminal.
7. a kind of positioning and guiding method for pile foundation construction, it is characterised in that: be used for using claim 1-6 is any described The intelligent positioning guiding device of pile foundation construction, method are as follows:
Operation platform is arranged, guiding installation pit is excavated, intelligent positioning guiding device is installed to the installation pit, the soil body is utilized The outer layer casing is fixed in backfill;
It carries out note mud off operation, carry out pile body construction operation or the accurate installation exercise of bored concrete pile bore operation, steel reinforcement cage,
When operation, the position data of the synchronous detection internal layer casing of positioning mechanism, and will test data and be processed into control positioning The control instruction of mechanism, position adjusting mechanism adjust position of the internal layer casing relative to outer layer casing according to control instruction, guarantee The verticality and levelness of internal layer casing meet construction requirement, until operation is completed.
8. the positioning and guiding method according to claim 7 for pile foundation construction, it is characterised in that: described by intelligent positioning Before guiding device is installed to the installation pit, intelligent positioning guiding device is obtained by positioning mechanism, accurate installation extremely is installed Location information.
9. the positioning and guiding method according to claim 7 for pile foundation construction, it is characterised in that: the position adjusts machine After structure adjusts the positional relationship of internal layer casing according to control instruction, positioning mechanism detects the location information of internal layer casing again, until Internal layer casing meets preset construction requirement.
10. a kind of pile foundation job engineering management method, it is characterised in that: described be used for pile foundation using claim 1-6 is any The intelligent positioning guiding device of construction, method are as follows:
It obtains in work progress, the position data for the detection synchronous with construction that positioning mechanism obtains is uploaded to cloud database;
Position data is arranged, pile foundation work data is converted into;
The positional relationship variation in work progress is obtained by pile foundation work data, and then pile foundation job engineering is managed.
CN201910358497.7A 2019-04-30 2019-04-30 Intelligent positioning guide device and method for pile foundation construction and engineering management method Active CN110130347B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910358497.7A CN110130347B (en) 2019-04-30 2019-04-30 Intelligent positioning guide device and method for pile foundation construction and engineering management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910358497.7A CN110130347B (en) 2019-04-30 2019-04-30 Intelligent positioning guide device and method for pile foundation construction and engineering management method

Publications (2)

Publication Number Publication Date
CN110130347A true CN110130347A (en) 2019-08-16
CN110130347B CN110130347B (en) 2024-05-24

Family

ID=67575887

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910358497.7A Active CN110130347B (en) 2019-04-30 2019-04-30 Intelligent positioning guide device and method for pile foundation construction and engineering management method

Country Status (1)

Country Link
CN (1) CN110130347B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111962505A (en) * 2020-08-14 2020-11-20 北京建工集团有限责任公司 Double-pile-casing positioning structure of collimation pile, double-pile-casing device, collimation pile and construction method
CN112160709A (en) * 2020-01-04 2021-01-01 江西基业良工桩机制造有限公司 Protect a section of thick bamboo and sink auxiliary device and have this auxiliary device's rig
CN112160316A (en) * 2020-09-14 2021-01-01 浙江中正岩土技术有限公司 Construction method of immersed tube cast-in-place pile
CN113389202A (en) * 2021-07-01 2021-09-14 山东省鲁南地质工程勘察院(山东省地勘局第二地质大队) Device and method for preventing aligning deviation of pile foundation engineering reinforcement cage
CN113469840A (en) * 2021-06-16 2021-10-01 浙江华东建设工程有限公司 Intelligent management system for pile foundation construction
CN113863296A (en) * 2021-08-24 2021-12-31 中国水利水电第十四工程局有限公司 Separable recovery steel protects a section of thick bamboo and control system
CN114703862A (en) * 2022-03-30 2022-07-05 中交(南京)建设有限公司 Vertical and rapid positioning device for mounting latticed column and mounting and positioning method
CN114808973A (en) * 2022-04-25 2022-07-29 宣城市恪荣机电科技有限公司 Foundation pit construction method for improving centering property of reinforcement cage based on foundation pit cover piece
CN116772814A (en) * 2023-08-18 2023-09-19 贵州省公路工程集团有限公司 Steel reinforcement cage perpendicularity detection device and method with positioning and adjusting functions

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5935183A (en) * 1996-05-20 1999-08-10 Caterpillar Inc. Method and system for determining the relationship between a laser plane and an external coordinate system
CN204266193U (en) * 2014-12-01 2015-04-15 中铁七局集团第六工程有限公司 Pile foundation steel bar cage locator
CN205475204U (en) * 2016-02-23 2016-08-17 宏润建设集团股份有限公司 Locator for steel reinforcement cage is transferred to drilling bored concrete pile
CN206521749U (en) * 2017-02-23 2017-09-26 中铁十七局集团第三工程有限公司 Locator under steel reinforcement cage
CN107503353A (en) * 2017-10-10 2017-12-22 山东省路桥集团有限公司 Pile foundation steel bar cage off normal and inclination preventing mean and method
CN109095351A (en) * 2018-10-10 2018-12-28 中建隧道建设有限公司 A kind of recyclable steel reinforcement cage hanging steel bar hanging method
CN210341924U (en) * 2019-04-30 2020-04-17 福建路港(集团)有限公司 Intelligent positioning and guiding device for pile foundation construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5935183A (en) * 1996-05-20 1999-08-10 Caterpillar Inc. Method and system for determining the relationship between a laser plane and an external coordinate system
CN204266193U (en) * 2014-12-01 2015-04-15 中铁七局集团第六工程有限公司 Pile foundation steel bar cage locator
CN205475204U (en) * 2016-02-23 2016-08-17 宏润建设集团股份有限公司 Locator for steel reinforcement cage is transferred to drilling bored concrete pile
CN206521749U (en) * 2017-02-23 2017-09-26 中铁十七局集团第三工程有限公司 Locator under steel reinforcement cage
CN107503353A (en) * 2017-10-10 2017-12-22 山东省路桥集团有限公司 Pile foundation steel bar cage off normal and inclination preventing mean and method
CN109095351A (en) * 2018-10-10 2018-12-28 中建隧道建设有限公司 A kind of recyclable steel reinforcement cage hanging steel bar hanging method
CN210341924U (en) * 2019-04-30 2020-04-17 福建路港(集团)有限公司 Intelligent positioning and guiding device for pile foundation construction

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112160709A (en) * 2020-01-04 2021-01-01 江西基业良工桩机制造有限公司 Protect a section of thick bamboo and sink auxiliary device and have this auxiliary device's rig
CN111962505A (en) * 2020-08-14 2020-11-20 北京建工集团有限责任公司 Double-pile-casing positioning structure of collimation pile, double-pile-casing device, collimation pile and construction method
CN112160316A (en) * 2020-09-14 2021-01-01 浙江中正岩土技术有限公司 Construction method of immersed tube cast-in-place pile
CN113469840A (en) * 2021-06-16 2021-10-01 浙江华东建设工程有限公司 Intelligent management system for pile foundation construction
CN113389202A (en) * 2021-07-01 2021-09-14 山东省鲁南地质工程勘察院(山东省地勘局第二地质大队) Device and method for preventing aligning deviation of pile foundation engineering reinforcement cage
CN113389202B (en) * 2021-07-01 2022-07-05 山东省鲁南地质工程勘察院(山东省地勘局第二地质大队) Device and method for preventing aligning deviation of pile foundation engineering reinforcement cage
CN113863296A (en) * 2021-08-24 2021-12-31 中国水利水电第十四工程局有限公司 Separable recovery steel protects a section of thick bamboo and control system
CN114703862A (en) * 2022-03-30 2022-07-05 中交(南京)建设有限公司 Vertical and rapid positioning device for mounting latticed column and mounting and positioning method
CN114808973A (en) * 2022-04-25 2022-07-29 宣城市恪荣机电科技有限公司 Foundation pit construction method for improving centering property of reinforcement cage based on foundation pit cover piece
CN116772814A (en) * 2023-08-18 2023-09-19 贵州省公路工程集团有限公司 Steel reinforcement cage perpendicularity detection device and method with positioning and adjusting functions
CN116772814B (en) * 2023-08-18 2023-10-17 贵州省公路工程集团有限公司 Steel reinforcement cage perpendicularity detection device and method with positioning and adjusting functions

Also Published As

Publication number Publication date
CN110130347B (en) 2024-05-24

Similar Documents

Publication Publication Date Title
CN110130347A (en) Intelligent positioning guiding device, method, project management method for pile foundation construction
Kavvadas Monitoring ground deformation in tunnelling: Current practice in transportation tunnels
Fan et al. Tunnel deformation and stress response under the bilateral foundation pit construction: A case study
CN103195058B (en) Be convenient to solution cavity and grow the method that regional bridge pier adopts many casings to construct
Stephansson Rock stress in the Fennoscandian shield
CN102094429B (en) Lowering control method of double-wall steel cofferdam
CN103243747A (en) Deviation rectifying method of prestressed concrete pipe pile foundation
CN106949877A (en) The monitoring method of ground settlement above a kind of various dimensions shield tunnel
CN107130592A (en) A kind of long screw auger and impact drill two-shipper is combined pore-creating filling pile construction
Schwamb et al. Considerations for monitoring of deep circular excavations
Li et al. Soil movement mechanism associated with arching effect in a multi-strutted excavation in soft clay
CN105672314A (en) Method for constructing steel pipe upright pile through semi-reversed-construction method
CN110260039A (en) A kind of Vertical Curve pipe jacking construction method based on BIM technology
CN210341924U (en) Intelligent positioning and guiding device for pile foundation construction
Fearnhead et al. Deep excavations: monitoring mechanisms of ground displacement
CN113174942A (en) Precise positioning device for cage core bag anti-floating anchor rod of deep foundation pit and construction method
CN207278251U (en) Country rock excavates response test structure under different unloding speed
CN110006595A (en) Ultra-deep foundation pit support structure plane leakage detection method
CN105484300B (en) Method for measuring critical specific gravity of large-aperture drilling retaining wall reinforcing slurry
CN102071925B (en) Method for tracking, positioning, quantifying and rectifying coordinate of reversed pendulum hole
CN209243731U (en) Facet foundation pit is inverse to make rapid construction device
CN108252316B (en) Land steel sheet pile cofferdam sinking guiding system and auxiliary sinking method
Michelin et al. Holistic approach for the construction monitoring of the Grand Paris Express metro network
CN106764055B (en) Push pipe sight alignment construction
CN111749243B (en) Semi-automatic excavator digital earthwork site elevation control construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant