CN110108564A - High-ground stress goaf tunnel model test method is worn under one kind - Google Patents

High-ground stress goaf tunnel model test method is worn under one kind Download PDF

Info

Publication number
CN110108564A
CN110108564A CN201910477900.8A CN201910477900A CN110108564A CN 110108564 A CN110108564 A CN 110108564A CN 201910477900 A CN201910477900 A CN 201910477900A CN 110108564 A CN110108564 A CN 110108564A
Authority
CN
China
Prior art keywords
goaf
lining
model
country rock
model test
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910477900.8A
Other languages
Chinese (zh)
Inventor
黄锋
向晋扬
屈苗迪
万国庆
王毅
刘星辰
童小东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Jiaotong University
Original Assignee
Chongqing Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Jiaotong University filed Critical Chongqing Jiaotong University
Priority to CN201910477900.8A priority Critical patent/CN110108564A/en
Publication of CN110108564A publication Critical patent/CN110108564A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N3/00Investigating strength properties of solid materials by application of mechanical stress
    • G01N3/08Investigating strength properties of solid materials by application of mechanical stress by applying steady tensile or compressive forces
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N3/00Investigating strength properties of solid materials by application of mechanical stress
    • G01N3/24Investigating strength properties of solid materials by application of mechanical stress by applying steady shearing forces
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N2203/00Investigating strength properties of solid materials by application of mechanical stress
    • G01N2203/0058Kind of property studied
    • G01N2203/0069Fatigue, creep, strain-stress relations or elastic constants
    • G01N2203/0075Strain-stress relations or elastic constants
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N2203/00Investigating strength properties of solid materials by application of mechanical stress
    • G01N2203/02Details not specific for a particular testing method
    • G01N2203/025Geometry of the test
    • G01N2203/0256Triaxial, i.e. the forces being applied along three normal axes of the specimen

Landscapes

  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Biochemistry (AREA)
  • General Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Immunology (AREA)
  • Pathology (AREA)
  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Abstract

The invention belongs to the Tunnel Engineering technical field in ground and underground engineering, it is related to wearing high-ground stress goaf tunnel model test method under one kind.Goaf analog material is made according to a certain ratio using quartz sand, gypsum, blanc fixe, water in this method, has larger porosity and stronger discreteness, more actually simulates practical goaf;Tunnel model test case is formed by welded steel, and size is big, intensity is high, can bear higher stress;The assembling of lining cutting mold is simple, and when making lining model, plastic film and steel wire are pasted in lining cutting mold, is easy to take out molding lining model, and lining model rigidity is big;Using servo-pressing machine vertical and laterally accurately apply pressure to tunnel model test case, compared with real simulation high-ground stress, final test result can more embody truth.

Description

High-ground stress goaf tunnel model test method is worn under one kind
Technical field
The invention belongs to the Tunnel Engineering technical field in ground and underground engineering, it is related to wearing high-ground stress under one kind mined out Area's tunnel model test method.
Background technique
The theory analysis of tunnel mechanics can not reflect Practical Project situation completely, therefore lot of domestic and international scholar proposes Model investigation method can avoid the difficulty on mathematics and mechanics under conditions of substantially meeting the principle of similitude, true, complete Face, stress characteristic, deformation tendency and the stability feature for intuitively reflecting country rock during tunnel excavation, therefore tunnel model tries Test the important method for becoming research tunnel problem.Wherein, during tunnel model test, selection with prototype tunnel lining cutting, Prototype country rock material, the similar cast material of prototype gob material mechanical property are basis and the model examination of model test Test the key of success.Weak intercalated layer is the special mass for having larger danger coefficient to Practical Project, compared to other rocks Body, mined out region have the characteristics that larger porosity, stronger discreteness and surrounding rock stability are poor.Therefore, for accurate mould Draw up the goaf in rock mass structure, it is desirable to be able to meet the goaf cast material of similarity relation and the tunnel based on the material Model test method.
Summary of the invention
In view of this, the purpose of the present invention is to provide the model examinations for wearing goaf Analyses of Tunnel Wall Rock Stability research under one kind Proved recipe method, material therefor and leiomyoma cells have closely similar physics, mechanical property, can sufficiently simulate high-ground stress and under wear Goaf tunnel surrounding actual condition.
In order to achieve the above objectives, the invention provides the following technical scheme:
High-ground stress goaf tunnel model test method is worn under one kind, and country rock analog material, mined out analog material are filled out It is filled with tunnel model test case and carries out tunnel During Geotechnical Tests, which comprises the following steps: consolidate tunnel model test case Surely it is placed in ground and levels;Lining model is made, and arranges several for testing its pressure in lining model inner side and outer side The foil gauge of power and deformation;Country rock analog material is successively layered to filling tunnel model test case, every layer loads progress after the completion Compacting of vibrating is placed in lining model, continues to fill up when it is A that the country rock analog material, which is loaded with the first plane vertical range, Country rock analog material is in close contact country rock and lining model, and arranges several pressure cells, displacement meter on country rock, described First plane is the plane where tunnel model test bottom seat, when the country rock analog material is loaded to vertical with the first plane When distance is B, continue to insert the angle of side and first plane of the country rock analog material to country rock far from ground to be 15 ° to 30 ° Position, vibrate compacting after goaf analog material is continuously and uniformly filled along country rock, according to test requirements document arrange respective thickness Goaf, then arrange several pressure cells, displacement meter on the goaf, then along the direction far from first plane Continuously and uniformly placement in layers country rock analog material stops filling until reaching when the vertical range away from first plane is C, Wherein C > B > A, according to the size of experiment demand adjustment A, B, C;After the completion of the maintenance of country rock analog material, using being enclosed on sheet-steel cover Rock, and apply pressure with the direction that servo-pressing machine is parallel and perpendicular to the first plane to tunnel model test case, during which acquire And analyze pressure, displacement and the pressure of lining cutting, deformation of country rock.
Preferably, use is to lining cutting mold when making lining model, the lining cutting mold include internal model, external mold, fixed link, Die bottom plate and die cover plate assemble, and the through-hole to match with fixed link is provided in the internal model and external mold, described Steel plate is equipped on the outside of internal model and on the inside of external mold;The external mold includes the first external mold and the second external mold, and passes through external mold connector Carry out splicing fixation;Internal model and external mold are fixed on die bottom plate by fixed link, then will be outside first by external mold connector Mould and the splicing of the second external mold are fixed, and the preparation of lining cutting mold is completed.
Preferably, lining model production method specifically: on the outside of internal model and on the inside of external mold successively fixed plastics film and Steel mesh;Lining model material is poured slowly into the gap of internal model and external mold composition after mixing evenly, and is vibrated with vibrating head Lining model material;Vaseline is coated in lining cutting die cover plate, and is sealed lining cutting mold with the lining cutting cover board;In room temperature ring The molding lining model of a couple of days taking-up is stood in border.
Preferably, displacement meter is evenly arranged in the goaf close to and far from the endface of the lining model.
Preferably, pressure cell is arranged around lining cutting along parallel or/and direction perpendicular to the first plane.
Preferably, the pressure cell includes for the horizontal pressure force box of testing level directional pressure and for testing vertical side To the vertical pressure box of pressure, the horizontal pressure force box are arranged in pairs with vertical pressure box, to test the horizontal pressure of same position Power and vertical pressure.
Preferably, lining model material, country rock analog material and goaf analog material are brilliant by quartz sand, gypsum, weight Successively 1:1:1.8:2,1:1:5.5:0.6 and 1:1.5:2.5:0.8 are mixed in mass ratio for mountain flour, water.
Preferably, A be 600mm to 800mm, B be 640mm to 850mm, C be 2000mm to 2200mm, the thickness in goaf For 200mm to 250mm.
Preferably, fill country rock analog material when every layer with a thickness of 8cm to 15cm.
Preferably, the tunnel model test case is formed using welded steel.
The beneficial effects of the present invention are: tunnel model test case is formed by welded steel, and size is big, intensity is high, can be with Bear higher stress;The assembling of lining cutting mold is simple, and when making lining model, plastic film and steel wire are pasted in lining cutting mold Net is easy to take out molding lining model, and lining model rigidity is big;Goaf analog material is by quartz sand, gypsum, barite Powder, water 1:1.5:2.5:0.8 in mass ratio are mixed, and larger porosity and stronger discreteness, physical and mechanical properties are steady It is fixed, more actually simulate practical goaf;Using servo-pressing machine vertical and laterally accurately applied to tunnel model test case Plus-pressure, compared with real simulation tunnel high-ground stress, final test result can more embody truth.
Other advantages, target and feature of the invention will be illustrated in the following description to a certain extent, and And to a certain extent, based on will be apparent to those skilled in the art to investigating hereafter, Huo Zheke To be instructed from the practice of the present invention.Target of the invention and other advantages can be realized by following specification and It obtains.
Detailed description of the invention
To make the objectives, technical solutions, and advantages of the present invention clearer, the present invention is made below in conjunction with attached drawing excellent The detailed description of choosing, in which:
Fig. 1 is tunnel model test case main view in the present invention;
Fig. 2 is tunnel model test case left view in the present invention;
Fig. 3 is lining cutting mold assembly structure diagram in the present invention;
Fig. 4 is goaf paving location schematic diagram in the present invention;
Fig. 5 is displacement meter layout drawing in the present invention;
Fig. 6 is pressure cell layout drawing in the present invention.
Specific embodiment
Illustrate embodiments of the present invention below by way of specific specific example, those skilled in the art can be by this specification Other advantages and efficacy of the present invention can be easily understood for disclosed content.The present invention can also pass through in addition different specific realities The mode of applying is embodied or practiced, the various details in this specification can also based on different viewpoints and application, without departing from Various modifications or alterations are carried out under spirit of the invention.It should be noted that diagram provided in following embodiment is only to show Meaning mode illustrates basic conception of the invention, and in the absence of conflict, the feature in following embodiment and embodiment can phase Mutually combination.
Wherein, the drawings are for illustrative purposes only and are merely schematic diagrams, rather than pictorial diagram, should not be understood as to this The limitation of invention;Embodiment in order to better illustrate the present invention, the certain components of attached drawing have omission, zoom in or out, not Represent the size of actual product;It will be understood by those skilled in the art that certain known features and its explanation may be omitted and be in attached drawing It is understood that.
The same or similar label correspond to the same or similar components in the attached drawing of the embodiment of the present invention;It is retouched in of the invention In stating, it is to be understood that if there is the orientation or positional relationship of the instructions such as term " on ", "lower", "left", "right", "front", "rear" To be based on the orientation or positional relationship shown in the drawings, be merely for convenience of description of the present invention and simplification of the description, rather than indicate or It implies that signified device or element must have a particular orientation, be constructed and operated in a specific orientation, therefore is described in attached drawing The term of positional relationship only for illustration, is not considered as limiting the invention, for the ordinary skill of this field For personnel, the concrete meaning of above-mentioned term can be understood as the case may be.
Please refer to Fig. 1-Fig. 6, the element numbers in attached drawing respectively indicate: tunnel model test case 1, chamber pedestal 11, Grid frame 12, side pressure load plate 13, front shroud 14, country rock 2, lining model 3, internal model 31, the first external mold 32, the second external mold 33, external mold connector 34, fixed link 35, die bottom plate 36, goaf 4, displacement meter 5, horizontal pressure force box 61, vertical pressure box 62。
The present invention, which provides, wears high-ground stress goaf tunnel model test method under one kind, by country rock analog material, mined out Analog material is packed into tunnel model test case 1 and carries out corresponding tunnel During Geotechnical Tests.
In the present embodiment, tunnel model test case 1 is welded by the chamber pedestal 11 of steel, grid frame 12, front shroud 14 It connects and assembles, rectangular parallelepiped structure, both sides are additionally provided with the side pressure load plate 13 for loading level pressure.The tunnel mould Length × height × width of type chamber 1 is 2.5m × 2.5m × 1.25m, and the size likelihood ratio is 1:30.
In the present embodiment, lining cutting mold includes internal model 31, external mold, fixed link 35, die bottom plate 36 and die cover plate assembling It forms, the through-hole to match with fixed link 35 is provided in the internal model 31 and external mold, the external mold includes 32 He of the first external mold Second external mold 33, first external mold 32 and the second external mold 33 carry out splicing fixation by external mold connector 34.To increase mold Rigidity, the steel plate of 1.5mm thickness is equipped on the inside of the outside of internal model 31 and external mold.Internal model 31 and external mold are passed through admittedly when use Fixed pole 35 is fixed on die bottom plate 36, then is fixed the first external mold 32 and the splicing of the second external mold 33 by external mold connector 34, Complete the preparation of lining cutting mold.
It is as follows that the step of tunnel ground is tested is carried out using above-mentioned tunnel model test case 1 and lining cutting mold:
(1) tunnel model test case 1 is fixedly placed in ground, and leveled.
(2) lining model 3 will be made using lining cutting mold, and arranges several in 3 inner side and outer side of lining model For testing the foil gauge of its pressure and deformation.
(3) country rock analog material is successively layered to filling tunnel model test case 1, carries out pressure of vibrating after the completion of every layer of filling Real, every layer with a thickness of 10cm;When it is A that the country rock analog material, which is loaded with the first plane vertical range, it is placed in step (2) institute The lining model 3 stated, continues to fill up country rock analog material, is in close contact country rock 2 and lining model 3, and arrange on country rock 2 Several pressure cells, displacement meter 5, first plane are the plane where chamber pedestal 11;When the country rock analog material When filling is extremely B with the first plane vertical range, continue the folder for inserting country rock analog material to country rock 2 upper surface and the first plane The position that angle is 15 ° to 30 °;It vibrates and continuously and uniformly fills goaf analog material along country rock 2 after being compacted, according to test requirements document The goaf 4 for arranging respective thickness, then arranges several pressure cells, displacement meter 5 on the goaf;Finally again along separate The direction layering filling country rock analog material of first plane, until reaching the vertical range away from first plane is C, it is complete At filling for entire country rock 2;Wherein C > B > A, according to the size of experiment demand adjustment A, B, C.
(4) after the country rock 2 in the step (3) conserves 40 days, 2 top of country rock covers the steel plate of 1.5cm thickness, with servo pressure Power machine to tunnel model test case 1 apply straight down, horizontal size to the left, horizontally to the right be 1Mpa pressure;It is described to answer Become piece, displacement meter 5 and pressure cell to be electrical connected with signal pickup assembly, the signal pickup assembly is for collecting displacement and power Signal, apply press process in acquired by signal acquiring system and analyze country rock 2 pressure, displacement and the pressure of lining cutting, Deformation.
It is wherein specific:
3 production method of lining model described in step (2) specifically: firstly, on the inside of 31 outside of internal model and external mold successively Fixed plastics film and steel mesh, and assemble lining cutting mold;Then, lining model material is poured slowly into after mixing evenly interior It in the gap of mould 31 and external mold composition, and is vibrated lining model material with vibrating head, to prevent generating bubble;Then, in lining cutting mould Vaseline is coated on the inside of tool upper cover plate, and is sealed lining cutting mold with the lining cutting cover board;Finally, in 25 ° of room temperature of environment It stands three days and takes out molding lining model 3.
In step (3) A be 700mm, B 734.25mm, C 2200mm, goaf 4 and the inclination angle of first plane are 20 °, goaf 4 with a thickness of 220mm.In other words, the detailed laying step in goaf 4 are as follows: firstly, country rock analog material is filled out When entering to 700mm height, prefabricated lining model 3 is put into tunnel model test case 1, and continues to insert the similar material of country rock Pause is filled when material to 734.25mm height;Then, remain unchanged 2 height of country rock of the leftmost side for the time being, with 20 ° of inclination angles of level Country rock analog material is inserted from left to right, angle is controlled with protractor in the process, when the country rock 2 of the rightmost side is filled to Whether pause is filled when 1644.17mm height, and be in substantially 20 ° of inclination angle with the first plane with protractor detection inclined-plane;Then, It is kept for 20 ° of level inclination and continuously and uniformly fills goaf analog material, make leftmost side reclamation level up to 968.37mm, the rightmost side Whether pause is filled when elevation reaches 1878.30mm, substantially inclined again with the first plane in 20 ° with protractor detection inclined-plane Angle;Finally, successively continuously filling country rock analog material from the bottom up, layering paves landfill from lower to upper, every layer thick for 10cm, Compacting of vibrating is carried out after every one layer of casting, completion is filled when final left and right paving is to design altitude 2200mm.
Displacement meter 5 is evenly arranged in the goaf 4 close to and far from the end of the lining model 3 in the step (3) At face, the both ends in the goaf 4 are respectively arranged with 8 displacement meters 5.
Pressure cell in the step (3) is arranged around lining cutting along parallel or/and direction perpendicular to the first plane.Institute Stating pressure cell includes the vertical pressure for the horizontal pressure force box 61 of testing level directional pressure and for testing vertical direction pressure Power box 62, the horizontal pressure force box 61 are arranged in pairs with vertical pressure box 62, to test the horizontal pressure force of same position and to erect Vertical compression power.When specific setting, guarantee that pressure cell is spread over around the 3 of lining model, and take inside area 4, about 4 goaf 2 region of country rock is arranged with pressure cell.
The present embodiment is according to existing investigative technique, the 3 material selection quartz sand of lining model, gypsum, blanc fixe, water For raw material, by direct shear test and GDS triaxial compression test, the proportion for obtaining the lining cutting analog material of simulation lining cutting is 1: 1:1.8:2;Country rock analog material and goaf analog material are also mixed by quartz sand, gypsum, blanc fixe, water, according to Secondary mass ratio is 1:1:5.5:0.6 and 1:1.5:2.5:0.8.
Goaf analog material is made according to a certain ratio using quartz sand, gypsum, blanc fixe, water in the present invention, is had Larger porosity and stronger discreteness, physical and mechanical properties are stablized, and practical goaf 4 is more actually simulated;Tunnel model Chamber 1 is formed by welded steel, and size is big, intensity is high, can bear higher stress;The assembling of lining cutting mold is simple, production When lining model 3, plastic film and steel wire are pasted in lining cutting mold, are easy to take out molding lining model 3, and lining cutting mould 3 rigidity of type is big;Using servo-pressing machine vertical and laterally accurately apply pressure, truer mould to tunnel model test case 1 Quasi- tunnel high-ground stress, final test result can more embody truth.
Finally, it is stated that the above examples are only used to illustrate the technical scheme of the present invention and are not limiting, although referring to compared with Good embodiment describes the invention in detail, those skilled in the art should understand that, it can be to skill of the invention Art scheme is modified or replaced equivalently, and without departing from the objective and range of the technical program, should all be covered in the present invention Scope of the claims in.

Claims (10)

1. wearing high-ground stress goaf tunnel model test method under one kind, country rock analog material, mined out analog material are filled Enter tunnel model test case and carry out tunnel During Geotechnical Tests, which comprises the following steps:
Tunnel model test case is fixedly placed in ground and is leveled;
Lining model is made, and arranges several for testing the strain of its pressure and deformation in lining model inner side and outer side Piece;
Country rock analog material is successively layered to filling tunnel model test case, carries out compacting of vibrating after the completion of every layer of filling;Work as institute State country rock analog material load with the first plane vertical range be A when, be placed in lining model, continue to fill up country rock analog material, It is in close contact country rock and lining model, and arranges several pressure cells, displacement meter on country rock, first plane is tunnel Plane where model test box pedestal;When the country rock analog material load to the first plane vertical range be B when, continue Insert the position that the angle of side and first plane of the country rock analog material to country rock far from ground is 15 ° to 30 °;It vibrates compacting Goaf analog material is continuously and uniformly filled along country rock afterwards, the goaf of respective thickness is arranged according to test requirements document, is then existed Several pressure cells, displacement meter are arranged on the goaf;It is continuously and uniformly layered along the direction far from first plane again Country rock analog material is filled, stops filling when the vertical range away from first plane is C until reaching;Wherein C > B > A, according to The size of the adjustment of experiment demand A, B, C;
After the completion of the maintenance of country rock analog material, using country rock on sheet-steel cover, and it is flat to tunnel model test case with servo-pressing machine It goes and applies pressure perpendicular to the direction of the first plane, during which acquire and analyze pressure, displacement and the pressure of lining cutting, shape of country rock Become.
2. wearing high-ground stress goaf tunnel model test method under as described in claim 1, which is characterized in that production lining Build model when use to lining cutting mold, the lining cutting mold include internal model, external mold, fixed link, die bottom plate and die cover plate Assemble, the through-hole to match with fixed link is provided in the internal model and external mold, the internal model outside and external mold inside are Equipped with steel plate;The external mold includes the first external mold and the second external mold, and carries out splicing fixation by external mold connector;By internal model and External mold is fixed on die bottom plate by fixed link, then is fixed the first external mold and the splicing of the second external mold by external mold connector, Complete the preparation of lining cutting mold.
3. wearing high-ground stress goaf tunnel model test method under as described in claim 2, which is characterized in that lining cutting mould Type production method specifically: successively fixed plastics film and steel mesh on the outside of internal model and on the inside of external mold;By lining model material It is poured slowly into the gap of internal model and external mold composition after mixing evenly, and vibrated lining model material with vibrating head;In lining cutting mould Tool cover board coats vaseline, and is sealed lining cutting mold with the lining cutting cover board;A couple of days taking-up molding is stood in room temperature environment Lining model.
4. wearing high-ground stress goaf tunnel model test method under as described in claim 1, which is characterized in that displacement meter The goaf is evenly arranged in close to and far from the endface of the lining model.
5. wearing high-ground stress goaf tunnel model test method under as described in claim 1, which is characterized in that pressure cell It is arranged around lining cutting along parallel or/and direction perpendicular to the first plane.
6. wearing high-ground stress goaf tunnel model test method under as described in claim 5, which is characterized in that the pressure Power box includes the vertical pressure box for the horizontal pressure force box of testing level directional pressure and for testing vertical direction pressure, institute It states horizontal pressure force box to be arranged in pairs with vertical pressure box, to test the horizontal pressure force and vertical pressure of same position.
7. wearing high-ground stress goaf tunnel model test method under as described in claim 1, which is characterized in that lining cutting mould Profile material, country rock analog material and goaf analog material are by quartz sand, gypsum, blanc fixe, water successively in mass ratio 1: 1:1.8:2,1:1:5.5:0.6 and 1:1.5:2.5:0.8 mix.
8. wearing high-ground stress goaf tunnel model test method under as described in claim 1, which is characterized in that A is 600mm to 800mm, B be 640mm to 850mm, C be 2000mm to 2200mm, goaf with a thickness of 200mm to 250mm.
9. wearing high-ground stress goaf tunnel model test method under as described in claim 1, which is characterized in that filling is enclosed When rock analog material every layer with a thickness of 8cm to 15cm.
10. wearing high-ground stress goaf tunnel model test method, feature under as described in any one of claim 1 to 9 It is, the tunnel model test case is formed using welded steel.
CN201910477900.8A 2019-06-03 2019-06-03 High-ground stress goaf tunnel model test method is worn under one kind Pending CN110108564A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910477900.8A CN110108564A (en) 2019-06-03 2019-06-03 High-ground stress goaf tunnel model test method is worn under one kind

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910477900.8A CN110108564A (en) 2019-06-03 2019-06-03 High-ground stress goaf tunnel model test method is worn under one kind

Publications (1)

Publication Number Publication Date
CN110108564A true CN110108564A (en) 2019-08-09

Family

ID=67493612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910477900.8A Pending CN110108564A (en) 2019-06-03 2019-06-03 High-ground stress goaf tunnel model test method is worn under one kind

Country Status (1)

Country Link
CN (1) CN110108564A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111175150A (en) * 2020-02-22 2020-05-19 中铁十九局集团轨道交通工程有限公司 Test method for measuring compression shearing performance of filling material behind tunnel lining wall
CN113155336A (en) * 2021-03-11 2021-07-23 中铁二十局集团第三工程有限公司 Anchor cable dynamometer mounting device

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102004054A (en) * 2010-09-21 2011-04-06 同济大学 Three-way loading mechanical property test system of multifunctional lining segment joint
CN103604698A (en) * 2013-12-02 2014-02-26 淮北矿业(集团)有限责任公司 Compaction simulation experimental method for secondary deformation of fractured rock mass in caving zone of old goaf of coal mine
CN105459253A (en) * 2015-12-25 2016-04-06 福州市规划设计研究院 Large-volume lining model pouring device for tunnel model test and method of large-volume lining model pouring device
CN106198208A (en) * 2016-06-21 2016-12-07 中电建路桥集团有限公司 A kind of interbedding of soft and hard rocks surrounding rock tunnel method for analog construction considering layer reason effect
CN106568606A (en) * 2016-10-25 2017-04-19 招商局重庆交通科研设计院有限公司 Tunnel stress experiment method for goaf crossing simulation
CN107060829A (en) * 2017-05-24 2017-08-18 福州大学 Precast lining structure for tunnel model test and preparation method thereof
CN108776065A (en) * 2018-04-19 2018-11-09 河南理工大学 A kind of dynamic load prediction technique adopted induction goaf and laterally resist unstability generation stubbornly
CN108827684A (en) * 2018-07-20 2018-11-16 重庆交通大学 A kind of tunnel model test method using vaseline and film production weak intercalated layer
CN108917694A (en) * 2018-07-16 2018-11-30 三峡大学 Deformation monitoring and the device and method of supporting after a kind of tunnel Rock And Soil excavates
CN109443930A (en) * 2018-11-30 2019-03-08 西南交通大学 A kind of shield tunnel segment lining structure longitudinal rigidity test device and method

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102004054A (en) * 2010-09-21 2011-04-06 同济大学 Three-way loading mechanical property test system of multifunctional lining segment joint
CN103604698A (en) * 2013-12-02 2014-02-26 淮北矿业(集团)有限责任公司 Compaction simulation experimental method for secondary deformation of fractured rock mass in caving zone of old goaf of coal mine
CN105459253A (en) * 2015-12-25 2016-04-06 福州市规划设计研究院 Large-volume lining model pouring device for tunnel model test and method of large-volume lining model pouring device
CN106198208A (en) * 2016-06-21 2016-12-07 中电建路桥集团有限公司 A kind of interbedding of soft and hard rocks surrounding rock tunnel method for analog construction considering layer reason effect
CN106568606A (en) * 2016-10-25 2017-04-19 招商局重庆交通科研设计院有限公司 Tunnel stress experiment method for goaf crossing simulation
CN107060829A (en) * 2017-05-24 2017-08-18 福州大学 Precast lining structure for tunnel model test and preparation method thereof
CN108776065A (en) * 2018-04-19 2018-11-09 河南理工大学 A kind of dynamic load prediction technique adopted induction goaf and laterally resist unstability generation stubbornly
CN108917694A (en) * 2018-07-16 2018-11-30 三峡大学 Deformation monitoring and the device and method of supporting after a kind of tunnel Rock And Soil excavates
CN108827684A (en) * 2018-07-20 2018-11-16 重庆交通大学 A kind of tunnel model test method using vaseline and film production weak intercalated layer
CN109443930A (en) * 2018-11-30 2019-03-08 西南交通大学 A kind of shield tunnel segment lining structure longitudinal rigidity test device and method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张玉东: "隧道下伏采空区移动盆地综合探测和评价技术应用", 《能源与保护》 *
王瑞鹏: "基于改进熵_云模型的隧道采空区稳定性评价", 《现代矿业》 *
邹广平: "《能源大辞典》", 31 July 1997 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111175150A (en) * 2020-02-22 2020-05-19 中铁十九局集团轨道交通工程有限公司 Test method for measuring compression shearing performance of filling material behind tunnel lining wall
CN113155336A (en) * 2021-03-11 2021-07-23 中铁二十局集团第三工程有限公司 Anchor cable dynamometer mounting device
CN113155336B (en) * 2021-03-11 2023-03-21 中铁二十局集团第三工程有限公司 Anchor cable dynamometer mounting device

Similar Documents

Publication Publication Date Title
CN110954676B (en) Visual test device for simulating shield tunneling existing tunnel construction
CN107228791A (en) A kind of friction pile reinforcing side slope visible model testing device and test method
CN107505196B (en) It is a kind of can flexible operating three-dimensional soil arching effect development test device and operating method
CN104713987B (en) Model test apparatus for stimulating tunnel excavation process
CN101308126B (en) Offshore mining top board seepage flow sudden inflow test method and device
CN108088982B (en) Simulate the Experimental Method in Laboratory of fine grained seepage inflow erosion inside deep aquifers sand
CN108362864A (en) A kind of multifunction combined tunnel excavation similar model test device
CN103983742B (en) Coal seam overlying strata are disrumpent feelings coal and rock gas migration and extraction experimental system
CN108872530A (en) A kind of full-scale model test device for simulating asymmetric small-clear-distance tunnel digging process
CN107621524B (en) Transparent soil model test device and test method for simulating tunnel excavation deformation
CN106644336B (en) A kind of frame structure crosses over ground fissure experimental system and method
CN104792966B (en) A kind of testing apparatus and method simulating subway shield tunnel construction initiation cavity, stratum
CN106124268B (en) A method of experiment test block is made with similarity simulation experiment test block prepressing device
CN110108564A (en) High-ground stress goaf tunnel model test method is worn under one kind
CN106546483B (en) Two-dimentional mechanical models for soil and rock experimental rig and method
CN211602719U (en) Stope mine pressure three-dimensional physical simulation test platform of multi-functional top bottom plate gushing water
CN208685680U (en) A kind of geosynthetic reinforced pile supported embankments on soft soil model test apparatus
CN111380760A (en) Tunnel blasting excavation model test system and method
CN108507878A (en) A kind of soil pressure simulating test device and method
CN108535451A (en) It a kind of box culvert-type subway station and closes on surface infrastructure and crosses over ground fissure experimental system and method
CN103898929B (en) Prestressed concrete pipe pile horizontal bearing attribute testing model and data test method
Johannesson et al. Prototype repository: A full scale experiment at Äspö HRL
CN209703582U (en) A kind of high slope and anchorage excavation of foundation pit influence each other the model assay systems of mechanism
CN206095660U (en) Indoor testing system of quiet dynamic response characteristic of multi -functional reduced scale tunnel structure
CN208398855U (en) Shield tunnel construction stress deformation indoor model test device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190809