CN109979073B CN201711444435.5A CN201711444435A CN109979073B CN 109979073 B CN109979073 B CN 109979073B CN 201711444435 A CN201711444435 A CN 201711444435A CN 109979073 B CN109979073 B CN 109979073B
Authority
CN
China
Prior art keywords
gate
working state
controller
channel controller
corresponding relation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711444435.5A
Other languages
Chinese (zh)
Other versions
CN109979073A (en
Inventor
李林
申川
康卫昌
杨文伟
郭伟峰
陈蔚
刘梦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Hikvision Digital Technology Co Ltd
Original Assignee
Hangzhou Hikvision Digital Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Hikvision Digital Technology Co Ltd filed Critical Hangzhou Hikvision Digital Technology Co Ltd
Priority to CN201711444435.5A priority Critical patent/CN109979073B/en
Priority to PCT/CN2018/100446 priority patent/WO2019128255A1/en
Publication of CN109979073A publication Critical patent/CN109979073A/en
Application granted granted Critical
Publication of CN109979073B publication Critical patent/CN109979073B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G07CHECKING-DEVICES
    • G07CTIME OR ATTENDANCE REGISTERS; REGISTERING OR INDICATING THE WORKING OF MACHINES; GENERATING RANDOM NUMBERS; VOTING OR LOTTERY APPARATUS; ARRANGEMENTS, SYSTEMS OR APPARATUS FOR CHECKING NOT PROVIDED FOR ELSEWHERE
    • G07C1/00Registering, indicating or recording the time of events or elapsed time, e.g. time-recorders for work people
    • GPHYSICS
    • G07CHECKING-DEVICES
    • G07CTIME OR ATTENDANCE REGISTERS; REGISTERING OR INDICATING THE WORKING OF MACHINES; GENERATING RANDOM NUMBERS; VOTING OR LOTTERY APPARATUS; ARRANGEMENTS, SYSTEMS OR APPARATUS FOR CHECKING NOT PROVIDED FOR ELSEWHERE
    • G07C9/00Individual registration on entry or exit
    • GPHYSICS
    • G07CHECKING-DEVICES
    • G07CTIME OR ATTENDANCE REGISTERS; REGISTERING OR INDICATING THE WORKING OF MACHINES; GENERATING RANDOM NUMBERS; VOTING OR LOTTERY APPARATUS; ARRANGEMENTS, SYSTEMS OR APPARATUS FOR CHECKING NOT PROVIDED FOR ELSEWHERE
    • G07C9/00Individual registration on entry or exit
    • G07C9/10Movable barriers with registering means
    • GPHYSICS
    • G07CHECKING-DEVICES
    • G07CTIME OR ATTENDANCE REGISTERS; REGISTERING OR INDICATING THE WORKING OF MACHINES; GENERATING RANDOM NUMBERS; VOTING OR LOTTERY APPARATUS; ARRANGEMENTS, SYSTEMS OR APPARATUS FOR CHECKING NOT PROVIDED FOR ELSEWHERE
    • G07C2209/00Indexing scheme relating to groups G07C9/00 - G07C9/38
    • G07C2209/04Access control involving a hierarchy in access rights

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Time Recorders, Dirve Recorders, Access Control (AREA)
  • Lock And Its Accessories (AREA)
  • Traffic Control Systems (AREA)

Abstract

The application provides a pedestrian passageway gate control method and device and a pedestrian passageway gate. The method comprises the following steps: acquiring gate plan information; recording a first corresponding relation between the working state of the gate and the working time of the working state in the gate plan information; reading the first corresponding relation from the gate plan information, and monitoring the system time in real time; and indicating a channel controller in the pedestrian channel gate to set the working state of the gate based on the read first corresponding relation and the monitored system time. Therefore, the problem that the labor cost is high when the working state of the gate is changed frequently can be solved through the scheme.

Description

Pedestrian passageway gate control method and device and pedestrian passageway gate
Technical Field
The application relates to the field of intelligent security inspection, in particular to a pedestrian passageway gate control method and device and a pedestrian passageway gate.
Background
The man-way gate is a device which integrates mechanical, electronic and microprocessor control and various read-write technologies, and is mainly used in places where people need to be controlled to enter and exit or tickets need to be checked to enter and exit. Wherein, the control part of the pedestrian passageway gate usually comprises: an authority controller and a channel controller. Specifically, the authority controller is used for judging the user authority, and when the user authority is judged to be passed, a control instruction (such as a brake opening instruction or a brake closing instruction) is sent to the channel controller; and the channel controller is used for receiving the control instruction issued by the authority controller and controlling the motor system to operate so as to control the action of the gate. In addition, in order to meet different scene requirements, the gate of the pedestrian passageway gate has a plurality of working states, such as: a no-pass state to prohibit passage, a controlled state to check authority to pass, and a free state to unrestricted passage.
In the prior art, the working state of the gate is set in a manual dial mode, which is as follows: the staff opens the shell of people's bank of china's road floodgate, stirs corresponding button in the cavity is inside to send corresponding dial indicator to the channel control ware, it is corresponding, channel control ware responds to this dial indicator, sets up the gate into the operating condition who corresponds with this dial indicator.
Although artifical dial mode can effectively set up the operating condition of gate among the prior art, however, to the condition that the operating condition of gate often changed, because the setting of operating condition all is manual setting at every turn, make the human cost higher undoubtedly, especially big batch manway floodgate need set up simultaneously, for example: and a large amount of pedestrian passage gates are required to be arranged at the same time in the morning and evening.
Disclosure of Invention
In view of this, the present application provides a pedestrian passageway gate control method, a pedestrian passageway gate control device, and a pedestrian passageway gate, so as to solve the problem of high labor cost when the working state of the gate is frequently changed.
Specifically, the method is realized through the following technical scheme:
in a first aspect, the application provides a pedestrian passageway gate control method, which is applied to an authority controller in a pedestrian passageway gate; the method comprises the following steps:
acquiring gate plan information; wherein, the gate plan information records a first corresponding relation between the working state of the gate and the working time of the working state;
reading the first corresponding relation from the gate plan information, and monitoring the system time in real time;
and indicating a channel controller in the man-way channel gate to set the working state of the gate based on the read first corresponding relation and the monitored system time.
Optionally, before the step of obtaining the gate plan information, the method further includes:
detecting priority configuration information aiming at a gate, wherein the priority configuration information is configured with the priority of the channel controller and the priority of the authority controller;
and when the priority of the authority controller in the priority configuration information is higher than the priority of the channel controller, executing the step of obtaining gate plan information.
Optionally, the step of instructing a channel controller in the pedestrian channel gate to set an operating state of the gate based on the read first corresponding relationship and the monitored system time includes:
when the monitored system time is the starting time point corresponding to a working time in the first corresponding relation, determining a target working state corresponding to the working time in the first corresponding relation;
determining a target dial instruction corresponding to the target working state based on a second corresponding relation which is stored in advance and relates to the working state and the dial instruction;
and issuing the target dial-up instruction to a channel controller in the man-way channel gate, so that the channel controller sets the working state of the gate to be the target working state after receiving the target dial-up instruction.
Optionally, after the step of issuing the target dial-up instruction to the channel controller in the pedestrian channel barrier, the method further includes:
and when the monitored system time is the end time point corresponding to the working time, issuing a state recovery instruction to the channel controller so that the channel controller restores the working state of the gate to the latest working state before the target working state.
Optionally, the method further comprises:
when the electrification is finished, sending a data request for requesting the second corresponding relation to the channel controller, so that the channel controller feeds back the second corresponding relation to the authority controller after receiving the data request;
and receiving and storing the second corresponding relation fed back by the channel controller.
In a second aspect, the present application provides a pedestrian passageway gate control apparatus, which is applied to an authority controller in a pedestrian passageway gate; the device comprises:
an information obtaining unit for obtaining gate plan information; wherein, the gate plan information records a first corresponding relation between the working state of the gate and the working time of the working state;
a correspondence reading unit configured to read the first correspondence from the gate plan information;
the time monitoring unit is used for monitoring the system time in real time;
and the working state control unit is used for indicating a channel controller in the pedestrian channel gate to set the working state of the gate based on the read first corresponding relation and the monitored system time.
Optionally, the apparatus further comprises:
a configuration information detection unit, configured to detect priority configuration information for a gate before the information obtaining unit obtains gate plan information, where the priority configuration information is configured with priorities of the channel controller and the permission controller;
and the detection result processing unit is used for triggering the information obtaining unit when the priority of the authority controller in the priority configuration information is higher than the priority of the channel controller.
Optionally, the operating state control unit is specifically configured to:
when the monitored system time is the starting time point corresponding to a working time in the first corresponding relation, determining a target working state corresponding to the working time in the first corresponding relation;
determining a target dial instruction corresponding to the target working state based on a second corresponding relation which is stored in advance and relates to the working state and the dial instruction;
and issuing the target dial-up instruction to a channel controller in the man-way channel gate, so that the channel controller sets the working state of the gate to be the target working state after receiving the target dial-up instruction.
Optionally, the operating state control unit is further configured to:
and when the monitored system time is the end time point corresponding to the working time, issuing a state recovery instruction to the channel controller so that the channel controller restores the working state of the gate to the latest working state before the target working state.
Optionally, the apparatus further comprises:
a data request sending unit, configured to send a data request for requesting the second corresponding relationship to the channel controller when power-on is finished, so that the channel controller feeds back the second corresponding relationship to the permission controller after receiving the data request;
and the second corresponding relation storage unit is used for receiving and storing the second corresponding relation fed back by the channel controller.
In a third aspect, the present application provides a pedestrian passageway gate, comprising: an authority controller and a channel controller;
the authority controller is used for acquiring gate plan information; wherein, the gate plan information records a first corresponding relation between the working state of the gate and the working time of the working state; reading the first corresponding relation from the gate plan information, and monitoring the system time in real time; instructing the channel controller to set a working state of the gate based on the read first correspondence and the monitored system time;
and the channel controller is used for setting the working state of the gate under the indication of the authority controller.
Optionally, the permission controller is further configured to:
detecting priority configuration information aiming at a gate, wherein the priority configuration information is configured with the priority of the channel controller and the priority of the authority controller; and when the priority of the authority controller in the priority configuration information is higher than the priority of the channel controller, executing the step of obtaining gate plan information.
Optionally, the authority controller instructs the channel controller to set the operating state of the gate based on the read first corresponding relationship and the monitored system time, specifically:
when the monitored system time is the starting time point corresponding to a working time in the first corresponding relation, determining a target working state corresponding to the working time in the first corresponding relation;
determining a target dial instruction corresponding to the target working state based on a second corresponding relation which is stored in advance and relates to the working state and the dial instruction;
issuing the target dial-up instruction to a channel controller in the man-way channel gate;
the channel controller is in under authority controller's instruction, set up the operating condition of gate specifically is:
and after the target dial-up instruction is received, setting the working state of the gate to be the target working state.
Optionally, the permission controller is further configured to:
and after the target dial-up instruction is issued to the channel controller, when the monitored system time is the end time point corresponding to the working time, issuing a state recovery instruction to the channel controller so that the channel controller recovers the working state of the gate to the latest working state before the target working state.
Optionally, the permission controller is further configured to:
when the electrification is finished, sending a data request for requesting the second corresponding relation to the channel controller; receiving and storing the second corresponding relation fed back by the channel controller;
the channel controller is further configured to: and after receiving the data request, feeding back the second corresponding relation to the authority controller.
Compared with the prior art, the scheme provided by the application indicates the channel controller to set the working state of the gate by the authority controller according to the first corresponding relation between the working state of the gate and the working time of the working state, and manual dial operation performed when the working state is changed at every time is avoided, so that the problem of high labor cost when the working state of the gate is changed frequently can be solved through the scheme.
Drawings
FIG. 1 is a schematic diagram of a pedestrian passageway gate in the prior art;
fig. 2 is a flowchart of a pedestrian passageway gate control method according to an embodiment of the present disclosure;
fig. 3 is another flowchart of a pedestrian passageway gate control method according to an embodiment of the present disclosure;
fig. 4 is a schematic structural diagram of a pedestrian passageway gate control device according to an embodiment of the present application;
fig. 5 is another schematic structural diagram of a pedestrian passageway gate control device according to an embodiment of the present disclosure;
fig. 6 is a schematic structural diagram of a pedestrian path gate according to an embodiment of the present disclosure.
Detailed Description
Reference will now be made in detail to the exemplary embodiments, examples of which are illustrated in the accompanying drawings. When the following description refers to the accompanying drawings, like numbers in different drawings represent the same or similar elements unless otherwise indicated. The embodiments described in the following exemplary embodiments do not represent all embodiments consistent with the present application. Rather, they are merely examples of apparatus and methods consistent with certain aspects of the present application, as detailed in the appended claims.
The terminology used herein is for the purpose of describing particular embodiments only and is not intended to be limiting of the application. As used in this application and the appended claims, the singular forms "a", "an", and "the" are intended to include the plural forms as well, unless the context clearly indicates otherwise. It should also be understood that the term "and/or" as used herein refers to and encompasses any and all possible combinations of one or more of the associated listed items.
It is to be understood that although the terms first, second, third, etc. may be used herein to describe various information, such information should not be limited to these terms. These terms are only used to distinguish one type of information from another. For example, first information may also be referred to as second information, and similarly, second information may also be referred to as first information, without departing from the scope of the present application. The word "if" as used herein may be interpreted as "at … …" or "when … …" or "in response to a determination", depending on the context.
To facilitate the understanding of the scheme, the basic structure of the pedestrian passageway gate in the prior art is first described.
Fig. 1 shows a schematic structure of a pedestrian passageway gate in the prior art. As shown in fig. 1, the pedestrian passageway gate comprises an authority controller 1, a passageway controller comprising a master passageway controller 2 and a slave passageway controller 3, a card reader 4, a motor system 5, a synchronization line 6 and a gate 7, wherein the master passageway controller 2 and the slave passageway controller 3 are connected through the synchronization line 6; the basic working principle of the pedestrian passageway gate in the prior art is as follows: the card reader 4 collects identity information and reports the identity information to the authority controller 1, the authority controller 1 judges the user authority based on the received identity information, and when the user authority is judged to be passed, a control instruction (such as a gate opening or closing instruction) is sent to the main channel controller 2 and the slave channel controller 3; after receiving the control command, the main channel controller 2 and the slave channel controller 3 control the operation of the motor system 5, thereby controlling the action of the gate 7. In which the various component parts are embodied by filling colors of different grey levels in fig. 1, such as the grey levels of the filling colors of the right controller 1, the channel controllers including the master channel controller 2 and the slave channel controller 3, the card reader 4, the motor system 5 and the shutter 7 are different, it is emphasized that the filling colors in fig. 1 only serve to distinguish the components and do not have any limiting meaning.
In order to solve the problem that the labor cost is high when the working state of the gate is changed frequently, the embodiment of the application provides a pedestrian passageway gate control method and device and a pedestrian passageway gate.
First, a pedestrian passageway gate control method provided in the embodiment of the present application will be described.
As shown in fig. 2, a pedestrian passageway gate control method provided in the embodiment of the present application is applied to an authority controller in a pedestrian passageway gate, and the method may include the following steps:
s101, acquiring gate plan information; wherein, the gate plan information records a first corresponding relation between the working state of the gate and the working time of the working state;
wherein, the working state of the gate can include but is not limited to: a no-pass state to prohibit passage, a controlled state to check authority to pass, and a free state to unrestricted passage.
It should be noted that the trigger timing for the authority controller to obtain the gate plan information may be set according to actual conditions. For example: after each power-on, the authority controller can obtain the gate plan information, so as to open the automatic setting process of the working state of the gate; alternatively, the authority controller may obtain the gate plan information when a predetermined time point is reached, thereby opening an automatic setting process of the operating state of the gate, and the like.
In addition, in a specific application, the specific form of the working time recorded in the first corresponding relation may be a time period, such as 8:00-9:00, 17:00-19:00, and the like, or a starting time point, such as 8:00, 9:00, and the like.
It can be understood that the staff can set the gate plan information meeting the specific requirements through the configuration interface provided by the pedestrian passageway gate; or, the staff may set the gate plan information meeting the specific requirements through a configuration interface provided by the client device or the cloud server corresponding to the pedestrian passageway gate. For the case that the gate plan information is configured through the client device or the cloud server, the client device or the cloud server may issue the configured gate plan information to the permission controller, and correspondingly, the permission controller may receive and store the gate plan information; of course, the client device or the cloud server may store the gate plan information by itself, and when the working state of the gate needs to be set, the authority controller may request to obtain the gate plan information from the client device or the cloud server.
S102, reading the first corresponding relation from the gate plan information, and monitoring the system time in real time;
after the gate plan information is obtained, the first corresponding relationship may be read from the gate plan information, and then a subsequent automatic setting process may be performed based on the first corresponding relationship. And because the working time of each working state and the working state is recorded in the first corresponding relation, the system time can be monitored in real time, and when the monitored system time accords with the working time in the first corresponding relation, the channel controller is indicated to set the corresponding working state for the gate.
S103, indicating a channel controller in the man-way channel gate to set the working state of the gate based on the read first corresponding relation and the monitored system time.
For the purpose of automatically setting the working state of the gate, after the first corresponding relationship is read, the channel controller may be instructed to set the working state of the gate based on the read first corresponding relationship and the monitored system time.
Specifically, the step of instructing a channel controller in the pedestrian channel gate to set the operating state of the gate based on the read first corresponding relationship and the monitored system time may include:
when the monitored system time is the starting time point corresponding to a working time in the first corresponding relation, determining a target working state corresponding to the working time in the first corresponding relation;
determining a target dial instruction corresponding to the target working state based on a second corresponding relation which is stored in advance and relates to the working state and the dial instruction;
and issuing the target dial-up instruction to a channel controller in the man-way channel gate so that the channel controller sets the working state of the gate to be the target working state after receiving the target dial-up instruction.
It should be noted that the authority controller may request the channel controller to obtain the second corresponding relationship between the operating state and the dial-up command.
Optionally, in a specific implementation manner, the authority controller may send a data request for requesting the second corresponding relationship to the channel controller when power-on is finished, so that the channel controller feeds back the second corresponding relationship to the authority controller after receiving the data request; furthermore, the right controller can receive and store the second corresponding relation fed back by the channel controller. It is understood that, in a specific application, the permission controller may also request the channel controller to obtain the second corresponding relationship when a certain specific time point is reached, and of course, the permission controller may also request the channel controller to obtain the second corresponding relationship when an obtaining instruction sent by a user is received. The permission controller may send the data request to the channel controller in a serial port manner, which is not limited to this.
It should be noted that, for the case that only the starting time points of the working time exist in the first corresponding relationship, the authority controller instructs the channel controller to set the gate to the corresponding working state each time the starting time points are reached, that is, the working state of the gate is changed at each starting time point, and the working state of the gate can be kept unchanged in the time period between the adjacent starting time points.
For the case that the ending time point of the working time exists in the first corresponding relationship, for example, the specific form of the working time is a time period form, and since the ending time of the working state is given, after the step of issuing the target dial-up command to the channel controller, the method may further include:
and when the monitored system time is the end time point corresponding to the working time, issuing a state recovery instruction to the channel controller so that the channel controller restores the gate state of the gate to the latest working state before the target working state.
Compared with the prior art, the scheme provided by the application indicates the channel controller to set the working state of the gate by the authority controller according to the first corresponding relation between the working state of the gate and the working time of the working state, and manual dial operation performed when the working state is changed at every time is avoided, so that the problem of high labor cost when the working state of the gate is changed frequently can be solved through the scheme.
In order to facilitate the staff to freely select manual dialing and automatic setting according to the requirements, the embodiment of the application also provides a pedestrian passageway gate control method, and the pedestrian passageway gate control method is applied to an authority controller in a pedestrian passageway gate.
As shown in fig. 3, a pedestrian passageway gate control method provided in the embodiment of the present application may include the following steps:
s201, detecting priority configuration information aiming at a gate, wherein the priority configuration information is configured with the priority of a channel controller and an authority controller in the pedestrian channel gate;
the working personnel can configure priority configuration information meeting specific requirements through a configuration interface provided by client equipment or a cloud server corresponding to the pedestrian passage gate, namely configuring different priorities for the passage controller and the authority controller; of course, the staff may also configure the priority configuration information meeting the specific requirements through the configuration interface provided by the pedestrian gateway itself. Specifically, when the priority of the authority controller in the priority configuration information is higher than the priority of the channel controller, the authority controller is allowed to automatically set the working state of the gate; and when the priority of the authority controller in the priority configuration information is lower than the priority of the channel controller, the authority controller is not allowed to automatically set the working state of the gate, and manual dial-up needs to be performed on the channel controller to set the working state of the gate. Wherein, the priority can be embodied by high or low words, or embodied by specific numerical values, etc.
It is understood that the trigger time for detecting the priority configuration information of the gate may be when each power-on is finished, or when a predetermined time point is reached, and so on, which is reasonable.
S202, when the priority of the authority controller in the priority configuration information is higher than the priority of the channel controller, gate plan information is obtained; wherein, the gate plan information records a first corresponding relation between the working state of the gate and the working time of the working state;
when the priority of the authority controller in the priority configuration information is higher than the priority of the channel controller, the authority controller is allowed to automatically set the working state of the gate, at the moment, the gate plan information can be obtained, and then the subsequent automatic setting process of the working state of the gate is executed. And when the priority of the authority controller in the priority configuration information is lower than the priority of the channel controller, indicating that manual dial-up needs to be performed on the channel controller to set the working state of the gate, and at this time, ending the processing flow.
Wherein, the working state of the gate can include but is not limited to: a no-pass state to prohibit passage, a controlled state to check authority to pass, and a free state to unrestricted passage.
It should be noted that the trigger timing for the authority controller to obtain the gate plan information may be set according to actual conditions. For example: after each power-on, the authority controller can obtain the gate plan information, so as to open the automatic setting process of the working state of the gate; alternatively, the authority controller may obtain the gate plan information when a predetermined time point is reached, thereby opening an automatic setting process of the operating state of the gate, and the like.
In addition, in a specific application, the specific form of the working time recorded in the first corresponding relation may be a time period, such as 8:00-9:00, 17:00-19:00, and the like, or a starting time point, such as 8:00, 9:00, and the like.
It can be understood that the staff can set the gate plan information meeting the specific requirements through the configuration interface provided by the pedestrian passageway gate; or, the staff may set the gate plan information meeting the specific requirements through a configuration interface provided by the client device or the cloud server corresponding to the pedestrian passageway gate. For the case that the gate plan information is configured through the client device or the cloud server, the client device or the cloud server may issue the configured gate plan information to the permission controller, and correspondingly, the permission controller may receive and store the gate plan information; of course, the client device or the cloud server may store the gate plan information by itself, and when the working state of the gate needs to be set, the authority controller may request to obtain the gate plan information from the client device or the cloud server.
S203, reading the first corresponding relation from the gate plan information, and monitoring the system time in real time;
and S204, indicating a channel controller in the man-way channel gate to set the working state of the gate based on the read first corresponding relation and the monitored system time.
S203-S204 in this embodiment are the same as S102-S103 in the above embodiments, and are not described herein again.
In the solution provided in this embodiment, when the priority of the authority controller in the priority configuration information is higher than the priority of the channel controller, the authority controller automatically instructs the channel controller to set the operating state of the gate according to the first corresponding relationship between the operating state of the gate and the operating time of the operating state, so as to avoid manual dial operation performed each time the operating state is changed. Therefore, the problem of high labor cost when the working state of the gate is frequently changed can be solved through the scheme; moreover, the method provides possibility for staff to freely select manual dialing and automatic setting according to requirements.
Corresponding to the method embodiment, the embodiment of the application provides a pedestrian passageway gate control device, which is applied to an authority controller in a pedestrian passageway gate; as shown in fig. 4, the apparatus includes:
an information obtaining unit 410 for obtaining gate plan information; wherein, the gate plan information records a first corresponding relation between the working state of the gate and the working time of the working state;
a correspondence reading unit 420, configured to read the first correspondence from the gate plan information;
a time monitoring unit 430 for monitoring the system time in real time;
and a working state control unit 440, configured to instruct a channel controller in the pedestrian channel gate to set a working state of the gate based on the read first corresponding relationship and the monitored system time.
Compared with the prior art, the scheme provided by the application indicates the channel controller to set the working state of the gate by the authority controller according to the first corresponding relation between the working state of the gate and the working time of the working state, and manual dial operation performed when the working state is changed at every time is avoided, so that the problem of high labor cost when the working state of the gate is changed frequently can be solved through the scheme.
Optionally, on the basis of including the information obtaining unit 410, the corresponding relationship reading unit 420, the time monitoring unit 430, and the working state control unit 440, as shown in fig. 5, the apparatus provided in the embodiment of the present application may further include:
a configuration information detection unit 400A configured to detect priority configuration information for a gate, where the priority configuration information includes priorities of the channel controller and the access controller;
a detection result processing unit 400B, configured to trigger the information obtaining unit 410 when the priority of the authority controller in the priority configuration information is higher than the priority of the channel controller.
Optionally, the working state control unit 440 is specifically configured to:
when the monitored system time is the starting time point corresponding to a working time in the first corresponding relation, determining a target working state corresponding to the working time in the first corresponding relation;
determining a target dial instruction corresponding to the target working state based on a second corresponding relation which is stored in advance and relates to the working state and the dial instruction;
and the target dial-up instruction issuing subunit is used for issuing the target dial-up instruction to a channel controller in the man-way channel gate so that the channel controller sets the working state of the gate to be the target working state after receiving the target dial-up instruction.
Optionally, the operating state control unit 440 is further configured to:
and when the monitored system time is the end time point corresponding to the working time, issuing a state recovery instruction to the channel controller so that the channel controller restores the working state of the gate to the latest working state before the target working state.
Optionally, on the basis of including the target working state determining subunit, the target dial-up instruction determining subunit, and the target dial-up instruction issuing subunit, the apparatus provided in this embodiment of the application may further include:
a data request sending unit, configured to send a data request for requesting the second corresponding relationship to the channel controller when power-on is finished, so that the channel controller feeds back the second corresponding relationship to the permission controller after receiving the data request;
and the second corresponding relation storage unit is used for receiving and storing the second corresponding relation fed back by the channel controller.
Corresponding to the method embodiment, the application embodiment provides a pedestrian channel gate. As shown in fig. 6, the pedestrian passageway gate may include: an authority controller 610 and a channel controller 620;
the authority controller 610 is configured to obtain gate plan information; wherein, the gate plan information records a first corresponding relation between the working state of the gate and the working time of the working state; reading the first corresponding relation from the gate plan information, and monitoring the system time in real time; instructing the channel controller to set a working state of the gate based on the read first correspondence and the monitored system time;
and the channel controller 620 is used for setting the working state of the gate under the instruction of the authority controller.
Compared with the prior art, the scheme provided by the application indicates the channel controller to set the working state of the gate by the authority controller according to the first corresponding relation between the working state of the gate and the working time of the working state, and manual dial operation performed when the working state is changed at every time is avoided, so that the problem of high labor cost when the working state of the gate is changed frequently can be solved through the scheme.
Optionally, the authority controller 610 is further configured to:
detecting priority configuration information aiming at a gate, wherein the priority configuration information is configured with the priority of the channel controller and the priority of the authority controller; and when the priority of the authority controller in the priority configuration information is higher than the priority of the channel controller, executing the step of obtaining gate plan information.
Optionally, the authority controller 610 instructs the channel controller to set the working state of the gate based on the read first corresponding relationship and the monitored system time, specifically:
when the monitored system time is the starting time point corresponding to a working time in the first corresponding relation, determining a target working state corresponding to the working time in the first corresponding relation;
determining a target dial instruction corresponding to the target working state based on a second corresponding relation which is stored in advance and relates to the working state and the dial instruction;
issuing the target dial-up instruction to a channel controller in the man-way channel gate;
the channel controller 620 sets the working state of the gate under the instruction of the authority controller, specifically:
and after the target dial-up instruction is received, setting the working state of the gate to be the target working state.
Optionally, the authority controller 610 is further configured to:
and after the target dial-up instruction is issued to the channel controller, when the monitored system time is the end time point corresponding to the working time, issuing a state recovery instruction to the channel controller so that the channel controller recovers the working state of the gate to the latest working state before the target working state.
Optionally, the authority controller 610 is further configured to:
when the electrification is finished, sending a data request for requesting the second corresponding relation to the channel controller; receiving and storing the second corresponding relation fed back by the channel controller;
the channel controller 620 is further configured to: and after receiving the data request, feeding back the second corresponding relation to the authority controller.
The implementation process of the functions and actions of each unit in the above device is specifically described in the implementation process of the corresponding step in the above method, and is not described herein again.
For the device embodiments, since they substantially correspond to the method embodiments, reference may be made to the partial description of the method embodiments for relevant points. The above-described embodiments of the apparatus are merely illustrative, and the units described as separate parts may or may not be physically separate, and parts displayed as units may or may not be physical units, may be located in one place, or may be distributed on a plurality of network units. Some or all of the modules can be selected according to actual needs to achieve the purpose of the scheme of the application. One of ordinary skill in the art can understand and implement it without inventive effort.
The above description is only exemplary of the present application and should not be taken as limiting the present application, as any modification, equivalent replacement, or improvement made within the spirit and principle of the present application should be included in the scope of protection of the present application.

Claims (12)

1. A pedestrian passageway gate control method is characterized by being applied to a right controller in a pedestrian passageway gate; the method comprises the following steps:
acquiring gate plan information; wherein, the gate plan information records a first corresponding relation between the working state of the gate and the working time of the working state;
reading the first corresponding relation from the gate plan information, and monitoring the system time in real time;
when the monitored system time is the starting time point corresponding to a working time in the first corresponding relation, determining a target working state corresponding to the working time in the first corresponding relation; determining a target dial instruction corresponding to the target working state based on a second corresponding relation which is stored in advance and relates to the working state and the dial instruction; and issuing the target dial-up instruction to a channel controller in the man-way channel gate, so that the channel controller changes the current working state of the gate into the target working state after receiving the target dial-up instruction.
2. The method of claim 1, wherein the step of obtaining gate plan information is preceded by the method further comprising:
detecting priority configuration information aiming at a gate, wherein the priority configuration information is configured with the priority of the channel controller and the priority of the authority controller;
and when the priority of the authority controller in the priority configuration information is higher than the priority of the channel controller, executing the step of obtaining gate plan information.
3. The method of claim 1, wherein after the step of issuing the target dialing instruction to a channel controller in the man channel gate, the method further comprises:
and when the monitored system time is the end time point corresponding to the working time, issuing a state recovery instruction to the channel controller so that the channel controller restores the working state of the gate to the latest working state before the target working state.
4. The method of claim 1, further comprising:
when the electrification is finished, sending a data request for requesting the second corresponding relation to the channel controller, so that the channel controller feeds back the second corresponding relation to the authority controller after receiving the data request;
and receiving and storing the second corresponding relation fed back by the channel controller.
5. A pedestrian passageway gate control device is characterized by being applied to an authority controller in a pedestrian passageway gate; the device comprises:
an information obtaining unit for obtaining gate plan information; wherein, the gate plan information records a first corresponding relation between the working state of the gate and the working time of the working state;
a correspondence reading unit configured to read the first correspondence from the gate plan information;
the time monitoring unit is used for monitoring the system time in real time;
the working state control unit is used for determining a target working state corresponding to working time in the first corresponding relation when the monitored system time is an initial time point corresponding to the working time in the first corresponding relation; determining a target dial instruction corresponding to the target working state based on a second corresponding relation which is stored in advance and relates to the working state and the dial instruction; and issuing the target dial-up instruction to a channel controller in the man-way channel gate, so that the channel controller changes the current working state of the gate into the target working state after receiving the target dial-up instruction.
6. The apparatus of claim 5, further comprising:
a configuration information detection unit, configured to detect priority configuration information for a gate before the information obtaining unit obtains gate plan information, where the priority configuration information is configured with priorities of the channel controller and the permission controller;
and the detection result processing unit is used for triggering the information obtaining unit when the priority of the authority controller in the priority configuration information is higher than the priority of the channel controller.
7. The apparatus of claim 5, wherein the operating state control unit is further configured to:
and when the monitored system time is the end time point corresponding to the working time, issuing a state recovery instruction to the channel controller so that the channel controller restores the working state of the gate to the latest working state before the target working state.
8. The apparatus of claim 5, further comprising:
a data request sending unit, configured to send a data request for requesting the second corresponding relationship to the channel controller when power-on is finished, so that the channel controller feeds back the second corresponding relationship to the permission controller after receiving the data request;
and the second corresponding relation storage unit is used for receiving and storing the second corresponding relation fed back by the channel controller.
9. A pedestrian passageway gate, comprising: an authority controller and a channel controller;
the authority controller is used for acquiring gate plan information; wherein, the gate plan information records a first corresponding relation between the working state of the gate and the working time of the working state; reading the first corresponding relation from the gate plan information, and monitoring the system time in real time; when the monitored system time is the starting time point corresponding to a working time in the first corresponding relation, determining a target working state corresponding to the working time in the first corresponding relation; determining a target dial instruction corresponding to the target working state based on a second corresponding relation which is stored in advance and relates to the working state and the dial instruction; issuing the target dial-up instruction to a channel controller in the man-way channel gate, so that the channel controller changes the current working state of the gate into the target working state after receiving the target dial-up instruction;
and the channel controller is used for setting the working state of the gate under the indication of the authority controller.
10. The pedestrian walkway gate of claim 9, wherein the permission controller is further configured to:
detecting priority configuration information aiming at a gate, wherein the priority configuration information is configured with the priority of the channel controller and the priority of the authority controller; and when the priority of the authority controller in the priority configuration information is higher than the priority of the channel controller, executing the step of obtaining gate plan information.
11. The pedestrian walkway gate of claim 9, wherein the permission controller is further configured to:
and after the target dial-up instruction is issued to the channel controller, when the monitored system time is the end time point corresponding to the working time, issuing a state recovery instruction to the channel controller so that the channel controller recovers the working state of the gate to the latest working state before the target working state.
12. The pedestrian walkway gate of claim 9, wherein the permission controller is further configured to:
when the electrification is finished, sending a data request for requesting the second corresponding relation to the channel controller; receiving and storing the second corresponding relation fed back by the channel controller;
the channel controller is further configured to: and after receiving the data request, feeding back the second corresponding relation to the authority controller.
CN201711444435.5A 2017-12-27 2017-12-27 Pedestrian passageway gate control method and device and pedestrian passageway gate Active CN109979073B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201711444435.5A CN109979073B (en) 2017-12-27 2017-12-27 Pedestrian passageway gate control method and device and pedestrian passageway gate
PCT/CN2018/100446 WO2019128255A1 (en) 2017-12-27 2018-08-14 Pedestrian channel gate control method and apparatus, and pedestrian channel gate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711444435.5A CN109979073B (en) 2017-12-27 2017-12-27 Pedestrian passageway gate control method and device and pedestrian passageway gate

Publications (2)

Publication Number Publication Date
CN109979073A CN109979073A (en) 2019-07-05
CN109979073B true CN109979073B (en) 2021-03-23

Family

ID=67065063

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711444435.5A Active CN109979073B (en) 2017-12-27 2017-12-27 Pedestrian passageway gate control method and device and pedestrian passageway gate

Country Status (2)

Country Link
CN (1) CN109979073B (en)
WO (1) WO2019128255A1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116168480A (en) * 2023-02-21 2023-05-26 深圳市德翼智能科技有限公司 Remote intelligent control method, system and equipment for realizing channel gate based on Internet of things

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101622952A (en) * 2009-08-13 2010-01-13 中国灌溉排水发展中心 Water management informatization structure system of irrigation district
CN102381158A (en) * 2011-09-23 2012-03-21 奇瑞汽车股份有限公司 Method and device for ventilation control
CN102434038A (en) * 2011-12-16 2012-05-02 济南安宝科技有限公司 Electric control lock
CN102568063A (en) * 2011-12-14 2012-07-11 深圳市中联创新自控***有限公司 Door opening method for door control system, and door control system
CN202512642U (en) * 2011-12-14 2012-10-31 杭州市公安局拱墅区分局 Intelligent access control system
CN104234575A (en) * 2014-09-21 2014-12-24 王俭俭 Control system and control method for automatic door
CN104481331A (en) * 2014-12-12 2015-04-01 柳州铁道职业技术学院 Remote door opening/closing control system
CN204436132U (en) * 2014-12-12 2015-07-01 柳州铁道职业技术学院 Remote switch accelerator control system
CN105321240A (en) * 2015-11-04 2016-02-10 张泽 Control method and device of intelligent door lock and intelligent door control system
CN105421298A (en) * 2015-11-04 2016-03-23 福建四创软件有限公司 Sluice gate control method based on multiple-screen display
CN105927051A (en) * 2015-02-26 2016-09-07 陆洪瑞 Controller and controller switching method
CN206256428U (en) * 2016-12-16 2017-06-16 贺州学院 A kind of small-sized gate opening/closing supervising device

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203376792U (en) * 2013-07-04 2014-01-01 纳米新能源(唐山)有限责任公司 Mobile terminal-based access control system and access control terminal
CN105528816A (en) * 2014-09-28 2016-04-27 ***通信集团辽宁有限公司 Intelligent gate inhibition realization method, terminal, gate inhibition identification apparatus and user authorization service center
CN104992485B (en) * 2015-06-11 2018-10-02 苏州爱开客信息技术有限公司 Banister based on Internet of Things controls open method
CN105354898A (en) * 2015-09-10 2016-02-24 北京中软万维网络技术有限公司 Scissor-like door gate transit logic identification device and method
KR101763140B1 (en) * 2016-03-24 2017-07-31 주식회사 유니온커뮤니티 Authentification Method by User Terminal Connecting Access Controller, Software therefor, and Program Distributing Server Storing the Software

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101622952A (en) * 2009-08-13 2010-01-13 中国灌溉排水发展中心 Water management informatization structure system of irrigation district
CN102381158A (en) * 2011-09-23 2012-03-21 奇瑞汽车股份有限公司 Method and device for ventilation control
CN102568063A (en) * 2011-12-14 2012-07-11 深圳市中联创新自控***有限公司 Door opening method for door control system, and door control system
CN202512642U (en) * 2011-12-14 2012-10-31 杭州市公安局拱墅区分局 Intelligent access control system
CN102434038A (en) * 2011-12-16 2012-05-02 济南安宝科技有限公司 Electric control lock
CN104234575A (en) * 2014-09-21 2014-12-24 王俭俭 Control system and control method for automatic door
CN104481331A (en) * 2014-12-12 2015-04-01 柳州铁道职业技术学院 Remote door opening/closing control system
CN204436132U (en) * 2014-12-12 2015-07-01 柳州铁道职业技术学院 Remote switch accelerator control system
CN105927051A (en) * 2015-02-26 2016-09-07 陆洪瑞 Controller and controller switching method
CN105321240A (en) * 2015-11-04 2016-02-10 张泽 Control method and device of intelligent door lock and intelligent door control system
CN105421298A (en) * 2015-11-04 2016-03-23 福建四创软件有限公司 Sluice gate control method based on multiple-screen display
CN206256428U (en) * 2016-12-16 2017-06-16 贺州学院 A kind of small-sized gate opening/closing supervising device

Also Published As

Publication number Publication date
WO2019128255A1 (en) 2019-07-04
CN109979073A (en) 2019-07-05

Similar Documents

Publication Publication Date Title
CN112468527A (en) Linkage control system and linkage control method
CN107833329B (en) Access control system for regional control and anti-diving-back management
CN108806322A (en) parking lot management method, system and storage medium
CN108009728A (en) Regional security management method and system in park
CN106920298B (en) A kind of access control method based on wireless communication technique, apparatus and system
CN109979073B (en) Pedestrian passageway gate control method and device and pedestrian passageway gate
CN112017467A (en) Parking space detection method and device
CN104155502A (en) Voltage fluctuation detection method and system
CN114202839A (en) Gate passage control method, device, equipment and storage medium
CN110221551B (en) Method, device and system for controlling barrier gate
CN105913521A (en) Personnel in and out management method, system and terminal equipment with system
CN113511570A (en) Elevator control method, device, monitoring equipment and system
CN111988571B (en) Method and device for detecting access information
WO2018227120A1 (en) Location-based behavioral monitoring
CN112765574B (en) Identity verification method and device, system, power equipment and storage medium
CN102592334B (en) Method and device for indicating state and analyzing fault of access control system
CN111144199A (en) Parking lot parking space management method and device and storage medium
CN114553474B (en) Access control permission control method and device based on Internet of things
CN104851151A (en) Safety identification monitoring system
CN204965510U (en) Control management system of power equipment room
CN109960995B (en) Motion data determination system, method and device
CN115359593B (en) Access control method, system, electronic equipment and storage medium
CN104851156A (en) Safety identification monitoring system
CN113362518B (en) Barrier gate state control method and device and electronic equipment
CN214846859U (en) Cage entrance guard automatic control system based on animal identification

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant