CN109972737A - A kind of bamboo-the concrete combination beam and manufacturing method of combined type connection - Google Patents

A kind of bamboo-the concrete combination beam and manufacturing method of combined type connection Download PDF

Info

Publication number
CN109972737A
CN109972737A CN201910382327.2A CN201910382327A CN109972737A CN 109972737 A CN109972737 A CN 109972737A CN 201910382327 A CN201910382327 A CN 201910382327A CN 109972737 A CN109972737 A CN 109972737A
Authority
CN
China
Prior art keywords
bamboo
trunk
concrete
reinforcing rib
filler material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910382327.2A
Other languages
Chinese (zh)
Inventor
魏洋
王志远
陈思
赵鲲鹏
董峰辉
金子恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Forestry University
Original Assignee
Nanjing Forestry University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Forestry University filed Critical Nanjing Forestry University
Priority to CN201910382327.2A priority Critical patent/CN109972737A/en
Publication of CN109972737A publication Critical patent/CN109972737A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/30Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts being composed of two or more materials; Composite steel and concrete constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/29Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

A kind of bamboo-concrete combination beam of combined type connection, including bamboo beam, concrete slab, bamboo trunk, high-strength filler material, reinforcing rib, concrete slab is located at the top of bamboo beam, the lateral surface of the middle and lower part of bamboo trunk is bonded within build-in Yu Zhukong by adhesive coating, the position in concrete slab bamboo corresponding with bamboo beam hole is provided with preformed hole, preformed hole changes in up big and down small step, reinforcing rib is set to inside being longitudinally arranged along bamboo trunk of bamboo trunk, high-strength filler material pours in the preformed hole and bamboo trunk that riddle concrete slab, and wrapped stiffener.The present invention realizes that concrete slab is connect with the high efficient and reliable of bamboo beam using natural raw bamboo bamboo trunk and reinforcing rib, the combination of high-strength filler material, Multiple Combination connection plays the not obtainable combined effect of singular association form, ideal failure mode with ductility, natural raw bamboo bamboo trunk constraint avoids the concrete premature degradation of junction, and bamboo beam and concrete slab is effectively avoided to separate above and below.

Description

A kind of bamboo-the concrete combination beam and manufacturing method of combined type connection
Technical field
The present invention relates to a kind of bamboo-concrete combined component, especially a kind of bamboo-concrete combination beam of combined type connection And manufacturing method, belong to civil construction field.
Background technique
Bamboo wood is a kind of native organism, has the characteristics that intensity height, light weight, renewable and environmental-friendly, with timber It compares, there are the basic performances such as the higher ratio of strength to weight, better wearability and relatively low expansion rate of water absorption, intensity is compared with one As timber it is high by 50~100%, specific strength is 1.5~2.5 times of China fir, is 2~3 times of medium carbon steel.China's bamboo timber resource is abundant, The speed of growth of the excellent in mechanical performance of bamboo, bamboo wood is fast, is real renewable green resource, the exploitation and benefit of engineering bamboo wood With the material discrete problem for overcoming raw bamboo, bamboo wood is allowed to be applied to structural engineering field.Since new century, bamboo knot Structure has obtained developing relatively broadly as a kind of new structural systen in fields such as building, bridges.
The stress performance and timber structure of bamboo structure have certain similitude: Deformation Control Design, load totally carry water It puts down low.To improve bamboo structure performance, the relevant technologies propose FRP enhancing bamboo structure, however, FRP enhancing bamboo structure is still rigid Spend control design case.Bamboo and concrete combined structure by bamboo wood and concrete with connector in conjunction with work together, undoubtedly solve bamboo The effective way of rigidity of structure control design case, has given full play to the superior tensile property of lower part bamboo wood and top concrete is stronger Compressive property, possess better mechanical property, for bamboo-concrete combined structure, connection type is both to make collaboration work The key of work.
Due to the material properties of bamboo wood, the connection of bamboo wood and concrete is difficult to realize complete rigid between bamboo wood and concrete Property connection or realize that preferable rigidity is connect with preferable ductility simultaneously, such as Chinese patent " 201220551921.3 " number, openly A kind of semi-assembly bamboo-concrete composite bridge, cast-in-place concrete layer are vertical with bamboo respectively by stringer recess, crossbeam recess Beam, bamboo crossbeam form mechanical snap, and metalwork is equipped in stringer recess, crossbeam recess, guarantee cast-in-place concrete layer and bamboo stringer, The co-operation of bamboo crossbeam, however, the recess of the combination beam cross section overall with setting bamboo stringer, bamboo crossbeam are caused it is biggish Damage, recess are easy to be destroyed first by concentrated stress, and recess production need to specially set up template, and construction is complicated, and metalwork is set In recess inside concrete, recess concrete lacks necessary constraint, in load bearing process, due to recess concrete cracking, metal Part is difficult to play a role.
Summary of the invention
It is main to apply the object of the present invention is to provide the bamboo-concrete combination beam and manufacturing method of a kind of connection of combined type In solution bamboo-concrete combined structure connectivity problem.Several bamboo trunks are pasted on the bamboo hole of bamboo beam using adhesive by the present invention In, the concrete slab with preformed hole is poured, after the completion of concrete slab maintenance, splicing assembling concrete slab and Zhu Liang, in bamboo Reinforcing rib is arranged in the inside of pipe, and high-strength filler material is then poured in preformed hole and bamboo trunk, realizes the company of concrete slab and bamboo beam Combination is connect, the present invention is efficient with bamboo beam using natural raw bamboo bamboo trunk and reinforcing rib, high-strength filler material combination realization concrete slab It is reliably connected, high-strength filler material provides the shear stiffness of connector, and reinforcing rib offer connector is cut blending forming technology, naturally Raw bamboo bamboo trunk provides effective hoop constraint for the concrete in bamboo trunk, avoids the concrete premature degradation in bamboo trunk and causes to add Strengthening tendons are difficult to play a role, meanwhile, natural raw bamboo bamboo trunk provides the pin joint pipe of the large scale hollow form of cheap high rigidity, And natural raw bamboo bamboo trunk provides the template of connecting member forming, and preformed hole changes in up big and down small step, by upper and lower Build-in mechanism the resistance to plucking carrying between concrete slab and bamboo beam be provided act on, avoid bamboo beam and concrete slab from separating above and below.This Bamboo-concrete combination beam connector material of invention is natural raw bamboo bamboo trunk and reinforcing rib, high-strength filler material, material source letter Single, low cost, construction are convenient.
The present invention provides a kind of bamboo-concrete combination beam of combined type connection, it is characterised in that including bamboo beam, concrete Plate, bamboo trunk, high-strength filler material, reinforcing rib, concrete slab are located at the top of bamboo beam, and the top surface of bamboo beam, which is spaced apart, is equipped with several bamboos Hole, the diameter in bamboo hole and the outer diameter of bamboo trunk are equal, and the lateral surface of the middle and lower part of bamboo trunk bonds build-in in bamboo by adhesive coating Within hole, the position in concrete slab bamboo corresponding with bamboo beam hole is provided with preformed hole, and preformed hole is in up big and down small step deformation Change, center line is consistent with bamboo hole, and reinforcing rib is set to inside being longitudinally arranged along bamboo trunk of bamboo trunk, and high-strength filler material pours It riddles in the preformed hole and bamboo trunk of concrete slab, and wrapped stiffener, the top surface of high-strength filler material and the top surface of concrete slab It flushes, concrete slab is integrated with bamboo beam by bamboo trunk, high-strength filler material, reinforcing rib interconnection, the resistance to compression of high-strength filler material Intensity is not less than 80MPa.
The high-strength filler material is one of concrete, mortar, epoxy resin mortar, structure glue, epoxide-resin glue
The bamboo beam is using one of bamboo material stacked material, bamboo glulam or recombining bamboo.
The coarse aggregate size of the high-strength filler material be not more than 25mm, and in bamboo trunk and preformed hole one-time-concreting at Type, the setting quantity of reinforcing rib are no less than 1 in everywhere bamboo trunk and preformed hole, and the top of reinforcing rib is lower than high-strength filler material Top surface 10mm~30mm, the bottom end of reinforcing rib is not higher than the bottom end of bamboo trunk.
The reinforcing rib is one kind of metal material, composite material, bamboo wood, timber.
The bamboo trunk is made of natural raw bamboo, and the depth of bamboo trunk insertion bamboo beam is no less than 30mm.
A kind of bamboo-concrete combination beam manufacturing method of combined type connection, it is characterised in that will be several using adhesive Bamboo trunk is pasted in the bamboo hole of bamboo beam, pours the concrete slab with preformed hole, after the completion of concrete slab maintenance, splicing assembling Concrete slab and Zhu Liang then pour high-strength filler material in preformed hole and bamboo trunk, realize the connection group of concrete slab and bamboo beam It closes, its step are as follows:
A. it drills: being drilled with several bamboo holes according to predetermined position in the top surface of bamboo beam;
B. it is embedded in bamboo trunk: to the lateral surface adhesive coating of the middle and lower part of bamboo trunk, and being rotatably inserted into bonding build-in Yu Zhukong Within, bamboo trunk is made of natural raw bamboo, and the depth of bamboo trunk insertion bamboo beam is no less than 30mm;
C. casting concrete plate: casting concrete plate, and the position in concrete slab bamboo corresponding with bamboo beam hole stay set it is pre- It boxes out, preformed hole changes in up big and down small step, and center line is consistent with bamboo hole;
D., reinforcing rib is set: bamboo trunk is set to using gluing, binding or insertion technique fixed setting reinforcing rib, reinforcing rib Inside is longitudinally arranged along bamboo trunk, and the setting quantity of reinforcing rib is no less than 1 in everywhere bamboo trunk and preformed hole, reinforcing rib Top be lower than top surface 10mm~30mm of high-strength filler material, the bottom end of reinforcing rib is not higher than the bottom end of bamboo trunk.
E. it pours high-strength filler material: pouring high-strength filler material and riddle in the preformed hole and bamboo trunk of concrete slab, package Reinforcing rib, the top surface of high-strength filler material are flushed with the top surface of concrete slab, and intensity is not less than 80MPa, and coarse aggregate size is not more than 25mm。
F. it conserves and is surface-treated: conserving high-strength filler material, cleaning treatment is carried out to component surface.
The present invention is efficient with bamboo beam using natural raw bamboo bamboo trunk and reinforcing rib, high-strength filler material combination realization concrete slab It being reliably connected, the ideal failure mode with ductility, natural raw bamboo bamboo trunk constraint avoids the concrete premature degradation of junction, Effectively bamboo beam and concrete slab is avoided to separate above and below, material source is simple, manufacture craft is simple, standardized production easy to accomplish. The invention has the following advantages:
1) natural raw bamboo bamboo trunk provides effective hoop constraint for the concrete in bamboo trunk, and the concrete in bamboo trunk is avoided to mention It is preceding destruction and cause reinforcing rib to be difficult to play a role.
2) large scale that natural connection of the raw bamboo bamboo trunk between bamboo wood and concrete provides cheap high rigidity is hollow The pin joint pipe of form.
3) natural raw bamboo bamboo trunk and reinforcing rib, the combination of high-strength filler material, Multiple Combination connection play singular association form not Obtainable combined effect, high reliablity, the bearing capacity with higher while resistant slide rigidity with higher destroy mould Formula ductility.
4) preformed hole realizes upper and lower build-in mechanism in up big and down small step varied configurations, avoids bamboo beam and coagulation Native plate separates above and below.
5) natural raw bamboo bamboo trunk and reinforcing rib, the combination of high-strength filler material and the contact surface of bamboo wood and concrete product are big, Stress is avoided to concentrate.
6) bamboo trunk is environmentally protective, and steel using amount is small, low cost, and manufacture craft is simple.
7) manufacturing process is the assembled process of component one by one, standardized production easy to accomplish.
Detailed description of the invention
The following drawings are only intended to schematically illustrate and explain the present invention, not delimit the scope of the invention.
A kind of bamboo-concrete combination beam solid details of combined type connection of Fig. 1 shows schematic diagram;
A kind of bamboo-concrete combination beam stereoscopic schematic diagram of combined type connection of Fig. 2;
A kind of bamboo-concrete combination beam floor map of combined type connection of Fig. 3;
A kind of positive elevational schematic view of bamboo-concrete combination beam of combined type connection of Fig. 4;
A kind of bamboo-concrete combination beam side elevation schematic diagram of combined type connection of Fig. 5;
A kind of bamboo-concrete combination beam Section A-A figure of combined type connection of Fig. 6;
A kind of bamboo-concrete combination beam section B-B figure of combined type connection of Fig. 7;
A kind of bamboo-concrete combination beam C-C sectional view of combined type connection of Fig. 8;
A kind of bamboo-concrete combination beam of combined type connection of Fig. 9 and the process flow chart of manufacturing method;
A kind of assembling schematic diagram of bamboo-concrete combination beam manufacturing method of combined type connection of Figure 10;
A kind of bamboo beam drilling schematic diagram of bamboo-concrete combination beam manufacturing method of combined type connection of Figure 11;
A kind of concrete slab of bamboo-concrete combination beam manufacturing method of combined type connection of Figure 12, which stays, sets preformed hole signal Figure;
A kind of bamboo beam of bamboo-concrete combination beam manufacturing method of combined type connection of Figure 13 is embedded in bamboo trunk schematic diagram.
In the accompanying drawings, 1 is bamboo beam, and 2 be concrete slab, and 3 be bamboo trunk, and 4 be high-strength filler material, and 5 be reinforcing rib, and 11 be bamboo Hole, 21 be preformed hole.
Specific embodiment
In order to which to technology of the invention, feature, purpose and effect are more clearly understood, this hair of Detailed description of the invention is now compareed Bright specific embodiment.
Such as attached drawing, the present invention provides a kind of bamboo-concrete combination beam of combined type connection, it is characterised in that including bamboo beam 1, Concrete slab 2, bamboo trunk 3, high-strength filler material 4, reinforcing rib 5, concrete slab 2 are located at the top of bamboo beam 1, the top surface interval of bamboo beam 1 Several bamboo holes are offered, the diameter in bamboo hole is equal with the outer diameter of bamboo trunk 3, and the lateral surface of the middle and lower part of bamboo trunk 3 passes through coating gluing Agent bonds within build-in Yu Zhukong, and the position in the bamboo corresponding with bamboo beam 1 of concrete slab 2 hole is provided with preformed hole 21, preformed hole 21 Change in up big and down small step, center line is consistent with bamboo hole, and reinforcing rib 5 is set to the inside of bamboo trunk 3 along bamboo trunk 3 It is longitudinally arranged, high-strength filler material 4 pours in the preformed hole 21 and bamboo trunk 3 that riddle concrete slab 2, and wrapped stiffener 5, high-strength The top surface of filler material 4 is flushed with the top surface of concrete slab 2, and concrete slab 2 and bamboo beam 1 pass through bamboo trunk 3, high-strength filler material 4, reinforcement The interconnection of muscle 5 is integrated, and the compression strength of high-strength filler material 4 is not less than 80MPa.
The high-strength filler material 4 is one of concrete, mortar, epoxy resin mortar, structure glue, epoxide-resin glue.
The bamboo beam 1 is using one of bamboo material stacked material, bamboo glulam or recombining bamboo.
The coarse aggregate size of the high-strength filler material 4 is not more than 25mm, and the one-time-concreting in bamboo trunk 3 and preformed hole 21 Molding, the setting quantity of reinforcing rib 5 are no less than 1 in everywhere bamboo trunk 3 and preformed hole 21, and the top of reinforcing rib 5 is lower than height Top surface 10mm~30mm of strong filler material 4, the bottom end of reinforcing rib 5 are not higher than the bottom end of bamboo trunk 3.
The reinforcing rib 5 is one kind of metal material, composite material, bamboo wood, timber.
The bamboo trunk 3 is made of natural raw bamboo, and the depth that bamboo trunk 3 is embedded in bamboo beam 1 is no less than 30mm.
A kind of bamboo-concrete combination beam manufacturing method of combined type connection, it is characterised in that will be several using adhesive Bamboo trunk is pasted in the bamboo hole of bamboo beam, pours the concrete slab with preformed hole, after the completion of concrete slab maintenance, splicing assembling Concrete slab and Zhu Liang are arranged reinforcing rib in the inside of bamboo trunk, high-strength filler material are then poured in preformed hole and bamboo trunk, is realized Concrete slab is combined with the connection of bamboo beam, and its step are as follows:
A. it drills: being drilled with several bamboo holes according to predetermined position in the top surface of bamboo beam 1;
B. it is embedded in bamboo trunk: to the lateral surface adhesive coating of the middle and lower part of bamboo trunk 3, and being rotatably inserted into bonding build-in Yu Zhukong Within, bamboo trunk 3 is made of natural raw bamboo, and the depth that bamboo trunk 3 is embedded in bamboo beam 1 is no less than 30mm;
C. casting concrete plate: casting concrete plate 2, and stay and set in the position in the bamboo corresponding with bamboo beam 1 of concrete slab 2 hole Preformed hole 21, preformed hole 21 change in up big and down small step, and center line is consistent with bamboo hole;
D., reinforcing rib is set: bamboo trunk is set to using gluing, binding or insertion technique fixed setting reinforcing rib 5, reinforcing rib 5 3 inside is longitudinally arranged along bamboo trunk 3, and the setting quantity of reinforcing rib 5 is no less than 1 in everywhere bamboo trunk 3 and preformed hole 21 Root, the top of reinforcing rib 5 are lower than top surface 10mm~30mm of high-strength filler material 4, and the bottom end of reinforcing rib 5 is not higher than the bottom of bamboo trunk 3 End.
E. it pours high-strength filler material: pouring high-strength filler material 4 and riddle in the preformed hole 21 and bamboo trunk 3 of concrete slab 2, The top surface of wrapped stiffener 5, high-strength filler material 4 is flushed with the top surface of concrete slab 2, and intensity is not less than 80MPa, coarse aggregate size No more than 25mm.
F. it conserves and is surface-treated: conserving high-strength filler material 4, cleaning treatment is carried out to component surface.

Claims (7)

1. a kind of bamboo-concrete combination beam of combined type connection, it is characterised in that including bamboo beam (1), concrete slab (2), bamboo trunk (3), high-strength filler material (4), reinforcing rib (5), concrete slab (2) are located at the top of bamboo beam (1), and the top surface of bamboo beam (1) is spaced apart Equipped with several bamboo holes (11), the diameter of bamboo hole (11) is equal with the outer diameter of bamboo trunk (3), and the lateral surface of the middle and lower part of bamboo trunk (3) is logical It crosses within adhesive coating bonding build-in Yu Zhukong (11), the position in concrete slab (2) bamboo corresponding with bamboo beam (1) hole (11) is set Be equipped with preformed hole (21), preformed hole (21) changes in up big and down small step, center line and bamboo hole (11) unanimously, reinforcing rib (5) it is set to inside being longitudinally arranged along bamboo trunk (3) of bamboo trunk (3), high-strength filler material (4), which pours, riddles concrete slab (2) in preformed hole (21) and bamboo trunk (3), and wrapped stiffener (5), top surface and concrete slab (2) of high-strength filler material (4) Top surface flushes, and concrete slab (2) is connected to one by bamboo trunk (3), high-strength filler material (4), reinforcing rib (5) with bamboo beam (1) The compression strength of body, high-strength filler material (4) is not less than 80MPa.
2. a kind of bamboo-concrete combination beam of combined type connection according to claim 1, it is characterised in that high-strength filler material It (4) is one of concrete, mortar, epoxy resin mortar, structure glue, epoxide-resin glue.
3. a kind of bamboo-concrete combination beam of combined type connection according to claim 1, it is characterised in that bamboo beam (1) is adopted With one of bamboo material stacked material, bamboo glulam or recombining bamboo.
4. a kind of bamboo-concrete combination beam of combined type connection according to claim 1, it is characterised in that described is high-strength The coarse aggregate size of filler material (4) is not more than 25mm, and in bamboo trunk (3) and the interior one-time-concreting molding of preformed hole (21), reinforcing rib (5) setting quantity no less than 1 in everywhere bamboo trunk (3) and preformed hole (21), fill out lower than high-strength by the top of reinforcing rib (5) Top surface 10mm~30mm of charge (4), the bottom end of reinforcing rib (5) are not higher than the bottom end of bamboo trunk (3).
5. a kind of bamboo-concrete combination beam of combined type connection according to claim 1, it is characterised in that the reinforcement Muscle (5) is one kind of metal material, composite material, bamboo wood, timber.
6. a kind of bamboo-concrete combination beam of combined type connection according to claim 1, it is characterised in that the bamboo trunk (3) it is made of natural raw bamboo, the depth of bamboo trunk (3) insertion bamboo beam (1) is no less than 30mm.
7. a kind of bamboo-concrete combination beam manufacturing method of combined type connection, it is characterised in that use adhesive by several bamboos Pipe is pasted in the bamboo hole of bamboo beam, pours the concrete slab with preformed hole, and after the completion of concrete slab maintenance, splicing assembling is mixed Concrete board and Zhu Liang are arranged reinforcing rib in the inside of bamboo trunk, high-strength filler material are then poured in preformed hole and bamboo trunk, realize mixed Concrete board is combined with the connection of bamboo beam, and its step are as follows:
A. it drills: being drilled with several bamboo holes (11) according to predetermined position in the top surface of Zhu Liang (1);
B. it is embedded in bamboo trunk: to the lateral surface adhesive coating of the middle and lower part of bamboo trunk (3), and being rotatably inserted into bonding build-in Yu Zhukong (11) within, bamboo trunk (3) is made of natural raw bamboo, and the depth of bamboo trunk (3) insertion bamboo beam (1) is no less than 30mm;
C. casting concrete plate: casting concrete plate (2), and in the position in concrete slab (2) bamboo corresponding with bamboo beam (1) hole (11) It sets to stay and set preformed hole (21), preformed hole (21) changes in up big and down small step, and center line and bamboo hole (11) are consistent;
D., reinforcing rib is set: bamboo trunk is set to using gluing, binding or insertion technique fixed setting reinforcing rib (5), reinforcing rib (5) (3) inside is longitudinally arranged along bamboo trunk (3), and the setting quantity of reinforcing rib (5) is in everywhere bamboo trunk (3) and preformed hole (21) Interior no less than 1, the top of reinforcing rib (5) is lower than the top surface 10mm~30mm of high-strength filler material (4), the bottom end of reinforcing rib (5) Not higher than the bottom end of bamboo trunk (3).
E. it pours high-strength filler material: pouring high-strength filler material (4) and riddle the preformed hole (21) and bamboo trunk of concrete slab (2) (3) in, the top surface of wrapped stiffener (5), high-strength filler material (4) is flushed with the top surface of concrete slab (2), and intensity is not less than 80MPa, coarse aggregate size are not more than 25mm.
F. it conserves and is surface-treated: conserving high-strength filler material (4), cleaning treatment is carried out to component surface.
CN201910382327.2A 2019-05-07 2019-05-07 A kind of bamboo-the concrete combination beam and manufacturing method of combined type connection Pending CN109972737A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910382327.2A CN109972737A (en) 2019-05-07 2019-05-07 A kind of bamboo-the concrete combination beam and manufacturing method of combined type connection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910382327.2A CN109972737A (en) 2019-05-07 2019-05-07 A kind of bamboo-the concrete combination beam and manufacturing method of combined type connection

Publications (1)

Publication Number Publication Date
CN109972737A true CN109972737A (en) 2019-07-05

Family

ID=67073128

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910382327.2A Pending CN109972737A (en) 2019-05-07 2019-05-07 A kind of bamboo-the concrete combination beam and manufacturing method of combined type connection

Country Status (1)

Country Link
CN (1) CN109972737A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001270767A (en) * 2000-03-27 2001-10-02 Dainichi:Kk Charcoal-containing concrete block and method for manufacturing the same
CN204983396U (en) * 2015-09-29 2016-01-20 南京林业大学 Bamboo - aerated concrete combination beam
CN107268890A (en) * 2017-07-31 2017-10-20 湖南大学 A kind of assembled bamboo and wood concrete combination beam
CN109057161A (en) * 2018-08-21 2018-12-21 南京林业大学 A kind of prefabricated bamboo wood lightweight concrete column
CN209891405U (en) * 2019-05-07 2020-01-03 南京林业大学 Combined connection bamboo-concrete combined beam

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001270767A (en) * 2000-03-27 2001-10-02 Dainichi:Kk Charcoal-containing concrete block and method for manufacturing the same
CN204983396U (en) * 2015-09-29 2016-01-20 南京林业大学 Bamboo - aerated concrete combination beam
CN107268890A (en) * 2017-07-31 2017-10-20 湖南大学 A kind of assembled bamboo and wood concrete combination beam
CN109057161A (en) * 2018-08-21 2018-12-21 南京林业大学 A kind of prefabricated bamboo wood lightweight concrete column
CN209891405U (en) * 2019-05-07 2020-01-03 南京林业大学 Combined connection bamboo-concrete combined beam

Similar Documents

Publication Publication Date Title
CN101328753B (en) Fiber reinforcement composite material - concrete combination beam
CN106978884B (en) One kind can assemble light steel tube-constraint timber with small diameter combination load-bearing pillar and the practice
CN106638274A (en) Unidirectional prestressed ultrahigh-performance concrete thin-walled box girder standard segment
CN208137185U (en) A kind of prefabricated steel shear wall transverse joint connecting node construction
CN109972737A (en) A kind of bamboo-the concrete combination beam and manufacturing method of combined type connection
CN209891405U (en) Combined connection bamboo-concrete combined beam
CN208844789U (en) A kind of Concrete Filled raw bamboo composite structure
CN211645919U (en) Adopt combination box girder construction that bamboo muscle is connected
CN105239666B (en) A kind of assembled bamboo air entrained concrete combining structure and preparation method
CN108316530A (en) The assembled steel reinforced concrete composite floor and installation method connected using self-locking
CN208039583U (en) A kind of large span sandwich concrete floor
CN103924728B (en) End soap-free emulsion polymeization variable strength reinforced beam
CN209129253U (en) A kind of air entrained concrete tongue and groove contignation with ribbing
CN208219389U (en) Based on short-line prefabrication assembly girder construction
CN100537947C (en) A kind of cast-in-situ reinforcing steel bar concrete hollow slab
CN100467735C (en) Stereo bearing shuttering for reinforced concrete
CN207998962U (en) A kind of raw bamboo concrete combined floor
CN1769624B (en) Hollow pipe for concrete filling
CN100445494C (en) Stereo bearing shuttering for reinforced concrete
CN111021219A (en) Adopt combination box girder construction that bamboo muscle is connected
CN1743578B (en) Steel reinforced concrete three-dimensional force-bearing structure floorslab
CN108222348A (en) A kind of raw bamboo concrete combined floor and its casting method
CN106812217A (en) A kind of prefabricated assembled node
CN100537949C (en) A kind of cast-in-situ reinforcing steel bar concrete hollow slab
CN101240571B (en) Three-dimensional force-bearing formwork for reinforced concrete

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination