CN109960818A - Generate the method and device of the simulation air speed data of wind power plant - Google Patents

Generate the method and device of the simulation air speed data of wind power plant Download PDF

Info

Publication number
CN109960818A
CN109960818A CN201711401828.8A CN201711401828A CN109960818A CN 109960818 A CN109960818 A CN 109960818A CN 201711401828 A CN201711401828 A CN 201711401828A CN 109960818 A CN109960818 A CN 109960818A
Authority
CN
China
Prior art keywords
wind speed
speed data
difference
value
historical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711401828.8A
Other languages
Chinese (zh)
Other versions
CN109960818B (en
Inventor
董辰辉
左丽叶
马辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Jinfeng Software Technology Co ltd
Beijing Goldwind Smart Energy Service Co Ltd
Original Assignee
Beijing Gold Wind Technology Co Ltd Huineng
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Gold Wind Technology Co Ltd Huineng filed Critical Beijing Gold Wind Technology Co Ltd Huineng
Priority to CN201711401828.8A priority Critical patent/CN109960818B/en
Publication of CN109960818A publication Critical patent/CN109960818A/en
Application granted granted Critical
Publication of CN109960818B publication Critical patent/CN109960818B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Wind Motors (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

A kind of method and device of simulation air speed data generating wind power plant is provided.The described method includes: obtaining the historical wind speed data in the special time period of specific wind power plant, wherein the historical wind speed data includes the historical wind speed value at each time point in the special time period;Count the difference profile situation of the historical wind speed data, wherein the distribution situation of the difference value between the historical wind speed value of the difference profile situation instruction adjacent time point of the historical wind speed data;Based on the historical wind speed data, the random air speed data for meeting the difference profile situation of the historical wind speed data is generated, wherein the random wind speed data packet includes the random air speed value at each time point in the special time period;Using the random air speed data of generation as the simulation air speed data in the special time period of current wind power plant.

Description

Generate the method and device of the simulation air speed data of wind power plant
Technical field
All things considered of the present invention is related to technical field of wind power generation, more particularly, is related to a kind of mould for generating wind power plant The method and device of quasi- air speed data.
Background technique
With the extensive development of wind-power electricity generation, the total installed capacity of wind-powered electricity generation is increasing, and wind-power electricity generation is increasingly becoming weight The energy source case wanted.In wind-powered electricity generation related fields, it is often necessary to generate some random wind speed similar with actual wind speed data characteristic Data, to be used to test program relevant to wind speed, or for drawing some display diagrams relevant to air speed data (for example, curve of air speed data) etc..
Currently, the Weibull distribution situation of actual wind speed data is normally based on, to generate corresponding random air speed data. However, the random air speed data generated in this way, although the Weibull of Weibull distribution parameters and actual wind speed data Distribution parameter is similar, but wave characteristic is larger compared to the wave characteristic difference of actual wind speed data, it is difficult to meet application demand.
For example, Fig. 2 shows the random wind speed that the Weibull distribution parameters based on actual wind speed data shown in fig. 1 generate The curve of data, it can be seen that curve of the curve compared to actual wind speed data of the random air speed data of generation, localised waving More acutely.
Summary of the invention
Exemplary embodiment of the present invention is to provide a kind of method and device of simulation air speed data for generating wind power plant, It is larger that it is able to solve wave characteristic difference between the simulation air speed data of generation of the existing technology and actual wind speed data The problem of.
An exemplary embodiment of the present invention provides a kind of method of simulation air speed data for generating wind power plant, described Method includes: the historical wind speed data in the special time period for obtain specific wind power plant, wherein the historical wind speed data includes The historical wind speed value at each time point in the special time period;The difference profile situation of the historical wind speed data is counted, In, the distribution of the difference value between the historical wind speed value of the difference profile situation instruction adjacent time point of the historical wind speed data Situation;Based on the historical wind speed data, the random wind speed number for meeting the difference profile situation of the historical wind speed data is generated According to, wherein the random wind speed data packet includes the random air speed value at each time point in the special time period;By generation with Machine air speed data is as the simulation air speed data in the special time period of current wind power plant.
Optionally, the step of counting the difference profile situation of the historical wind speed data includes: by the historical wind speed number According to air speed value range be divided into multiple wind speed sections at a predetermined interval;Determine wind speed belonging to the historical wind speed value at each time point Section;The difference profile situation of each wind speed section is counted respectively, wherein the difference profile situation of the wind speed section indicates the wind speed section The distribution situation of difference value between the historical wind speed value of the future time point of interior historical wind speed value and the historical wind speed value.
Optionally, it is based on the historical wind speed data, generates the difference profile situation for meeting the historical wind speed data The step of random air speed data includes: to execute following steps respectively for each time point in the special time period: being determined Wind speed section belonging to the historical wind speed value at a upper time point at the time point;Generate the difference profile feelings for meeting determining wind speed section The random difference score value of condition;The historical wind speed value at a upper time point at the time point and the random difference score value of generation are superimposed, with To the random air speed value at the time point.
Optionally, the step of counting the difference profile situation of each wind speed section respectively includes: for each wind speed section, respectively It executes following steps: counting the historical wind speed value of the future time point of the historical wind speed value and the historical wind speed value in the wind speed section Between difference value fall in the probability distribution in each difference section, wherein the length of each difference section is identical;By the wind speed section of statistics Difference value probability distribution be converted to the wind speed section difference value cumulative probability distribution.
Optionally, the step of generating the random difference score value for the difference profile situation for meeting determining wind speed section includes: to generate One is more than or equal to 0 and the uniform random number less than or equal to 1;Determine the wind speed section of determination corresponding to the uniform random number generated Difference value cumulative probability distribution probability interval;A difference is generated based on difference section corresponding to determining probability interval Value is used as random difference score value.
Optionally, the specific wind power plant be current wind power plant, the neighbouring wind power plant of current wind power plant and with current wind One of similar wind power plant of the wind speed characteristics of electric field.
Optionally, using the random air speed data of generation as the simulation wind speed in the special time period of current wind power plant The step of data includes: overall distribution situation of the statistics historical wind speed data in the special time period;Described in statistics Random overall distribution situation of the air speed data in the special time period;When the overall distribution situation of the historical wind speed data When difference between the overall distribution situation of the random air speed data meets preset condition, the random air speed data is made For the simulation air speed data in the special time period of current wind power plant.
Optionally, overall distribution situation of the historical wind speed data in the special time period includes: the history Weibull distribution situation of the air speed data in the special time period;The random air speed data is in the special time period Overall distribution situation include: Weibull distribution situation of the random air speed data in the special time period.
In accordance with an alternative illustrative embodiment of the present invention, a kind of device of simulation air speed data generating wind power plant is provided, Described device includes: historical wind speed data acquiring unit, is configured as obtaining the history in the special time period of specific wind power plant Air speed data, wherein the historical wind speed data includes the historical wind speed value at each time point in the special time period;Difference Distribution statistics unit is configured as counting the difference profile situation of the historical wind speed data, wherein the historical wind speed data Difference profile situation instruction adjacent time point historical wind speed value between difference value distribution situation;Random air speed data is raw At unit, it is configured as generating the difference profile situation for meeting the historical wind speed data based on the historical wind speed data Random air speed data, wherein the random wind speed data packet includes the random air speed value at each time point in the special time period; Air speed data determination unit is simulated, the specific time of the random air speed data that will be generated as current wind power plant is configured as Simulation air speed data in section.
Optionally, difference profile statistic unit is also configured to the air speed value range by the historical wind speed data with pre- Fixed interval is divided into multiple wind speed sections;Determine wind speed section belonging to the historical wind speed value at each time point;Each wind speed is counted respectively The difference profile situation of section, wherein the difference profile situation of the wind speed section indicate historical wind speed value in the wind speed section with should The distribution situation of difference value between the historical wind speed value of the future time point of historical wind speed value.
Optionally, random wind speed data generating unit was additionally configured to for each time in the special time period Point executes following operation respectively: determining wind speed section belonging to the historical wind speed value at a upper time point at the time point;Generation meets The random difference score value of the difference profile situation of determining wind speed section;By the historical wind speed value and life at a upper time point at the time point At random difference score value superposition, to obtain the random air speed value at the time point.
Optionally, difference profile statistic unit is additionally configured to for each wind speed section, executes following operation: statistics respectively Difference value between the historical wind speed value of the future time point of historical wind speed value and the historical wind speed value in the wind speed section is fallen in Probability distribution in each difference section, wherein the length of each difference section is identical;By the probability of the difference value of the wind speed section of statistics point Cloth is converted to the cumulative probability distribution of the difference value of the wind speed section.
Optionally, random wind speed data generating unit is also configured to generate one more than or equal to 0 and is less than or equal to 1 Uniform random number;Determine the general of the cumulative probability distribution of the difference value of the wind speed section of determination corresponding to the uniform random number generated Rate section;A difference value is generated as random difference score value based on difference section corresponding to determining probability interval.
Optionally, the specific wind power plant be current wind power plant, the neighbouring wind power plant of current wind power plant and with current wind One of similar wind power plant of the wind speed characteristics of electric field.
Optionally, simulation air speed data determination unit is also configured to count the historical wind speed data described specific Overall distribution situation in period;Count overall distribution situation of the random air speed data in the special time period; When the difference between the overall distribution situation of the historical wind speed data and the overall distribution situation of the random air speed data is full When sufficient preset condition, using the random air speed data as the simulation wind speed number in the special time period of current wind power plant According to.
Optionally, overall distribution situation of the historical wind speed data in the special time period includes: the history Weibull distribution situation of the air speed data in the special time period;The random air speed data is in the special time period Overall distribution situation include: Weibull distribution situation of the random air speed data in the special time period.
In accordance with an alternative illustrative embodiment of the present invention, a kind of computer-readable storage being stored with computer program is provided Medium realizes the side of the simulation air speed data as described above for generating wind power plant when the computer program is executed by processor Method.
In accordance with an alternative illustrative embodiment of the present invention, a kind of computing device is provided, the computing device includes: processing Device;Memory is stored with computer program, when the computer program is executed by processor, realizes as described above generate The method of the simulation air speed data of wind power plant.
The method and device of the simulation air speed data according to an exemplary embodiment of the present invention for generating wind power plant, the mould of generation Between quasi- air speed data and historical wind speed data, either overall distribution situation or wave characteristic are all more approximate, Neng Gouman Sufficient application demand.
Part in following description is illustrated into the other aspect and/or advantage of present general inventive concept, there are also one Dividing will be apparent by description, or can learn by the implementation of present general inventive concept.
Detailed description of the invention
By below with reference to be exemplarily illustrated embodiment attached drawing carry out description, exemplary embodiment of the present it is upper Stating will become apparent with other purposes and feature, in which:
Fig. 1 shows the example of the curve of actual wind speed data;
Fig. 2 shows the examples of the curve of the random air speed data generated according to the prior art;
Fig. 3 shows the process of the method for the simulation air speed data according to an exemplary embodiment of the present invention for generating wind power plant Figure;
Fig. 4 shows the method for the difference profile situation of statistical history air speed data according to an exemplary embodiment of the present invention Flow chart;
Fig. 5 shows the histogram of the difference profile situation of different wind speed sections according to an exemplary embodiment of the present invention;
Fig. 6 shows the flow chart of the method according to an exemplary embodiment of the present invention for generating random air speed data;
Fig. 7 shows the example of the curve of historical wind speed data;
Fig. 8 shows the example of the curve of the random air speed data of an exemplary embodiment of the present invention generation;
Fig. 9 shows the block diagram of the device of the simulation air speed data according to an exemplary embodiment of the present invention for generating wind power plant.
Specific embodiment
It reference will now be made in detail the embodiment of the present invention, examples of the embodiments are shown in the accompanying drawings, wherein identical mark Number identical component is referred to always.It will illustrate the embodiment, by referring to accompanying drawing below to explain the present invention.
Fig. 3 shows the process of the method for the simulation air speed data according to an exemplary embodiment of the present invention for generating wind power plant Figure.Here, the wind power plant is the wind power plant for needing to generate simulation air speed data, hereinafter referred to as current wind power plant.
The historical wind speed data in the special time period of specific wind power plant is obtained in step S10 referring to Fig. 3.
Here, the historical wind speed data includes: the historical wind speed value at each time point in the special time period.As Example, historical wind speed value can be the actually detected air speed value arrived.
It should be understood that being spaced predetermined time interval between adjacent time point in the special time period.As an example, institute Stating predetermined time interval can be 15 minutes.
As an example, the specific wind power plant can for current wind power plant, the neighbouring wind power plant of current wind power plant and with work as One of similar wind power plant of the wind speed characteristics of preceding wind power plant.
In step S20, the difference profile situation of the historical wind speed data is counted.Here, the historical wind speed data Difference profile situation indicates the distribution situation of the difference value between the historical wind speed value of adjacent time point.
In the following, the method that the difference profile situation for counting the historical wind speed data will be described in detail in conjunction with Fig. 4 and Fig. 5 Exemplary embodiment.
In step S30, it is based on the historical wind speed data, generates the difference profile situation for meeting the historical wind speed data Random air speed data.Here, the random wind speed data packet includes: the random wind speed at each time point in the special time period Value.
In the following, by the random of the difference profile situation for meeting the historical wind speed data is generated in conjunction with Fig. 6 to be described in detail The exemplary embodiment of the method for air speed data.
In step S40, using the random air speed data of generation as the simulation in the special time period of current wind power plant Air speed data.Between the simulation air speed data generated according to example embodiment of the present invention and the historical wind speed data, in institute The overall distribution situation stated in designated time period is approximate, and the wave characteristic in the designated time period is also approximate.
As an example, can be directly using the random air speed data of generation as in the special time period of current wind power plant Simulate air speed data.
As another example, overall distribution situation of the statistics available historical wind speed data in the special time period, And count overall distribution situation of the random air speed data of generation in the special time period;Then, the history wind can be worked as When difference between the overall distribution situation of fast data and the overall distribution situation of the random air speed data meets preset condition, Using the random air speed data as the simulation air speed data in the special time period of current wind power plant.
Further, as an example, overall distribution situation of the historical wind speed data in the special time period can It include: Weibull distribution (Weibull distribution) feelings of the historical wind speed data in the special time period Condition;Overall distribution situation of the random air speed data in the special time period can include: the random air speed data exists Weibull distribution situation in the special time period.
From the point of view of probability theory and angle of statistics, Weibull distribution is successional probability distribution, and probability density f can be such as Shown in following formula:
Wherein, x is stochastic variable, and λ is scale parameter (scale parameter), and k is form parameter (shape Parameter), wherein λ > 0, k > 0.
For example, when the Weibull distribution parameters λ of the historical wind speed data and the Weibull point of the random air speed data Difference between cloth parameter lambda is less than the first preset threshold, also, the Weibull distribution parameters k of the historical wind speed data and institute It, can be by the random wind speed when stating the difference between the Weibull distribution parameters k of random air speed data less than the second preset threshold Data are as the simulation air speed data in the special time period of current wind power plant.
In addition, the historical wind speed data and the random air speed data can also be measured by other distribution statistical parameters Overall distribution situation in the special time period.For example, the distribution statistical parameters may include among following item at least One: average value, variance, standard deviation.
Fig. 4 shows the method for the difference profile situation of statistical history air speed data according to an exemplary embodiment of the present invention Flow chart.Here, the method can be performed when executing step S20.
In step S201, the air speed value range of the historical wind speed data is divided into multiple wind speed sections at a predetermined interval.
As an example, the predetermined space can be 1 meter per second or 0.5 meter per second.For example, when the predetermined space is 1m/s When, the air speed value range of the historical wind speed data is segmented using 1 meter per second as step-length, for example, dividing are as follows: [0,1), [1, 2), [2,3) etc. multiple wind speed sections.
In step S202, wind speed section belonging to the historical wind speed value at each time point is determined.
In step S203, the difference profile situation of each wind speed section is counted respectively.Here, the difference profile of the wind speed section Situation indicates the difference between the historical wind speed value of the future time point of historical wind speed value and the historical wind speed value in the wind speed section The distribution situation of score value.Here, the difference between the historical wind speed value of the future time of historical wind speed value and historical wind speed value point Score value may is that the historical wind speed value of the future time point of the historical wind speed value subtracts the obtained difference of historical wind speed value.
As an example, each wind speed section can be directed to, following steps are executed respectively to obtain the difference profile of each wind speed section Situation: the difference between the historical wind speed value in the wind speed section and the historical wind speed value of the future time point of the historical wind speed value is counted Score value falls in the probability distribution in each difference section;The probability distribution of the difference value of the wind speed section of statistics is converted into the wind speed section Difference value cumulative probability distribution.Here, it should be appreciated that the length of each difference section is identical.
Fig. 5 shows the histogram of the difference profile situation of different wind speed sections according to an exemplary embodiment of the present invention.Such as Fig. 5 Shown, x-axis indicates that the historical wind speed value of each data point, y-axis indicate the historical wind speed value of the future time point of each data point Difference between the historical wind speed value of the data point, z-axis indicate the quantity of the data point in each distributed areas, that is, often The quantity for the data point in region that a wind speed section and each difference section are formed.
Fig. 6 shows the difference profile situation according to an exemplary embodiment of the present invention for generating and meeting the historical wind speed data Random air speed data method flow chart.Here, the method can be performed when executing step S30, can be for described Each time point in special time period executes the random wind speed that step S301 generates each time point to step S303 respectively Value.
In step S301, wind speed section belonging to the historical wind speed value at a upper time point at the time point was determined.
In step S302, the random difference score value for meeting the difference profile situation of determining wind speed section is generated.
As an example, when the cumulative probability distribution situation for the difference value that the difference profile situation of wind speed section is wind speed section, Step S302 can comprise the following steps that generating one is more than or equal to 0 and the uniform random number less than or equal to 1;Then, it is determined that generating Uniform random number corresponding to step S301 determine wind speed section difference value cumulative probability distribution probability interval;It connects Get off, a difference value is generated as random difference score value based on difference section corresponding to determining probability interval.
As an example, can using the corresponding difference value of an endpoint of difference section corresponding to determining probability interval as with Machine difference value;Alternatively, can be by the median of difference section corresponding to determining probability interval (that is, the corresponding difference of two endpoints The mean value of value) it is used as random difference score value.In addition, as an example, one can also be generated at random, to belong to determining probability interval institute right The value for the difference section answered is as random difference score value.
In step S303, the historical wind speed value at a upper time point at the time point and the random difference score value of generation were superimposed, To obtain the random air speed value at the time point.
For example, when the historical wind speed value at the upper time point sometime put in the special time period is 5m/s, In step S301, determine wind speed section belonging to 5m/s be [5,6) this wind speed section, for example, if there is 4 historical wind speed values belong to [5,6) this wind speed section, wherein the difference value difference between each historical wind speed value and the historical wind speed value of its future time point Are as follows: -0.5,0,0.5,1, then [5,6) this corresponding difference value -0.5 of wind speed section, 0,0.5,1, fall in difference section [- 1,0), [0,1), [1,2) probability distribution are as follows: 0.25,0.5,0.25, correspondingly, [5,6) this corresponding difference value -0.5 of wind speed section, 0,0.5,1, fall in difference section [- 1,0), [0,1), [1,2) cumulative probability distribution are as follows: 0.25,0.75,1, cumulative probability distribution Probability interval be then [0,0.25], (0.25,0.75], (0.75,1], respectively correspond difference section [- 1,0), [0,1), [1,2). Then, it in step S302, generates one and is more than or equal to 0 and the uniform random number less than or equal to 1, for example, if what is generated is uniform Random number is 0.4, since uniform random number 0.4 is greater than 0.25 and less than 0.75, then the corresponding cumulative probability of uniform random number 0.4 The section of distribution be (0.25,0.75], and the corresponding difference in this section be segmented into [0,1), therefore, can based on difference section [0,1) A difference value is generated as random difference score value, for example, can by difference section [0,1) left end point 0m/s as stochastic difference Value.Next, in step S303, by the random difference score value of the historical wind speed value 5m/s at a upper time point at the time point and generation 0m/s superposition, then the random air speed value for obtaining the time point is 5m/s.
The method that Fig. 8 shows the simulation air speed data according to an exemplary embodiment of the present invention for generating wind power plant is based on Fig. 7 Shown in historical wind speed data random air speed data generated curve, it can be seen that the overall distribution situation of the two is more It is approximate, wherein the Weibull distribution parameters λ of the historical wind speed data shown in Fig. 7 is 8.2033, k 1.7307;Shown in Fig. 8 The Weibull distribution parameters λ of random air speed data is 8.6814, k 2.0676, the difference between the Weibull distribution parameters of the two Value is smaller, within an acceptable range.Also, the wave characteristic of the two is more approximate, and the random air speed data of generation has certain Fluctuation, and in a short time have comparable continuity.
Fig. 9 shows the block diagram of the device of the simulation air speed data according to an exemplary embodiment of the present invention for generating wind power plant. As shown in figure 9, the device of the simulation air speed data according to an exemplary embodiment of the present invention for generating wind power plant includes: historical wind speed Data capture unit 10, difference profile statistic unit 20, random wind speed data generating unit 30 and simulation air speed data determine single Member 40.
Particularly, historical wind speed data acquiring unit 10 is configured as in the special time period for obtaining specific wind power plant Historical wind speed data, wherein the historical wind speed data includes the historical wind speed value at each time point in the special time period.
As an example, the specific wind power plant can for current wind power plant, the neighbouring wind power plant of current wind power plant and with work as One of similar wind power plant of the wind speed characteristics of preceding wind power plant.
Difference profile statistic unit 20 is configured as counting the difference profile situation of the historical wind speed data, wherein institute State the distribution situation of the difference value between the historical wind speed value of the difference profile situation instruction adjacent time point of historical wind speed data.
As an example, difference profile statistic unit 20 is also configured to: by the air speed value model of the historical wind speed data It encloses and is divided into multiple wind speed sections at a predetermined interval;Determine wind speed section belonging to the historical wind speed value at each time point;Statistics is every respectively The difference profile situation of a wind speed section, wherein the difference profile situation of the wind speed section indicates the historical wind speed in the wind speed section The distribution situation of difference value between the historical wind speed value of the future time point of value and the historical wind speed value.
As an example, difference profile statistic unit 20 is also configured to for each wind speed section, following behaviour is executed respectively Make: counting the difference between the historical wind speed value in the wind speed section and the historical wind speed value of the future time point of the historical wind speed value Value falls in the probability distribution in each difference section, wherein the length of each difference section is identical;By the difference value of the wind speed section of statistics Probability distribution is converted to the cumulative probability distribution of the difference value of the wind speed section.
Random wind speed data generating unit 30 is configured as based on the historical wind speed data, and generation meets the history wind The random air speed data of the difference profile situation of fast data, wherein the random wind speed data packet includes in the special time period Each time point random air speed value.
As an example, random wind speed data generating unit 30 is also configured to for each of in the special time period Time point executes following operation respectively: determining wind speed section belonging to the historical wind speed value at a upper time point at the time point;It generates Meet the random difference score value of the difference profile situation of determining wind speed section;By the historical wind speed value at a upper time point at the time point It is superimposed with the random difference score value of generation, to obtain the random air speed value at the time point.
As an example, random wind speed data generating unit 30 is also configured to: generate one more than or equal to 0 and be less than etc. In 1 uniform random number;Determine the cumulative probability point of the difference value of the wind speed section of determination corresponding to the uniform random number generated The probability interval of cloth;A difference value is generated as random difference score value based on difference section corresponding to determining probability interval.
Simulation air speed data determination unit 40 is configured as institute of the random air speed data that will be generated as current wind power plant State the simulation air speed data in special time period.
As an example, simulation air speed data determination unit 40 is also configured to: counting the historical wind speed data in institute State the overall distribution situation in special time period;Count overall distribution of the random air speed data in the special time period Situation;Difference between the overall distribution situation of the historical wind speed data and the overall distribution situation of the random air speed data It is different when meeting preset condition, using the random air speed data as the simulation wind speed in the special time period of current wind power plant Data.
As an example, overall distribution situation of the historical wind speed data in the special time period can include: described Weibull distribution situation of the historical wind speed data in the special time period;The random air speed data is in the specific time Overall distribution situation in section can include: Weibull distribution situation of the random air speed data in the special time period.
It should be understood that the device of the simulation air speed data according to an exemplary embodiment of the present invention for generating wind power plant is specific Implementation may be incorporated by reference the related specific implementation that Fig. 3 to Fig. 8 is described to realize, details are not described herein.
The computer readable storage medium for being stored with computer program of an exemplary embodiment of the present invention, when described The simulation air speed data of generation wind power plant described in the above exemplary embodiments is realized when computer program is executed by processor Method.
The computing device of an exemplary embodiment of the present invention includes: that processor (not shown) and memory (do not show Out), wherein memory is stored with computer program, when the computer program is executed by processor, realizes above-mentioned example The method of the simulation air speed data of generation wind power plant described in embodiment.
The method and device of the simulation air speed data according to an exemplary embodiment of the present invention for generating wind power plant, the mould of generation Between quasi- air speed data and historical wind speed data, either overall distribution situation or wave characteristic are all more approximate, Neng Gouman Sufficient application demand.
Moreover, it should be understood that the device of the simulation air speed data according to an exemplary embodiment of the present invention for generating wind power plant In each unit can be implemented hardware component and/or component software.Those skilled in the art are according to each unit institute of restriction The processing of execution, can such as use site programmable gate array (FPGA) or specific integrated circuit (ASIC) realize each list Member.
In addition, the method for the simulation air speed data according to an exemplary embodiment of the present invention for generating wind power plant can be implemented For the computer code in computer readable recording medium.Those skilled in the art can be according to the description to the above method come real The existing computer code.The above method of the invention is realized when the computer code is performed in a computer.
Although having show and described some exemplary embodiments of the invention, it will be understood by those skilled in the art that It, can be to these in the case where not departing from the principle and spirit of the invention defined by the claims and their equivalents Embodiment is modified.

Claims (18)

1. a kind of method for the simulation air speed data for generating wind power plant, which is characterized in that the described method includes:
Obtain the historical wind speed data in the special time period of specific wind power plant, wherein the historical wind speed data includes described The historical wind speed value at each time point in special time period;
Count the difference profile situation of the historical wind speed data, wherein the difference profile situation of the historical wind speed data refers to Show the distribution situation of the difference value between the historical wind speed value of adjacent time point;
Based on the historical wind speed data, the random wind speed number for meeting the difference profile situation of the historical wind speed data is generated According to, wherein the random wind speed data packet includes the random air speed value at each time point in the special time period;
Using the random air speed data of generation as the simulation air speed data in the special time period of current wind power plant.
2. the method according to claim 1, wherein counting the difference profile situation of the historical wind speed data Step includes:
The air speed value range of the historical wind speed data is divided into multiple wind speed sections at a predetermined interval;
Determine wind speed section belonging to the historical wind speed value at each time point;
The difference profile situation of each wind speed section is counted respectively, wherein the difference profile situation of the wind speed section indicates the wind speed The distribution situation of difference value between the historical wind speed value of the future time point of historical wind speed value and the historical wind speed value in section.
3. according to the method described in claim 2, generation meets described go through it is characterized in that, being based on the historical wind speed data When the step of random air speed data of the difference profile situation of history air speed data includes: for each in the special time period Between point, execute following steps respectively:
Determined wind speed section belonging to the historical wind speed value at a upper time point at the time point;
Generate the random difference score value for meeting the difference profile situation of determining wind speed section;
The historical wind speed value at a upper time point at the time point and the random difference score value of generation were superimposed, to obtain the time point Random air speed value.
4. according to the method described in claim 3, it is characterized in that, counting the step of the difference profile situation of each wind speed section respectively Suddenly include: to execute following steps respectively for each wind speed section:
Count the difference between the historical wind speed value in the wind speed section and the historical wind speed value of the future time point of the historical wind speed value Score value falls in the probability distribution in each difference section, wherein the length of each difference section is identical;
The probability distribution of the difference value of the wind speed section of statistics is converted to the cumulative probability distribution of the difference value of the wind speed section.
5. according to the method described in claim 4, it is characterized in that, generating the difference profile situation for meeting determining wind speed section The step of random difference score value includes:
It generates one and is more than or equal to 0 and the uniform random number less than or equal to 1;
Determine the probability interval of the cumulative probability distribution of the difference value of the wind speed section of determination corresponding to the uniform random number generated;
A difference value is generated as random difference score value based on difference section corresponding to determining probability interval.
6. the method according to claim 1, wherein the specific wind power plant is current wind power plant, current wind-powered electricity generation One of neighbouring wind power plant and wind power plant similar with the wind speed characteristics of current wind power plant of field.
7. the method according to claim 1, wherein using the random air speed data of generation as current wind power plant The step of simulation air speed data in the special time period includes:
Count overall distribution situation of the historical wind speed data in the special time period;
Count overall distribution situation of the random air speed data in the special time period;
Difference between the overall distribution situation of the historical wind speed data and the overall distribution situation of the random air speed data It is different when meeting preset condition, using the random air speed data as the simulation wind speed in the special time period of current wind power plant Data.
8. the method according to the description of claim 7 is characterized in that
Overall distribution situation of the historical wind speed data in the special time period includes: the historical wind speed data in institute State the Weibull distribution situation in special time period;
Overall distribution situation of the random air speed data in the special time period includes: the random air speed data in institute State the Weibull distribution situation in special time period.
9. a kind of device for the simulation air speed data for generating wind power plant, which is characterized in that described device includes:
Historical wind speed data acquiring unit is configured as obtaining the historical wind speed data in the special time period of specific wind power plant, Wherein, the historical wind speed data includes the historical wind speed value at each time point in the special time period;
Difference profile statistic unit is configured as counting the difference profile situation of the historical wind speed data, wherein the history The distribution situation of difference value between the historical wind speed value of the difference profile situation instruction adjacent time point of air speed data;
Random wind speed data generating unit is configured as based on the historical wind speed data, and generation meets the historical wind speed number According to difference profile situation random air speed data, wherein the random wind speed data packet includes each in the special time period The random air speed value at time point;
Air speed data determination unit is simulated, the random air speed data for being configured as to generate is as the described specific of current wind power plant Simulation air speed data in period.
10. device according to claim 9, which is characterized in that difference profile statistic unit is also configured to
The air speed value range of the historical wind speed data is divided into multiple wind speed sections at a predetermined interval;
Determine wind speed section belonging to the historical wind speed value at each time point;
The difference profile situation of each wind speed section is counted respectively, wherein the difference profile situation of the wind speed section indicates the wind speed The distribution situation of difference value between the historical wind speed value of the future time point of historical wind speed value and the historical wind speed value in section.
11. device according to claim 10, which is characterized in that random wind speed data generating unit is additionally configured to be directed to Each time point in the special time period executes following operation respectively:
Determined wind speed section belonging to the historical wind speed value at a upper time point at the time point;
Generate the random difference score value for meeting the difference profile situation of determining wind speed section;
The historical wind speed value at a upper time point at the time point and the random difference score value of generation were superimposed, to obtain the time point Random air speed value.
12. device according to claim 11, which is characterized in that difference profile statistic unit is additionally configured to for each Wind speed section executes following operation respectively:
Count the difference between the historical wind speed value in the wind speed section and the historical wind speed value of the future time point of the historical wind speed value Score value falls in the probability distribution in each difference section, wherein the length of each difference section is identical;
The probability distribution of the difference value of the wind speed section of statistics is converted to the cumulative probability distribution of the difference value of the wind speed section.
13. device according to claim 12, which is characterized in that random wind speed data generating unit is also configured to
It generates one and is more than or equal to 0 and the uniform random number less than or equal to 1;
Determine the probability interval of the cumulative probability distribution of the difference value of the wind speed section of determination corresponding to the uniform random number generated;
A difference value is generated as random difference score value based on difference section corresponding to determining probability interval.
14. device according to claim 9, which is characterized in that the specific wind power plant is current wind power plant, current wind-powered electricity generation One of neighbouring wind power plant and wind power plant similar with the wind speed characteristics of current wind power plant of field.
15. device according to claim 9, which is characterized in that simulation air speed data determination unit is also configured to
Count overall distribution situation of the historical wind speed data in the special time period;
Count overall distribution situation of the random air speed data in the special time period;
Difference between the overall distribution situation of the historical wind speed data and the overall distribution situation of the random air speed data It is different when meeting preset condition, using the random air speed data as the simulation wind speed in the special time period of current wind power plant Data.
16. device according to claim 15, which is characterized in that
Overall distribution situation of the historical wind speed data in the special time period includes: the historical wind speed data in institute State the Weibull distribution situation in special time period;
Overall distribution situation of the random air speed data in the special time period includes: the random air speed data in institute State the Weibull distribution situation in special time period.
17. a kind of computer readable storage medium for being stored with computer program, which is characterized in that when the computer program quilt The side of the simulation air speed data of the generation wind power plant as described in any one in claim 1 to 8 is realized when processor executes Method.
18. a kind of computing device, which is characterized in that the computing device includes:
Processor;
Memory is stored with computer program, when the computer program is executed by processor, realizes such as claim 1 to 8 In any one described in generation wind power plant simulation air speed data method.
CN201711401828.8A 2017-12-22 2017-12-22 Method and device for generating simulated wind speed data of wind power plant Active CN109960818B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711401828.8A CN109960818B (en) 2017-12-22 2017-12-22 Method and device for generating simulated wind speed data of wind power plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711401828.8A CN109960818B (en) 2017-12-22 2017-12-22 Method and device for generating simulated wind speed data of wind power plant

Publications (2)

Publication Number Publication Date
CN109960818A true CN109960818A (en) 2019-07-02
CN109960818B CN109960818B (en) 2023-06-20

Family

ID=67019039

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711401828.8A Active CN109960818B (en) 2017-12-22 2017-12-22 Method and device for generating simulated wind speed data of wind power plant

Country Status (1)

Country Link
CN (1) CN109960818B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110717277A (en) * 2019-10-14 2020-01-21 河北工业大学 Time sequence wind speed simulation method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140344209A1 (en) * 2010-08-23 2014-11-20 Institute Of Nuclear Energy Research, Atomic Energy Council, Executive Yuan Wind energy forecasting method with extreme wind speed prediction function
CN104794325A (en) * 2015-03-10 2015-07-22 国家电网公司 Colony wind power plant output timing sequence simulation method based on random difference equation
CN106251242A (en) * 2016-08-08 2016-12-21 东南大学 A kind of wind power output interval combinations Forecasting Methodology
CN106407627A (en) * 2016-11-23 2017-02-15 西南石油大学 Wind speed probability distribution modeling method and system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140344209A1 (en) * 2010-08-23 2014-11-20 Institute Of Nuclear Energy Research, Atomic Energy Council, Executive Yuan Wind energy forecasting method with extreme wind speed prediction function
CN104794325A (en) * 2015-03-10 2015-07-22 国家电网公司 Colony wind power plant output timing sequence simulation method based on random difference equation
CN106251242A (en) * 2016-08-08 2016-12-21 东南大学 A kind of wind power output interval combinations Forecasting Methodology
CN106407627A (en) * 2016-11-23 2017-02-15 西南石油大学 Wind speed probability distribution modeling method and system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110717277A (en) * 2019-10-14 2020-01-21 河北工业大学 Time sequence wind speed simulation method

Also Published As

Publication number Publication date
CN109960818B (en) 2023-06-20

Similar Documents

Publication Publication Date Title
Zhao et al. Data-driven correction approach to refine power curve of wind farm under wind curtailment
Kaveh et al. Damage detection based on MCSS and PSO using modal data
CN103424654B (en) A kind of appraisal procedure of voltage dip sensitivity of sensitive equipment
CN111427750B (en) GPU power consumption estimation method, system and medium of computer platform
US8086640B2 (en) System and method for improving data coverage in modeling systems
KR102109493B1 (en) Method for building fatigue load models for wind turbine
CN104901823A (en) Method and device for generating alarm threshold value, and method and device for monitoring service performance index
CN108204341B (en) method and device for identifying operating state of wind power plant
CN105843733B (en) A kind of method for testing performance and device of big data platform
JP2016539333A (en) Target positioning method and system
Rybacki et al. Experiments with single core, multi-core, and GPU based computation of cellular automata
CN102982250A (en) Stochastic model modification method based on uncertainty of stochastic response surface estimated parameter
CN103885867A (en) Online evaluation method of performance of analog circuit
Fu et al. CPS information security risk evaluation system based on Petri net
CN112365044A (en) Tunnel face failure probability prediction method based on k nearest neighbor algorithm and support vector machine
CN109960818A (en) Generate the method and device of the simulation air speed data of wind power plant
CN112199850B (en) Method for researching system elastic distribution rule based on process characteristics
CN109299531A (en) Electromagnetical transient emulation method and device
CN110413622A (en) A kind of data processing method based on electric power big data platform
CN111488649B (en) Nonparametric estimation method for load distribution of parts of combine harvester
Yan et al. The research on fault restoration considering distributed generation based particle swarm optimization
CN109377510B (en) Particle tracking method and system on supercomputing cluster
JP4977193B2 (en) A method for searching the nearest value of a search point from an arbitrary group of real numbers
CN108073502B (en) Test method and system thereof
CN111382479A (en) Method and apparatus for estimating weight of casting

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20190717

Address after: Room 209, 2nd floor, No. 1 Building, 19 Kangding Street, Beijing Economic and Technological Development Zone, 100176

Applicant after: BEIJING GOLDWIND SMART ENERGY SERVICE Co.,Ltd.

Applicant after: Jiangsu Jinfeng Software Technology Co.,Ltd.

Address before: Room 209, 2nd floor, No. 1 Building, 19 Kangding Street, Beijing Economic and Technological Development Zone, Daxing District, Beijing, 100176

Applicant before: BEIJING GOLDWIND SMART ENERGY SERVICE Co.,Ltd.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant