CN109944260A - Counter-slope system and its excavation method are protected close to existing railway high slope active network - Google Patents

Counter-slope system and its excavation method are protected close to existing railway high slope active network Download PDF

Info

Publication number
CN109944260A
CN109944260A CN201910372571.0A CN201910372571A CN109944260A CN 109944260 A CN109944260 A CN 109944260A CN 201910372571 A CN201910372571 A CN 201910372571A CN 109944260 A CN109944260 A CN 109944260A
Authority
CN
China
Prior art keywords
slope
rope
sns
counter
side slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910372571.0A
Other languages
Chinese (zh)
Inventor
江真
李晓倩
华祥瑞
杨翔
王淼
李丽萍
余红卫
颜立
张庆明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHONGQING JIANGONG MUNICIPAL TRANSPORTATION PROJECT Co Ltd
Chongqing Construction Engineering Group Co Ltd
Original Assignee
CHONGQING JIANGONG MUNICIPAL TRANSPORTATION PROJECT Co Ltd
Chongqing Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHONGQING JIANGONG MUNICIPAL TRANSPORTATION PROJECT Co Ltd, Chongqing Construction Engineering Group Co Ltd filed Critical CHONGQING JIANGONG MUNICIPAL TRANSPORTATION PROJECT Co Ltd
Priority to CN201910372571.0A priority Critical patent/CN109944260A/en
Publication of CN109944260A publication Critical patent/CN109944260A/en
Pending legal-status Critical Current

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The present invention relates to counter-slope system and its excavation method is protected close to existing railway high slope active network, suitable for preventing slope surface Rock Mass Caving close to traffic routes side slope non-explosive excavations such as business railways and constituting the security protection construction work of security threat close to other infrastructure such as construction of structures;SNS Initiative Defence System and passive protection system are combined non-explosion counter-slope digging mode by the engineering method, form a comprehensive protection system, entire side slope is wrapped up using SNS flexible net before slope excavating and being protected, solve threat of the large rock mass avalanche to the infrastructure such as construction composition is closed on, passive protection system measure is recycled, prevents SNS Initiative Defence System " slipping through the net " or high cut slope excavation fritter from implementing Impact Foundation facility.Using counter-slope digging mode, on the inside of first excavation slope, protection band is formed in side slope top of the slope, rock is reduced and enters safety guard net, realize that the secured fashion that counter-slope excavates, construction safety are more preferably guaranteed.

Description

Counter-slope system and its excavation method are protected close to existing railway high slope active network
Technical field
The present invention relates to building safety technical field of construction, and in particular to anti-close to the protection of existing railway high slope active network Slope system and its excavation method, suitable for close to business railway high slope non-explosive excavation prevent slope surface Rock Mass Caving and close to Other infrastructure such as construction of structures constitute the security protection construction work of security threat.
Background technique
As infrastructure construction in china constantly promotes, close to it is existing build, the side slope construction of structures will be more and more, Protect difficulty and security threat also increasing.More especially close to the excavation high slope of existing railway in operation, highway, The gradient is steep, top of the slope slope foot height difference is big, and side slope often has collapse rock-fall disaster during excavation disturbance, to close to traffic route Normal operation bring very big security threat.
The especially Mountainous City as Chongqing, by taking the engineering of Chongqing somewhere as an example, proposed place is located at the Changjiang river west bank Hills location, engineering club, east side, flat field rock excavation region are close to existing Chengdu-Chongqing railway line, and high slope and railway line height difference are about 30 meters, existing slope surface is locally uneven, does not take safeguard procedures, and Weathering Zones of Igneous Rock, danger stone is more, using conventional directly excavation side Formula will constitute safely great threat to existing railway, even if being all difficult to ensure safety using mechanical non-explosive excavation comprehensively.
Summary of the invention
In view of problems of the prior art, the present invention provides a kind of anti-close to the protection of existing railway high slope active network Slope system and its excavation method, SNS flexible protective technology protect slope surface, and not needing can side slope using blasting technique It carries out ending construction, counter-slope face excavation construction engineering method avoids increasing the slope surface load of high slope, is conducive to the stabilization of slope surface, applying Reduce the influence for excavating falling rocks to traffic routes such as railway, highways between duration to the greatest extent, it is ensured that traffic is normally safe.
To realize the above-mentioned technical purpose, The technical solution adopted by the invention is as follows:
One kind protecting counter-slope system close to existing railway high slope active network, and the slope protection system construction includes SNS active Guard system and passive protection system, the SNS Initiative Defence System is mainly by SNS flexible net, cross-brace rope, longitudinal bracing Rope, suture rope and prestressed anchor composition, excavate anchor pole aperture by the arrangement of direction in length and breadth in side slope, prestressed anchor is fixed on In anchor pole aperture, cross-brace rope and longitudinal bracing rope are tied up on prestressed anchor, and SNS flexible net is connected to cross using suture rope To on supporting rope and longitudinal bracing rope, and SNS flexible net is close to side slope surface;Groove, passive protection are excavated in side slope bottom System is set up in the trench, and the passive protection system is mainly made of SNS flexible net column foot, upright bar and gear backplate, in groove Interior horizontally-arranged setting several upright bar spacing hole, upright bar are injected in upright bar spacing hole and are fixed, laterally take between two adjacent upright bars Equipped with gear backplate;The SNS flexible net column foot is fixed on gear backplate avris and its height is higher than the height of gear backplate and upright bar.
The beneficial effect of the design compared with prior art is: due to using SNS Initiative Defence System, side slope slope surface Flexible protective is carried out, it is highly-safe, it can be avoided the slope surface load for increasing side slope, avoid damage to original shape of flaw-piece, increase The stability of slope surface keeps its construction environment safer.Due to using passive protection system, with SNS Initiative Defence System knot It closes, constitutes the stereoscopic protective system of the side slope of traffic route side, be capable of the unstability rock of multiple control slope excavating generation, Effectively control security risk.
A kind of excavation method close to existing railway high slope active network protection counter-slope system, includes the following steps:
(1) survey and construction scene, preliminary surveying understand side slope rocky condition, by crag, orphan close to the side slope area of traffic route Stone etc. marks, and determines that SNS is actively anti-according to the importance of the side slope situation and surrounding enviroment and protection of actually examining wiping Protecting system type;
(2) SNS Initiative Defence System is installed
1. safety rope anchor pole is arranged on side slope top or side slope middle and upper part, safety rope is restrain on safety rope anchor pole,
2. with cement grout anchoring safety rope anchor pole, setting time at least 48 hours;
3. construction personnel clears up country rock in side slope slopes using safety rope, close traffic, lower section personnel are needed before cleaning Safety area should be withdrawn to, if having local bulk crag when cleaning, cannot clear up, should make a mark, in construction in later period, drilling operating It will avoid constructing herein;
4. drilling anchor rod aperture mouth, side slope carries out unwrapping wire and determines anchor pole hole location, and paints paint and determine boring point, then according to side slope The gradient, drilled using hanging basket or double-pole scaffold, drilling anchor rod aperture mouth use diameter phi 45 drill bit, hole depth rate prestressing force 1.0m, 2m, the construction of 2.5 drilling rods need to be respectively adopted in the long 5cm or more of rock-bolt length, and it is heavy on hole wall to clean out after the completion of drilling Quarrel and water body are viscous;
5. prestressed anchor is perfused, first prestressed anchor is put into anchor pole aperture, the exposed lantern ring top of prestressed anchor is not It can be higher by earth surface of side slope, then pour into prepared mortar in anchor pole aperture, perfusion is closely knit, is perfused when making firm by ramming, and anchor is discharged Air in rod aperture mouth at least condenses 48 hours or more after mortar injection, it is curved that wirerope lantern ring is finally hung on anchor pole tail portion On hook;
6. installing cross-brace rope and longitudinal bracing rope, before vertical, horizontal supporting rope blanking installation, every supporting rope two is accurately measured Hold the spacing between prestressed anchor, when vertical, horizontal supporting rope blanking its length should on the basis of measuring every root long degree both ends Each to increase 1m, then vertical, horizontal supporting rope sequentially passes through the exposed lantern ring of prestressed anchor upper end, and vertical, horizontal supporting rope reaches Behind the last one end of prestressed anchor, tail of rope is passed through into last root prestressed anchor, and be bent, with tightening force not less than 5KN's Euphroe or cucurbit tensioning finally fix tail end rope card;
7. linked network sutures, SNS flexible net is tightly attached to side slope surface and is installed, and vertical, horizontal supporting rope is under SNS flexible net Side, carries out suture connection using suture rope between SNS flexible net and vertical, horizontal supporting rope, and suture rope two ends are preferably stacked not small In the length of 0.5m, sutures rope end and two rope cards is respectively used to connect with SNS flexible net, after formerly fixing one end in this connection procedure, Euphroe cucurbit tensioning suture rope with tightening force not less than 5KN, then the fixed other end;
(3) the passive protection system construction in side slope hillside fields
Before construction, first the sundries of Slope bottom earth's surface is understood and flattened, then excavates row's shallow trench, and between one row's upright bar of brill Away from hole, upright bar is injected in upright bar spacing hole and is fixed, and gear backplate is finally transversely mounted between upright bar, and gear backplate height is at least 2m;
(4) side slope first floor counter-slope excavates and the layering of SNS Initiative Defence System is removed and locked, and before slope excavating, divides layering first It excavation height and stays and sets the counter-slope earth-retaining ridge, from top to bottom, sequence excavation slope step by step;
When first layer excavates, first on the inside of excavation slope, it is 3m that every layer, which is excavated general height, stays on the outside of side slope and sets counter-slope earth-retaining The ridge, earth-retaining ridge width are not preferably less than 3m;Then the counter-slope earth-retaining ridge is excavated again, and keeps counter-slope low bank of earth between fields height not less than 1.5m, instead It when earth-retaining stalk in slope excavates, hooks dig from outside to inside, native stone when to excavate rolls to counter-slope outside;When excavating the earth-retaining ridge, release When releasing, end clip is unclamped for the SNS flexible net to match with dug layer, and with the traction vertical, horizontal support of manual Hu reed Rope, gradually unclamps, when vertical, horizontal supporting rope is in nature suspending weight state, releases this layer of SNS flexible net, and carry out the earth-retaining ridge It excavates, it is every to excavate one layer, the above construction is repeated, is completed until excavating;
When counter-slope excavates, part SNS flexible net is removed i.e. vertically and horizontally after supporting rope, remaining side slope outer upper opening portion Vertically and horizontally supporting rope is suitably tightened, and it is actively anti-that rock of the protection low bank of earth between fields in the favorite outer whereabouts of digging process can enter locking SNS It is caught in protecting system;
(5) after slope excavating, SNS Initiative Defence System complete liquidation is appeared on the scene, finally removes passive protection system.
It further limits, the height of the SNS flexible net column foot is higher than upright bar and keeps off the height of backplate, in SNS flexible net Column foot is equipped with cushion towards side slope side on one side.
Above-mentioned elaboration protects counter-slope system and its excavation method close to existing railway high slope active network, anti-in conjunction with side slope Protecting system construction, is excavated from the counter-slope face of side slope, forms protection band in side slope top of the slope, it is no longer necessary to carry out explosion, crag is removed Cleaning is striked to slope excavating protection facility opposite direction using mechanical equipment, reduction rock enters safety and states SNS flexible net, real The secured fashion of existing digging mode, construction safety are more preferably guaranteed.Also, SNS active protecting net system by anchor pole and SNS flexible mesh integrally wraps up scar, small compared to traditional rigid protection measure construction work amount, and module may be implemented Change installation, construction technology is simple;Passive protection net takes upright bar and automobile tire combination, securely and reliably, reduce costs.
It further limits, the SNS flexible net column foot is H profile steel plate, and H profile steel plate stands on the gear backplate away from side slope side Outside, and two upright bars and gear backplate adjacent with H profile steel plate are higher than other upright bars being arranged in groove and gear backplate, In, cushion is suspended on H profile steel plate close to the side of gear backplate using waste tire.
It further limits, is additionally provided with the pull rod for being fixed on side slope bottom on the H profile steel plate, prevents higher-height SNS Flexible net column foot collapses.
It further limits, the anchor pole aperture is anchor pole pit, and the upper plane in anchor pole aperture is lower than side slope upper surface.
It further limits, is additionally provided with buffer trench at Slope bottom.For the impact force for reducing passive protection system, setting buffering Ditch reduces the rock impact energy surprisingly tumbled.
Further limit, anchoring rod: using M30 cement grout anchoring rod, setting time is not less than 48 hours.Cement The selection of slurry, label are not less than the cement of M30, preferably use cement-sand ratio 1:1~1:2, the cement slurry or water of the ratio of mud 0.45~0.50 The neat slurry of gray scale 0.45~0.50, cement preferably use 425 ordinary portland cements, preferential to select partial size no more than in 3mm Fine sand.
It further limits, bore 20cm, the deep 15cm of anchor pole pit, when facilitating SNS flexible net extravagance as far as possible Firmly it is tightly attached to side slope surface.
Detailed description of the invention
Fig. 1 is the schematic diagram of prestressed anchor of the invention and the perfusion installation of anchor pole aperture;
Fig. 2 is SNS Initiative Defence System schematic diagram of the invention;
Fig. 3 is the schematic diagram of slope protection system and layering counter-slope excavation construction process of the invention;
Fig. 4 is the schematic diagram of passive protection system of the invention;
Fig. 5 is the schematic diagram of slope protection system of the invention and first layer counter-slope excavation construction process;
Fig. 6 is the schematic diagram of slope protection system of the invention and first layer counter-slope earth-retaining ridge construction technology;
Fig. 7 is the schematic diagram of slope protection system of the invention and second layer counter-slope excavation construction process;
Fig. 8 is the schematic diagram of slope protection system of the invention and second layer counter-slope earth-retaining ridge construction technology.
Specific embodiment
In order to which those skilled in the art may be better understood, with reference to the accompanying drawings and examples to the technology of the present invention Scheme further illustrates.
As Figure 1-Figure 4 is a kind of actively anti-close to existing railway high slope active network protection counter-slope system, including SNS Protecting system and passive protection system, the SNS Initiative Defence System is mainly by SNS flexible net 2, cross-brace rope 3, longitudinal bracing Rope 4, suture rope 5 and prestressed anchor 6 form, and excavate anchor pole aperture 7 by the arrangement of direction in length and breadth in side slope 1, anchor pole aperture 7 is Anchor pole pit, the bore 20cm of anchor pole pit, the upper plane of deep 15cm, anchor pole aperture 7 are lower than 1 upper surface of side slope, system cloth Often prestressed anchor 6 is arranged using natural indentation position in the flexibility set.Prestressed anchor 6 is fixed in anchor pole aperture 7, horizontal It is tied up on prestressed anchor 6 to supporting rope 3 and longitudinal bracing rope 4, SNS flexible net 2 is connected to cross-brace rope using suture rope 5 3 and longitudinal bracing rope 4 on, and SNS flexible net 2 be close to 1 slope surface of side slope.The main model of SNS flexible net 2 preferentially use GAR1, GAR2, GPS1, GPS2 etc., vertical, horizontal supporting rope are wire rope net or iron wire grid.
Excavate groove in 1 bottom of side slope, passive protection system sets up in the trench, the passive protection system mainly by SNS flexible net column foot 8, upright bar 9 and gear backplate 10 form, and horizontally-arranged setting several upright bar spacing hole, upright bar 9 are injected vertical in the trench It is fixed in distance between tie rods hole, gear backplate 10 is laterally erected between two adjacent upright bars 9, upright bar 9 can use 43kg rail, The long 3m of rail, is embedded to 1m, exposed 2m, and gear backplate 10 can directly utilize railroad tie, save the cost, the high 2m of sleeper, every pillow The long 2.5m of wood, tie joint position set 2 rail, and rail edge is far from sleeper end 30cm;By side slope excavation line side, every rail Place sets 20 reinforced anchor bolt of Φ.The SNS flexible net column foot 8 is fixed on gear 10 avris of backplate and its height is higher than gear 10 He of backplate The height of upright bar 9 is equipped with cushion 81 towards 1 side of side slope in SNS flexible net column foot 8 on one side.The SNS flexible net column foot 8 be H profile steel plate, and H profile steel plate stands on away from 10 outside of gear backplate of 1 side of side slope, is additionally provided on H profile steel plate and is fixed on side slope The pull rod 11 of 1 bottom, and two upright bars 9 and gear backplate 10 adjacent with H profile steel plate are higher than other upright bars 9 being arranged in groove With gear backplate 10, wherein cushion 81 is suspended on H profile steel plate close to the side of gear backplate 10 using waste tire.
A kind of excavation method close to existing railway high slope active network protection counter-slope system as shown in Figure 5-Figure 8, packet Include following steps:
(1) survey and construction scene, preliminary surveying understand 1 rocky condition of side slope, will endanger close to 1 area of side slope of traffic route 12 Rock, boulder etc. mark, and determine SNS according to the importance of the side slope situation and surrounding enviroment and protection of actually examining wiping Initiative Defence System type;For close to business construction of railways, security risk is larger, preferably select the stronger GPS2 of safeguard function anti- Protective net structure, specific type selecting structure list are as follows:
Model Net type Supporting rope Suture rope Primary protection function The scope of application
GAP1(is commonly simple Monotype) Wirerope Net 16 edge Φ (or upper limb) steel 16 side slope of cord anchor pole+Φ (or upper limb) supporting rope 8 steel wire of Φ Rope The effect of going along with sb. to guard him, limits falling rocks motion range, and part inhibits avalanche Occur. The gradient is not suddenly in 1:1, side slope rock Body is complete, no earthing
GAR2(is common Type) Wirerope Net 16 system ropes anchor pole of Φ+ 16 cross-brace rope+Φ 16 of Φ (12) longitudinal bracing rope 8 steel wire of Φ Rope Slope reinforcing inhibits avalanche and weathering off, slips the generation collapsed, Limitation part or a small amount of falling rocks motion range. The gradient is not suddenly in 1:0.75, side Slope rock mass is more complete, has a small amount of Earthing
GPS1(is commonly normal With type) Wirerope Net+steel wire Grid 16 edge Φ (or upper limb) steel 16 side slope of cord anchor pole+Φ (or upper limb) supporting rope 8 steel wire of Φ Rope Falling rocks motion range is limited, part inhibits the generation of avalanche.Have small It is selected when block falling rocks. The gradient is not suddenly in 1:0.5, side slope Rock Mass Integrality is bad, has few Measure earthing
GPS2(is commonly normal With type) Wirerope Net+steel wire Grid 16 system ropes anchor pole of Φ+ 16 cross-brace rope+Φ 16 of Φ (12) longitudinal bracing rope 8 steel wire of Φ Rope Slope reinforcing inhibits avalanche and weathering off, slips the generation collapsed, Limitation part or a small amount of falling rocks motion range, have fritter falling rocks or It is selected when upper matter side slope. Slope rock mass is relatively broken, has small It is selected when block danger stone or soil-slope With
(2) SNS Initiative Defence System is installed
1. safe line anchor is arranged on 1 top of side slope or 1 middle and upper part of side slope for the person and equipment safety that fully ensure that construction personnel Bar (uses 28 reinforced anchor bolts, hole depth 1.5m), spacing distance 5m, restrains safety rope, staff on safety rope anchor pole High-altitude prune job can be carried out using safety rope, and is provided conveniently for drilling installation later;
2. with label M30 cement grout anchoring safety rope anchor pole, setting time at least 48 hours;The selection of cement slurry, label is not Cement lower than M30, using cement-sand ratio 1:1~1.2, the cement mortar of the ratio of mud 0.45~0.50 or the ratio of mud 0.45~0.50 Neat slurry, 425 ordinary portland cements of cement, the preferential medium-fine sand for selecting partial size to be not more than 3mm;
3. after the completion of above several procedures, crag cleaning process can be carried out, construction personnel is using safety rope in 1 slopes of side slope Country rock is cleared up, close traffic is needed before cleaning, lower section personnel should withdraw safety area to, if there is local bulk to endanger when cleaning Rock cannot be cleared up, and should make a mark, and in construction in later period, drilling operating will avoid constructing herein, to prevent the work in construction in later period Journey disturbance causes crag to loosen downslide;
4. drilling anchor rod aperture mouth 7, side slope 1 carries out unwrapping wire and determines anchor pole hole location, usually in length and breadth away from being 4.5m(according to orographic condition, Pitch of holes can have the adjustment amount of 0.3m), and paint paint and determine boring point, within the scope of the adjustment amount that pitch of holes allows, to the greatest extent may be used Anchor pole aperture 7 can be selected in pocket, be close to the bolthole of slope surface as far as possible to non-pocket or after not being able to satisfy system installation Mouth 7(is general, and continuous hanging area is not greater than 5m2, the local anchor pole that length is not less than 2.5m is otherwise preferably added, which can adopt The reinforced anchor bolt with crotch or diameter with diameter not less than φ 16 are not less than the bifilar wire rope anchor of 2 × φ 16), then basis The gradient of side slope 1, is drilled using hanging basket or double-pole scaffold, drill bit of drilling anchor rod aperture mouth 7 using diameter phi 45, hole depth rate The long 5cm or more of prestressed anchor pole length need to be respectively adopted 1.0m, 2m, the construction of 2.5 drilling rods, hole wall is cleaned out after the completion of drilling On heavy quarrel and water body it is viscous, 2.5m drilling rod cannot be directlyed adopt and prevent bit freezing, disconnected bar phenomenon, as bore position is in loose rock Layer, it is necessary to ratify through relevant department, redefine bore position, cannot arbitrarily construct, guarantee that slopes outer drilling depth reaches 2.5m, slopes middle part reach 2m.When being limited by rock drilling equipment, two strands of steel cables for constituting every anchor pole can anchor into two holes respectively In anchor hole of the diameter not less than φ 35, chevron shaped anchor pole is formed, angle is 15~30 ° between two strands of steel cables, to reach same anchoring Effect;
After drilling anchor rod aperture mouth 7 reaches projected depth, it cannot stop to bore immediately, it is desirable that surely bore 1~2 minute, prevent bottom hole pinching, up to not To design aperture.Borehole wall must not have heavy quarrel and water body viscous, it is necessary to clean out, after the completion of drilling, use high pressure sky Gas (0.2~0.4MPa of wind pressure) rock powder in hole and water body are all removed portal it is outer, in order to avoid reduce cement mortar and hole wall ground The adhesion strength of body must not be rinsed in addition to the complete rock anchorage of relative rigid using high pressure water;
5. prestressed anchor 6 is perfused, first prestressed anchor 6 is put into anchor pole aperture 7, the exposed lantern ring top of prestressed anchor 6 End cannot be higher by 1 earth's surface of side slope, then pour into prepared mortar in anchor pole aperture 7.It is perfused closely knit, is perfused when making firm by ramming, The air in anchor pole aperture 7 is discharged, at least condenses 48 hours or more after mortar injection, curing time not up to requires, forbid into Row next process, and ensure that wirerope lantern ring not by external force, is finally hung on prestressed anchor 6 by prestressed anchor 6 On the crotch of tail portion;
6. installing cross-brace rope 3 and longitudinal bracing rope 4, before vertical, horizontal supporting rope blanking installation, every supporting rope is accurately measured Spacing between both ends prestressed anchor 6, its length should be two on the basis of measuring every root long degree when vertical, horizontal supporting rope blanking Each increase 1m is held, i.e., increases 2m altogether, then vertical, horizontal supporting rope sequentially passes through the exposed lantern ring of 6 upper end of prestressed anchor, uses The fixed one end of rope card being adapted with supporting rope diameter, restrict 5~l0mm of card spacing, and rope end stays length not less than 20cm's after fixing Free tail rope, according to bearing length, (supporting rope length is 2 when being less than 10m to rope card quantity, is 4 when being greater than 30m, is therebetween 3 It is a) it is selected;Since one end prestressed anchor 6, supporting rope sequentially passes through the exposed lantern ring of prestressed anchor 6, until the row Last root prestressed anchor 6;After vertical, horizontal supporting rope reaches the last one end of prestressed anchor 6, tail of rope is passed through into last root Prestressed anchor 6, and be bent, the euphroe or cucurbit with tightening force not less than 5KN are tensioned, if length is longer therebetween, because of support Friction between prestressed anchor 6 and ground is big and when cannot be tensioned, can be tensioned paragraph by paragraph, finally by tail end with rope card using with The identical mode in starting point is fixed;
3 length of cross-brace rope should add fixation when being more than no more than 10m no more than 50m, 4 length of longitudinal bracing rope End;
7. linked network sutures, SNS flexible net 2 is tightly attached to 1 slope surface of side slope and is installed, and vertical, horizontal supporting rope is in SNS flexible net 2 Lower section, and hung along support Rope Shop, every two lattice (above and below i.e. or left and right) are laid with two SNS flexible nets 2, take between 2 net block of SNS flexible net Width is connect not less than 10cm;SNS flexible net 2(steel wire grid) it is not less than the iron wire ligation of small 1.2mm, suture between net block with diameter SNS flexible net 2(steel wire grid net) and supporting rope between with small 2.2mm tied silk ligation, ligation point spacing is not more than 1 m, is laid with side SNS flexible net 2(steel wire grid net at boundary) reverse folded width is not less than 20cm;
Suture connection is carried out using suture rope 5 between SNS flexible net 2 and vertical, horizontal supporting rope, suture 5 two ends of rope are preferably stacked Length not less than 0.5m, 5 ends of suture rope respectively use two rope cards to connect with SNS flexible net 2, formerly fix one in this connection procedure Behind end, the euphroe cucurbit tensioning suture with tightening force not less than 5KN is restricted, then the fixed other end;If it is determined that single suture rope 5 When error is larger, then extra end may extend into adjacent linked network unit, be mended without foot length degree by the suture rope of next adjacent linked network It fills.
(3) the passive protection system construction in side slope hillside fields
Before construction, first the sundries of 1 bottom of slope earth's surface of side slope is understood and flattened, then excavates row's shallow trench, and bore row's upright bar 9 Spacing hole, upright bar 9 are injected in upright bar spacing hole and are fixed, and gear backplate 10,10 height of gear backplate are finally transversely mounted between upright bar 9 At least 2m;
In order to reduce the impact force of passive protection system, buffer trench is additionally provided in 1 bottom of slope of side slope.Slope foot buffer trench can be according to tool The setting of body situation can be set to the left and right deeply 1m wide+0.8m when conditions permit.It, can be with when condition is restricted It is filled in slope foot and rolls oblique 30 ° or more of counter-slope to side slope 1.
(4) 1 first floor counter-slope of side slope excavates and the layering of SNS Initiative Defence System is removed and locked, and before slope excavating, divides first It layering 1-1 excavation height and stays and sets counter-slope 1-2 and counter-slope earth-retaining ridge 1-3, from top to bottom, sequence excavation slope step by step;
When first layer is layered 1-1 excavation, first on the inside of excavation slope, it is 3m that every layer, which is excavated general height, stays and sets on the outside of side slope Counter-slope earth-retaining ridge 1-3, earth-retaining ridge 1-3 width are not preferably less than 3m;Then counter-slope earth-retaining ridge 1-3 is excavated again, and keeps counter-slope earth-retaining Ridge 1-3 height is not less than 1.5m, when counter-slope earth-retaining is obstructed 1-3 and excavated, hooks dig from outside to inside, and native stone when to excavate is to counter-slope 1- 2 outside rollings;When excavating the earth-retaining ridge, the SNS flexible net 2 to match with dug layer is released, when releasing, end clip is unclamped, And vertical, horizontal supporting rope is drawn with manual Hu reed, it gradually unclamps, when vertical, horizontal supporting rope is in nature suspending weight state, releases This layer of SNS flexible net 2, and earth-retaining ridge 1-3 excavation is carried out, it is every to excavate one layer, the above construction is repeated, is completed until excavating;
Machinery from top to bottom successively should excavate when cutting the earth, forbid rock steathily or cut the earth under boulder, and night should have sufficient illumination. In side slope operation, the change conditions of side slope 1 should be paid attention at any time, as discovery has large area image crack phenomenon, it is necessary to which pause is applied Work, while being contacted with railway department, it passes through again after eliminating danger;
When counter-slope 1-2 is excavated, after removing part SNS flexible net 3 and vertical, horizontal supporting rope, remaining 1 outer upper of side slope opening Partial vertical, horizontal supporting rope is suitably tightened, and rock of the protection low bank of earth between fields in the favorite outer whereabouts of digging process can enter locking SNS It is caught in Initiative Defence System;
When 1 operation of side slope, it is necessary to wear a safety helmet, prevent that soil block above and other objects fall and injure head by a crashing object, meet underground water infiltration When out, water should be guided to sump and be excluded, side slope linked network tears net construction open and must fasten seat belts.
(5) after side slope 1 is excavated, SNS Initiative Defence System complete liquidation is appeared on the scene, finally tears passive protection system open It removes.
The technological principle of this engineering method is: SNS Initiative Defence System and passive protection system are excavated in conjunction with non-explosion counter-slope Mode forms a comprehensive protection system, and the side slope 1 being introduced into close to construction is excavated in protection works, especially high slope Engineering, highly-safe, simple process.Entire side slope 1 is wrapped up using SNS flexible net 2 before side slope 1 is excavated and being protected, is solved big Threat of the block rock failure to the infrastructure such as construction composition is closed on, recycles passive protection system measure, prevents SNS actively Guard system " slipping through the net " or high cut slope excavation fritter implement Impact Foundation facility.It is excavated in 1 digging process of side slope using counter-slope 1-2 Mode that is, first on the inside of excavation slope 1, forms protection band in 1 top of the slope of side slope, crag, which is removed, to be opened using mechanical equipment to side slope 1 It digs protection facility opposite direction and strikes cleaning, reduce rock and enter safety guard net, realize the secured fashion of digging mode, construct Safety is more preferably guaranteed.
Above to provided by the invention a kind of close to existing railway high slope active network protection counter-slope system and its excavation side Method is described in detail, and the explanation of specific embodiment is merely used to help understand method and its core concept of the invention.It answers It, for those skilled in the art, without departing from the principle of the present invention, can also be to this when pointing out Some improvement and modification can also be carried out for invention, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.

Claims (9)

1. counter-slope system, including SNS Initiative Defence System and passive protection system are protected close to existing railway high slope active network, It is characterized by:
The SNS Initiative Defence System is mainly by SNS flexible net, cross-brace rope, longitudinal bracing rope, suture rope and prestressed anchor Bar composition excavates anchor pole aperture by the arrangement of direction in length and breadth in side slope, and prestressed anchor is fixed in anchor pole aperture, cross-brace Rope and longitudinal bracing rope tie up on prestressed anchor, and SNS flexible net is connected to cross-brace rope and longitudinal bracing using suture rope On rope, and SNS flexible net is close to side slope surface;
Groove is excavated in side slope bottom, passive protection system is set up in the trench, and the passive protection system is mainly by SNS flexibility Net column foot, upright bar and gear backplate composition, horizontally-arranged setting several upright bar spacing hole, upright bar are injected solid in upright bar spacing hole in the trench It is fixed, gear backplate is laterally erected between two adjacent upright bars;The SNS flexible net column foot be fixed on gear backplate avris and Its height is higher than the height of gear backplate and upright bar.
2. as described in claim 1 close to the excavation method of existing railway high slope active network protection counter-slope system, feature It is: includes the following steps:
(1) survey and construction scene, preliminary surveying understand side slope rocky condition, by crag, orphan close to the side slope area of traffic route Stone etc. marks, and determines that SNS is actively anti-according to the importance of the side slope situation and surrounding enviroment and protection of actually examining wiping Protecting system type;
(2) SNS Initiative Defence System is installed
1. safety rope anchor pole is arranged on side slope top or side slope middle and upper part, safety rope is restrain on safety rope anchor pole,
2. with cement grout anchoring safety rope anchor pole, setting time at least 48 hours;
3. construction personnel clears up country rock in side slope slopes using safety rope, close traffic, lower section personnel are needed before cleaning Safety area should be withdrawn to, if having local bulk crag when cleaning, cannot clear up, should make a mark, in construction in later period, drilling operating It will avoid constructing herein;
4. drilling anchor rod aperture mouth, side slope carries out unwrapping wire and determines anchor pole hole location, and paints paint and determine boring point, then according to side slope The gradient, drilled using hanging basket or double-pole scaffold, drilling anchor rod aperture mouth use diameter phi 45 drill bit, hole depth rate prestressing force 1.0m, 2m, the construction of 2.5 drilling rods need to be respectively adopted in the long 5cm or more of rock-bolt length, and it is heavy on hole wall to clean out after the completion of drilling Quarrel and water body are viscous;
5. prestressed anchor is perfused, first prestressed anchor is put into anchor pole aperture, the exposed lantern ring top of prestressed anchor is not It can be higher by earth surface of side slope, then pour into prepared mortar in anchor pole aperture, perfusion is closely knit, is perfused when making firm by ramming, and anchor is discharged Air in rod aperture mouth at least condenses 48 hours or more after mortar injection, it is curved that wirerope lantern ring is finally hung on anchor pole tail portion On hook;
6. installing cross-brace rope and longitudinal bracing rope, before vertical, horizontal supporting rope blanking installation, every supporting rope two is accurately measured Hold the spacing between prestressed anchor, when vertical, horizontal supporting rope blanking its length should on the basis of measuring every root long degree both ends Each to increase 1m, then vertical, horizontal supporting rope sequentially passes through the exposed lantern ring of prestressed anchor upper end, and vertical, horizontal supporting rope reaches Behind the last one end of prestressed anchor, tail of rope is passed through into last root prestressed anchor, and be bent, with tightening force not less than 5KN's Euphroe or cucurbit tensioning finally fix tail end rope card;
7. linked network sutures, SNS flexible net is tightly attached to side slope surface and is installed, and vertical, horizontal supporting rope is under SNS flexible net Side, carries out suture connection using suture rope between SNS flexible net and vertical, horizontal supporting rope, and suture rope two ends are preferably stacked not small In the length of 0.5m, sutures rope end and two rope cards is respectively used to connect with SNS flexible net, after formerly fixing one end in this connection procedure, Euphroe cucurbit tensioning suture rope with tightening force not less than 5KN, then the fixed other end;
(3) the passive protection system construction in side slope hillside fields
Before construction, first the sundries of Slope bottom earth's surface is understood and flattened, then excavates row's shallow trench, and between one row's upright bar of brill Away from hole, upright bar is injected in upright bar spacing hole and is fixed, and gear backplate is finally transversely mounted between upright bar, and gear backplate height is at least 2m;
(4) side slope first floor counter-slope excavates and the layering of SNS Initiative Defence System is removed and locked, and before slope excavating, divides layering first It excavation height and stays and sets the counter-slope earth-retaining ridge, from top to bottom, sequence excavation slope step by step;
When first layer excavates, first on the inside of excavation slope, it is 3m that every layer, which is excavated general height, stays on the outside of side slope and sets counter-slope earth-retaining The ridge, earth-retaining ridge width are not preferably less than 3m;Then the counter-slope earth-retaining ridge is excavated again, and keeps counter-slope low bank of earth between fields height not less than 1.5m, instead It when earth-retaining stalk in slope excavates, hooks dig from outside to inside, native stone when to excavate rolls to counter-slope outside;When excavating the earth-retaining ridge, release When releasing, end clip is unclamped for the SNS flexible net to match with dug layer, and with the traction vertical, horizontal support of manual Hu reed Rope, gradually unclamps, when vertical, horizontal supporting rope is in nature suspending weight state, releases this layer of SNS flexible net, and carry out the earth-retaining ridge It excavates, it is every to excavate one layer, the above construction is repeated, is completed until excavating;
When counter-slope excavates, part SNS flexible net is removed i.e. vertically and horizontally after supporting rope, remaining side slope outer upper opening portion Vertically and horizontally supporting rope is suitably tightened, and it is actively anti-that rock of the protection low bank of earth between fields in the favorite outer whereabouts of digging process can enter locking SNS It is caught in protecting system;
(5) after slope excavating, SNS Initiative Defence System complete liquidation is appeared on the scene, finally removes passive protection system.
3. according to claim 1 protect counter-slope system close to existing railway high slope active network, it is characterised in that: described The height of SNS flexible net column foot is higher than upright bar and keeps off the height of backplate, in SNS flexible net column foot towards the installation on one side of side slope side There is cushion.
4. according to claim 3 protect counter-slope system close to existing railway high slope active network, it is characterised in that: described SNS flexible net column foot is H profile steel plate, and H profile steel plate is stood on the outside of the gear backplate of side slope side, and adjacent with H profile steel plate Two upright bars and gear backplate be higher than other upright bars being arranged in groove and gear backplate, wherein cushion is outstanding using waste tire H profile steel plate is hung over close to the side of gear backplate.
5. according to claim 4 protect counter-slope system close to existing railway high slope active network, it is characterised in that: described The pull rod for being fixed on side slope bottom is additionally provided on H profile steel plate.
6. according to claim 1 protect counter-slope system close to existing railway high slope active network, it is characterised in that: described Anchor pole aperture is anchor pole pit, and the upper plane in anchor pole aperture is lower than side slope upper surface.
7. according to claim 5 or 6 protect counter-slope system close to existing railway high slope active network, it is characterised in that: Buffer trench is additionally provided at Slope bottom.
8. the excavation method according to claim 2 close to existing railway high slope active network protection counter-slope system, special Sign is: the cement mortar or the ratio of mud 0.45 of cement grout cement-sand ratio 1:1~1.2, the ratio of mud 0.45~0.50~ 0.50 neat slurry, 425 ordinary portland cements of cement, Sha Caiyong partial size are not more than the medium-fine sand of 3mm.
9. according to claim 6 protect counter-slope system close to existing railway high slope active network, it is characterised in that: described Anchor pole pit bore 20cm, deep 15cm.
CN201910372571.0A 2019-05-06 2019-05-06 Counter-slope system and its excavation method are protected close to existing railway high slope active network Pending CN109944260A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910372571.0A CN109944260A (en) 2019-05-06 2019-05-06 Counter-slope system and its excavation method are protected close to existing railway high slope active network

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910372571.0A CN109944260A (en) 2019-05-06 2019-05-06 Counter-slope system and its excavation method are protected close to existing railway high slope active network

Publications (1)

Publication Number Publication Date
CN109944260A true CN109944260A (en) 2019-06-28

Family

ID=67017073

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910372571.0A Pending CN109944260A (en) 2019-05-06 2019-05-06 Counter-slope system and its excavation method are protected close to existing railway high slope active network

Country Status (1)

Country Link
CN (1) CN109944260A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110306571A (en) * 2019-07-03 2019-10-08 中铁二十五局集团第五工程有限公司 A kind of cutting excavation construction method
CN110904981A (en) * 2019-12-02 2020-03-24 贵州建工集团第一建筑工程有限责任公司 Mountain road rock slope SNS flexible network protection system
CN111456041A (en) * 2020-04-08 2020-07-28 中国五冶集团有限公司 Steep mountain protection and excavation method close to existing road
CN112459086A (en) * 2020-10-20 2021-03-09 中铁二局集团有限公司 Construction method for cleaning top stone of steep side slope adjacent to existing line
CN114737581A (en) * 2022-06-14 2022-07-12 中国铁路设计集团有限公司 Construction method and protection system for excavating deep cutting close to railway business line
CN114922203A (en) * 2022-05-20 2022-08-19 中国建筑第二工程局有限公司 Lattice beam prestressing force anchor rope side slope supporting construction

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060038266A (en) * 2004-10-29 2006-05-03 재 술 나 A method for one-body type slope protection and reinforcement
CN103572761A (en) * 2012-07-19 2014-02-12 中铁十九局集团第二工程有限公司 Protection method for existing line nearby construction by using brook protective screenings
CN105484174A (en) * 2014-09-15 2016-04-13 五冶集团上海有限公司 Slope anti-rockfall guard net and construction method thereof
CN105569059A (en) * 2016-02-29 2016-05-11 中铁隧道集团有限公司 Passive protective net and installation method thereof
CN108978682A (en) * 2018-06-30 2018-12-11 中国水利水电第九工程局有限公司 A kind of construction method of road slope active protecting net system
CN208328952U (en) * 2018-06-21 2019-01-04 中铁十五局集团第三工程有限公司 Side slope Initiative Defence System

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060038266A (en) * 2004-10-29 2006-05-03 재 술 나 A method for one-body type slope protection and reinforcement
CN103572761A (en) * 2012-07-19 2014-02-12 中铁十九局集团第二工程有限公司 Protection method for existing line nearby construction by using brook protective screenings
CN105484174A (en) * 2014-09-15 2016-04-13 五冶集团上海有限公司 Slope anti-rockfall guard net and construction method thereof
CN105569059A (en) * 2016-02-29 2016-05-11 中铁隧道集团有限公司 Passive protective net and installation method thereof
CN208328952U (en) * 2018-06-21 2019-01-04 中铁十五局集团第三工程有限公司 Side slope Initiative Defence System
CN108978682A (en) * 2018-06-30 2018-12-11 中国水利水电第九工程局有限公司 A kind of construction method of road slope active protecting net system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
梁博: "边坡柔性防护网***在既有铁路危岩落石中的应用", 华东公路, no. 212, pages 88 - 90 *
黄胜明: "既有通车高速旁高路堑开挖防护措施设置", 公路与汽运, no. 175, pages 133 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110306571A (en) * 2019-07-03 2019-10-08 中铁二十五局集团第五工程有限公司 A kind of cutting excavation construction method
CN110904981A (en) * 2019-12-02 2020-03-24 贵州建工集团第一建筑工程有限责任公司 Mountain road rock slope SNS flexible network protection system
CN111456041A (en) * 2020-04-08 2020-07-28 中国五冶集团有限公司 Steep mountain protection and excavation method close to existing road
CN112459086A (en) * 2020-10-20 2021-03-09 中铁二局集团有限公司 Construction method for cleaning top stone of steep side slope adjacent to existing line
CN114922203A (en) * 2022-05-20 2022-08-19 中国建筑第二工程局有限公司 Lattice beam prestressing force anchor rope side slope supporting construction
CN114737581A (en) * 2022-06-14 2022-07-12 中国铁路设计集团有限公司 Construction method and protection system for excavating deep cutting close to railway business line

Similar Documents

Publication Publication Date Title
CN109944260A (en) Counter-slope system and its excavation method are protected close to existing railway high slope active network
CN106400813B (en) A kind of foundation pit support system and its construction method
CN106638673B (en) A kind of construction method of compound retaining structure
CN104032758B (en) Extra-high reinforced construction method in discarded pit
CN104481552B (en) Super-huge karst cave hole roof fall stone protection construction method
CN204098049U (en) A kind of protective reinforcing structure of broken rock mass slope
CN107761584A (en) A kind of freeway tunnel mouth Dangerous Rock Body Treatment Methods
CN106368224A (en) Graded slope reinforcing reverse construction method for high slope under complicated geology
CN207633352U (en) A kind of slope reinforcement structure for rapid rescue construction
CN107250460A (en) Pre- ingot bar keeping wall method for preventing landslide
CN105401956B (en) A kind of flexible protective device and construction method of the anti-rock burst falling rocks of tunnel excavation
CN104912088A (en) Slope protection structure and construction method thereof
CN105421468A (en) Basement support without concrete diagonal brace
CN110043269A (en) A kind of excavation construction process of freeway tunnel barrel
CN110485433A (en) Sand gravel geology Among Piles In Deep Foundation Pit formula diaphragm wall steel anchor method for protecting support
CN108914954A (en) Slope support method of the pre support in conjunction with permanent support
CN107012874A (en) A kind of upper-soft lower-hard ground subway station building enclosure
CN204125850U (en) A kind of cantilever shed tunnel being provided with steel tube concrete pile and prestress anchorage cable
CN204283438U (en) Portal supporting and protection structure
CN207714344U (en) A kind of passive protection net for complex mountainous cut slope
CN110080775A (en) Complex environment digs a well basic microvariations excavation method
CN209975544U (en) Active net protection back slope system next to existing railway high slope
CN206736934U (en) A kind of side slope of embankment safeguard structure
CN113622956B (en) Construction method for high-speed railway double-track tunnel to penetrate through vertical mud gushing karst cave
CN206220104U (en) A kind of Frozen Soil Cylinder Foundation Supported with Composite Soil Nailing system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Jiang Zhen

Inventor after: Mao Hong

Inventor after: Li Bingyue

Inventor after: Hu Jianbo

Inventor after: Li Hongling

Inventor after: Ma Yingfu

Inventor after: Xie Yonghui

Inventor after: Wang Hai

Inventor after: Jiang Bo

Inventor after: Deng Yongqiang

Inventor after: Chen Zhenyu

Inventor after: Li Xiaoqian

Inventor after: Liu Zhongfu

Inventor after: Duan Jili

Inventor after: Xu Li

Inventor after: Zhai Xuru

Inventor after: Hua Xiangrui

Inventor after: Yang Xiang

Inventor after: Wang Miao

Inventor after: Li Liping

Inventor after: Yu Hongwei

Inventor after: Yan Li

Inventor after: Zhang Qingming

Inventor before: Jiang Zhen

Inventor before: Li Xiaoqian

Inventor before: Hua Xiangrui

Inventor before: Yang Xiang

Inventor before: Wang Miao

Inventor before: Li Liping

Inventor before: Yu Hongwei

Inventor before: Yan Li

Inventor before: Zhang Qingming

CB03 Change of inventor or designer information