CN109930833A CN201910142557.1A CN201910142557A CN109930833A CN 109930833 A CN109930833 A CN 109930833A CN 201910142557 A CN201910142557 A CN 201910142557A CN 109930833 A CN109930833 A CN 109930833A
Authority
CN
China
Prior art keywords
construction
layer
microwave radiation
radiation protection
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910142557.1A
Other languages
Chinese (zh)
Inventor
谭万鹏
张志刚
孔大庆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Air Force Engineering University of PLA
Original Assignee
Air Force Engineering University of PLA
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Air Force Engineering University of PLA filed Critical Air Force Engineering University of PLA
Priority to CN201910142557.1A priority Critical patent/CN109930833A/en
Publication of CN109930833A publication Critical patent/CN109930833A/en
Pending legal-status Critical Current

Links

Landscapes

  • Shielding Devices Or Components To Electric Or Magnetic Fields (AREA)

Abstract

The present invention relates to a kind of radar microwave radiation protection construction method, the construction method includes base treatment, the fixed construction of metallic shield net linked network, the construction of electromagnetic radiation protection door and window, conductive earthing, boundary layer construction, inhales the construction of wave shielded layer, the construction of wave absorption magnetic conduction temperature-control coating, plastering crack-resistant layer construction.The present invention provides the radar microwave radiation protection construction method that a kind of suitable simple process, strong operability, microwave radiation shield effectiveness are good, and Yu Xinjian or existing building radar microwave radiation protection is answered to be transformed.

Description

Radar microwave radiation protection construction method
Technical field
The invention belongs to the realm of building construction, and in particular to a kind of radar microwave radiation protection construction method.
Background technique
Radar wave has very high transmission power, and the building microwave radiation closed on severely exceeds.Medical research shows not With in frequency range electromagnetic wave, influence of the microwave to human body is maximum.Influence of the electromagnetic radiation to human body has synergistic effect, seriously threatens It is firmly physically and mentally healthy with personnel, it is significant to carry out radar microwave radiation protection construction correlative study.
The achievement the published not research to radar microwave radiation protection construction method lacks to newly-built or existing thunder The guidance method constructed up to barracks microwave radiation protecting improvement project.
Summary of the invention
The object of the present invention is to provide one kind to be adapted to newly-built or existing building radar microwave radiation protection transformation, technique Simply, the apparent radar microwave radiation protection construction method of strong operability, application effect.
In order to achieve the above object, the present invention has following technical solution:
The invention discloses a kind of radar microwave radiation protection construction method, construction procedure includes base treatment, metal screen It covers the fixed construction of net linked network, the construction of electromagnetic radiation protection door and window, conductive earthing, boundary layer construction, inhale the construction of wave shielded layer, wave absorption The construction of magnetic conduction temperature-control coating, plastering crack-resistant layer construction.
Wherein, the base treatment is mainly for the existing building for needing to carry out microwave radiation protecting transformation, including outer The hole and crack repairing of wall and roof wall, spot cleaning, dabbing processing, it is therefore an objective to for construction of prevention work provide it is clean, smooth, The good construction plane of conjugation;
The repairing of hole and crack in base treatment is scraped with the cement fine sand slurry of 1:1 into gap, big when having the gap depth In 20mm, when mortar is scraped not on earth, slurry is scraped by lower mouth and scrapes high 500mm upwards, lower part reserves an aperture, removed with large size syringe In syringe needle inspiration cement slurry injection seam, when having cement slurry outflow in oral pore instantly, with hole blocked;
Spot cleaning in base treatment includes: the floating ash for brushing wall and roof surface with steel wire scrubbing brush, greasy dirt, isolation Agent, clast, ornament, outer heat insulation layer, and other discarded sundries, if there is interleaving agent, greasy dirt etc., it should with 10% caustic soda Aqueous solution washes, and is rinsed well and dried with clear water;
Dabbing processing in base treatment includes: to carry out dabbing processing to smooth surface, and chisel hole is preferably uniformly distributed, and spacing is protected 100-150mm is held, for the wall of concreting, chisel cheats depth 3-5mm, needs completely to be brushed one times with wire brush after dabbing, removes Surface debris, not dabbing when roofing construction, but need to remove loose heat-insulated or flexible water expose structure sheaf, common brick wall without Dabbing is needed, newly constructed house brick wall base must dabbing without processing, smooth concrete surface.
Wherein, the fixed construction of the metallic shield net linked network, including linked network and the fixed two parts of substep, in order to give Building constructs one from roof, the continuous metallic shield web frame of exterior wall to corner, shields reflection electromagnetic wave;
Preferably, metallic shield net uses the steel wire or wire netting of antirust treatment;
Preferably, linked network is preferably laid with along longer direction, building facade paving is hung, can according to actual manpower and tool , can also transversely to be laid with fix from top to bottom along short transverse, paving, which is hung, from left to right fixes, and adjacent shields net overlap joint is wide Degree should be not less than 60mm, and roofing and metope lap-joint width are 150-220mm, in the external corner and internal corner part of building, overlap joint Width is 100-150mm;
Preferably, when substep is fixed in such a way that air gun steel nail and bar for line joint are fixed, between steel nail is fixed Away from 150-200mm, bar for line constant density is not less than 5 Ge/㎡, is distributed in plum blossom-shaped.
Wherein, the electromagnetic radiation protection door and window construction includes the installation of doorframe, window frame construction and door, window;
The reserved metal mesh of doorframe, window frame construction should effectively be overlapped with the gauze screen of external wall, lap width 150- 200mm, the installation of door, window with doorframe, the effective of window frame it is ensured that be electrically connected;
Wherein, the conductive earthing includes that roof and exterior wall press strip, building underground conductive earthing are applied around band, grounding electrode Work;
Preferably, the press strip of roof and exterior wall is spaced 5-10m, continuous zinc-coated flat steel sheet is arranged along building lateral length Press strip;
Preferably, building underground conductive earthing surround band apart from building 300-500mm, ring building one week, it is arranged The zinc-coated flat steel sheet band of closure is embedded to underground 500-600mm, concordantly connect with the zinc-plated press strip on the continuous protective net in underground;
Preferably, the grounding electrode of grounding electrode construction uses zinc-coated flat steel sheet, what zinc-coated flat steel sheet and exterior wall extended Zinc-coated flat steel sheet press strip link, 500-600mm vertically builds direction and stretches out about 2-3m to the periphery below level ground, protrudes into underground About 800-1000mm.
Wherein, the boundary layer construction includes that material prepares and smear two steps of slurry, it is therefore an objective to reflect electromagnetism for metallic shield net Wave provides reflecting interface, while the binding ability for inhaling wave shielded layer and building wall can be improved;
Preferably, the material ratio of mud is 0.18-0.24 when boundary material mixes and stirs;
Preferably, interface construction is smeared with sawtooth plasterer's trowel, and it is primary to construct with a thickness of 3-5mm, it avoids receiving light, keep Hair side, it is desirable that smear uniformly, be compacted, smooth out, and plucking, 100% grid of guarantee is full, 100% smears and 100% plucking.
Wherein, the suction wave shielded layer construction includes that material prepares and two step of construction in layer, it is therefore an objective to provide even compact ELECTROMAGNETIC RADIATION SHIELDING layer, absorb consumption electromagnetic wave;
Preferably, when suction wave shielding material mixes and stirs, ratio of mud 0.2-0.25;
Preferably, construction in layer, using 2 layers of smearing of sawtooth plasterer's trowel point, compacting smoothes out, and guarantee reaches design thickness, Hair pulling treatment is carried out again.
Wherein, the wave absorption magnetic conduction temperature-control coating construction includes that material prepares and two step of construction in layer, it is therefore an objective to optimize impedance Matching, transmits more electromagnetic waves, by porous closing chamber, extends reflection of electromagnetic wave, route of transmission, is adhered to by cavity inner wall Wave absorption agent, increase electromagnetic wave consumption, be converted into thermal energy, while can realize heat preservation, fire protecting performance;
Preferably, when wave absorption magnetic conduction thermal control material mixes and stirs, ratio of mud 0.7-0.9;
Preferably, wave absorption magnetic conduction temperature-control coating construction in layer generally divides 3 layers of progress, when construction, is close to inhale wave shielded layer, applies Wave screen will be inhaled with clear water first before work and covers layer surface wetting, and first layer will be compacted as possible, and for thickness between 8-13mm, slurry is uniform It is closely knit, it is Nian Jie with shielded layer secured.Hair pulling treatment is carried out after floating, first layer natural curing, dry 8-12h (can be according to reality Environment temperature adjustment time), after surface tentatively has intensity, starts to smear the second layer, be compacted, smooth out.Preceding two layers of construction thickness The sum of be no more than 20-25mm, third layer construction, control overall thickness be 30-40mm;
Wherein, the construction of the plastering crack-resistant layer includes decorative mortar and glass fiber reticular cloth construction, in order to be prevented Cracking improves alkali resistant ability, improves the durability of safeguard structure;
Preferably, the total 4-6mm of decorative mortar, including patch wave absorption magnetic layer and bottom decorative mortar, bottom decorative mortar With a thickness of 2mm to 3mm, after uniformly being smeared with plasterer's trowel, it is compacted, smoothes out.
Wherein, the fixed construction of the metallic shield net linked network, boundary layer construction, the construction of suction wave shielded layer, wave absorption magnetic conduction tune Warm layer construction will extend to earth's surface or less 500-600mm along wall face, constitute the continuous protective net in underground by zinc-coated flat steel sheet press strip, Purpose is that surface em wave is effectively prevent to be transmitted to one layer of building interior.
It is anti-that radar microwave radiation protection construction method proposed by the present invention can provide effective microwave radiation for radar barracks Shield is adapted to newly-built or existing building radar microwave radiation protection and is transformed, strong operability, and application effect is obvious.
Detailed description of the invention
Fig. 1 is radar microwave radiation protection construction process schematic diagram of the present invention.
Specific embodiment
Present invention is further described in detail combined with specific embodiments below, but not as a limitation of the invention.It is real Applying the special characteristic, structure or feature in example can be combined by any suitable form.
Referring to Fig. 1, a kind of radar microwave radiation protection construction method, steps are as follows:
1. preparation of construction
1.1 construction tools prepare in place;
1.2 construction materials prepare in place.
2. construction
2.1 base treatment
Base treatment is mainly for the existing building for needing to carry out microwave radiation protecting transformation, including exterior wall and roof wall The hole and crack repairing of body, spot cleaning, dabbing processing;
The repairing of hole and crack in base treatment is scraped with the cement fine sand slurry of 1:1 into gap, big when having the gap depth In 20mm, when mortar is scraped not on earth, slurry is scraped by lower mouth and scrapes high 500mm upwards, lower part reserves an aperture, removed with large size syringe In syringe needle inspiration cement slurry injection seam, when having cement slurry outflow in oral pore instantly, with hole blocked;
Spot cleaning in base treatment includes: the floating ash for brushing wall and roof surface with steel wire scrubbing brush, greasy dirt, isolation Agent, clast, ornament, outer heat insulation layer, and other discarded sundries, if there is interleaving agent, greasy dirt etc., it should with 10% caustic soda Aqueous solution washes, and is rinsed well and dried with clear water;
Dabbing processing in base treatment includes: to carry out dabbing processing to smooth surface, and chisel hole is uniformly distributed, and spacing is kept 100-150mm, for the wall of concreting, chisel cheats depth 3-5mm, needs completely to be brushed one times with wire brush after dabbing, removes table Face clast, not dabbing when roofing construction, but loose heat-insulated or flexible water need to be removed, expose structure sheaf, common brick wall is not necessarily to Dabbing, newly constructed house brick wall base must dabbings without processing, smooth concrete surface.
The fixed construction of 2.2 metallic shield net linked networks
The fixed construction of metallic shield net linked network, including linked network and the fixed two parts of substep, metallic shield net is using at antirust The steel wire or wire netting of reason;Linked network is laid with along longer direction, and building facade paving is hung, can be with according to actual manpower and tool Along short transverse, it is laid with fixes from top to bottom, can also transversely, paving, which is hung, from left to right fixes, adjacent shields net lap width 60mm should be not less than, roofing and metope lap-joint width are 150-220mm, and in the external corner and internal corner part of building, overlap joint is wide Degree is 100-150mm;When metallic shield net substep is fixed in such a way that air gun steel nail and bar for line joint are fixed, steel nail Constant spacing 150-200mm, bar for line constant density are not less than 5 Ge/㎡, are distributed in plum blossom-shaped.
The construction of 2.3 electromagnetic radiation protection door and windows and conductive earthing
The construction of electromagnetic radiation protection door and window includes the installation of doorframe, window frame construction and door, window;
The reserved metal mesh of doorframe, window frame construction should effectively be overlapped with the gauze screen of external wall, lap width 150- 200mm, the installation of door, window with doorframe, the effective of window frame it is ensured that be electrically connected;
The construction of conductive earthing includes roof, exterior wall press strip, building underground conductive earthing around band, grounding electrode construction; The press strip edge building lateral length on roof, exterior wall, is spaced 5-10m, continuous zinc-coated flat steel sheet press strip is arranged;Building underground conduction connects Ground, apart from building 300-500mm, ring building one week, is arranged the zinc-coated flat steel sheet band of closure, is embedded to underground 500- around band 600mm is concordantly connect with the zinc-coated flat steel sheet press strip on the continuous protective net in underground;The grounding electrode of grounding electrode construction is using zinc-plated Band steel, the zinc-coated flat steel sheet press strip link extended with exterior wall, it is outside vertically to build direction by 500-600mm below level ground It encloses and stretches out about 2-3m, protrude into underground about 800-1000mm.
2.4 gauze screens overlap joint checks
Gauze screen overlap joint it is intact, carry out next step construction, continued to complete if not putting up previous step construction until It is intact.
The construction of 2.5 boundary layers
Boundary layer construction includes that material prepares and smear two steps of slurry, and when boundary material mixes and stirs, the material ratio of mud is 0.18- 0.24;Interface construction is smeared with sawtooth plasterer's trowel, primary to construct with a thickness of 3-5mm, is avoided receiving light, is kept hair side, it is desirable that smears Uniformly, it is compacted, smoothes out, and plucking, guarantee full 100% grid, 100% smearing and 100% plucking.
2.6 inhale the construction of wave shielded layer
Suction wave shielded layer construction includes material preparation and two step of construction in layer, and when suction wave shielding material mixes and stirs, the ratio of mud is 0.2-0.25;The construction of wave shielded layer is inhaled using 2 layers of smearing of sawtooth plasterer's trowel point, compacting smoothes out, and guarantee reaches design thickness, then Carry out hair pulling treatment.
The construction of 2.7 wave absorption magnetic conduction temperature-control coatings
The construction of wave absorption magnetic conduction temperature-control coating includes material preparation and two step of construction in layer, when wave absorption magnetic conduction thermal control material mixes and stirs, The ratio of mud is 0.7-0.9;General point of 3 layers of progress of wave absorption magnetic conduction temperature-control coating construction, when construction, are close to inhale wave shielded layer, first before constructing Wave screen, which first will be inhaled, with clear water covers layer surface wetting, first layer will be compacted as possible, and for thickness between 8-13mm, slurry is uniformly closely knit, It is Nian Jie with shielded layer secured, hair pulling treatment is carried out after floating, first layer natural curing, dry 8-12h (can be according to actual environment temperature Spend adjustment time), after surface tentatively has intensity, starts to smear the second layer, be compacted, smooth out.The sum of preceding two layers of construction thickness is no More than 20-25mm, third layer construction, control overall thickness is 30-40mm;
2.8 plastering crack-resistant layer constructions
The construction of plastering crack-resistant layer includes that decorative mortar and glass fiber reticular cloth construction, the total 4-6mm of decorative mortar, including patch disappear Waveguide magnetosphere and bottom decorative mortar, bottom decorative mortar is with a thickness of 2mm to 3mm, and after uniformly being smeared with plasterer's trowel, compacting is smeared It is flat.
3. embodiment:
A kind of radar microwave radiation protection construction method has carried out microwave radiation protecting rebuilding construction in certain radar station, the station There are two radars, the building Su Ban totally 3 floor, about 2500 ㎡ of external wall reconstruction area, every layer of position according to left, center, right is respectively set 3 Measuring point, totally 9 measuring points.Test is according to GJB5313-2004 " electromagnetic radiation exposure limit value and measurement method ".After radar booting, survey Radiation field intensity in the case of runin window and pass window.It is as shown in table 1 to absorb shield effectiveness:
The test of certain radar station Su Ban of table 1 building microwave radiation protecting correctional effect
For 9, the building Su Ban measuring point when closing window, the radiation field intensity of two radars meets national military standard set quota limit Value.For radar first, under open state, closing window than windowing radiation field intensity averagely reduces by 92.17%;For radar second, be switched on shape Under state, closing window than windowing radiation field intensity averagely reduces by 90.83%.
Shown in above-mentioned table 1, radar microwave radiation protection construction method proposed by the present invention, strong operability passes through base Processing, metal mesh linked network are fixed, electromagnetic shielding door and window construction, conductive earthing, and boundary layer inhales the construction of wave shielded layer, and underground is continuous Protection, wave absorption magnetic layer, plastering crack-resistant layer construction can solve radar microwave radiation excessive problem, be adapted to newly-built or existed building Object radar microwave radiation protection transformation can provide for operator and well live to use environment, and by exemplary application, shield effectiveness is excellent Show, simple process, index is clear, strong operability.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any Those familiar with the art in the technical scope disclosed by the present invention, can easily think of the change or the replacement, and should all contain Lid is within protection scope of the present invention.Therefore, protection scope of the present invention should be based on the protection scope of the described claims.

Claims (10)

1. a kind of radar microwave radiation protection construction method, it is characterised in that: the construction method includes base treatment, metal screen It covers the fixed construction of net linked network, the construction of electromagnetic radiation protection door and window, conductive earthing, boundary layer construction, inhale the construction of wave shielded layer, wave absorption The construction of magnetic conduction temperature-control coating, plastering crack-resistant layer construction.
2. a kind of radar microwave radiation protection construction method as described in claim 1, it is characterised in that: the base treatment master Will be for the existing or New Buildings for needing to carry out microwave radiation protecting transformation, the hole including interior wall or exterior wall and roof wall Hole and crack repairing, spot cleaning, dabbing processing;
Wherein, the repairing of the hole in base treatment and crack is scraped with the cement fine sand of 1:1 slurry into gap, when having the gap depth Greater than 20mm, when mortar is scraped not on earth, slurry is scraped by lower mouth and scrapes high 500mm upwards, lower part reserves an aperture, gone with large size syringe Fall in syringe needle inspiration cement slurry injection seam, when having cement slurry outflow in oral pore instantly, with blocking hole;
Wherein, the spot cleaning in base treatment includes: the floating ash for brushing wall and roof surface with steel wire scrubbing brush, greasy dirt, every From agent, clast, ornament, outer heat insulation layer, and other discarded sundries, if there is interleaving agent, greasy dirt etc., it should with 10% fire Aqueous alkali washes, and is rinsed well and dried with clear water;
Wherein, the dabbing processing in base treatment includes: to carry out dabbing processing to smooth surface, and chisel hole is uniformly distributed, and spacing is protected 100-150mm is held, for the wall of concreting, chisel cheats depth 3-5mm, needs completely to be brushed one times with wire brush after dabbing, removes Surface debris, not dabbing when roofing construction, but need to remove loose heat-insulated or flexible water expose structure sheaf, common brick wall without Dabbing is needed, newly constructed house brick wall base must dabbing without processing, smooth concrete surface.
3. a kind of radar microwave radiation protection construction method as described in claim 1, it is characterised in that: the metallic shield net The fixed construction of linked network, including linked network and the fixed two parts of substep;
Wherein, metallic shield net uses the steel wire or wire netting of antirust treatment;
Wherein, linked network is laid with along longer direction, and building facade paving is hung, can be along height side according to actual manpower and tool To, it is laid with fixes from top to bottom, can also transversely, paving, which is hung, from left to right fixes, and adjacent shields net lap width should be not less than 60mm, roofing and metope lap-joint width are 150-220mm, in the external corner and internal corner part of building, lap width 100- 150mm;
Wherein, when substep is fixed in such a way that air gun steel nail and bar for line joint are fixed, steel nail constant spacing 150- 200mm, bar for line constant density are not less than 5 Ge/㎡, are distributed in plum blossom-shaped.
4. a kind of radar microwave radiation protection construction method as described in claim 1, it is characterised in that: the electromagnetic radiation is anti- Protect the installation that door and window construction includes doorframe, window frame construction and door, window;
Wherein, the reserved metallic shield net of doorframe, window frame construction should effectively be overlapped with the metallic shield net of external wall, and overlap joint is wide Degree is 150-200mm;
Wherein, the installation of door, window with doorframe, the effective of window frame it is ensured that be electrically connected.
5. a kind of radar microwave radiation protection construction method as described in claim 1, it is characterised in that: conductive earthing includes room Top and exterior wall press strip, building underground conductive earthing are around band, grounding electrode construction;
Wherein, roof and exterior wall press strip are spaced 5-10m, continuous zinc-coated flat steel sheet press strip are arranged along building lateral length;
Wherein, ring building one week, the plating of closure is arranged around band apart from building 300-500mm in building underground conductive earthing Zinc band steel band is embedded to underground 500-600mm, concordantly connect with the zinc-coated flat steel sheet press strip on the continuous protective net in underground;
Wherein, the grounding electrode of grounding electrode construction uses zinc-coated flat steel sheet, the zinc-coated flat steel sheet that zinc-coated flat steel sheet and exterior wall extend Press strip link, 500-600mm vertically builds direction and stretches out about 2-3m to the periphery below level ground, protrudes into underground about 800- 1000mm。
6. a kind of radar microwave radiation protection construction method as described in claim 1, it is characterised in that: the boundary layer construction Prepare and smear two steps of slurry including material;
Wherein, material prepares: boundary material mix, and the material ratio of mud is 0.18-0.24 when mixing and stirring;
Wherein, smear slurry: interface construction sawtooth plasterer's trowel is smeared, primary to construct with a thickness of 3-5mm, is avoided receiving light, is kept hair Face, it is desirable that smear uniformly, be compacted, smooth out, and plucking, 100% grid of guarantee is full, 100% smears and 100% plucking.
7. a kind of radar microwave radiation protection construction method as described in claim 1, it is characterised in that: the suction wave shielded layer Construction includes that material prepares and two step of construction in layer;
Wherein, material prepares: inhaling wave shielding material mix, the ratio of mud is 0.2-0.25 when mixing and stirring;
Wherein, construction in layer is smoothed out using 2 layers of smearing of sawtooth plasterer's trowel point, compacting, and guarantee reaches design thickness, then is drawn Hair processing.
8. a kind of radar microwave radiation protection construction method as described in claim 1, it is characterised in that: the wave absorption magnetic conduction tune Warm layer construction includes that material prepares and two step of construction in layer;
Wherein, wave absorption magnetic conduction temperature adjustment layer material prepares: wave absorption magnetic conduction thermal control material mix, and the ratio of mud is 0.7-0.9 when mixing and stirring;
Wherein, wave absorption magnetic conduction temperature-control coating construction in layer generally divides 3 layers of progress, and when construction is close to inhale wave shielded layer, before construction first Wave screen, which will be inhaled, with clear water covers layer surface wetting, first layer will be compacted as possible, and for thickness between 8-13mm, slurry is uniformly closely knit, with Shielded layer bonding securely, carries out hair pulling treatment, first layer natural curing, dry 8-12h(can be according to actual ambient temperatures after floating Adjustment time), after surface tentatively has intensity, starts to smear the second layer, be compacted, smooth out, the sum of preceding two layers of construction thickness does not surpass 20-25mm, third layer construction are crossed, control overall thickness is 30-40mm.
9. a kind of radar microwave radiation protection construction method as described in claim 1, it is characterised in that: the plastering crack-resistant layer Construction includes that decorative mortar and glass fiber reticular cloth are constructed;
Wherein, the total 4-6mm of decorative mortar, including patch wave absorption magnetic layer and bottom decorative mortar, bottom decorative mortar is with a thickness of 2mm To 3mm, after uniformly being smeared with plasterer's trowel, it is compacted, smoothes out.
10. a kind of radar microwave radiation protection construction method as described in claim 1, it is characterised in that: the metallic shield The fixed construction of net linked network, boundary layer construction, the construction of suction wave shielded layer, the construction of wave absorption magnetic conduction temperature-control coating will extend to ground along wall face 500-600mm below table constitutes the continuous protective net in underground by zinc-coated flat steel sheet press strip.
CN201910142557.1A 2019-02-26 2019-02-26 Radar microwave radiation protection construction method Pending CN109930833A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910142557.1A CN109930833A (en) 2019-02-26 2019-02-26 Radar microwave radiation protection construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910142557.1A CN109930833A (en) 2019-02-26 2019-02-26 Radar microwave radiation protection construction method

Publications (1)

Publication Number Publication Date
CN109930833A true CN109930833A (en) 2019-06-25

Family

ID=66985975

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910142557.1A Pending CN109930833A (en) 2019-02-26 2019-02-26 Radar microwave radiation protection construction method

Country Status (1)

Country Link
CN (1) CN109930833A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111042569A (en) * 2019-12-31 2020-04-21 广东省第一建筑工程有限公司 Construction method for additionally building linear accelerator machine room in limited space of basement of hospital

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5673769A (en) * 1994-09-15 1997-10-07 Rexroad; John Safety/debris net system
CN102635240A (en) * 2012-04-18 2012-08-15 浙江省建工集团有限责任公司 Construction method of indoor anti-static shielding mesh system
CN103452200A (en) * 2012-05-30 2013-12-18 深圳市栢富电子有限公司 Wave absorbing assembly and manufacturing method and microwave unreflected chamber and construction method
CN104746764A (en) * 2015-02-09 2015-07-01 国家电网公司 Construction method for preventing and treating civil building sensing electricity
CN105275106A (en) * 2015-11-05 2016-01-27 中国建筑材料科学研究总院 Anti-electromagnetic radiation building
CN107575029A (en) * 2017-09-12 2018-01-12 浙江新华建设有限公司 A kind of construction of hospital's unique construction radiation proof room
CN109098479A (en) * 2018-09-26 2018-12-28 吉林省泰华电子股份有限公司 A kind of construction technology of light electromagnetic shielding chamber

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5673769A (en) * 1994-09-15 1997-10-07 Rexroad; John Safety/debris net system
CN102635240A (en) * 2012-04-18 2012-08-15 浙江省建工集团有限责任公司 Construction method of indoor anti-static shielding mesh system
CN103452200A (en) * 2012-05-30 2013-12-18 深圳市栢富电子有限公司 Wave absorbing assembly and manufacturing method and microwave unreflected chamber and construction method
CN104746764A (en) * 2015-02-09 2015-07-01 国家电网公司 Construction method for preventing and treating civil building sensing electricity
CN105275106A (en) * 2015-11-05 2016-01-27 中国建筑材料科学研究总院 Anti-electromagnetic radiation building
CN107575029A (en) * 2017-09-12 2018-01-12 浙江新华建设有限公司 A kind of construction of hospital's unique construction radiation proof room
CN109098479A (en) * 2018-09-26 2018-12-28 吉林省泰华电子股份有限公司 A kind of construction technology of light electromagnetic shielding chamber

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张巨松: "《泡沫混凝土》", 31 January 2016 *
李继业: "《建筑施工质量问题与防治措施》", 30 June 2003 *
袁孝敏: "《新型建筑材料实用手册》", 31 December 1987 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111042569A (en) * 2019-12-31 2020-04-21 广东省第一建筑工程有限公司 Construction method for additionally building linear accelerator machine room in limited space of basement of hospital
CN111042569B (en) * 2019-12-31 2023-10-31 广东省第一建筑工程有限公司 Construction method for additionally building linear accelerator machine room in limited space of hospital basement

Similar Documents

Publication Publication Date Title
US9032679B2 (en) Roof panel and method of forming a roof
CN108952041A (en) A kind of external wall Stucco finish structure and its method for repairing and constructing
CN109098479B (en) Construction process of light electromagnetic shielding chamber
CN104674962B (en) The construction method of expanded perlite thermal-nsulation plate exterior wall external heat preservation system
CN109930833A (en) Radar microwave radiation protection construction method
CN105275106A (en) Anti-electromagnetic radiation building
CN109972755A (en) A kind of radiation proof composite structure of radar microwave
CN208934297U (en) A kind of hollowing cracking falls off maintenance and renovation renewing outer wall
DE8915902U1 (en) Facade construction of high-rise buildings
CN110173116A (en) A kind of skyscraper quickly interts cross construction method
CN103321393B (en) Plastering on inner walls construction method
DD280988A5 (en) WATER REPELLENT EXTERNAL CLOTHING FOR BUILDINGS
CN108533125B (en) A kind of installation method of energy conservation auxiliary frame antiseep
CN207268090U (en) Reserved joint bar protective device
NO319768B1 (en) Insulation plates with protection against electromagnetic fields
CN208996342U (en) A kind of external wall Stucco finish structure
CN107761760A (en) Based on the technique for improving cable duct efficiency of construction
CN208089182U (en) One kind is floatd window water proof structure
CN106380164B (en) Tempest concrete and the combined wall built up using it and its construction method
CN108951904A (en) A kind of steel core concrete column outsourcing pea gravel concreten fireprotection layer construction
ES2925504T3 (en) Architectural ensemble that forms a shield against electromagnetic radiation
CN108193791B (en) Indoor electromagnetic protection system and protection method thereof
WO2005120146A2 (en) Construction material having an heat-insulating finish and/or protection against electrosmog and method for production thereof
CN106760032A (en) Wall body structure and building
CN209523324U (en) A kind of rock wool complex wave contact plate

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190625