CN109911756A - The experimental rig and method for transporting and lifting convenient for bridge floor continuous structure test component - Google Patents
The experimental rig and method for transporting and lifting convenient for bridge floor continuous structure test component Download PDFInfo
- Publication number
- CN109911756A CN109911756A CN201910315923.9A CN201910315923A CN109911756A CN 109911756 A CN109911756 A CN 109911756A CN 201910315923 A CN201910315923 A CN 201910315923A CN 109911756 A CN109911756 A CN 109911756A
- Authority
- CN
- China
- Prior art keywords
- steel plate
- girder
- bridge floor
- vertical
- test component
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The experimental rig that the present invention relates to a kind of to transport and lift convenient for bridge floor continuous structure test component, connecting plate including two girders and on two girder adjacent end portions, top, the lower section of two girder adjacent end portions are equipped with horizontal steel plate, left side, the right side of two girder adjacent end portions are equipped with vertical steel plate, two horizontal steel plates are through vertical screw rod by connecting plate, two end of main beam bandings, and two vertical steel plates are through transverse screw by two end of main beam bandings.The structure of the experimental rig for transporting and lifting convenient for bridge floor continuous structure test component is simple.
Description
Technical field
The experimental rig and method that the present invention relates to a kind of to transport and lift convenient for bridge floor continuous structure test component.
Background technique
Jump brought by bridge expanssion joint vehicle and due to telescopic device damage the secondary adverse effect of bring (such as structure it is attached
Add internal force, leak to corrosion of structure etc.) it is the thorny problem that current domestic and abroad bridge is frequently encountered in actual operations.By
The jump vehicle caused by telescopic device not only causes very big percussion to bridge, but also can reduce the driving of driver and passenger
Comfort level.In addition, maintenance and replacement to expansion gap device often will cause serious friendship with the increasingly increase of the magnitude of traffic flow
It is logical to interrupt, and then generate huge economic loss.It can be seen that solving bridge expanssion joint bring a series of problems has been that gesture exists
It must go.In order to fundamentally solve the problems, such as that telescopic device, the continuous freely-supported bridge of bridge floor come into being.Bridge floor continuous freely supported beam bridge
It is that a kind of be combined together adjacent girder by using connecting plate becomes the continuous overall structure of bridge floor, while guaranteeing again
The structure of its girder freely-supported.Bridge floor continuous freely supported beam bridge had both had the mechanical characteristic of simply supported girder bridge, and simple structure is easy for construction;
There is no telescopic device again, save telescopic device construction, maintenance and maintenance cost, improve driving stationarity, lowers driving to bridge
Impact load.Due to eliminating the telescopic device between adjacent girder, beam body is due to temperature deformation, concrete shrinkage and creep etc.
The stroke of generation is absorbed by connecting plate.
Connecting plate in bridge floor continuous freely supported beam bridge is the weak link of structure.Itself with regard to structure, since girder is
Simply supported beam, connecting plate are located at the beam-ends of girder, not only to bear girder temperature movement displacement transfer and the vertical bridge that comes is to deformation, also
It bears the end of main beam rotational deformation of the vertical loads such as automobile generation and the concentrated force and percussion of wheel, stress is multiple
Miscellaneous, it is improper to design, construct and conserve, and can cause to crack.Currently, domestic scholars carry out experimental study to bridge floor continuous structure
When, it usually needs bridge floor continuous structure test component, including two blocks of girders and girder are made in special test specimen production place
Between connecting plate.Then bridge floor continuous structure test component is transported to test load place and carries out test.It is continuous in bridge floor
It carries out the operation such as lifting during structural test component conveying.In bridge floor continuous structure, compared with girder, connecting plate category
In weak link, it is easy to since two girders the changing of the relative positions of horizontal position or elevation location occur and go out in transport or hoisting process
The phenomenon that existing connecting plate cracking, cause test that can not carry on.
Summary of the invention
In view of the deficiencies in the prior art, technical problem to be solved by the invention is to provide one kind to be convenient for bridge floor continuous structure
The experimental rig and method of test component transport and lifting, are not only simple in structure, and convenient and efficient.
In order to solve the above-mentioned technical problem, the technical scheme is that a kind of be convenient for bridge floor continuous structure test component
The experimental rig of transport and lifting, the connecting plate including two girders and on two girder adjacent end portions, two girders
Top, the lower section of adjacent end portion are equipped with horizontal steel plate, and left side, the right side of two girder adjacent end portions are equipped with vertical steel plate,
Two horizontal steel plates are through vertical screw rod by connecting plate, two end of main beam bandings, and two vertical steel plates are through transverse screw by two end of main beam
Banding.
Preferably, the adjacent end portion upper surface of two girders is equipped with the step for being embedded connecting plate, connecting plate upper surface with
Girder upper surface flushes.
Preferably, upper horizontal lower surface of steel plate is adjacent to connecting plate upper surface, lower horizontal upper surface of steel plate and girder
Lower surface is adjacent to, and vertical screw rod is symmetrically distributed in the left and right sides of horizontal steel plate, and the end of vertical screw rod both passes through ipsilateral level
Installation through-hole on steel plate, and through nut check.
Preferably, the right surface of left side vertical steel plate is adjacent to girder left surface, and right vertical steel plate left surface and girder are right
Surface is adjacent to, and transverse screw is symmetrically distributed in the front and rear sides of vertical steel plate, and the end of transverse screw both passes through ipsilateral vertical steel
Installation through-hole on plate, and through nut check.
Preferably, more lateral steel pipes are vertically embedded on the adjacent end portion of two girders, lateral steel pipe is for laterally
Screw rod passes through.
Preferably, two girders are embedded with hanging ring in the left and right sides close to connecting plate.
A kind of construction method for the experimental rig for transporting and lifting convenient for bridge floor continuous structure test component, according to the following steps
It carries out: (1) making the horizontal steel plate with installation through-hole and vertical steel plate;(2) in two pre-buried hanging rings of end of main beam and vertical row
The lateral steel pipe for being horizontally through girder of column;(3) two girders and connecting plate of cast in situs bridge floor continuous structure test component
Concrete, transverse screw is inserted into lateral steel pipe after demoulding;(4) vertical steel plate is inserted in transverse direction at left and right sides of girder respectively
Screw rod, in transverse screw both ends nut tightening;(5) two sides are fixed with horizontal steel plate above and below end of main beam, and by vertical spiral shell
Bar passes through horizontal steel plate, in vertical screw rod both ends nut tightening.
Compared with prior art, the invention has the following advantages: by end of main beam and connecting plate position setting
Screw rod and steel plate are reinforced, and realize bridge floor continuous structure test component in transport and hoisting process, two girders do not occur
The changing of the relative positions of horizontal position or elevation location and the phenomenon that cause connecting plate to crack.It reaches and tests in bridge floor continuous structure test component
After loading place, screw rod and steel plate are removed, the load of bridge floor continuous structure test component can be carried out, to ensure that bridge floor is continuously tied
The smooth development of structure test.
The present invention will be further described in detail with reference to the accompanying drawings and detailed description.
Detailed description of the invention
Fig. 1 is the top view of the embodiment of the present invention.
Fig. 2 is the main view of the embodiment of the present invention.
Fig. 3 is the side view of the embodiment of the present invention.
Fig. 4 is the Construction State schematic diagram one of the embodiment of the present invention.
Fig. 5 is the Construction State schematic diagram two of the embodiment of the present invention.
Fig. 6 is the Construction State schematic diagram three of the embodiment of the present invention.
Fig. 7 is the Construction State schematic diagram four of the embodiment of the present invention.
Fig. 8 is the handling status diagram one of the embodiment of the present invention.
Fig. 9 is the handling status diagram two of the embodiment of the present invention.
Specific embodiment
To make the foregoing features and advantages of the present invention clearer and more comprehensible, special embodiment below, and cooperate attached drawing, make detailed
Carefully it is described as follows.
As shown in Fig. 1 ~ 9, a kind of experimental rig for transporting and lifting convenient for bridge floor continuous structure test component, including two
Girder 1 and the connecting plate 2 on two girder adjacent end portions, top, the lower section of two girder adjacent end portions are equipped with water
Plain plate 3, left side, the right side of two girder adjacent end portions are equipped with vertical steel plate 4, and two horizontal steel plates will be even through vertical screw rod 5
Fishplate bar, two end of main beam bandings, two vertical steel plates are through transverse screw 6 by two end of main beam bandings.
In embodiments of the present invention, the adjacent end portion upper surface of two girders is equipped with the step 7 for being embedded connecting plate, connection
Plate upper surface is flushed with girder upper surface.
In embodiments of the present invention, upper horizontal lower surface of steel plate is adjacent to connecting plate upper surface, on lower horizontal steel plate
Surface is adjacent to girder lower surface, and vertical screw rod is symmetrically distributed in the left and right sides of horizontal steel plate, and the end of vertical screw rod is worn
The installation through-hole on ipsilateral horizontal steel plate is crossed, and is locked through nut 8.
In embodiments of the present invention, the right surface of left side vertical steel plate is adjacent to girder left surface, right vertical steel plate left-handed watch
Face is adjacent to the right surface of girder, and transverse screw is symmetrically distributed in the front and rear sides of vertical steel plate, and the end of transverse screw both passes through
Installation through-hole on ipsilateral vertical steel plate, and through nut check.
In embodiments of the present invention, more lateral steel pipes 9, lateral steel are vertically embedded on the adjacent end portion of two girders
Pipe is passed through for transverse screw.
In embodiments of the present invention, two girders are embedded with hanging ring 10 in the left and right sides close to connecting plate.
A kind of construction method for the experimental rig for transporting and lifting convenient for bridge floor continuous structure test component, according to the following steps
It carries out: (1) making the horizontal steel plate with installation through-hole and vertical steel plate;(2) in two pre-buried hanging rings of end of main beam and vertical row
The lateral steel pipe for being horizontally through girder of column;(3) two girders and connecting plate of cast in situs bridge floor continuous structure test component
Concrete, transverse screw is inserted into lateral steel pipe after demoulding;(4) vertical steel plate is inserted in transverse direction at left and right sides of girder respectively
Screw rod, in transverse screw both ends nut tightening;(5) two sides are fixed with horizontal steel plate above and below end of main beam, and by vertical spiral shell
Bar passes through horizontal steel plate, in vertical screw rod both ends nut tightening.
In embodiments of the present invention, hanging device is connect when lifting with the hanging ring on girder, screw rod and steel plate will be used
The bridge floor continuous structure test component integral hoisting of reinforcing is simultaneously transported to test load place, and is placed in support 11 and concrete
On block 12.Screw rod and steel plate are removed, the load of bridge floor continuous structure test component can be carried out.
The present invention is not limited to above-mentioned preferred forms, anyone can show that other are each under the inspiration of the present invention
The experimental rig and method for transporting and lifting convenient for bridge floor continuous structure test component of kind form.It is all according to the present patent application patent
The equivalent changes and modifications that range is done, are all covered by the present invention.
Claims (7)
1. it is a kind of convenient for bridge floor continuous structure test component transport and lift experimental rig, including two girders and be located at two
Connecting plate on root girder adjacent end portion, it is characterised in that: top, the lower section of two girder adjacent end portions are equipped with horizontal steel
Plate, left side, the right side of two girder adjacent end portions are equipped with vertical steel plate, and two horizontal steel plates are through vertical screw rod by connecting plate, two
End of main beam banding, two vertical steel plates are through transverse screw by two end of main beam bandings.
2. the experimental rig according to claim 1 for transporting and lifting convenient for bridge floor continuous structure test component, feature
Be: the adjacent end portion upper surface of two girders is equipped with the step for being embedded connecting plate, connecting plate upper surface and girder upper surface
It flushes.
3. the experimental rig according to claim 1 for transporting and lifting convenient for bridge floor continuous structure test component, feature
Be: upper horizontal lower surface of steel plate is adjacent to connecting plate upper surface, and lower horizontal upper surface of steel plate is adjacent to girder lower surface,
Vertical screw rod is symmetrically distributed in the left and right sides of horizontal steel plate, and the end of vertical screw rod both passes through the installation on ipsilateral horizontal steel plate
Through-hole, and through nut check.
4. the experimental rig according to claim 1 for transporting and lifting convenient for bridge floor continuous structure test component, feature
Be: the right surface of left side vertical steel plate is adjacent to girder left surface, and right vertical steel plate left surface is adjacent to the right surface of girder, horizontal
The front and rear sides of vertical steel plate are symmetrically distributed in screw rod, it is logical that the end of transverse screw both passes through the installation on ipsilateral vertical steel plate
Hole, and through nut check.
5. the experimental rig according to claim 1 for transporting and lifting convenient for bridge floor continuous structure test component, feature
It is: is vertically embedded with more lateral steel pipes on the adjacent end portion of two girders, lateral steel pipe is passed through for transverse screw.
6. the experimental rig according to claim 1 for transporting and lifting convenient for bridge floor continuous structure test component, feature
Be: two girders are embedded with hanging ring in the left and right sides close to connecting plate.
7. a kind of any test dress for transporting and lifting convenient for bridge floor continuous structure test component as described in claim 1-6
The construction method set, which is characterized in that sequentially include the following steps: (1) horizontal steel plate of production with installation through-hole and vertical steel plate;
(2) in the pre-buried hanging ring of two end of main beam and the vertically disposed lateral steel pipe for being horizontally through girder;(3) cast in situs bridge floor connects
Transverse screw is inserted into lateral steel pipe after demoulding by the concrete of two girders and connecting plate of continuous structural test component;(4) it will erect
Straight steel plate is inserted in transverse screw at left and right sides of girder respectively, in transverse screw both ends nut tightening;(5) on end of main beam
Lower two sides are fixed with horizontal steel plate, and vertical screw rod is passed through horizontal steel plate, in vertical screw rod both ends nut tightening.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910315923.9A CN109911756A (en) | 2019-04-19 | 2019-04-19 | The experimental rig and method for transporting and lifting convenient for bridge floor continuous structure test component |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910315923.9A CN109911756A (en) | 2019-04-19 | 2019-04-19 | The experimental rig and method for transporting and lifting convenient for bridge floor continuous structure test component |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109911756A true CN109911756A (en) | 2019-06-21 |
Family
ID=66977858
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910315923.9A Pending CN109911756A (en) | 2019-04-19 | 2019-04-19 | The experimental rig and method for transporting and lifting convenient for bridge floor continuous structure test component |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109911756A (en) |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102587286A (en) * | 2012-03-28 | 2012-07-18 | 上海市第四建筑有限公司 | Simply supported-continuous construction method for bridge superstructure |
CN104612050A (en) * | 2015-02-09 | 2015-05-13 | 福州大学 | Simply supported girder bridge floor continuous new construction and construction method |
JP2016037746A (en) * | 2014-08-07 | 2016-03-22 | 山内 重一 | Embedded joint structure for road bridge and construction method for the embedded joint structure |
CN105484151A (en) * | 2015-12-04 | 2016-04-13 | 郑州大学 | Structure for enhancing connection among prefabricated concrete segments and construction method thereof |
CN107858919A (en) * | 2017-12-12 | 2018-03-30 | 衡水双盛工程橡胶有限公司 | A kind of novel fabricated bridge extension joint |
CN207210978U (en) * | 2017-09-27 | 2018-04-10 | 郑州大学 | A kind of bridge strengthening device |
CN108103928A (en) * | 2017-12-21 | 2018-06-01 | 昆山顶牛市政建设有限公司 | A kind of connection structure and construction method of multispan freely-supported bridge expanssion joint |
CN108755405A (en) * | 2018-05-30 | 2018-11-06 | 重庆交通大学 | Assembling steel plate bridge floor continuous structure and construction method |
CN109235235A (en) * | 2018-11-19 | 2019-01-18 | 绍兴文理学院 | A kind of steel reinforced concrete combined bridge bridge floor continuously locates the longitudinally connected method of girder |
CN209797235U (en) * | 2019-04-19 | 2019-12-17 | 福州大学 | Test device convenient to transportation and hoist of bridge floor continuous structure test component |
-
2019
- 2019-04-19 CN CN201910315923.9A patent/CN109911756A/en active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102587286A (en) * | 2012-03-28 | 2012-07-18 | 上海市第四建筑有限公司 | Simply supported-continuous construction method for bridge superstructure |
JP2016037746A (en) * | 2014-08-07 | 2016-03-22 | 山内 重一 | Embedded joint structure for road bridge and construction method for the embedded joint structure |
CN104612050A (en) * | 2015-02-09 | 2015-05-13 | 福州大学 | Simply supported girder bridge floor continuous new construction and construction method |
CN105484151A (en) * | 2015-12-04 | 2016-04-13 | 郑州大学 | Structure for enhancing connection among prefabricated concrete segments and construction method thereof |
CN207210978U (en) * | 2017-09-27 | 2018-04-10 | 郑州大学 | A kind of bridge strengthening device |
CN107858919A (en) * | 2017-12-12 | 2018-03-30 | 衡水双盛工程橡胶有限公司 | A kind of novel fabricated bridge extension joint |
CN108103928A (en) * | 2017-12-21 | 2018-06-01 | 昆山顶牛市政建设有限公司 | A kind of connection structure and construction method of multispan freely-supported bridge expanssion joint |
CN108755405A (en) * | 2018-05-30 | 2018-11-06 | 重庆交通大学 | Assembling steel plate bridge floor continuous structure and construction method |
CN109235235A (en) * | 2018-11-19 | 2019-01-18 | 绍兴文理学院 | A kind of steel reinforced concrete combined bridge bridge floor continuously locates the longitudinally connected method of girder |
CN209797235U (en) * | 2019-04-19 | 2019-12-17 | 福州大学 | Test device convenient to transportation and hoist of bridge floor continuous structure test component |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104963301B (en) | The dilatory translation downward putting device and method removed for pier top beam section and bridge pier | |
CN108824193B (en) | Method for quickly dismantling and installing bridge superstructure and replacing system thereof | |
CN203393848U (en) | Connection node structure of reinforced concrete column and steel I-beam | |
CN101603288A (en) | A kind of three-truss main girder structure of highway and railway bi-purpose cable-stayed bridge and mounting method thereof | |
CN203200914U (en) | Steel structure socle outward exposed connecting structure | |
CN106544958B (en) | 900 tons of Bridge Erector low levels of auxiliary nose-girder type cross the construction method of bale handle arch | |
CN109162204B (en) | Construction method for transverse block rapid assembling of bridge substructure | |
CN112049028B (en) | Damping and anti-overturning single-column pier bridge reinforcing device and installation method | |
CN102134832B (en) | Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane | |
CN210420902U (en) | Concrete box girder flange plate cutting and dismantling stabilizing device | |
CN205207907U (en) | Novel pipeline bracket of tape base plinth | |
CN201605527U (en) | Steel structure bent cap additionally arranged at top of pier stud | |
CN109911756A (en) | The experimental rig and method for transporting and lifting convenient for bridge floor continuous structure test component | |
CN209797235U (en) | Test device convenient to transportation and hoist of bridge floor continuous structure test component | |
CN105421251A (en) | Plate-girder jacking support mechanism and plate-girder jacking support tool | |
CN114033147B (en) | Construction method for disassembling and modifying I-shaped steel of overhanging scaffold in hoistway | |
CN215925647U (en) | Arch rib buckle cable anchoring beam for tower buckle integration | |
CN102003070A (en) | Construction method of suspending scaffold | |
CN109555021A (en) | It is a kind of without pre-buried, movable continuous beam 0# block bracket | |
CN214570413U (en) | Special device for underground rapid lifting pipeline of mine | |
CN205382563U (en) | Steel structure support frame | |
CN205152800U (en) | Unsettled template system of consolidating under complicated stress condition | |
CN210658043U (en) | Novel leveling device for mounting assembly type pier | |
CN110820518B (en) | Machining and hoisting method for steel arch bridge suspender | |
CN213653210U (en) | Novel cast-in-place support system of steel-concrete composite beam bridge deck cantilever |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |