CN109898414A - A kind of pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system - Google Patents

A kind of pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system Download PDF

Info

Publication number
CN109898414A
CN109898414A CN201910201699.0A CN201910201699A CN109898414A CN 109898414 A CN109898414 A CN 109898414A CN 201910201699 A CN201910201699 A CN 201910201699A CN 109898414 A CN109898414 A CN 109898414A
Authority
CN
China
Prior art keywords
anchorage
main push
towing rope
prestress
male cone
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910201699.0A
Other languages
Chinese (zh)
Other versions
CN109898414B (en
Inventor
左雷彬
陈晓辉
詹胜文
李国辉
任文明
徐大宝
马晓成
铁明亮
杨威
倪娜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Petroleum Corp
China Petroleum Pipeline Engineering Corp
Original Assignee
China National Petroleum Corp
China Petroleum Pipeline Engineering Corp
China Petroleum Pipeline Engineering Corp Design Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Petroleum Corp, China Petroleum Pipeline Engineering Corp, China Petroleum Pipeline Engineering Corp Design Branch filed Critical China National Petroleum Corp
Priority to CN201910201699.0A priority Critical patent/CN109898414B/en
Publication of CN109898414A publication Critical patent/CN109898414A/en
Application granted granted Critical
Publication of CN109898414B publication Critical patent/CN109898414B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to a kind of pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor systems, comprising: male cone body, head outside are equipped with main push-towing rope anchorage, and the lateral tail of the male cone body is equipped with whole anchor slab;Several prestress wires are equipped in the male cone body, one end of the prestress wire is anchored on the main push-towing rope anchorage, and the other end of the prestress wire is anchored on the whole anchor slab;Prestress anchorage cable, one end anchor the area Mao Zhi rear portion country rock, and the other end is anchored on the whole anchor slab, and under the action of the prestress anchorage cable, the area Mao Zhi rear portion country rock and male cone body are connected as an entirety and participate in stress jointly, resist the pulling force of external main push-towing rope.The area Mao Zhi country rock and male cone body are connected as an entirety by prestress anchorage cable and prestress wire by the present invention, the two participates in stress jointly, reach in features as poor geologic condition, Surrounding Rock Strength is low, tunnel anchorage safety coefficient is improved under structure cranny development rock mass conditions, reduce the purpose that male cone body excavates size.

Description

A kind of pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system
Technical field
The present invention relates to a kind of pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor systems, belong to oil-gas pipeline overhead crossing engineering and set Meter field.
Background technique
It is long oil and gas pipeline across one of common methods of barriers such as river, lake, valley that suspension, which is crossed over, and Over long distances, the preferred and main pattern that Long span is crossed over.As four big primary structures of suspension crossing, anchorage is anchoring master Cable transmits huge pulling force to the key member of ground, is broadly divided into self-anchored type and ground anchor type, built oil-gas pipeline suspension bridge All using ground anchor type anchorage.According to the difference of anchor body and ground connection type, ground anchor type anchorage is divided into gravity type and tunnel again Formula, gravity anchor pour mass concrete and form anchorage by excavation pit, and main push-towing rope drawing is resisted by self gravity Power, therefore the scale of construction is big, cost is high, large volume foundation pit disturbs surrounding enviroment larger;Tunnel-type anchorage is then by rock mass weight Tunnel excavation, casting concrete and country rock cooperatively form male cone body in tunnel, tension of main cable are born whereby, with gravity type Anchorage is compared, and the scale of construction is only the 20%~25% of gravity anchor, and is influenced on surrounding enviroment smaller.Tunnel anchorage require ROCK MASS JOINT compared with Less, integrality is good, some geological conditions are poor, Surrounding Rock Strength is lower, in the rock mass of structure cranny development, tunnel conventional at present Road anchor anchoring main push-towing rope mode is not able to satisfy design requirement then.
Summary of the invention
To solve the above problems, the purpose of the present invention is to provide a kind of pipeline suspension bridge tunnel-type anchorage main push-towing rope anchoring systems It is outstanding to realize pipeline by setting prestress anchorage cable, whole anchor slab, prestress wire, positioning anchor slab and main push-towing rope anchorage for system The anchoring of rope Oil pipeline main push-towing rope improves tunnel-type anchorage safety coefficient and reduces the purpose of the area Mao Zhi ambient enviroment disturbance, is Under complicated geological and limitation geographic and geomorphic conditions, solves aerial crossing pipeline structure tunnel-type anchorage safety and main push-towing rope anchorage problem provides A kind of new mode.
The purpose of the present invention is what is be achieved through the following technical solutions:
A kind of pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system, comprising:
External main push-towing rope, one end are anchored on king-tower, and the other end is anchored on the main push-towing rope anchorage on male cone body head;
Male cone body is located inside the area Mao Zhi country rock, and main push-towing rope anchorage, the anchor are equipped on the outside of the head of the male cone body The lateral tail of cock body is equipped with whole anchor slab;Several prestress wires are equipped in the male cone body, and described several pre- Prestress steel strand arranges that one end of the prestress wire is anchored at the main push-towing rope with the axis parallel of the male cone body On anchorage, the other end of the prestress wire is anchored on the whole anchor slab;
Prestress anchorage cable, one end anchor the area Mao Zhi rear portion country rock, and the other end is anchored on the whole anchor slab, described Under the action of prestress anchorage cable, the area Mao Zhi country rock and male cone body are connected as an entirety and participate in stress jointly, resist the outside The pulling force of main push-towing rope.
Further, the tilt angle of the male cone body and horizontal plane is identical as the angle of horizontal plane with external main push-towing rope.
Further, the male cone body is made of straightway and transition, wherein the cross section of the straightway is in strip Shape, the cross section of the transition are in isosceles trapezoid, and the side short side of the strip is the head of male cone body, the strip Other side short side connect with the upper bottom of the isosceles trapezoid, the bottom of the isosceles trapezoid is the tail portion of the male cone body;Institute The section of male cone body is stated in the shape of a hoof.
Further, inside the male cone body, the both ends of the prestress wire be respectively arranged with reinforced mesh into Row partial pressing.
Further, it is provided with positioning anchor slab below the main push-towing rope anchorage, positions the prestressing force for whole Steel strand wires guarantee the accuracy of the prestress wire anchorage point.
Further, described after the installation for completing positioning anchor slab, reinforced mesh, prestress wire and whole anchor slab It is filled inside male cone body using C30 concrete.
Further, through-hole needed for being provided with prestress wire on the whole anchor slab, and on the whole anchor slab Prestress steel twist line three-way hole and positioning anchor slab on prestress steel twist line three-way hole correspond, pre- answering on the entirety anchor slab Power steel strand wires through-hole is symmetrical in the two sides of whole anchor slab, and the middle of the entirety anchor slab, which is equipped with, is used for prestressed anchor The aperture of rope.
Further, when connecting prestress wire and prestress anchorage cable by the whole anchor slab, an examination is set Rope is tested, is detected after the test cable reaches design 1.5 times of anchor force through anchor force, then carry out the construction of prestress anchorage cable.
Further,
The external main push-towing rope end adjusts anchorage using double-screw type;
Main push-towing rope anchorage includes the vertical plate of level board and 4 parallel arrangements, and the vertical plate is arranged perpendicular to level board, And the vertical plate and level board are integrally formed, and are respectively provided between the level board and vertical plate and between vertical plate and vertical plate There is stiffener;Through-hole needed for the two sides of the level board are symmetrically arranged with prestress wire, and it is pre- on the level board Prestress steel twist line three-way hole on prestress steel strand through-hole and positioning anchor slab corresponds;It is had on 4 vertical plates For the hole that pin shaft passes through, the screw rod of the external main push-towing rope end is fixed on the main push-towing rope anchorage by pin shaft.
Further, the level board of the positioning anchor slab, whole anchor slab and main push-towing rope anchorage is each perpendicular to the male cone body Section setting.
The invention has the benefit that
The present invention passes through setting prestress anchorage cable, whole anchor slab, prestress wire, positioning anchor slab and main push-towing rope anchorage, The anchoring of pipeline suspension crossing structure main push-towing rope is realized, tunnel-type anchorage safety coefficient is improved and reduces the area Mao Zhi ambient enviroment and disturb Dynamic purpose is to solve the anchoring of aerial crossing pipeline structure tunnel-type anchorage main push-towing rope under complicated geological and limitation geographic and geomorphic conditions and ask Topic provides a kind of new mode.
Meanwhile when the area Mao Zhi is poor by geological conditions, Surrounding Rock Strength is lower, the rock mass orographic condition of structure cranny development When limitation, the area male cone Ti Hemaozhi country rock is made to participate in stress jointly, greatlys improve the safety coefficient of tunnel-type anchorage, and effectively Reduce tunnel excavation size, reduces the disturbance of the area Mao Zhi ambient enviroment.
Detailed description of the invention
Fig. 1 is pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system schematic cross-section of the present invention;
Fig. 2 is pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system overall structure diagram of the present invention;
Fig. 3 is main push-towing rope end construction schematic diagram outside the embodiment of the present invention;
Fig. 4 is main push-towing rope anchorage structural schematic diagram of the present invention;
Fig. 5 is entirety of embodiment of the present invention anchored framework schematic diagram;
Fig. 6 is prestress anchorage cable of embodiment of the present invention structural schematic diagram;
Wherein, 1- twin-screw adjusts anchorage, 2- main push-towing rope anchorage, and 3- positions anchor slab, 4- reinforced mesh, 5- male cone body straight line Section, 6- prestress wire, 7- pin shaft, 8- male cone body transition, 9- test cable, 10- prestress anchorage cable, 11- entirety anchor slab, 12-C30 concrete, the outside 13- main push-towing rope, 14- king-tower, the area 15- Mao Zhi country rock, 16- twin-screw hot casting anchor anchor cup, 17- zinc-copper close Gold, 18- sealing material, 19- prestress steel twist line three-way hole, 20- prestress anchorage cable aperture, 21- epoxy spray steel strand single layer is without viscous Connect muscle, 22- guiding cap, 23- anchor cable bellows, 24- isolating frame, 25- centering rack, 26- anchor cable, 27- Grouting Pipe, 28- pre-buried steel Pipe, 29- epoxy resin mortar, 30- spiral bar, 31- work clip sheet, 32- work anchor slab, 33- screw rod.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right The present invention is further elaborated.It should be appreciated that described herein, specific examples are only used to explain the present invention, not For limiting the present invention.
With reference to Fig. 1~2, a kind of pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system, comprising:
External main push-towing rope 13, one end are anchored on king-tower 14, the screw rod 33 that the other end passes through 13 end of the external main push-towing rope Insertion main push-towing rope anchorage 2 is anchored on the area Mao Zhi country rock 15.The end that the external main push-towing rope 13 connects main push-towing rope anchorage 2 uses institute It states external 13 end of main push-towing rope and anchorage is adjusted using double-screw type, as shown in Figure 3.
Male cone body is located inside the area Mao Zhi country rock 15, and main push-towing rope anchorage 2, institute are equipped on the outside of the head of the male cone body The lateral tail for stating male cone body is equipped with whole anchor slab 11;Several prestress wires 6 are equipped in the male cone body, and if described Dry root prestress wire 6 arranges that one end of the prestress wire 6 is anchored at the axis parallel of the male cone body On the main push-towing rope anchorage 2, the other end of the prestress wire 6 is anchored on the whole anchor slab 11.Pass through prestressing force The connection and power transmission of steel strand wires 6 are realized the connection of main push-towing rope anchorage 2 and entire male cone body, external tension of main cable are transferred to whole A male cone body.
The male cone body is made of straightway 5 and transition 8, wherein the cross section of the straightway 5 is elongated, it is described The cross section of transition 8 is in isosceles trapezoid, and the side short side of the strip is the head of male cone body, the strip it is another Side short side is connect with the upper bottom of the isosceles trapezoid, and the bottom of the isosceles trapezoid is the tail portion of the male cone body.Transition Design can enhance the withdrawal resistance of male cone body, reinforce male cone effect.
As shown in figure 4, main push-towing rope anchorage 2 include level board and 4 parallel arrangement vertical plates, the vertical plate perpendicular to Level board arrangement, and the vertical plate and level board are integrally formed, between the level board and vertical plate and vertical plate and vertical Stiffener is provided between plate;Through-hole needed for being provided with prestress wire 6 on the level board, and on the level board Prestress steel twist line three-way hole on prestress steel twist line three-way hole and positioning anchor slab 3 corresponds;It is opened respectively on 4 vertical plates There is the hole passed through for pin shaft, the screw rod 1 of 13 end of the external main push-towing rope is fixed on the main push-towing rope anchorage 2 by pin shaft 7.
Prestress anchorage cable 10, one end anchor the area Mao Zhi rear portion country rock, and the other end is anchored on the whole anchor slab 11, Under the action of the prestress anchorage cable 10, the area Mao Zhi rear portion country rock and male cone body are connected as an entirety and participate in stress jointly, support Resist the pulling force of the external main push-towing rope 13.
The tilt angle of entire male cone body and horizontal plane is identical as the angle of horizontal plane with external main push-towing rope 13, is external main push-towing rope The arctan function of 13 ratios of rise to span.
Preferably, inside the male cone body, the both ends of the prestress wire 6 be respectively arranged with reinforced mesh 4 into Row partial pressing.
The lower section of the main push-towing rope anchorage 2 is provided with positioning anchor slab 3, positions the prestress wire 6 for whole, Guarantee the accuracy of 6 anchorage point of prestress wire.
Further, after the installation for completing positioning anchor slab 3, reinforced mesh 4, prestress wire 6 and whole anchor slab 11, It is filled inside the male cone body using C30 concrete 12.
Further, as shown in figure 5, through-hole needed for being provided with prestress wire 6 on the entirety anchor slab 11, and institute The prestress steel twist line three-way hole stated on prestress steel twist line three-way hole and the positioning anchor slab 3 on whole anchor slab 11 corresponds.It is described The aperture for prestressed anchor cable 10 is additionally provided on whole anchor slab 11.
When connecting prestress wire 6 and prestress anchorage cable 10 by the whole anchor slab 11, a test cable is set 9, it is detected after the test cable 9 reaches design 1.5 times of anchor force through anchor force, then carry out the construction of prestress anchorage cable 10.Institute The specific structure for stating prestress anchorage cable 10 is as shown in Figure 6.
Embodiment
It is 355m that the present invention, which is applied in main span length, and main push-towing rope ratio of rise to span is straight on 1/10 pipeline suspension bridge, to transport one Diameter Ф 1016mm gas pipeline and a D150mm aqueduct.The pipeline suspension bridge includes 2 groups of main push-towing ropes altogether, and every group of spacing is 3m;Every group of main push-towing rope is made of 2 type twin-screw main push-towing ropes of PES5 × 265, every main push-towing rope spacing 550mm.Conduit bridge east bank main push-towing rope is adopted Pier is anchored with gravity type, slope surface is steeper at the main push-towing rope anchorage point of west bank, and using tunnel anchorage anchorage style, tunnel anchoring depth is 35m, u-shaped cross-section, tunnel front end section are 7.8 × 6m, and bottom section is 7.8 × 9.1m, section width 7.5m, and arch is straight Diameter 7.8m, straightway height 6m, transition bottom level 9.1m.Prestressed Rock is set on rear side of tunnel anchorage, 8 beam prestressing force are set Anchor cable, anchor cable model CPS15-24.
Prestress wire is anchored on the anchor face of male cone body transition by whole anchor slab in tunnel anchorage, and each anchor slab is long 1400mm, wide 2230mm, application example design four pieces of whole anchor slabs altogether, and prestress wire institute is respectively set in whole anchor slab two sides The through-hole needed is corresponded with positioning anchor slab aperture, and every piece of whole anchor slab installs 2 prestress anchorage cables.On the whole anchor slab of distance First layer HRB400 φ 16mm reinforced mesh is respectively set in square 100mm, and the whole anchor slab of first layer reinforced mesh distance is 100mm, Every layer of reinforced mesh spacing 80mm, bar spacing are 100 × 100mm, are equipped with 20 layers of reinforced mesh altogether.
As shown in fig. 6, application example designs 8 prestress anchorage cables altogether, prestress anchorage cable uses the underrelaxation of CPS15-24 type Epoxy sprays non-bending steel cable, using bellows+epoxide resin protective.Prestress anchorage cable should first be carried out excavating to hole bottom Test carries out anchor force detection after installing anchor cable experiment rope first, and reaching 1.5 times of predetermined anchor force or more qualifications can apply Work prestress anchorage cable.
On the contact surface of male cone body straightway front, the twin-screw of external main push-towing rope end adjusts anchorage and is anchored at main push-towing rope anchor Gu on seat, application example totally four main push-towing ropes, i.e. four main push-towing rope anchorages.The long 2130mm in anchorage bottom of every main push-towing rope, it is wide 1360mm, through-hole needed for prestress wire is respectively set in each anchorage two sides of the bottom, every main push-towing rope are equipped with 16 φ The prestress wire of 15.2mm × 4.It is followed successively by below main push-towing rope anchorage and positions anchor slab, HRB400 φ 16mm reinforced mesh, first Layer reinforced mesh Distance positioning anchor slab is 100mm, and every layer of reinforced mesh spacing is 80mm, and bar spacing is 100 × 100mm, altogether It is equipped with 20 layers of reinforced mesh.After completing positioning anchor slab, reinforced mesh, prestress wire, reinforced mesh and whole anchor slab installation, Male cone body straightway, transition are tamped using C30 concrete.
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field For art personnel, the invention may be variously modified and varied.All within the spirits and principles of the present invention, made any to repair Change, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system characterized by comprising
External main push-towing rope (13), one end are anchored on king-tower (14), and the other end is anchored at the main push-towing rope anchorage (2) on male cone body head On;
Male cone body is located at the area Mao Zhi country rock (15) inside, is equipped with main push-towing rope anchorage (2) on the outside of the head of the male cone body, institute The lateral tail for stating male cone body is equipped with whole anchor slab (11);Several prestress wires (6), and institute are equipped in the male cone body It states several prestress wires (6) to arrange with the axis parallel of the male cone body, the one of the prestress wire (6) End is anchored on the main push-towing rope anchorage (2), and the other end of the prestress wire (6) is anchored at the whole anchor slab (11) On;
Prestress anchorage cable (10), one end anchor the area Mao Zhi rear portion country rock, and the other end is anchored on the whole anchor slab (11), Under the action of the prestress anchorage cable (10), the area Mao Zhi country rock and male cone body are connected as an entirety and participate in stress jointly, resist The pulling force of the external main push-towing rope (13).
2. pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system according to claim 1, which is characterized in that the male cone The tilt angle of body and horizontal plane is identical as the angle of horizontal plane with external main push-towing rope (13).
3. pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system according to claim 2, which is characterized in that the male cone Body is made of straightway (5) and transition (8), wherein the cross section of the straightway (5) is elongated, the transition (8) Cross section be in isosceles trapezoid, the side short side of the strip is the head of male cone body, the other side short side of the strip It is connect with the upper bottom of the isosceles trapezoid, the bottom of the isosceles trapezoid is the tail portion of the male cone body;The male cone body breaks Face is in the shape of a hoof.
4. pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system according to claim 1, which is characterized in that in the anchor Inside cock body, the both ends of the prestress wire (6) are respectively arranged with reinforced mesh (4) and carry out partial pressing.
5. pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system according to claim 2, which is characterized in that in the master It is provided with positioning anchor slab (3) below cable anchorage (2), positions the prestress wire (6) for whole, guarantees described pre- The accuracy of prestress steel strand (6) anchorage point.
6. pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system according to claim 1, which is characterized in that complete to determine After position anchor slab (3), reinforced mesh (4), prestress wire (6) and the installation of whole anchor slab (11), adopted inside the male cone body It is filled with C30 concrete (12).
7. pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system according to claim 5, which is characterized in that the entirety Through-hole needed for being provided with prestress wire (6) on anchor slab (11), and the prestress wire on the whole anchor slab (11) Prestress steel twist line three-way hole on through-hole and positioning anchor slab (3) corresponds, the prestress steel twist on the entirety anchor slab (11) Line three-way hole is symmetrical in the two sides of whole anchor slab (11), and the middle of the entirety anchor slab (11), which is equipped with, is used for prestressed The aperture of anchor cable (10).
8. pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system according to claim 1, which is characterized in that passing through When stating whole anchor slab (11) connection prestress wire (6) and prestress anchorage cable (10), a test cable (9) is set, through anchoring After the power detection test cable (9) reaches 1.5 times of design anchor force, then carry out the construction of prestress anchorage cable (10).
9. pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system according to claim 5, which is characterized in that
External main push-towing rope (13) end adjusts anchorage (1) using double-screw type;
Main push-towing rope anchorage (2) includes the vertical plate of level board and 4 parallel arrangements, and the vertical plate is arranged perpendicular to level board, And the vertical plate and level board are integrally formed, and are respectively provided between the level board and vertical plate and between vertical plate and vertical plate There is stiffener;Through-hole needed for the two sides of the level board are symmetrically arranged with prestress wire (6), and on the level board Prestress steel twist line three-way hole on prestress steel twist line three-way hole and positioning anchor slab (3) corresponds;On 4 vertical plates respectively It is provided with the hole passed through for pin shaft (7), the screw rod (33) of described external main push-towing rope (13) end is fixed on the main push-towing rope by pin shaft (7) On anchorage (2).
10. pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system according to claim 9, which is characterized in that described fixed The level board of position anchor slab (3), whole anchor slab (11) and main push-towing rope anchorage (2) is each perpendicular to the section setting of the male cone body.
CN201910201699.0A 2019-03-18 2019-03-18 Suspension cable pipeline bridge tunnel type anchorage main cable anchoring system Active CN109898414B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910201699.0A CN109898414B (en) 2019-03-18 2019-03-18 Suspension cable pipeline bridge tunnel type anchorage main cable anchoring system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910201699.0A CN109898414B (en) 2019-03-18 2019-03-18 Suspension cable pipeline bridge tunnel type anchorage main cable anchoring system

Publications (2)

Publication Number Publication Date
CN109898414A true CN109898414A (en) 2019-06-18
CN109898414B CN109898414B (en) 2024-05-24

Family

ID=66953781

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910201699.0A Active CN109898414B (en) 2019-03-18 2019-03-18 Suspension cable pipeline bridge tunnel type anchorage main cable anchoring system

Country Status (1)

Country Link
CN (1) CN109898414B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB8327978D0 (en) * 1983-10-19 1983-11-23 Manuf Aceros Caucho Sa Cable anchorage
CN102352601A (en) * 2011-08-15 2012-02-15 四川省交通运输厅公路规划勘察设计研究院 Tunnel type composite anchorage
CN103590332A (en) * 2013-11-25 2014-02-19 中铁第四勘察设计院集团有限公司 Tunnel type anchorage suitable for soft rock area
CN108867378A (en) * 2018-09-17 2018-11-23 四川省铁路产业投资集团有限责任公司 A kind of Techniques of Tunnel-Type Anchorage for Suspension Bridge and construction method
CN209836796U (en) * 2019-03-18 2019-12-24 中国石油天然气集团有限公司 Tunnel type anchorage main cable anchoring system for suspension cable pipeline bridge
CN212358029U (en) * 2020-06-08 2021-01-15 中铁五局集团机械化工程有限责任公司 Tunnel type anchorage structure for cable crane

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB8327978D0 (en) * 1983-10-19 1983-11-23 Manuf Aceros Caucho Sa Cable anchorage
CN102352601A (en) * 2011-08-15 2012-02-15 四川省交通运输厅公路规划勘察设计研究院 Tunnel type composite anchorage
CN103590332A (en) * 2013-11-25 2014-02-19 中铁第四勘察设计院集团有限公司 Tunnel type anchorage suitable for soft rock area
CN108867378A (en) * 2018-09-17 2018-11-23 四川省铁路产业投资集团有限责任公司 A kind of Techniques of Tunnel-Type Anchorage for Suspension Bridge and construction method
CN209836796U (en) * 2019-03-18 2019-12-24 中国石油天然气集团有限公司 Tunnel type anchorage main cable anchoring system for suspension cable pipeline bridge
CN212358029U (en) * 2020-06-08 2021-01-15 中铁五局集团机械化工程有限责任公司 Tunnel type anchorage structure for cable crane

Also Published As

Publication number Publication date
CN109898414B (en) 2024-05-24

Similar Documents

Publication Publication Date Title
CN108867378B (en) Suspension bridge tunnel type anchorage and construction method
CN109322239B (en) Design method of wind-resistant system of pipeline suspension cable crossing structure
CN109505224B (en) Design method of wind-resistant system of pipeline suspension cable crossing structure
Muller The bi-stayed bridge concept: Overview of wind engineering problems
CN109914242B (en) Method for anchoring main cable of combined tunnel anchor type large-span suspension cable pipeline bridge
CN108999088A (en) A kind of construction method of cable-stayed bridge
CN209836796U (en) Tunnel type anchorage main cable anchoring system for suspension cable pipeline bridge
CN113073554A (en) Large-tonnage anchorage structure on steep slope and construction method thereof
CN109898414A (en) A kind of pipeline suspension bridge tunnel-type anchorage main push-towing rope anchor system
CN106948263A (en) A kind of cable-stayed bridge concrete pylon anchor tie plate
CN111705658A (en) Combined type tunnel anchor
CN111519530A (en) Pier head type tunnel anchor and construction method
CN206800195U (en) A kind of cable-stayed bridge concrete pylon anchor tie plate
Falbe-Hansen et al. Stonecutters bridge-detailed design
Dai et al. New Songhua river bridge: a continuous girder, tied arch, hybrid bridge with four rail tracks in Harbin, China
CN221167445U (en) Reverse anchoring structure suitable for suspension bridge
CN114858436B (en) Slidable steel anchor box combined cable tower model test device
CN108999073A (en) A kind of cable-stayed bridge
CN212357991U (en) Combined type tunnel anchor
CN103174087A (en) Suspended cable-cable-stayed cooperation system comprising inclined sling and variable cross-section main cable
Park et al. Planning and Design of Jeokgeum Grand Bridge
CN217231859U (en) Foundation pit truss steel support tensile structure
CN213538648U (en) Transversely unbalanced cable-stayed buckle hanging system
CN203716049U (en) Externally-prestressed bridge structure with replaceable steel cables
Svensson et al. THE CONCRETE CABLE-STAYED HELGELAND BRIDGE IN NORWAY.

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Country or region after: China

Address after: 100120 Xicheng District six paw Kang in Beijing City

Applicant after: CHINA NATIONAL PETROLEUM Corp.

Applicant after: China Petroleum Pipeline Engineering Co.,Ltd.

Applicant after: DESIGN BRANCH OF CHINA PETROLEUM PIPELINE ENGINEERING Corp.

Address before: 100120 Xicheng District six paw Kang in Beijing City

Applicant before: China National Petroleum Corp.

Country or region before: China

Applicant before: China Petroleum Pipeline Engineering Co.,Ltd.

Applicant before: DESIGN BRANCH OF CHINA PETROLEUM PIPELINE ENGINEERING Corp.

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20240426

Address after: 100120 Xicheng District six paw Kang in Beijing City

Applicant after: CHINA NATIONAL PETROLEUM Corp.

Country or region after: China

Applicant after: China Petroleum Pipeline Engineering Co.,Ltd.

Applicant after: CHINA PETROLEUM PIPELINE ENGINEERING Corp.

Address before: 100120 Xicheng District six paw Kang in Beijing City

Applicant before: CHINA NATIONAL PETROLEUM Corp.

Country or region before: China

Applicant before: China Petroleum Pipeline Engineering Co.,Ltd.

Applicant before: DESIGN BRANCH OF CHINA PETROLEUM PIPELINE ENGINEERING Corp.

GR01 Patent grant