CN109885289A - A kind of 3D visualization computer room management system and management method - Google Patents

A kind of 3D visualization computer room management system and management method Download PDF

Info

Publication number
CN109885289A
CN109885289A CN201810804450.4A CN201810804450A CN109885289A CN 109885289 A CN109885289 A CN 109885289A CN 201810804450 A CN201810804450 A CN 201810804450A CN 109885289 A CN109885289 A CN 109885289A
Authority
CN
China
Prior art keywords
computer room
data
management
module
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810804450.4A
Other languages
Chinese (zh)
Inventor
汪莹
李溢杰
亢中苗
刘紫健
李星南
梁文娟
林结昌
李仲斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Power Grid Co Ltd
Electric Power Dispatch Control Center of Guangdong Power Grid Co Ltd
Original Assignee
Guangdong Power Grid Co Ltd
Electric Power Dispatch Control Center of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Power Grid Co Ltd, Electric Power Dispatch Control Center of Guangdong Power Grid Co Ltd filed Critical Guangdong Power Grid Co Ltd
Priority to CN201810804450.4A priority Critical patent/CN109885289A/en
Publication of CN109885289A publication Critical patent/CN109885289A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of 3D visualization computer room management system and management methods, computer room management system is visualized including a kind of 3D, it is made of visual layers, functional layer, engine layers, process layer, accumulation layer and interface layer, and provide a kind of management method of 3D visualization computer room, computer room is subjected to 3D presentation, visualized operation by way of human-computer interaction, and computer room assets, capacity, monitoring, demonstration, communication framework are visualized, and achieve the purpose that 3D visually manages computer room.

Description

A kind of 3D visualization computer room management system and management method
Technical field
The present invention relates to electronic information technical fields, visualize computer room management system and pipe more particularly, to a kind of 3D Reason method.
Background technique
Computer room net hierarchical management at this stage at present, with intelligent development people's Shortcomings computer room net hierarchical at this stage Management, with the hierarchical management at this stage of intelligent development people's Shortcomings computer room net, with intelligent development people's Shortcomings Status and many kinds of status for serving single industry of corresponding information network O&M system and corresponding information network fortune It maintains many kinds of status for serving single industry of system and corresponding information network O&M system is many kinds of serves single industry It cannot achieve and be effectively decoupled between system.Traditional information system is guiding with business demand, and massive information data are not also imitated With using that can not fit the problem of repeated construction wastes, massive information data, which also do not obtain effect analysis and utilization, to fit for analysis The following intensive big management and running mode requirement is answered, comparing distinct issues has the following:
1) existing information system and O&M support usually take target based on single business, are to take mesh with data business mostly Mark is in a manner of database, chart text and two-dimensional network topology mostly, and there is only weak Lian Ku, figure between different business The mode of table text and two-dimensional network topology, there is only weak even library, chart text and two-dimensional networks to open up between different business The mode flutterred, there is only Weak links between different business, it is difficult to realize that intuitive management connects, it is difficult to realize intuitive management and point It analyses, data volume sea, which increases existing analysis, after intensive management will far be unable to meet production management requirement;
2) communication resource system is based on tabling look-up manually, is unable to satisfy under intensive management background and increases communication resource system on a large scale System is unable to satisfy under intensive management background extensive increased service supporting capacity based on tabling look-up manually;
3) existing alarm monitoring system province and district city's score of the game dissipates construction, can not be supported on multi-disciplinary, the cross-system of the whole province's level Association analysis application, cannot achieve the alarm of quick the whole network trace to the source and fault location.
For a long time, due to being realized that technology, operation management theory are limited by system, support computer room net fortune support computer room net The system Construction of operation management substantially centered on specialized function, thereby produce a large amount of point of professional operation management system, Point function operation management system and divide management domain operation management system, and then leads to the generation of a large amount of operation/maintenance data isolated islands, and The use that a large amount of operation maintenance personnels are responsible for system is needed to configure, the hair for the operation/maintenance data comprehensive benefit largely dispersed seriously is constrained It waves.Meanwhile with the introduction of new network technology, the proposition of new business demand, the construction of new operation management system, operation/maintenance data is also Will continue to divide and increase, valuable data can not capitalization, the income of operation support system is low, or even information-based overload phenomenon Become to become increasingly conspicuous.
On the other hand, transmission network and data network of the computer room net due to being distributed the whole province is related to a large amount of route, equipment and each The management of the computer rooms such as substation, once going wrong, is needed by a large amount of geography information, equipment during daily O&M Information and monitoring system, and the information that interconnects carry out analysis investigation failure, these information are dispersed in each tool at present Among, and network is to need that the effective assistant analysis of ability is presented in the form of topology, to the dimension of communications network architecture diagram itself A huge problem, a Zhang great Tu information content reach greatly pillar reason simultaneously, and a point several figures are difficult to search again, in addition each chain Road, each equipment port it there are also standby redundancy mechanism, the business information of physical location and support that it is related to is also Different, this is integrated into the information for needing to integrate many latitudes among one view, this day-to-day operation to communication network There is very real important and urgency with operation management.
Therefore it is necessary to carry out the research that provincial coordination communicates intensive management system, to construct intensive communication fortune Tie up management framework based theoretical.Meanwhile using three-dimensional modeling interaction linkage presentation technology, selection is suitable for computer room field Three-dimensional visualization scheme carries out traffic guidance's cockpit key technology research.
Summary of the invention
Present invention aim to address said one or multiple defects, propose that a kind of 3D visualizes computer room management system and pipe Reason method
To realize the above goal of the invention, the technical solution adopted is that:
A kind of 3D visualizes computer room management system, including visual layers, functional layer, engine layers, process layer, accumulation layer and connects Mouth layer;
The visual layers, the 3D scene that the unit in computer room and computer room is built using Virtual Simulation and Geographic information data carries out display and visualized operation;
The functional layer, emulation data and geographic information data to the 3D scene built using Virtual Simulation into Row management;
The engine layers, emulation data and geographic information data for driving 3D scene construction are shown in visual layers Show and visualized operation;
The process layer, for the emulation data and geographic information data of 3D scene construction to be carried out classificationization processing, The emulation data and geographic information data of different sub-systems are subjected to reconciliation process, and by the emulation data and ground of different sub-systems Reason information data is associated integration after carrying out integration and standardization;
The accumulation layer, for emulation data, geographic information data and the real time monitoring of 3D scene construction, operation data It is stored;
The interface layer, for connecting real time monitoring, the fortune of the unit in acquisition module acquisition computer room and computer room Seek data.
Preferably, the visual layers include 3D visualization model, GIS visualization model and framework visualization model;
The 3D visualization model, for the real time monitoring of the unit in computer room and computer room, the 3D of operation data Visualization display and visualized operation;
The GIS visualization model, the geographic information data for the unit in computer room and computer room carries out 3D can Depending on changing display and visualized operation;
The framework visualization model, for the computer rooms of different sub-systems, unit carry out 3D visualization display and Visualized operation.
Preferably, the functional layer includes Environment Management module, device management module, pipeline management module, GIS management Module, view management module, configuration management module and monitoring management module;
The appearance of computer room is completely presented with Virtual Simulation for the Environment Management module, according to the true appearance of computer room 3D modeling is completed, the basic specification information of building is managed;And
Computer room floor structure is completely presented with Virtual Simulation, 3D modeling is completed according to the practical building structure of floor, Analog true identity manages the information and equipment display case of each computer room;And
Computer room structure is completely presented with Virtual Simulation, 3D modeling is completed according to the practical building structure of computer room, it can mould The information and equipment display case of quasi- true identity management computer room;
The device management module, for the emulation data of the unit in computer room, geographic information data and in real time Monitoring, operation data are managed;
The pipeline management module, for connecting link and connecting link between unit emulation data, Reason information data and real time monitoring, operation data are managed;
The GIS management module, for the geographic information data of pipeline, the geographic information data of unit and computer room Geographic information data and real time monitoring, operation data be managed;
The view management module, for the mimetic view of pipeline, unit and computer room, geography information view and Real time monitoring, operation view are managed;
The configuration management module, for configuring the visualisation parameters management and visual layers engine configuration parameter of system Management;
The monitoring management module carries out pipe for the real time monitoring of pipeline, unit and computer room, operation data Reason.
Preferably, the engine layers include 3D engine modules, visualization engine module and 2D engine modules;
The 3D engine modules are for driving visual layers 3D rendering configurations;
The visualization engine module is used to drive the configuration and management of 3D visualization model in visual layers;
Docking of the 2D engine modules for system logic topology 2D processing and geography information.
Preferably, the process layer includes object data processing, Geoprocessing and operation data processing;
3D scene of the object data processing for building to Virtual Simulation is classified, integrated and is standardized Processing;
The Geoprocessing for classified to the geographic information data of the unit in computer room and computer room, Integration and standardization;
The operation data processing divides for the real time monitoring to pipeline, unit and computer room, operation data Class, integration and standardization.
Preferably, the accumulation layer includes threshold value memory module, monitoring and operation data memory module, 3D virtual scene Configuration storage module, system parameter memory module and manipulation memory module;
The threshold value memory module is used to join the security parameter of the pipeline of setting, unit and computer room and alarm Several storages;
Pipeline, unit and the computer room that the monitoring and operation data memory module are used to acquire acquisition module Real time data is stored;
The 3D virtual scene configuration storage module is used to carry out sorting parameter, integration parameters to the 3D scene of default And standardization parameter is stored;
The system parameter memory module is used for 3D rendering configurations parameter, visual configuration parameter, 2D to default Logical topology parameter, geography information parameter and engine configuration parameter are stored;
The manipulation memory module manipulates storage and manipulation log storage for user every time.
Preferably, the interface layer includes general-purpose interface and expansion interface.
Preferably, the visual layers further include the man-machine interactive interface for human-computer interaction.
The present invention also provides a kind of 3D visualization computer room management method, including by way of human-computer interaction by computer room Progress 3D presentation, visualized operation and computer room assets, capacity, monitoring, demonstration, communication framework are visualized, and reaching 3D can Purpose depending on managing computer room.
Compared with prior art, the beneficial effects of the present invention are:
1) have geographical location visualization function: mode and GIS including more scenes classification browsing and classification it is clear The browsing look at more sites, can be in the connection of GIS expression network line;
2) has computer room visualization function: can including environment, the visualization of assets pipeline, capacity visualization, monitoring and demonstration Depending on changing;
3) have communication construction visualization function: the management including shape library draws editor's visualization function: drawing editor And the distribution management function of view, have combination drill down query;
4) have end-to-end visualization function: geography information and physical message and logic being combined using GIS, can be connect The property alarm data for entering monitoring tools is combined with physical message and logic, can access the property alarm data view of monitoring tools It is associated analysis.
Detailed description of the invention
Fig. 1 is frame principle of the invention.
Specific embodiment
The attached figures are only used for illustrative purposes and cannot be understood as limitating the patent;
Below in conjunction with drawings and examples, the present invention is further elaborated.
Embodiment 1
Referring to Fig.1, the present invention provides a kind of 3D to visualize computer room management system, including visual layers, functional layer, engine Layer, process layer, accumulation layer and interface layer;
The visual layers, the 3D scene that the unit in computer room and computer room is built using Virtual Simulation and Geographic information data carries out display and visualized operation;And the visual layers further include the human-computer interaction for human-computer interaction Interface.
Wherein, the visual layers include 3D visualization model, GIS visualization model and framework visualization model;
The 3D visualization model, for the real time monitoring of the unit in computer room and computer room, the 3D of operation data Visualization display and visualized operation;
The GIS visualization model, the geographic information data for the unit in computer room and computer room carries out 3D can Depending on changing display and visualized operation;
The framework visualization model, for the computer rooms of different sub-systems, unit carry out 3D visualization display and Visualized operation.
The functional layer, emulation data and geographic information data to the 3D scene built using Virtual Simulation into Row management;
Wherein, the functional layer includes Environment Management module, device management module, pipeline management module, GIS management mould Block, view management module, configuration management module and monitoring management module;
The appearance of computer room is completely presented with Virtual Simulation for the Environment Management module, according to the true appearance of computer room 3D modeling is completed, the basic specification information of building is managed;And
Computer room floor structure is completely presented with Virtual Simulation, 3D modeling is completed according to the practical building structure of floor, Analog true identity manages the information and equipment display case of each computer room;And
Computer room structure is completely presented with Virtual Simulation, 3D modeling is completed according to the practical building structure of computer room, it can mould The information and equipment display case of quasi- true identity management computer room;
The device management module, for the emulation data of the unit in computer room, geographic information data and in real time Monitoring, operation data are managed;
The pipeline management module, for connecting link and connecting link between unit emulation data, Reason information data and real time monitoring, operation data are managed;
The GIS management module, for the geographic information data of pipeline, the geographic information data of unit and computer room Geographic information data and real time monitoring, operation data be managed;
The view management module, for the mimetic view of pipeline, unit and computer room, geography information view and Real time monitoring, operation view are managed;
The configuration management module, for configuring the visualisation parameters management and visual layers engine configuration parameter of system Management;
The monitoring management module carries out pipe for the real time monitoring of pipeline, unit and computer room, operation data Reason.
The engine layers, emulation data and geographic information data for driving 3D scene construction are shown in visual layers Show and visualized operation;
Wherein, the engine layers include 3D engine modules, visualization engine module and 2D engine modules;
The 3D engine modules are for driving visual layers 3D rendering configurations;
The visualization engine module is used to drive the configuration and management of 3D visualization model in visual layers;
Docking of the 2D engine modules for system logic topology 2D processing and geography information.
The process layer, for the emulation data and geographic information data of 3D scene construction to be carried out classificationization processing, The emulation data and geographic information data of different sub-systems are subjected to reconciliation process, and by the emulation data and ground of different sub-systems Reason information data is associated integration after carrying out integration and standardization;
Wherein, the process layer includes object data processing, Geoprocessing and operation data processing;
3D scene of the object data processing for building to Virtual Simulation is classified, integrated and is standardized Processing;
The Geoprocessing for classified to the geographic information data of the unit in computer room and computer room, Integration and standardization;
The operation data processing divides for the real time monitoring to pipeline, unit and computer room, operation data Class, integration and standardization.
The accumulation layer, for emulation data, geographic information data and the real time monitoring of 3D scene construction, operation data It is stored;
The accumulation layer includes threshold value memory module, monitoring and operation data memory module, the configuration storage of 3D virtual scene Module, system parameter memory module and manipulation memory module;
The threshold value memory module is used to join the security parameter of the pipeline of setting, unit and computer room and alarm Several storages;
Pipeline, unit and the computer room that the monitoring and operation data memory module are used to acquire acquisition module Real time data is stored;
The 3D virtual scene configuration storage module is used to carry out sorting parameter, integration parameters to the 3D scene of default And standardization parameter is stored;
The system parameter memory module is used for 3D rendering configurations parameter, visual configuration parameter, 2D to default Logical topology parameter, geography information parameter and engine configuration parameter are stored;
The manipulation memory module manipulates storage and manipulation log storage for user every time.
The interface layer, for connecting real time monitoring, the fortune of the unit in acquisition module acquisition computer room and computer room Seek data.
Wherein, the interface layer includes general-purpose interface and expansion interface.
The present invention also provides a kind of 3D visualization computer room management method, including by way of human-computer interaction by computer room Progress 3D presentation, visualized operation and computer room assets, capacity, monitoring, demonstration, communication framework are visualized, and reaching 3D can Purpose depending on managing computer room.
It is specifically included:
1. capacity visualizes: capacity visualized management function realizes the core place spatial content pipe as unit of cabinet Reason, is presented with tree data and three-dimensional scenic management two ways shows computer room and cabinet entirety service condition simultaneously, for It is accurately counted and is managed with space and available space.The capacity resource of more efficient management computer room where helping Core Field, It makes the load of all kinds of resources of computer room more balanced, makes operation maintenance personnel that the core place volume weight tube as unit of cabinet may be implemented Reason.
It realizes the core place spatial content statistical management as unit of cabinet, is presented and three-dimensional scenic pipe with tree data Reason two ways shows computer room and cabinet entirety service condition simultaneously, for use space and available space carries out accurate statistics with Management.
It is specific to be divided into again:
1) spatial statistics visualize: computer room cabinet space capacity statistical distribution statistics, energy are supported in 3D visible environment The position the U service condition of relevant cabinet is distinguished according to different colors, the position U such as used and residue U;It supports to computer room The distribution map visualization rendering performance of cabinet space.
2) power statistic visualizes: computer room cabinet rated power distribution statistics are supported in 3D visible environment, it can basis Different colors distinguishes relevant cabinet watt level;Support the distribution map visualization rendering performance to computer room cabinet power.
3) load-bearing statistics visualization: supporting to count computer room load-bearing distribution situation in 3D visible environment, can be with column Shape figure mode intuitively shows the weight bearing situations of each cabinet in current computer room, facilitates administrator to understand machine room layout in real time and carries out Effectively adjustment.
4) seat in the plane statistics visualization: having an X-rayed in 3D visible environment in current building environment, the seat in the plane used with The case where remaining seat in the plane.
Space search function is established by capacity visualization, finds with helping operation maintenance personnel quicklook and closes for newly added equipment Suitable restocking space, operation maintenance personnel can be according to device model, or directly defines U high, load-bearing requirements and the electricity of restocking equipment Multiple combination conditions such as force request carry out adaptation space search, and qualified space inspection can intuitively be presented in computer room outdoor scene Rope formulates and implements scheme as a result, space needed for enabling operation maintenance personnel accurately to position.
Computer room capacity query: it supports to look into the continuously available spatial distribution of cabinets all in computer room in 3D visible environment It askes, from U high, three dimensions of electric power and load-bearing are comprehensive to complete spatial statistics, and statistical result can be in 3D environment with histogram side Formula intuitively shows.
Cabinet capacity query: searching for cabinet in 3D visible environment, passes through input cabinet fuzzy query conditions retrieval Cabinet, system list qualified cabinet list of file names within the scope of active view, select a cabinet, check cabinet the position U, Electric power, load-bearing occupancy situation.
2. monitoring visualization: monitoring visualization will help core place integration dispersion monitoring tools, realize monitoring tools, The value maximization of monitoring data really changes monitoring data island phenomenon, establishes unified monitoring information interface, at the same reverse by Data and report spread unchecked situation caused by two-dimensional signal density is insufficient, and in the form of 3D by core place various aspects the case where is straight Expression is seen, it is horizontal to promote monitoring management conscientiously.
Visualization system support is docked with information technoloy equipment monitoring system, and the visualization for completing monitoring data and warning message is in Now, it can be achieved that pointing device can directly pop up the monitored picture of network management and monitoring system.
Monitoring equipment performance information management refers to the performance data information monitored by the management equipment of 3D view.Pass through Unique ID of equipment gets the current performance information index of this equipment, and current equipment is checked out on monitoring of tools information panel The performance data information of all indexs.Monitoring device is clicked, information panel occurs, selection monitoring button checks out performance monitoring The page.
Calculator room equipment warning information requires all warning information of computer room real time inspection on the interface computer room 3D.Main management Alarm equipment type is two classes: directly there is alarm icon and equipment discoloration prompt in this equipment in independent body equipment alarm, clicks Alarm icon or alarm equipment manage detailed warning information.Equipment alerts in cabinet, occurs alarm figure on affiliated cabinet Mark and cabinet discoloration prompt, click alarm icon or alarm equipment manages detailed warning information, under alarm status, double-click machine Cabinet enters in cabinet, and equipment discoloration prompt occurs in alarm equipment, and pointing device can check detailed warning information interface.
3. demonstration visualization: on the basis of visualization function physical environment simulation reconstruction where Core Field is reported in demonstration, Flexibly powerful visualized management function is provided, the diversified regulatory requirement of core place infrastructure, such as logic may be implemented Relationship expression, simulated failure, simulation air-flow, PPT integration and automatic detecting and demonstration route customization etc..Provide one it is powerful Virtual film studio and video display operating room, user can make abundant in content, lively core colorful, both pictures and texts are excellent on this platform Place is introduced and demo content, with the every aspect in fresh and new format management core place, strong promotion core place Overall image fully demonstrates the management level in core place.
It specifically includes:
PPT demonstration is reported: PPT presentation file is means most general in current introduction and report, and visualization is reported in demonstration Function supports user that multistage animation is embedded in PPT presentation file, and can shuangping san PPT and core place are three-dimensional in systems Simulating scenes realize the two-way interaction of PPT and three-dimensional artificial scene, to realize that best demonstration is reported to enrich lively means Effect.
PPT document management: PPT presentation file is means most general in current introduction and report, and visualization is reported in demonstration Function supports user that multistage animation is embedded in PPT presentation file, and can shuangping san PPT and core place are three-dimensional in systems Simulating scenes realize the two-way interaction of PPT and three-dimensional artificial scene, to realize that best demonstration is reported to enrich lively means Effect.
Computer room browsing demonstration: system provides powerful easy-to-use cartoon making function, and user can be in three-dimensional artificial scene Multiple watching focuses are defined, set watching focus residence time and switching time, and can define subtitle, broadcasting speed, visual angle and the road of animation Line, so that easily generating smooth lively core place introduces Show Me animation.
Work visual angle management: user saves the visual angle in virtual simulation environment, can be after then being clicked at once It carries out view angle switch (dancing mode), to promote the efficiency of information searching.Each user role can it is customized oneself Visual angle.Default view can be placed into virtual emulation desktop and form shortcut.
4. communication framework visualizes: the expected Architecture Analysis that provides of communication construction visualization manages platform, realizes management power grid The comprehensive analysis such as configuration data, topological view, the monitoring data of communication object and management.
5. end-to-end monitoring visualizes: systematicness combs the incidence relation between each layer configuration object, gets through each profession The technical barrier in field, connection transmission network to service application to IT infrastructure to geography information (GIS), formation are answered by business With, the end-to-end IT visualized management model that is constituted to GIS of system platform, network and infrastructure and physical environment.
6. monitoring data visualizes: the integration of monitoring data is broadly divided into alarm data and performance data, and alarm data is anti- Reflect be each logical node current state, by view end to end, the intuitive network architecture of reflection in real time, IT component, basis are set The alert event applied, alert event is associated with view, object, report of interest can be flexibly defined in the different monitoring page Alert event.Performance data refers to that systematicness combs the incidence relation of all kinds of monitor control indexes and monitor control index and management object, Different monitoring view, can be with monitor control index real time execution parameter that flexible choice to be presented.
The integration of monitoring data is broadly divided into alarm data and performance data, and alarm data reflection is each logical node Current state, by view end to end, the intuitive alert event for reflecting the network architecture, IT component, infrastructure in real time will be reported Alert event is associated with view, object, can flexibly define alert event of interest in the different monitoring page.Performance data is Refer to that systematicness combs the incidence relation of all kinds of monitor control indexes and monitor control index and management object, it, can be in different monitoring view The flexible choice monitor control index real time execution parameter to be presented.
Monitoring visualization will help the monitoring tools of core place integration dispersion, realize the valence of monitoring tools, monitoring data Value maximizes, and really changes monitoring data island phenomenon, establishes unified monitoring information interface, while reversing since two-dimensional signal is close Data and report spread unchecked situation caused by degree is insufficient, are intuitively expressed in core place in the form of 2D combination 3D.
7. alarm visualization: the intuitive alert event for reflecting application system, IT component, infrastructure in real time, by thing of alarming Part is associated with view, object, can flexibly define alert event of interest in the different monitoring page.
8. monitor control index visualizes: systematicness comb all kinds of monitor control indexes and monitor control index with manage being associated with for object Relationship can be with monitor control index real-time status that flexible choice to be presented in different monitoring view.
Obviously, the above embodiment of the present invention be only to clearly illustrate example of the present invention, and not be pair The restriction of embodiments of the present invention.For those of ordinary skill in the art, may be used also on the basis of the above description To make other variations or changes in different ways.There is no necessity and possibility to exhaust all the enbodiments.It is all this Made any modifications, equivalent replacements, and improvements etc., should be included in the claims in the present invention within the spirit and principle of invention Protection scope within.

Claims (9)

1. a kind of 3D visualizes computer room management system, which is characterized in that including visual layers, functional layer, engine layers, process layer, deposit Reservoir and interface layer;
The visual layers, the 3D scene that the unit in computer room and computer room is built using Virtual Simulation and geography Information data carries out display and visualized operation;
The functional layer carries out pipe to the emulation data and geographic information data of the 3D scene built using Virtual Simulation Reason;
The engine layers, for drive 3D scene construction emulation data and geographic information data visual layers shown with And visualized operation;
The process layer will not for the emulation data and geographic information data of 3D scene construction to be carried out classificationization processing Emulation data and geographic information data with subsystem carry out reconciliation process, and the emulation data of different sub-systems and geography are believed Breath data are associated integration after carrying out integration and standardization;
The accumulation layer is carried out for emulation data, geographic information data and the real time monitoring of 3D scene construction, operation data Storage;
The interface layer, for connecting real time monitoring, the operation number of the unit in acquisition module acquisition computer room and computer room According to.
2. a kind of 3D according to claim 1 visualizes computer room management system, which is characterized in that the visual layers include 3D Visualization model, GIS visualization model and framework visualization model;
The 3D visualization model, it is visual for the real time monitoring of the unit in computer room and computer room, the 3D of operation data Change display and visualized operation;
The GIS visualization model, the geographic information data for the unit in computer room and computer room carry out 3D visualization Display and visualized operation;
The framework visualization model carries out 3D visualization display and visual for the computer rooms of different sub-systems, unit Change operation.
3. a kind of 3D according to claim 1 visualizes computer room management system, which is characterized in that the functional layer includes ring Border management module, device management module, pipeline management module, GIS management module, view management module, configuration management module with And monitoring management module;
The appearance of computer room is completely presented with Virtual Simulation for the Environment Management module, is completed according to the true appearance of computer room 3D modeling manages the basic specification information of building;And computer room floor structure is completely presented with Virtual Simulation, according to floor Practical building structure complete 3D modeling, analog true identity manages the information and equipment display case of each computer room;And with Computer room structure is completely presented in Virtual Simulation, completes 3D modeling, analog true identity according to the practical building structure of computer room Manage the information and equipment display case of computer room;
The device management module, for the unit in computer room emulation data, geographic information data and real time monitoring, Operation data is managed;
The pipeline management module, emulation data, geographical letter for connecting link and connecting link between unit Breath data and real time monitoring, operation data are managed;
The GIS management module, the ground for the geographic information data of pipeline, the geographic information data of unit and computer room Reason information data and real time monitoring, operation data are managed;
The view management module, for the mimetic view of pipeline, unit and computer room, geography information view and in real time Monitoring, operation view are managed;
The configuration management module, for configuring the visualisation parameters management of system and the pipe of visual layers engine configuration parameter Reason;
The monitoring management module, is managed for the real time monitoring of pipeline, unit and computer room, operation data.
4. a kind of 3D according to claim 1 visualizes computer room management system, which is characterized in that the engine layers include 3D Engine modules, visualization engine module and 2D engine modules;
The 3D engine modules are for driving visual layers 3D rendering configurations;
The visualization engine module is used to drive the configuration and management of 3D visualization model in visual layers;
Docking of the 2D engine modules for system logic topology 2D processing and geography information.
5. a kind of 3D according to claim 1 visualizes computer room management system, which is characterized in that the process layer includes pair Image data processing, Geoprocessing and operation data processing;
3D scene of the object data processing for building to Virtual Simulation classified, integrate and standardization at Reason;
The Geoprocessing is for classifying to the geographic information data of the unit in computer room and computer room, being integrated And standardization;
The operation data processing is classified for the real time monitoring to pipeline, unit and computer room, operation data, is whole Conjunction and standardization.
6. a kind of 3D according to claim 1 visualizes computer room management system, which is characterized in that the accumulation layer includes threshold Be worth memory module, monitoring and operation data memory module, 3D virtual scene configuration storage module, system parameter memory module and Manipulate memory module;
The threshold value memory module is used for the security parameter of the pipeline of setting, unit and computer room and alarm parameters Storage;
It is described to monitor the real-time of pipeline, unit and the computer room for being used to acquire acquisition module with operation data memory module Data are stored;
The 3D virtual scene configuration storage module be used to carry out the 3D scene of default sorting parameter, integration parameters and Standardization parameter is stored;
The system parameter memory module is used for 3D rendering configurations parameter, visual configuration parameter, 2D logic to default Topological parameter, geography information parameter and engine configuration parameter are stored;
The manipulation memory module manipulates storage and manipulation log storage for user every time.
7. a kind of 3D according to claim 1 visualizes computer room management system, which is characterized in that the interface layer includes logical With interface and expansion interface.
8. a kind of 3D according to claim 1 visualizes computer room management system, which is characterized in that the visual layers further include Man-machine interactive interface for human-computer interaction.
9. a kind of management method of 3D visualization computer room, which is characterized in that including being carried out computer room by way of human-computer interaction 3D presentation, visualized operation and computer room assets, capacity, monitoring, demonstration, communication framework are visualized, and are reached 3D and are visually managed Manage the purpose of computer room.
CN201810804450.4A 2018-07-20 2018-07-20 A kind of 3D visualization computer room management system and management method Pending CN109885289A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810804450.4A CN109885289A (en) 2018-07-20 2018-07-20 A kind of 3D visualization computer room management system and management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810804450.4A CN109885289A (en) 2018-07-20 2018-07-20 A kind of 3D visualization computer room management system and management method

Publications (1)

Publication Number Publication Date
CN109885289A true CN109885289A (en) 2019-06-14

Family

ID=66924839

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810804450.4A Pending CN109885289A (en) 2018-07-20 2018-07-20 A kind of 3D visualization computer room management system and management method

Country Status (1)

Country Link
CN (1) CN109885289A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110796727A (en) * 2019-09-17 2020-02-14 国网天津市电力公司 Machine room remote panoramic monitoring method based on virtual reality technology
CN110831387A (en) * 2019-11-06 2020-02-21 北京宝兰德软件股份有限公司 Method and device for visually arranging and positioning machine room cabinet
CN111722576A (en) * 2020-06-24 2020-09-29 合肥供水集团有限公司 Water supply industry computer lab 3D visual fortune dimension management system
CN112862337A (en) * 2021-02-23 2021-05-28 广东电网有限责任公司 Data visualization platform management system
CN113297715A (en) * 2021-07-26 2021-08-24 北京优锘科技有限公司 Method, device, equipment and storage medium for realizing pipeline link visualization
CN113590417A (en) * 2021-07-06 2021-11-02 广东电网有限责任公司 Visual management system, method and storage medium for operation of machine room equipment
CN113778815A (en) * 2021-09-15 2021-12-10 深信服科技股份有限公司 Machine room alarm method, system, device and readable storage medium

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102411764A (en) * 2011-08-15 2012-04-11 广东省电力设计研究院 Data management system of electrical network equipment and management method thereof
CN105117835A (en) * 2015-08-18 2015-12-02 电子科技大学 A power grid information machine room three-dimensional visualized management platform based on a B/S framework
CN106095651A (en) * 2016-06-15 2016-11-09 浪潮(北京)电子信息产业有限公司 A kind of 3D virtual computer room method for managing and monitoring and system
CN106647586A (en) * 2017-01-20 2017-05-10 重庆邮电大学 Virtual machine room visualization monitoring management system based on B/S architecture and realization method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102411764A (en) * 2011-08-15 2012-04-11 广东省电力设计研究院 Data management system of electrical network equipment and management method thereof
CN105117835A (en) * 2015-08-18 2015-12-02 电子科技大学 A power grid information machine room three-dimensional visualized management platform based on a B/S framework
CN106095651A (en) * 2016-06-15 2016-11-09 浪潮(北京)电子信息产业有限公司 A kind of 3D virtual computer room method for managing and monitoring and system
CN106647586A (en) * 2017-01-20 2017-05-10 重庆邮电大学 Virtual machine room visualization monitoring management system based on B/S architecture and realization method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110796727A (en) * 2019-09-17 2020-02-14 国网天津市电力公司 Machine room remote panoramic monitoring method based on virtual reality technology
CN110831387A (en) * 2019-11-06 2020-02-21 北京宝兰德软件股份有限公司 Method and device for visually arranging and positioning machine room cabinet
CN110831387B (en) * 2019-11-06 2021-04-27 北京宝兰德软件股份有限公司 Method and device for visually arranging and positioning machine room cabinet
CN111722576A (en) * 2020-06-24 2020-09-29 合肥供水集团有限公司 Water supply industry computer lab 3D visual fortune dimension management system
CN112862337A (en) * 2021-02-23 2021-05-28 广东电网有限责任公司 Data visualization platform management system
CN113590417A (en) * 2021-07-06 2021-11-02 广东电网有限责任公司 Visual management system, method and storage medium for operation of machine room equipment
CN113297715A (en) * 2021-07-26 2021-08-24 北京优锘科技有限公司 Method, device, equipment and storage medium for realizing pipeline link visualization
CN113778815A (en) * 2021-09-15 2021-12-10 深信服科技股份有限公司 Machine room alarm method, system, device and readable storage medium

Similar Documents

Publication Publication Date Title
CN109885289A (en) A kind of 3D visualization computer room management system and management method
CN109889358A (en) A kind of 3D visualization IT monitoring management system
CN107563911A (en) One kind visualization general community information management system
CN108512691A (en) Cloud automatic early-warning O&M monitoring system based on Hadoop
CN109409678B (en) Efficient multifunctional technical standard information system applied to power grid
CN101820532A (en) Method for realizing full three-dimensional intelligent virtual computer room
CN111815751A (en) Intelligent fire-fighting Internet of things visual management system and method
CN109887068A (en) A kind of 3D visualization computer room
CN206039274U (en) Visual intelligent management and control platform of 3D suitable for building
CN110175368A (en) A kind of rail traffic data display systems based on BIM+GIS
CN103645716B (en) Data processing method in a kind of transformer station back brake system and device
CN106780719A (en) The three-dimensional scenic methods of exhibiting and platform of the confined space
CN112148708A (en) Power grid planning-oriented visual application system
CN102354387A (en) Multi-dimensional platform data mining method and system of power grid dispersed power supply information
CN115774488A (en) Cloud service fault simulation diagnosis method based on virtual reality
CN116542387A (en) Intelligent hydrologic system based on Unity3D
CN111106968A (en) Method for constructing information communication intelligent dispatching command sand table
Chen et al. Application research of virtual reality technology in green building design
Van Borkulo et al. Services for an Emergency response system in the Netherlands
CN105654535B (en) A kind of model manager system for three-dimensional simulation system
Katada et al. Development of practical scenario simulator for dissemination of disaster information
CN113112598A (en) System and method for realizing three-dimensional visual data model of urban geographic information
CN117459556B (en) Competitive sports wisdom stadium operation service system
Xin et al. Visual Power System based on Artificial Fish Swarm Algorithm
CN112885173A (en) Intelligent management cloud platform of smart classroom

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190614

RJ01 Rejection of invention patent application after publication