CN109870085A - A kind of middle weathering sandstone layer cubic meter of stone short-delay blasting excavation construction method - Google Patents

A kind of middle weathering sandstone layer cubic meter of stone short-delay blasting excavation construction method Download PDF

Info

Publication number
CN109870085A
CN109870085A CN201910220124.3A CN201910220124A CN109870085A CN 109870085 A CN109870085 A CN 109870085A CN 201910220124 A CN201910220124 A CN 201910220124A CN 109870085 A CN109870085 A CN 109870085A
Authority
CN
China
Prior art keywords
blasthole
here
cubic meter
sandstone layer
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910220124.3A
Other languages
Chinese (zh)
Inventor
彭涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CREEC Chengdu Survey Design and Research Co Ltd
Original Assignee
CREEC Chengdu Survey Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CREEC Chengdu Survey Design and Research Co Ltd filed Critical CREEC Chengdu Survey Design and Research Co Ltd
Priority to CN201910220124.3A priority Critical patent/CN109870085A/en
Publication of CN109870085A publication Critical patent/CN109870085A/en
Pending legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The invention discloses a kind of middle weathering sandstone layer cubic meter of stone short-delay blasting excavation construction methods, are related to blasting construction methods for rock excavation technical field, the present invention is the following steps are included: (1) smooth drilling machine working space;(2) drilling and powder charge;(3) explosion is blown out;(4) slope trimming, in step (2), cutting middle section rock excavation uses standing method, and cut slope part rock excavation uses photoface exploision method, and the present invention has the advantages that the control of explosion strength is accurate, blasting quality is high, guarantees that construction period carries out on time.

Description

A kind of middle weathering sandstone layer cubic meter of stone short-delay blasting excavation construction method
Technical field
The present invention relates to blasting construction methods for rock excavation technical fields, more particularly to a kind of middle weathering sandstone layer cubic meter of stone Short-delay blasting excavation construction method.
Background technique
Cut subgrade lower than original ground is known as cutting, refers to roadbed form made of excavating downwards from original place, it can rise The effect of ridge mouthful elevation control is passed through to mitigation road longitudinal grade or ridge crossing line.Cutting excavation refers to the construction of cut subgrade, Ying Gen According to concrete condition, using lateral overall with drivage method, i.e., the one or both ends of the entire section of cutting along longitudinal direction are excavated forward.Cutting The geological stratification encountered when excavation generally has intense weathering munstone, middle weathered mudstone, intense weathering soft rock, middle weathered sandstone, wherein apoplexy Change sandstone layer (V class stone) and belongs to time hard stone, it is motionless with excavator excavation when to rock excavation, then it can be to be excavated again after explosion Construction, cannot use great explosion, it is therefore an objective to which ensure roadbed side slope stablizes and close on house and the safety of personnel, therefore reasonable cloth It is most important to set blasthole position.
It should be rationally designed for the blast working scheme before the cutting excavation of middle weathering sandstone layer soil matrix, cutting middle part Divide and side slope part should use different blasting schemes, preferable chasm structuref could be formed, it is existing to be directed to middle weathered sandstone The Cutting Excavation Blasting excavation construction of layer uses same blasting procedure substantially, it is therefore an objective to reduce difficulty of construction, but when the later period excavates by It is poor in blasting quality, it is also necessary to which that the equipment such as excavator and drilling machine are modified, and finishing work amount is bigger, cause to apply instead The work duration is elongated.
Therefore above-mentioned technical problem how is solved, there is very much realistic meaning to those skilled in the art.
Summary of the invention
It is an object of the invention to: it is adopted substantially to solve the existing Cutting Excavation Blasting excavation construction for middle weathering sandstone layer With same blasting procedure, global blowup quality is poor, and the later period also needs various equipment to be modified when excavating, finishing work amount It is bigger, the technical problem that the construction period is elongated is caused instead, and the present invention provides a kind of middle weathering sandstone layer cubic meter of stone short-delay blasting Excavation construction method.
The present invention specifically uses following technical scheme to achieve the goals above:
A kind of middle weathering sandstone layer cubic meter of stone short-delay blasting excavation construction method, comprising the following steps: (1) smooth drilling machine operation Place;(2) drilling and powder charge;(3) explosion is blown out;(4) slope trimming, in step (2), cutting middle section rock excavation is adopted With standing method, cut slope part rock excavation uses photoface exploision method.
Further, the technical parameter of cutting middle section steel for shot is as follows:
A) when to dig the deep location for being less than 5m:
1. δ: δ=75 ° of blasthole inclination angle;
2. blasthole diameter d:d=40mm;
3. step height H:H >=(0.060-0.064) d, i.e. H >=2.4-2.56mm take H=4m here;
4. blast hole depth h:h is approximately equal to the deep depth of digging or step height H, and h >=0.8m, h=4m is taken here;
5. minimum burden W:W=(0.6-0.8) H, takes W=0.8H=3.2m here;
6. blasthole bottom over drilling depth h1:h1=0.25W=0.8m;
7. stemming length h0:h0=0.9W=2.88m;
8. blasthole spacing a: a=(1.4-2.0) W when using spark detonation takes a=2W=6.4m, when using electricity here A=(0.8-2.0) W when power is detonated, takes a=1.2W=3.84m here;
9. blasthole array pitch b:b=W=3.2m;
10. each hole charge Q:Q=qaWH, q are unit amount of consumption of drugs, q=0.3kg/m is taken here3, when using spark Q=24.576kg when detonation, Q=14.7456kg when using power initiation;
B) when to dig the deep location for being greater than 5m:
1. δ: δ=80 ° of blasthole inclination angle;
2. blasthole diameter d:d=100mm;
3. step height H:H=10m;
4. blast hole depth h:h=0.15H=1.5m;
5. minimum burden W:W=(0.6-0.9) H, takes W=0.7H=7m here;
6. blasthole bottom over drilling depth h1:h1=0.2W=1.4m;
7. stemming length h0:h0=0.8W=5.6m;
8. blasthole spacing a:a=mW, m are density coefficient, m=1.2, a=8.4m are taken here;
9. blasthole array pitch b:b=a=8.4m;
10. each hole charge Q:Q=qaWH, q are unit amount of consumption of drugs, q=0.3kg/m is taken here3, Q=176.4kg.
Further, the technical parameter of cut slope part steel for shot is as follows:
1. blasthole diameter D:D=50mm;
2. step height H1:H1=3m;
3. minimum burden W1:W1=(7-20) D, takes W1=12D=0.6m here;
4. blasthole spacing a1:a1=(0.6-0.8) W1, takes a1=0.6W1=0.36m here;
5. single hole explosive payload Q1=qa1W1H1, q are standing unit consumption dose, q=1.2kg/m is taken here3, Q1= 0.7776kg。
Further, in step (1), smooth compacting is carried out to working space, the plane error on ground is controlled in 5cm Within, use drilling machine for hydraulic down-the-hole drill.
Further, in step (4), cooperate excavator and dumper to be cut clearly with bull-dozer after explosion, adopt simultaneously It is modified with excavator equipped hydraulic hammer side slope.
Beneficial effects of the present invention are as follows:
1, the present invention uses standing method and photoface exploision method for the cutting excavation construction of middle weathering sandstone layer type Two kinds of blasting methods are applied in combination, and cutting middle section rock excavation uses standing method, and the cut slope part cubic meter of stone is opened It digs and uses photoface exploision method, optimal reference data and empirical equation are obtained according to multiple live blasting experiment, thus respectively to two The steel for shot technical parameter of kind blasting method carries out detailed design, reasonable blast working data is obtained, according to the construction number According to blast working is carried out, under the premise of guaranteeing the safety for stablizing and closing on house and personnel of roadbed side slope, accurately control quick-fried Broken strength makes its control in OK range, and blasting quality is high, so that later period finishing construction work amount is small, to guarantee to construct Period goes on smoothly.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to embodiments, to the present invention It is further elaborated.It should be appreciated that described herein, specific examples are only used to explain the present invention, is not used to limit The fixed present invention, i.e., described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Usually herein The component of the embodiment of the present invention shown in place can be arranged and be designed with a variety of different configurations.
Therefore, the model of claimed invention is not intended to limit to the detailed description in the embodiment of the present invention below It encloses, but is merely representative of selected embodiment of the invention.Based on the embodiment of the present invention, those skilled in the art's spirit is not being made Every other embodiment obtained, shall fall within the protection scope of the present invention under the premise of creative work.
It should be noted that the relational terms of term " first " and " second " or the like be used merely to an entity or Operation is distinguished with another entity or operation, and without necessarily requiring or implying between these entities or operation, there are any This actual relationship or sequence.Moreover, the terms "include", "comprise" or its any other variant be intended to it is non-exclusive Property include so that include a series of elements process, method, article or equipment not only include those elements, but also Further include other elements that are not explicitly listed, or further include for this process, method, article or equipment it is intrinsic Element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including described There is also other identical elements in the process, method, article or equipment of element.
In order to which those skilled in the art better understand the present invention, below following embodiment to the present invention make further it is detailed Thin description.
Embodiment 1
The present embodiment provides a kind of middle weathering sandstone layer cubic meter of stone short-delay blasting excavation construction methods, comprising the following steps: (1) Smooth drilling machine working space;(2) drilling and powder charge;(3) explosion is blown out;(4) slope trimming, in step (2), cutting middle part Rock excavation is divided to use standing method, cut slope part rock excavation uses photoface exploision method.
Further, the technical parameter of cutting middle section steel for shot is as follows:
A) when to dig the deep location for being less than 5m:
1. δ: δ=75 ° of blasthole inclination angle;
2. blasthole diameter d:d=40mm;
3. step height H:H >=(0.060-0.064) d, i.e. H >=2.4-2.56mm take H=4m here;
4. blast hole depth h:h is approximately equal to the deep depth of digging or step height H, and h >=0.8m, h=4m is taken here;
5. minimum burden W:W=(0.6-0.8) H, takes W=0.8H=3.2m here;
6. blasthole bottom over drilling depth h1:h1=0.25W=0.8m;
7. stemming length h0:h0=0.9W=2.88m;
8. blasthole spacing a: a=(1.4-2.0) W when using spark detonation takes a=2W=6.4m, when using electricity here A=(0.8-2.0) W when power is detonated, takes a=1.2W=3.84m here;
9. blasthole array pitch b:b=W=3.2m;
10. each hole charge Q:Q=qaWH, q are unit amount of consumption of drugs, q=0.3kg/m is taken here3, when using spark Q=24.576kg when detonation, Q=14.7456kg when using power initiation;
B) when to dig the deep location for being greater than 5m:
1. δ: δ=80 ° of blasthole inclination angle;
2. blasthole diameter d:d=100mm;
3. step height H:H=10m;
4. blast hole depth h:h=0.15H=1.5m;
5. minimum burden W:W=(0.6-0.9) H, takes W=0.7H=7m here;
6. blasthole bottom over drilling depth h1:h1=0.2W=1.4m;
7. stemming length h0:h0=0.8W=5.6m;
8. blasthole spacing a:a=mW, m are density coefficient, m=1.2, a=8.4m are taken here;
9. blasthole array pitch b:b=a=8.4m;
10. each hole charge Q:Q=qaWH, q are unit amount of consumption of drugs, q=0.3kg/m is taken here3, Q=176.4kg.
Further, the technical parameter of cut slope part steel for shot is as follows:
1. blasthole diameter D:D=50mm;
2. step height H1:H1=3m;
3. minimum burden W1:W1=(7-20) D, takes W1=12D=0.6m here;
4. blasthole spacing a1:a1=(0.6-0.8) W1, takes a1=0.6W1=0.36m here;
5. single hole explosive payload Q1=qa1W1H1, q are standing unit consumption dose, q=1.2kg/m is taken here3, Q1= 0.7776kg。
Further, in step (1), smooth compacting is carried out to working space, the plane error on ground is controlled in 5cm Within, use drilling machine for hydraulic down-the-hole drill.
Further, in step (4), cooperate excavator and dumper to be cut clearly with bull-dozer after explosion, adopt simultaneously It is modified with excavator equipped hydraulic hammer side slope.
The present invention uses standing method and photoface exploision method two for the cutting excavation construction of middle weathering sandstone layer type Kind blasting method is applied in combination, and cutting middle section rock excavation uses standing method, cut slope part rock excavation Using photoface exploision method, optimal reference data and empirical equation are obtained according to multiple live blasting experiment, thus respectively to two kinds The steel for shot technical parameter of blasting method carries out detailed design, reasonable blast working data is obtained, according to the construction data Blast working is carried out, under the premise of guaranteeing the safety for stablizing and closing on house and personnel of roadbed side slope, accurately controls explosion Strength makes its control in OK range, and blasting quality is high, so that later period finishing construction work amount is small, to guarantee construction week Phase goes on smoothly.
The above, only presently preferred embodiments of the present invention, are not intended to limit the invention, patent protection model of the invention It encloses and is subject to claims, it is all with equivalent variations made by specification of the invention, it similarly should be included in the present invention Protection scope in.

Claims (5)

1. a kind of middle weathering sandstone layer cubic meter of stone short-delay blasting excavation construction method, comprising the following steps: (1) smooth drilling machine operation field Ground;(2) drilling and powder charge;(3) explosion is blown out;(4) slope trimming, which is characterized in that in step (2), cutting middle section Rock excavation uses standing method, and cut slope part rock excavation uses photoface exploision method.
2. a kind of middle weathering sandstone layer cubic meter of stone short-delay blasting excavation construction method according to claim 1, which is characterized in that The technical parameter of cutting middle section steel for shot is as follows:
A) when to dig the deep location for being less than 5m:
1. δ: δ=75 ° of blasthole inclination angle;
2. blasthole diameter d:d=40mm;
3. step height H:H >=(0.060-0.064) d, i.e. H >=2.4-2.56mm take H=4m here;
4. blast hole depth h:h is approximately equal to the deep depth of digging or step height H, and h >=0.8m, h=4m is taken here;
5. minimum burden W:W=(0.6-0.8) H, takes W=0.8H=3.2m here;
6. blasthole bottom over drilling depth h1:h1=0.25W=0.8m;
7. stemming length h0:h0=0.9W=2.88m;
8. blasthole spacing a: a=(1.4-2.0) W when using spark detonation is taken a=2W=6.4m here, is risen when using electric power A=(0.8-2.0) W, takes a=1.2W=3.84m here when quick-fried;
9. blasthole array pitch b:b=W=3.2m;
10. each hole charge Q:Q=qaWH, q are unit amount of consumption of drugs, q=0.3kg/m is taken here3, when using spark detonation Q=24.576kg, Q=14.7456kg when using power initiation;
B) when to dig the deep location for being greater than 5m:
1. δ: δ=80 ° of blasthole inclination angle;
2. blasthole diameter d:d=100mm;
3. step height H:H=10m;
4. blast hole depth h:h=0.15H=1.5m;
5. minimum burden W:W=(0.6-0.9) H, takes W=0.7H=7m here;
6. blasthole bottom over drilling depth h1:h1=0.2W=1.4m;
7. stemming length h0:h0=0.8W=5.6m;
8. blasthole spacing a:a=mW, m are density coefficient, m=1.2, a=8.4m are taken here;
9. blasthole array pitch b:b=a=8.4m;
10. each hole charge Q:Q=qaWH, q are unit amount of consumption of drugs, q=0.3kg/m is taken here3, Q=176.4kg.
3. a kind of middle weathering sandstone layer cubic meter of stone short-delay blasting excavation construction method according to claim 2, which is characterized in that The technical parameter of cut slope part steel for shot is as follows:
1. blasthole diameter D:D=50mm;
2. step height H1:H1=3m;
3. minimum burden W1:W1=(7-20) D, takes W1=12D=0.6m here;
4. blasthole spacing a1:a1=(0.6-0.8) W1, takes a1=0.6W1=0.36m here;
5. single hole explosive payload Q1=qa1W1H1, q are standing unit consumption dose, q=1.2kg/m is taken here3, Q1= 0.7776kg。
4. a kind of middle weathering sandstone layer cubic meter of stone short-delay blasting excavation construction method according to claim 1, which is characterized in that In step (1), smooth compacting is carried out to working space, the plane error on ground is controlled within 5cm, uses drilling machine for liquid Press down-the-hole drill.
5. a kind of middle weathering sandstone layer cubic meter of stone short-delay blasting excavation construction method according to claim 1, which is characterized in that In step (4), excavator and dumper is cooperated to be cut clearly with bull-dozer after explosion, while using excavator equipped hydraulic hammer pair Side slope is modified.
CN201910220124.3A 2019-03-21 2019-03-21 A kind of middle weathering sandstone layer cubic meter of stone short-delay blasting excavation construction method Pending CN109870085A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910220124.3A CN109870085A (en) 2019-03-21 2019-03-21 A kind of middle weathering sandstone layer cubic meter of stone short-delay blasting excavation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910220124.3A CN109870085A (en) 2019-03-21 2019-03-21 A kind of middle weathering sandstone layer cubic meter of stone short-delay blasting excavation construction method

Publications (1)

Publication Number Publication Date
CN109870085A true CN109870085A (en) 2019-06-11

Family

ID=66921012

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910220124.3A Pending CN109870085A (en) 2019-03-21 2019-03-21 A kind of middle weathering sandstone layer cubic meter of stone short-delay blasting excavation construction method

Country Status (1)

Country Link
CN (1) CN109870085A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113529771A (en) * 2021-07-23 2021-10-22 湖北工业大学 Method for blasting and excavating open caisson by using rock foundation of jack and constructing shaft
CN113624083A (en) * 2021-07-12 2021-11-09 中国化学工程重型机械化有限公司 Cutting earthwork construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101793486A (en) * 2009-09-23 2010-08-04 中交二公局第六工程有限公司 High-grade highway rock cutting blasting construction process
CN102230769A (en) * 2011-06-16 2011-11-02 汇通路桥建设集团有限公司 Multi-row micro-differential roadbed deep hole blasting construction method
CN107063014A (en) * 2017-05-23 2017-08-18 安徽江南***工程有限公司 Cutting shallow hole step controlled blasting slope cutting method in complex environment
CN108360527A (en) * 2018-03-07 2018-08-03 中铁十九局集团第七工程有限公司 A kind of earthwork evacuation construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101793486A (en) * 2009-09-23 2010-08-04 中交二公局第六工程有限公司 High-grade highway rock cutting blasting construction process
CN102230769A (en) * 2011-06-16 2011-11-02 汇通路桥建设集团有限公司 Multi-row micro-differential roadbed deep hole blasting construction method
CN107063014A (en) * 2017-05-23 2017-08-18 安徽江南***工程有限公司 Cutting shallow hole step controlled blasting slope cutting method in complex environment
CN108360527A (en) * 2018-03-07 2018-08-03 中铁十九局集团第七工程有限公司 A kind of earthwork evacuation construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113624083A (en) * 2021-07-12 2021-11-09 中国化学工程重型机械化有限公司 Cutting earthwork construction method
CN113529771A (en) * 2021-07-23 2021-10-22 湖北工业大学 Method for blasting and excavating open caisson by using rock foundation of jack and constructing shaft

Similar Documents

Publication Publication Date Title
CN103615941B (en) The blasting method of modernized railway shallow-buried sector
Singh et al. Controlled blasting for long term stability of pit-walls
CN108286920A (en) A kind of implementation of Tunnel Blasting and excavation
CN112179227A (en) Coal face ultra-deep hole blasting roof cutting pressure relief control method and blasting charge structure
CN108360527A (en) A kind of earthwork evacuation construction method
CN101793486A (en) High-grade highway rock cutting blasting construction process
CN109870085A (en) A kind of middle weathering sandstone layer cubic meter of stone short-delay blasting excavation construction method
CN107542468A (en) A kind of natural caving method
CN105466290A (en) Cutting excavation blasting method
CN105021096A (en) Five-segment-type millisecond electric detonator secondary blasting construction method applied to blasting of high-gas large-section tunnel
CN107762511B (en) A kind of class strip-type coal-mining method cut top filling and close on goaf
CN109870082A (en) A kind of middle weathering sandstone layer cubic meter of stone standing excavation construction method
CN110924398B (en) High-strength rock slope widening excavation construction method under condition of traffic protection
CN108917503A (en) The horizontal presplit blasting method of deep hole applied to power station rock excavation
CN103791789B (en) Blasting construction method based on certain angle formed between boreholes and joints
Leighton Correlating rotary drill performance to powder factors for improved blasting control
Jhanwar et al. Application of air decks in production blasting to improve fragmentation and economics of an open pit mine
CN109883280A (en) A kind of middle weathering sandstone layer cubic meter of stone photoface exploision excavation construction method
Kotsiuruba et al. Justification of the requirements for the construction of protective structures by means underground workings in an explosive manner
CN216132352U (en) Foundation pit blasting excavation system
CN115854803B (en) Rock-soil control blasting method for old industrial factory
O’Donnell The Use of Destressing at INCO’s Creighton Mine
Hansen Drilling and blasting techniques for morrow point power plant
Lindi The Effectiveness of Pre-Splitting as a Method of Wall Control and Minimize Over-Break in North Mara Gold Mine
Abdulai et al. Pit wall optimisation and effective wall management strategies at Invincible Open Pit, St Ives Gold Mines

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190611

RJ01 Rejection of invention patent application after publication