CN109826629A - A kind of coal mine ground pressure break tight roof technique choosing method - Google Patents

A kind of coal mine ground pressure break tight roof technique choosing method Download PDF

Info

Publication number
CN109826629A
CN109826629A CN201910061538.6A CN201910061538A CN109826629A CN 109826629 A CN109826629 A CN 109826629A CN 201910061538 A CN201910061538 A CN 201910061538A CN 109826629 A CN109826629 A CN 109826629A
Authority
CN
China
Prior art keywords
pressure break
well
fractured
horizontal well
mode
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910061538.6A
Other languages
Chinese (zh)
Other versions
CN109826629B (en
Inventor
高瑞
于斌
孟祥斌
匡铁军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taiyuan University of Technology
Original Assignee
Taiyuan University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taiyuan University of Technology filed Critical Taiyuan University of Technology
Priority to CN201910061538.6A priority Critical patent/CN109826629B/en
Publication of CN109826629A publication Critical patent/CN109826629A/en
Application granted granted Critical
Publication of CN109826629B publication Critical patent/CN109826629B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing Or Calibration Of Command Recording Devices (AREA)
  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

Fracturing technology choosing method when the present invention relates to using ground fracturing technology to tight roof progress pressure break, specially a kind of coal mine ground pressure break tight roof technique choosing method solve to lack the method that coal mine tight roof ground fracturing technique is chosen at present.Step are as follows: one, mark pressure break destination layer three-dimensional stress;Two, orientation and working face mining direction are arranged according to horizontal well, marks two different horizontal well arrangements;Three, mini-frac destination layer three-dimensional stress distribution;Four, reasonable pressure break mode is determined in conjunction with fractured well itself arrangement of features according to three-dimensional stress distribution;Five, it is chosen according to fractured well as a result, carrying out pressure break in ground configuration fractured well.This method comprehensively, reliable, strong flexibility, be with a wide range of applications.

Description

A kind of coal mine ground pressure break tight roof technique choosing method
Technical field
The invention belongs to the methods of ground fracturing to carry out fracturing control, specifically a kind of coal mine to tight roof is covered on coal seam Ground fracturing tight roof technique choosing method.
Background technique
Coal bed underground exploitation, CONTROL OF STRATA MOVEMENT is core, and particularly with tight roof, because its intensity is big, breaking span is wide, hard Resisting the fracture of plate large area stubbornly easily causes the strong mine pressure of stope to show, or even brings storm wind disaster, is a big difficulty of Roof Control.Mesh The preceding control for tight roof, often in underground using control technologies means such as hydraulic fracturing or explosions, but by underground construction ring The restriction of the execution conditions such as border and drillable length is generally only to implement to weaken to top plate in the tunnel of working face two sides, weakens model It encloses and is confined to 50m above coal seam, control effect is limited.For this purpose, being directed to the limitation of current control technology, can innovate using ground The method that face pressure is split is equipped by ground fracturing, beat fracturing borehole downwards from earth's surface and implement pressure break to top plate.According to fractured well Method for arranging, ground fracturing tight roof can use vertical well, fractured horizontal well two ways, wherein use vertical well pressure Split advantage of lower cost;When ground fracturing, fracturing fracture extends form and stratum three-dimensional stress is closely bound up, therefore, different Under the conditions of fractured well arrangement, rock stratum difference three-dimensional stress, crack extension effect is different therewith, and fracturing effect is therewith by shadow It rings.So suitable fractured well arrangement should be selected according to rock stress state, pressure break demand, utmostly meet to the greatest extent hard It resists plate pressure break demand stubbornly, and reduces ground fracturing cost as far as possible.
Summary of the invention
Ground fracturing tight roof technique is chosen when the present invention is in order to solve the problem of tight roof mining area seam mining, A kind of coal mine ground pressure break tight roof technique choosing method is provided.
The present invention takes following technical scheme: a kind of coal mine ground pressure break tight roof technique choosing method, including following Step,
A. remember pressure break destination layer three-dimensional stress, being parallel to working face mining direction stress is σh, perpendicular to working face mining direction Stress is σH, vertical direction stress is σv
B. ground fracturing can use two kinds of pressure break modes of vertical well and horizontal well, and wherein fractured horizontal well includes two kinds again Arrangement, note horizontal well horizontal segment be parallel to working face mining direction arrangement be fractured horizontal well mode 1., it is horizontal Well horizontal segment perpendicular to working face mining direction arrangement be fractured horizontal well mode 2..
C. test analysis is carried out to pressure break destination layer three-dimensional stress state using detecting earth stress device;
Work as σH> σh> σvWhen, 1. pressure break is carried out using fractured horizontal well mode,
Work as σH> σv> σhWhen, 1. or 2. fractured horizontal well mode can carry out pressure break using vertical well or fractured horizontal well mode, Compare three kinds of fractured well costs at this time, the pressure break mode for selecting cost low;
When there is σh> σH> σv、σh> σv> σH、σv> σH> σhAnd σv> σh> σHWhen several stress states, it is all made of level 2. well pressure break mode carries out pressure break.
D. it is chosen according to fractured well as a result, carrying out pressure break in ground configuration fractured well.
Compared with prior art, the invention has the following advantages that 1) cover the possible distribution of all three-dimensional stresses in rock stratum State ensure that the comprehensive and reliability of choosing method;2) fully considered that arrangement and the technology of each fracturing process are special Point chooses suitable pressure break mode according to different ambient stresses;3) the choosing method process is simple, need to only be opened according to working face Adopt state, rock stratum three-dimensional stress distribution characteristics can determine that ground fracturing mode, strong applicability, application prospect is extensive.
Detailed description of the invention
Fig. 1 is ground fracturing well pressure break arrangement schematic diagram;
Fig. 2 is that ground fracturing tight roof technique chooses flow chart;
In figure: 1- working face, 2- pressure break destination layer, 3- horizontal segment are parallel to the fractured horizontal well mode in working face mining direction 1. 4- horizontal segment perpendicular to working face mining direction fractured horizontal well mode 2..
Specific embodiment
Below by taking the tight roof ground fracturing of Datong Mine Area as an example, in conjunction with attached drawing, the invention will be further described.
It is a kind of fractured well arrangement of coal mine ground pressure break tight roof technique choosing method of the present invention as shown in Figure 1 Schematic diagram, Fig. 2 are that specific fracturing technology chooses flow chart, according to pressure break destination layer three-dimensional stress state, are expanded in conjunction with hydraulic fracture The suitable fracturing technology of Feature Selection is opened up, the specific steps are that.
A. according to 1 mining state of working face, remember 2 three-dimensional stress of pressure break destination layer, be parallel to 1 direction of extraction stress of working face For σh, it is σ perpendicular to 1 direction of extraction stress of working faceH, vertical direction stress is σv
B. it is fractured horizontal well mode 1. 3, water that note horizontal well horizontal segment, which is parallel to the arrangement of 1 direction of extraction of working face, Horizontal well horizontal segment is fractured horizontal well mode 2. 4 perpendicular to the arrangement of 1 direction of extraction of working face;
C. test analysis is carried out to pressure break destination layer three-dimensional stress state using detecting earth stress device, the results showed that, pressure break mesh Marking three-dimensional stress distribution in layer is σH> σh> σv
D. according to Fig. 2,1. pressure break is carried out using fractured horizontal well mode.
E. it is chosen according to fractured well as a result, carrying out pressure break in ground configuration horizontal well.
Field monitoring the result shows that, the parallel maximum principal stress σ in crackHDirection, vertical minimum principal stress σvDirectional Extension, Horizontal fracture face is formed in pressure break destination layer, reduces the thickness of tight roof;Ore pressure monitor shows after ground fracturing, hard The mine pressure action intensity of hard Roof Breaking unstability is substantially reduced, and force piece resistance reduces by 15%, and roadway deformation amount reduces 45%, Demonstrate the correctness of ground fracturing technique selection.The side chosen by using above-mentioned ground fracturing tight roof reasonable process Method weakens the strong mine of stope and presses disaster, guarantee the safety and high efficiency in tight roof mining area coal seam for efficiently controlling tight roof Have great importance.

Claims (1)

1. a kind of coal mine ground pressure break tight roof technique choosing method, it is characterised in that: include the following steps,
A. remember pressure break destination layer three-dimensional stress, being parallel to working face mining direction stress is σh, answered perpendicular to working face mining direction Power is σH, vertical direction stress is σv
B. ground fracturing can use two kinds of pressure break modes of vertical well and horizontal well, and wherein fractured horizontal well includes two kinds of arrangements again Mode, note horizontal well horizontal segment be parallel to working face mining direction arrangement be fractured horizontal well mode 1., horizontal well water Flat section perpendicular to working face mining direction arrangement be fractured horizontal well mode 2.;
C. test analysis is carried out to pressure break destination layer three-dimensional stress state using detecting earth stress device;
Work as σH> σh> σvWhen, 1. pressure break is carried out using fractured horizontal well mode,
Work as σH> σv> σhWhen, 1. or 2. fractured horizontal well mode can carry out pressure break using vertical well or fractured horizontal well mode, Compare three kinds of fractured well costs at this time, the pressure break mode for selecting cost low;
When there is σh> σH> σv、σh> σv> σH、σv> σH> σhAnd σv> σh> σHWhen several stress states, it is all made of level 2. well pressure break mode carries out pressure break;
D. it is chosen according to fractured well as a result, carrying out pressure break in ground configuration fractured well.
CN201910061538.6A 2019-01-23 2019-01-23 Coal mine ground fracturing hard roof process selection method Active CN109826629B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910061538.6A CN109826629B (en) 2019-01-23 2019-01-23 Coal mine ground fracturing hard roof process selection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910061538.6A CN109826629B (en) 2019-01-23 2019-01-23 Coal mine ground fracturing hard roof process selection method

Publications (2)

Publication Number Publication Date
CN109826629A true CN109826629A (en) 2019-05-31
CN109826629B CN109826629B (en) 2020-09-18

Family

ID=66861873

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910061538.6A Active CN109826629B (en) 2019-01-23 2019-01-23 Coal mine ground fracturing hard roof process selection method

Country Status (1)

Country Link
CN (1) CN109826629B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110295880A (en) * 2019-07-04 2019-10-01 中国矿业大学 A kind of optimization of various dimensions hydraulic fracturing roof stops the method for adopting line
CN112160792A (en) * 2020-08-31 2021-01-01 太原理工大学 Staged hydraulic fracturing working method for underground hard top plate

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102279131A (en) * 2011-07-18 2011-12-14 中国石油大学(北京) Simulation experiment method of coal seam hydraulic fracture
CN103390108A (en) * 2013-07-25 2013-11-13 中国石油大学(北京) Well type design method and device based on compressibility of fractured geologic body
CN105952429A (en) * 2016-05-17 2016-09-21 中国地质大学(武汉) Terrestrial facies shale gas fracture network fracture parameter optimizing method
CN106150503A (en) * 2016-07-05 2016-11-23 重庆大学 The method of tight roof is administered in a kind of fracturing
CN107524432A (en) * 2016-06-21 2017-12-29 中国石油化工股份有限公司 A kind of real-time parameter adjustment method in pressing crack construction
CN107589020A (en) * 2017-07-17 2018-01-16 华北水利水电大学 A kind of hydraulic fracturing test method based on stress path

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102279131A (en) * 2011-07-18 2011-12-14 中国石油大学(北京) Simulation experiment method of coal seam hydraulic fracture
CN103390108A (en) * 2013-07-25 2013-11-13 中国石油大学(北京) Well type design method and device based on compressibility of fractured geologic body
CN105952429A (en) * 2016-05-17 2016-09-21 中国地质大学(武汉) Terrestrial facies shale gas fracture network fracture parameter optimizing method
CN107524432A (en) * 2016-06-21 2017-12-29 中国石油化工股份有限公司 A kind of real-time parameter adjustment method in pressing crack construction
CN106150503A (en) * 2016-07-05 2016-11-23 重庆大学 The method of tight roof is administered in a kind of fracturing
CN107589020A (en) * 2017-07-17 2018-01-16 华北水利水电大学 A kind of hydraulic fracturing test method based on stress path

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李彬刚: "《芦岭煤矿碎软低渗煤层高效抽采技术》", 《煤田地质与勘探》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110295880A (en) * 2019-07-04 2019-10-01 中国矿业大学 A kind of optimization of various dimensions hydraulic fracturing roof stops the method for adopting line
CN112160792A (en) * 2020-08-31 2021-01-01 太原理工大学 Staged hydraulic fracturing working method for underground hard top plate

Also Published As

Publication number Publication date
CN109826629B (en) 2020-09-18

Similar Documents

Publication Publication Date Title
CN102536239B (en) Long-wall working face coal pillar-free mining method
CN102080526B (en) Method for extracting gas from bedding level fractured well of ground coal seam roof
CN112879011B (en) Method for controlling height of water guide crack zone by hard overburden rock pre-cracking weakening under aquifer
CN102678092B (en) A kind ofly abovegroundly combine construction coal and the coal bed gas method of adopting altogether down
CN102392678A (en) Gas drainage method combining surface and underground fracturing and permeability improvement
CN102777180A (en) Method for actively and regionally preventing and controlling rock burst in coal mines
CN104863629A (en) Method for extracting gas from separation layer below overlying strata, draining water and grouting through combined drill hole
CN101440704B (en) Ground-dipping ore bed continuous high-energy gas fracturing seepage increasing method and specific high-energy gas generator
CN109855966B (en) Method for selecting coal mine ground fracturing hard roof layer position
WO2015196939A1 (en) Solid filling mining design method under a water body
CN101608552A (en) The seat earth aquifer reinforces and protects the method for water barrier in reinforcing process
CN103982137B (en) Design method for underground hydraulic fracturing drilled hole azimuth angle of coal mine
CN110173264A (en) Lane bump method is stayed with conventional release prevention and treatment tight roof in disconnected top
CN103953386A (en) Upstream-blocking and downstream-seepage method for extracting gas in mining area
CN110685688B (en) Coal mine surrounding rock control method based on chemical modification
CN108412453A (en) A kind of coal mining water controls system and construction method altogether with gas
CN102777185A (en) Inclined well shaft construction technology
CN105239964A (en) Protective coal seam decompressing ground and underground three-dimensional coal and coal seam gas coordinated development method
CN108086977A (en) A kind of coal seam prevents water-resisting floor coal-mining method for water-bearing layer
CN105673014A (en) Method for controlling rock burst of hard roof jump mining working face
CN110067592A (en) Top plate gas cooperative control method based on tight roof ground fracturing
CN111827878A (en) Method for quickly and accurately probing hidden water inrush channel of coal seam floor
CN109826629A (en) A kind of coal mine ground pressure break tight roof technique choosing method
CN109779634B (en) Method for determining position of fractured hard top plate of coal mine ground vertical well
CN106285770A (en) A kind of working seam base plate mud stone is as the method for protective layer increase the most projecting coal bed group breathability

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant