CN109826203A - The support system of fender post and water-stop curtain building-in depth Length discrepancy - Google Patents

The support system of fender post and water-stop curtain building-in depth Length discrepancy Download PDF

Info

Publication number
CN109826203A
CN109826203A CN201910171081.4A CN201910171081A CN109826203A CN 109826203 A CN109826203 A CN 109826203A CN 201910171081 A CN201910171081 A CN 201910171081A CN 109826203 A CN109826203 A CN 109826203A
Authority
CN
China
Prior art keywords
water
fender post
stop curtain
foundation pit
main structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910171081.4A
Other languages
Chinese (zh)
Inventor
魏庆繁
李科龙
王立新
邵莹
张建春
毛念华
王俊
袁海龙
戴志仁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Survey and Design Institute Group Ltd
Original Assignee
China Railway First Survey and Design Institute Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Survey and Design Institute Group Ltd filed Critical China Railway First Survey and Design Institute Group Ltd
Priority to CN201910171081.4A priority Critical patent/CN109826203A/en
Publication of CN109826203A publication Critical patent/CN109826203A/en
Pending legal-status Critical Current

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The present invention relates to the support systems of a kind of fender post and water-stop curtain building-in depth Length discrepancy, and including station main structure, fender post and the water-stop curtain in foundation pit, fender post and water-stop curtain were arranged along station main structure outer profile one week, are closed foundation pit;Fender post is located on the inside of water-stop curtain, maintains an equal level at the top of fender post and water-stop curtain, goes along with sb. to guard him pile length greater than water-stop curtain;Longitudinal crown beam and lateral concrete support are provided at the top of fender post.The present invention uses fender post+water-stop curtain+inner support support system, is provided with crown beam and concrete barricade at the top of fender post, capping beam is provided between crown beam and main structure, undertakes anti-floating effect;Underground water drawdown on the outside of foundation pit can be kept minimum under the conditions of meeting base pit dewatering drawdown using water-stop curtain, effectively control influence of the base pit dewatering to surrounding enviroment.

Description

The support system of fender post and water-stop curtain building-in depth Length discrepancy
Technical field
The invention belongs to the support technology fields of subway engineering, and in particular to a kind of fender post and water-stop curtain building-in depth The support system of Length discrepancy.
Background technique
Subway foundation pit refers to carry out the space of below ground that the construction of subway is excavated, after excavation, subway foundation pit Surrounding generates multiple free faces, constitutes foundation pit containment body, certain one side of foundation pit containment body is known as foundation pit side-wall by us.
The excavation of subway foundation pit necessarily affects to surrounding enviroment, to guarantee underground construction structure and foundation pit week The safety of surrounding environment, to support, reinforcing and safeguard measure that foundation pit side-wall and surrounding enviroment use, here it is pattern foundation pit supporting structures.
Currently, with the investment of each big city metro project in the whole nation, the base pit engineering of construction project in quantity, is excavated Depth, square size and the development that high speed is all obtained using field etc., deep big foundation pit is very universal, traditional slope Excavation technology and a small amount of steel sheet pile support technology of use have been difficult to ensure underground construction structure and subway foundation pit surrounding enviroment Safety.
Subway foundation pit engineering in general is located at the area of building dense, environment complexity, after the accidents such as collapse, will make At huge personnel, property loss, while supporting measure, as temporary supporting structure, the design of its support of base pit engineering again must not Do not consider economic factor, therefore in the design and work progress of foundation pit supporting project, adaptation to local conditions, reasonable selection reach peace Entirely, economic harmony is that design, construction personnel will consider the problems of emphatically.
To guarantee that earth excavation and Underground Construction are in " drying " state, code requirement level of ground water should be reduced to base Excavate 0.5 ~ 1.0m or less of bottom surface in hole.Base pit engineering focus on controlling underground water and therefore caused by periphery earth's surface it is heavy Drop, under building enclosure and the collective effect of dewatering measure, can satisfy construction requirement, improves the stabilization of foundation pit enclosure structure Property, the engineering accident of the initiations such as anti-fluid stopping soil, piping and bottom heave.
In city, construction of structures is intensive, underground utilities laying is complicated, and the excessive stratum that will lead to of deepening of ground water table generates position It moves and deforms, and then jeopardize and build, the safety and normal use of structures and pipeline.Therefore in city underground engineering construction process, Under the conditions of meeting base pit dewatering drawdown, keep influence of the base pit dewatering to surrounding enviroment minimum, in economy, the base of technological rationality On plinth, the important topic that influence of the base pit dewatering to surrounding enviroment has become city underground engineering construction is effectively controlled.
Lowering heartn type water-stop curtain is by the water barrier at water-stop curtain insertion foundation pit bottom, inside and outside water-stop curtain partition hole Level supply is aided with dewatering well in hole using the inside and outside vertical supply in water barrier partition hole.Due to cheating inside and outside hydraulic connection partition, Pit Discharge is smaller, and precipitation has substantially no effect on surrounding enviroment.But when hole, relative water resisting layer buried depth in bottom is very big, is stopped using lowering heartn type Water curtain cost is higher and quality is difficult to ensure, or hole bottom without relative water resisting layer when, suspension type water-stop curtain need to be used.Due to hole Inside and outside hydraulic connection does not separate completely, and in foundation pit when precipitation, the water outside foundation pit can cause under the water level outside foundation pit around flowing in hole It drops (about 1.5m), Pit Discharge increases, and precipitation has smaller influence to surrounding enviroment.
Summary of the invention
The object of the present invention is to provide the support systems of a kind of fender post and water-stop curtain building-in depth Length discrepancy, are guaranteeing While overall cost-effective performance and safety coefficient, it is more applicable for complicated foundation pit surrounding environment, is built in the guarantee existing construction in periphery Under the premise of object safety, safety, the economic existing base pit engineering of carry out.
The technical scheme adopted by the invention is as follows:
The support system of fender post and water-stop curtain building-in depth Length discrepancy, it is characterised in that:
Including station main structure, fender post and the water-stop curtain in foundation pit, fender post and water-stop curtain are along station main body knot It is arranged within structure outer profile one week, is closed foundation pit;
Fender post is located on the inside of water-stop curtain, maintains an equal level at the top of fender post and water-stop curtain, goes along with sb. to guard him pile length greater than water-stop curtain;
Longitudinal crown beam and lateral concrete support are provided at the top of fender post.
It is whole by the levelling formation of in-network processing between fender post.
Crown beam width at the top of fender post is greater than fender post, sets between the beam section bottom surface inwardly stretched out and station main structure It is equipped with longitudinal capping beam.
Crown beam top surface is provided with longitudinal concrete barricade and stops the side soil body.
The side plate of station main structure is close to perform with fender post, and there are gaps between water-stop curtain and fender post.
The invention has the following advantages that
(1) using water-stop curtain underground water drawdown on the outside of foundation pit can be kept minimum, effectively controlled under the conditions of meeting base pit dewatering drawdown Influence of the base pit dewatering processed to surrounding enviroment.
(2) when hole, relative water resisting layer buried depth in bottom is very big, higher using lowering heartn type water-stop curtain cost and quality is difficult to ensure, Or when cheating bottom without relative water resisting layer, using suspension type water-stop curtain, water-stop curtain length can be effectively reduced, economy is high.Due to It cheats inside and outside hydraulic connection not separate completely, in foundation pit when precipitation, the water outside foundation pit can lead to the water level outside foundation pit around flowing in hole Decline (about 1.5m), Pit Discharge increases, although comprehensive analysis precipitation has smaller influence on surrounding enviroment, but from economy angle Degree considers that these influences are acceptables.
(3) most of foundation pit enclosure stake and water-stop curtain building-in depth are usually isometric setting, and the build-in of fender post is deep Degree is all longer, and the present invention carries out anti-seepage flow stability computation according to suspension type water-stop curtain, and final water-stop curtain building-in depth need not With the isometric setting of fender post, water-stop curtain length is effectively reduced.
Detailed description of the invention
Fig. 1 is structure organigram of the invention;
Fig. 2 is the portion A diagrammatic cross-section in Fig. 1;
In figure, 1- fender post, 2- water-stop curtain, 3- crown beam, the support of 4- concrete, 5- bracing members, 6- fashioned iron purlin, 7- capping beam, 8- Concrete barricade, 9- plain concrete cushion layer, the station 10- main structure, 11- first time excavation face, second of excavation face of 12-, 13- third Secondary excavation face, the 4th excavation face of 14-, 15- building, 16- municipal pipeline.
Specific embodiment
The present invention will be described in detail With reference to embodiment.
The present invention relates to the support systems of a kind of fender post and water-stop curtain building-in depth Length discrepancy, including the vehicle in foundation pit Main structure of standing 10, fender post 1 and water-stop curtain 2, fender post 1 and water-stop curtain 2 are along 10 outer profile one of station main structure Week setting, is closed foundation pit.Fender post 1 is located at 2 inside of water-stop curtain, maintains an equal level at the top of fender post 1 and water-stop curtain 2, fender post 1 Length is greater than water-stop curtain 2.Longitudinal crown beam 3 and lateral concrete support 4 are provided at the top of fender post 1.
It is whole by the levelling formation of in-network processing between fender post 1.The side plate and fender post 1 of station main structure 10 are tight Patch performs, and there are gaps between water-stop curtain 2 and fender post 1.
3 width of crown beam at 1 top of fender post is greater than fender post 1, the beam section bottom surface inwardly stretched out and station main structure 10 Between be provided with longitudinal capping beam 7.3 top surface of crown beam is provided with longitudinal concrete barricade 8 and stops the side soil body.
When construction:
Fender post 1 and water-stop curtain 2 were arranged along 10 outer profile of station main structure one week, were closed foundation pit, 1 top of fender post It is provided with crown beam 3 and concrete barricade 8;
Excavation of foundation pit uses 100mm thickness in-network processing levelling, sets up concrete branch to first time excavation face 11 between fender post 1 Support 4;
It is excavated to second of excavation face 12, it is levelling using 100mm thickness in-network processing between fender post 1, set up fashioned iron purlin 6 With bracing members 5;
It is excavated to third time excavation face 13, it is levelling using 100mm thickness in-network processing between fender post 1, set up fashioned iron purlin 6 With bracing members 5;
It is excavated to the 4th excavation face 14, it is levelling using 100mm thickness in-network processing between fender post 1, pour plain concrete Bed course 9 successively pours station main structure 10 from the bottom to top and successively removes steel purlin 6 and bracing members 5;
After pouring to station main structure 10, capping beam 7 is poured between crown beam 3 and station main structure 10, to station After 10 intensity of main structure reaches design strength 100%, concrete support 4 and concrete barricade 8 are removed, foundation pit is backfilled, restores road surface.
The contents of the present invention are not limited to cited by embodiment, and those of ordinary skill in the art are by reading description of the invention And to any equivalent transformation that technical solution of the present invention is taken, all are covered by the claims of the invention.

Claims (5)

1. the support system of fender post and water-stop curtain building-in depth Length discrepancy, it is characterised in that:
Including station main structure (10), fender post (1) and the water-stop curtain (2) in foundation pit, fender post (1) and water-stop curtain (2) it is arranged within outer profile one week along station main structure (10), is closed foundation pit;
Fender post (1) is located on the inside of water-stop curtain (2), maintains an equal level at the top of fender post (1) and water-stop curtain (2), fender post (1) length Greater than water-stop curtain (2);
The concrete support (4) of longitudinal crown beam (3) and transverse direction is provided at the top of fender post (1).
2. the support system of fender post according to claim 1 and water-stop curtain building-in depth Length discrepancy, it is characterised in that:
It is whole by the levelling formation of in-network processing between fender post (1).
3. the support system of fender post according to claim 1 and water-stop curtain building-in depth Length discrepancy, it is characterised in that:
Crown beam (3) width at the top of fender post (1) is greater than fender post (1), the beam section bottom surface inwardly stretched out and station main structure (10) longitudinal capping beam (7) are provided between.
4. the support system of fender post according to claim 1 and water-stop curtain building-in depth Length discrepancy, it is characterised in that:
Crown beam (3) top surface is provided with longitudinal concrete barricade (8) and stops the side soil body.
5. the support system of fender post according to claim 1 and water-stop curtain building-in depth Length discrepancy, it is characterised in that:
The side plate of station main structure (10) is close to perform with fender post (1), exists between water-stop curtain (2) and fender post (1) Gap.
CN201910171081.4A 2019-03-07 2019-03-07 The support system of fender post and water-stop curtain building-in depth Length discrepancy Pending CN109826203A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910171081.4A CN109826203A (en) 2019-03-07 2019-03-07 The support system of fender post and water-stop curtain building-in depth Length discrepancy

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910171081.4A CN109826203A (en) 2019-03-07 2019-03-07 The support system of fender post and water-stop curtain building-in depth Length discrepancy

Publications (1)

Publication Number Publication Date
CN109826203A true CN109826203A (en) 2019-05-31

Family

ID=66865623

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910171081.4A Pending CN109826203A (en) 2019-03-07 2019-03-07 The support system of fender post and water-stop curtain building-in depth Length discrepancy

Country Status (1)

Country Link
CN (1) CN109826203A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110453688A (en) * 2019-08-19 2019-11-15 中铁十二局集团有限公司 The excavation method of foundation pit

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104775440A (en) * 2015-04-21 2015-07-15 五洋建设集团股份有限公司 Mineshaft-type underground garage deep foundation pit supporting structure
WO2018117861A1 (en) * 2016-12-23 2018-06-28 Statoil Petroleum As Subsea assembly modularisation
CN109208654A (en) * 2018-10-26 2019-01-15 中铁第勘察设计院集团有限公司 The anti-floating system and its construction method that corbel type crown beam is combined with oblique type capping beam
CN209798765U (en) * 2019-03-07 2019-12-17 中铁第一勘察设计院集团有限公司 Supporting system with unequal embedded depths of fender post and waterproof curtain

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104775440A (en) * 2015-04-21 2015-07-15 五洋建设集团股份有限公司 Mineshaft-type underground garage deep foundation pit supporting structure
WO2018117861A1 (en) * 2016-12-23 2018-06-28 Statoil Petroleum As Subsea assembly modularisation
CN109208654A (en) * 2018-10-26 2019-01-15 中铁第勘察设计院集团有限公司 The anti-floating system and its construction method that corbel type crown beam is combined with oblique type capping beam
CN209798765U (en) * 2019-03-07 2019-12-17 中铁第一勘察设计院集团有限公司 Supporting system with unequal embedded depths of fender post and waterproof curtain

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110453688A (en) * 2019-08-19 2019-11-15 中铁十二局集团有限公司 The excavation method of foundation pit

Similar Documents

Publication Publication Date Title
CN105041349B (en) A kind of excavating construction method that station is digged on the basis of Subway Tunnel shield tunnel
CN100497841C (en) Supporting leg type underground continuous wall construction method
CN105862930B (en) A kind of protection structure to creating existing tunnel below underground engineering
CN101280568A (en) Station pit construction method forming protection for neighboring operated subway interval tunnel
CN107178393A (en) A kind of Tunnel Second Lining water pressure control structure
CN110374112B (en) Deep foundation pit supporting system for weak soil field and construction method thereof
CN105587320B (en) Rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method
CN103486403A (en) In-situ protection construction method of pipeline above foundation pit
CN105239578B (en) Water-rich sand layer deep foundation pit underwater construction method
AU2021103956A4 (en) Construction method for protecting overpass structure around deep foundation pits
CN104652444A (en) Construction method for overall reverse operation of ultra-large type deep foundation pit center island type alternative earth excavation
CN109723089A (en) Protect structure and method in a kind of high-tension electricity pipe culvert original place
CN104790435A (en) Post-subsidence pouring belt advancing waterstop impermeable concrete structure and construction technology thereof
CN111411992A (en) Integrated structure system penetrating through giant karst cave and construction method thereof
CN109162741B (en) Method for synchronous construction of shield penetrating piston air duct and upper structure of piston air duct
CN207093138U (en) A kind of Tunnel Second Lining water pressure control structure
CN106567365B (en) Earth and rockfill dam longitudinal reinforcement construction method
CN109826203A (en) The support system of fender post and water-stop curtain building-in depth Length discrepancy
CN208816132U (en) Collapsible loess combination land pebble stratum tunneling air duct connects the ventilating shaft of shield tunnel
CN110939139A (en) Pile slab wall structure based on rigid contact of post-pile special-shaped retaining wall and construction method thereof
CN209798765U (en) Supporting system with unequal embedded depths of fender post and waterproof curtain
CN110042851A (en) Reduce and wears riverway cofferdam and river bed reinforcement means under neighbouring high-speed rail deformation of pile foundation
CN105986830A (en) Underground-excavation building method for roadside strip-shaped underground garage
CN205502070U (en) A dual -purpose underground gallery structure
CN212154795U (en) Integral structure system for passing through giant karst cave

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination