CN109816557A - Approaches to IM in a kind of electric energy meter life cycle - Google Patents

Approaches to IM in a kind of electric energy meter life cycle Download PDF

Info

Publication number
CN109816557A
CN109816557A CN201910105367.2A CN201910105367A CN109816557A CN 109816557 A CN109816557 A CN 109816557A CN 201910105367 A CN201910105367 A CN 201910105367A CN 109816557 A CN109816557 A CN 109816557A
Authority
CN
China
Prior art keywords
electric energy
energy meter
information
change
archive information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910105367.2A
Other languages
Chinese (zh)
Other versions
CN109816557B (en
Inventor
魏海斌
章华峤
林仁雄
林琪
林展翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Fujian Electric Power Co Ltd
Putian Power Supply Co of State Grid Fujian Electric Power Co Ltd
Original Assignee
State Grid Fujian Electric Power Co Ltd
Putian Power Supply Co of State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Fujian Electric Power Co Ltd, Putian Power Supply Co of State Grid Fujian Electric Power Co Ltd filed Critical State Grid Fujian Electric Power Co Ltd
Priority to CN201910105367.2A priority Critical patent/CN109816557B/en
Publication of CN109816557A publication Critical patent/CN109816557A/en
Application granted granted Critical
Publication of CN109816557B publication Critical patent/CN109816557B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to approaches to IM in a kind of electric energy meter life cycle, using electric energy meter bar code as the inquiry entrance of the information such as electric energy meter geographical location and owning user;Pass through the electric energy meter bar code on the scanning function scanning work list in terminal device APP, show the details such as geographical location and the owning user of the electric energy meter, it realizes and is accurately contacted and the quick lookup to electric energy meter position with electric energy meter user, gage work personnel can be significantly facilitated to the assembly and disassembly efficiency and electric energy meter life cycle management of electric energy meter.

Description

Approaches to IM in a kind of electric energy meter life cycle
Technical field
The present invention relates to technical field of information management, approaches to IM in especially a kind of electric energy meter life cycle.
Background technique
With the development of social progress and electronic technology, accuracy and power supply service of the Electricity customers to electrical energy measurement More stringent requirements are proposed.In order to realize that power grid is strong, assets are excellent, service is high-quality, achievement is outstanding " the last one three is excellent " is modern The strategic objective of company needs to be updated traditional operating mode in terms of electrical energy measurement.With personnel transfer and The growth year by year of old employee's retirement quantity, the business of changing the outfit of electric energy meter face serious challenge.It changes the outfit industry receiving electric energy meter When business, young employee can not find the position of needed to change electric energy meter often;For old employee, because the time limit is older and city township The construction in town changes, also when and can not find the position of electric energy meter.Meanwhile for business electrical client, when responsible switchgear house management When the information of maintenance personnel changes, new contact details are updated into Electric Power Marketing System not in time, cause to measure work Make personnel in booking work, does not often get in touch with distribution management maintenance personnel of corresponding enterprise etc..Problems above is serious The working efficiency for affecting gage work personnel causes inconvenience to gage work.
Summary of the invention
It is an object of the invention to overcome the deficiencies in the prior art, information management side in a kind of electric energy meter life cycle is proposed The electrical energy measurement working time is shortened in method, the accuracy for advantageously reducing the difficulty of electric energy meter location lookup and contacting with user.
The technical solution adopted by the present invention to solve the technical problems is:
Approaches to IM in a kind of electric energy meter life cycle, comprising:
Step S1 receives the relevant job note of electric energy meter, judges the task classification of the job note;The work is appointed Business classification includes new clothes, rotation, increase and decrease appearance, cancellation, shifting table and field test;
Step S2 is arranged on the new clothes electric energy meter of terminal device scans working site if the task classification is new clothes Bar code, receive the archive information of the new clothes electric energy meter of input in the messagewindow of display, establish and electric energy meter table number phase The archive information of associated new clothes electric energy meter, and receive the working site photo of upload;The archive information includes user information And geographical location information;The user information include user's name, in every family number, station address, contact person and contact method;If The task classification is non-new clothes, executes step S3;
Step S3, corresponding electric energy meter bar code on terminal device scans job note, obtains in the messagewindow of display The archive information or terminal device of corresponding electric energy meter obtain the archive information of corresponding electric energy meter according to the electric energy meter table number of input;It is logical The contact person and contact details crossed in the archive information carries out work reservation, and obtains the location information in the archive information To navigate;
Step S4, the bar code being arranged on the electric energy meter of terminal device scans working site, judge display archive information and Whether working site photo changes, and if there is a change, carries out information modification.
Preferably, in the step S4, judge whether the archive information of display and working site photo change, if It changes, carries out information modification, comprising:
Step S41, judge user's name, in every family number, station address, one in contact person and contact method and multinomial Whether change, if so, carrying out the change of corresponding informance;
Step S42, judges whether geographical location information changes, if so, change or newly-increased geographical location information;
Step S43 judges whether working site photo changes or wrong, if so, change or newly-increased scene are shone Piece.
The invention has the following beneficial effects:
(1) approaches to IM in a kind of electric energy meter life cycle of the present invention, using electric energy meter bar code and electric energy meter It is associated to manage position, can be convenient positioning and lookup of the electric energy meter in life cycle;When department personnel change, Avoid newly arrive staff as do not know electric energy meter position and caused by redundant work amount, reduce electric energy meter hunting time, Improve working efficiency;
(2) approaches to IM in a kind of electric energy meter life cycle of the present invention, using electric energy meter bar code and electric energy meter User information is associated, is updated user information corresponding to electric energy meter in time when working site executes task, Realize to the accurate of user and quickly contacting, avoid as user contact and contact details generation are changed and caused by can not The trying situation contacted in time is obtained with user.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention for those skilled in the art without any creative labor, can be with root Other attached drawings are obtained according to these attached drawings.
Fig. 1 is the flow chart of approaches to IM in a kind of electric energy meter life cycle of the present invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
It is shown in Figure 1, approaches to IM in a kind of electric energy meter life cycle of the present invention, comprising:
Step S1 receives the relevant job note of electric energy meter, judges the task classification of the job note;The work is appointed Business classification includes new clothes, rotation, increase and decrease appearance, cancellation, shifting table and field test;
Step S2 is arranged on the new clothes electric energy meter of terminal device scans working site if the task classification is new clothes Bar code, receive the archive information of the new clothes electric energy meter of input in the messagewindow of display, establish and electric energy meter table number phase The archive information of associated new clothes electric energy meter, and receive the working site photo of upload;The archive information includes user information And geographical location information;The user information include user's name, in every family number, station address, contact person and contact method;If The task classification is non-new clothes, executes step S3;
Specifically, the work on the spot photo includes live switchgear house photo, the scene switchgear house photo can be in work It shoots and uploads again at the end of work, search the switchgear house position in the convenient course of work later.If task classification is new Dress, then after uploading operation scene photograph, then complete the typing of information in new electric energy meter life cycle, and process ends here, It is subsequent then to inquire the user information and geographical location information of the electric energy meter before carrying out other tasks, it is subsequent When carrying out other tasks, the user information and geographical location information of the electric energy meter can be modified according to the actual situation. If task classification is rotation, increase and decrease appearances, cancellation, shifting table or field test, then follow the steps S3 and later the step of.
Step S3, corresponding electric energy meter bar code on terminal device scans job note, obtains in the messagewindow of display The archive information or terminal device of corresponding electric energy meter obtain the archive information of corresponding electric energy meter according to the electric energy meter table number of input;It is logical The contact person and contact details crossed in the archive information carries out work reservation, and obtains the location information in the archive information To navigate;
Specifically, staff goes to corresponding electric energy meter position according to the location information found, or according to finding Location information electric energy meter position is navigated to work by the navigation software of mobile terminal.
Step S4, the bar code being arranged on the electric energy meter of terminal device scans working site, judge display archive information and Whether working site photo changes, and if there is a change, carries out information modification, terminates this workflow;If user believes Breath, location information and scene do not change, then modify without information.
Preferably, in the step S4, judge whether the archive information of display and working site photo change, if It changes, carries out information modification, comprising:
Step S41, judge user's name, in every family number, station address, one in contact person and contact method and multinomial Whether change, if so, carrying out the change of corresponding informance;
Step S42, judges whether geographical location information changes, if so, change or newly-increased geographical location information;
Step S43 judges whether working site photo changes or wrong, if so, change or newly-increased scene are shone Piece.
It should be noted that the terminal device can include but is not limited to the energy such as handheld terminal, mobile phone and tablet computer Enough installations have the APP of bar code scanning function, and the specific embodiment of the present invention is not particularly limited.
In conclusion approaches to IM in a kind of electric energy meter life cycle of the present invention, provides to electric energy meter Life Cycle The management method of the important informations such as geographical location information and user information in phase, to electric energy meter when advantageously reducing work on the spot Difficulty is searched, especially when departmental staff changes, the personnel of newly arriving can quickly incorporate work on the spot, for the following electric energy meter The development of life cycle management proposes guidance.
Specific embodiment is applied in the present invention, and principle and implementation of the present invention are described, above embodiments Explanation be merely used to help understand method and its core concept of the invention;At the same time, for those skilled in the art, According to the thought of the present invention, there will be changes in the specific implementation manner and application range, in conclusion in this specification Appearance should not be construed as limiting the invention.

Claims (2)

1. approaches to IM in a kind of electric energy meter life cycle characterized by comprising
Step S1 receives the relevant job note of electric energy meter, judges the task classification of the job note;The task class It Bao Kuo not new clothes, rotation, increase and decrease appearance, cancellation, shifting table and field test;
Step S2, if the task classification is new clothes, the item being arranged on the new clothes electric energy meter of terminal device scans working site Shape code receives the archive information of the new clothes electric energy meter of input in the messagewindow of display, establishes associated with electric energy meter table number New clothes electric energy meter archive information, and receive the working site photo of upload;The archive information includes user information and ground Manage location information;The user information include user's name, in every family number, station address, contact person and contact method;If described Task classification is non-new clothes, executes step S3;
Step S3, corresponding electric energy meter bar code on terminal device scans job note are obtained in the messagewindow of display and are corresponded to The archive information or terminal device of electric energy meter obtain the archive information of corresponding electric energy meter according to the electric energy meter table number of input;Pass through institute State contact person and contact details in archive information and carry out work reservation, and obtain the location information in the archive information with into Row navigation;
Step S4, the bar code being arranged on the electric energy meter of terminal device scans working site judge archive information and the work of display Whether scene photograph changes, and if there is a change, carries out information modification.
2. approaches to IM in electric energy meter life cycle according to claim 1, which is characterized in that the step S4 In, judge whether the archive information of display and working site photo change, if there is a change, carries out information modification, packet It includes:
Step S41, judge user's name, in every family number, station address, one in contact person and contact method and it is multinomial whether It changes, if so, carrying out the change of corresponding informance;
Step S42, judges whether geographical location information changes, if so, change or newly-increased geographical location information;
Step S43 judges whether working site photo changes or wrong, if so, change or newly-increased scene photograph.
CN201910105367.2A 2019-02-01 2019-02-01 Method for managing information in life cycle of electric energy meter Active CN109816557B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910105367.2A CN109816557B (en) 2019-02-01 2019-02-01 Method for managing information in life cycle of electric energy meter

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910105367.2A CN109816557B (en) 2019-02-01 2019-02-01 Method for managing information in life cycle of electric energy meter

Publications (2)

Publication Number Publication Date
CN109816557A true CN109816557A (en) 2019-05-28
CN109816557B CN109816557B (en) 2022-09-13

Family

ID=66606386

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910105367.2A Active CN109816557B (en) 2019-02-01 2019-02-01 Method for managing information in life cycle of electric energy meter

Country Status (1)

Country Link
CN (1) CN109816557B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111089993A (en) * 2020-01-21 2020-05-01 国网福建省电力有限公司莆田供电公司 Electric energy meter box and electric energy meter label standardized construction and meter box positioning method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101650772A (en) * 2009-09-18 2010-02-17 衡水供电公司 Method for realizing newly installed electric meter relative information automatic input in one-household and one-meter engineering by applying bar code
CN102436624A (en) * 2011-09-09 2012-05-02 荣科科技股份有限公司 Method for processing flow and standard of power-marketing site services on basis of handheld terminal
CN206378532U (en) * 2017-01-13 2017-08-04 国网湖南省电力公司 A kind of intelligent electric energy meter
EP3358307A1 (en) * 2017-02-03 2018-08-08 Sagemcom Energy & Telecom SAS Method for managing an auxiliary power supply of a meter

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101650772A (en) * 2009-09-18 2010-02-17 衡水供电公司 Method for realizing newly installed electric meter relative information automatic input in one-household and one-meter engineering by applying bar code
CN102436624A (en) * 2011-09-09 2012-05-02 荣科科技股份有限公司 Method for processing flow and standard of power-marketing site services on basis of handheld terminal
CN206378532U (en) * 2017-01-13 2017-08-04 国网湖南省电力公司 A kind of intelligent electric energy meter
EP3358307A1 (en) * 2017-02-03 2018-08-08 Sagemcom Energy & Telecom SAS Method for managing an auxiliary power supply of a meter

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
林炳锋: "电能表生命周期信息化管理的实现", 《资源节约与环保》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111089993A (en) * 2020-01-21 2020-05-01 国网福建省电力有限公司莆田供电公司 Electric energy meter box and electric energy meter label standardized construction and meter box positioning method

Also Published As

Publication number Publication date
CN109816557B (en) 2022-09-13

Similar Documents

Publication Publication Date Title
US9661467B2 (en) System and method for indoor location mapping and tracking
CN107124695B (en) Method and system for marking visited position based on contact information
CN109074550A (en) Context-aware dispatches special case
RU2597511C2 (en) Creating maps of private spaces using sensors of mobile computing devices
KR20110028216A (en) Dynamic event planning through location awareness
CN102254357A (en) Attendance system and attendance method
CN106658704A (en) Positioning method and system of starting point of indoor positioning
KR101135774B1 (en) Watt hour meter management system and method using technology of augmented reality
CN102682366A (en) Property position registering method, managing method and system
CN112653748B (en) Information pushing method and device, electronic equipment and readable storage medium
CN103995859A (en) Geographical-tag-oriented hot spot area event detection system applied to LBSN
CN105117853A (en) Gridding based GIS supervision and law-enforcing method and system
AU2012339654A1 (en) Detecting travel information
KR20130033948A (en) Method for sharing personal traveling schedule
CN109816557A (en) Approaches to IM in a kind of electric energy meter life cycle
WO2016172974A1 (en) Service processing method and device
CN109598461B (en) Distribution method, distribution device and computer readable storage medium
JP2015038744A (en) Data structure of sensing data provision contract and utilization contract
US20190303829A1 (en) Selectively processing data based on the type of data available
CN107563529A (en) A kind of electric power geography information operating system based on GPS and inertial positioning
CN1598489A (en) Method and system of public communication source guiding
CN202009403U (en) Intelligent interactive processing system containing geographical position information
JP2015038484A (en) Sensing data generation method
CN105550326B (en) Electricity consumption querying method, device
CN103926607B (en) Distance to a declared goal positioning measurement air navigation aid and device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant