CN109816252A - Tailings Dam integrated risk quantifies method for early warning and device - Google Patents

Tailings Dam integrated risk quantifies method for early warning and device Download PDF

Info

Publication number
CN109816252A
CN109816252A CN201910083773.3A CN201910083773A CN109816252A CN 109816252 A CN109816252 A CN 109816252A CN 201910083773 A CN201910083773 A CN 201910083773A CN 109816252 A CN109816252 A CN 109816252A
Authority
CN
China
Prior art keywords
variable
risk
warning
time
dynamic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910083773.3A
Other languages
Chinese (zh)
Other versions
CN109816252B (en
Inventor
施富强
廖学燕
张铱莹
郭万佳
王立娟
施轶凡
龚志刚
周帅
蒋耀港
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SICHUANSHENG SAFETY SCIENCE AND TECHNOLOGY RESEARCH INSTITUTE
Original Assignee
SICHUANSHENG SAFETY SCIENCE AND TECHNOLOGY RESEARCH INSTITUTE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SICHUANSHENG SAFETY SCIENCE AND TECHNOLOGY RESEARCH INSTITUTE filed Critical SICHUANSHENG SAFETY SCIENCE AND TECHNOLOGY RESEARCH INSTITUTE
Priority to CN201910083773.3A priority Critical patent/CN109816252B/en
Publication of CN109816252A publication Critical patent/CN109816252A/en
Application granted granted Critical
Publication of CN109816252B publication Critical patent/CN109816252B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Alarm Systems (AREA)

Abstract

The present invention relates to Safety of Tailings Dam system engineering field, especially a kind of Tailings Dam integrated risk quantifies method for early warning and device.The present invention differentiates the attribute of various risks variable data by science, the information such as time, space and the function embodied according to data, it is divided into important steady-state variable, basic guarantee variable and crucial dynamic variable three categories, risk discriminant approach is taken respectively to different classes of variable, the risk relevant information that comprehensive utilization variable data is contained to the maximum extent, quantitatively calculate Tailings Dam Risk-warning numerical value, according to the corresponding different brackets of Risk-warning numerical value, the Risk-warning signal of corresponding grade is sent.This method uses round-the-clock real time monitoring to crucial dynamic variable, carries out real-time change tracing analysis, continue to the evolutionary process of catastrophe, timely monitor.Spatialization, time domain, systematism are carried out to risk variable data, data classification adheres to separately, orderly function by different level, realizes data management data, deepens artificial intelligence.

Description

Tailings Dam integrated risk quantifies method for early warning and device
Technical field
The present invention relates to Safety of Tailings Dam system engineering field, especially a kind of Tailings Dam integrated risk quantifies method for early warning And device.
Background technique
The necessary facility that normally produces of metal mine is maintained as the place of stockpiling metal or non-metal mine industrial residue, Tailings Dam is the major hazard source with the artificial mud-rock flow of high potential energy, once dam break occurs, it will to the life wealth of downstream resident It produces safety and environment causes to seriously threaten.Recently as the rapid development of industry, the increasing number of domestic and international Tailings Dam is adjoint Taking place frequently for dam-break accident, the safety evaluation of Tailings Dam and Risk-warning are a urgent problems to be solved.
Safety assessment of tailing reservoir and Risk-warning should based on the safe condition for studying tailing dam and its auxiliary construction, To evaluate the security level of Tailings Dam, the danger source in operational process is reduced and controls, reaching reduces security risk, prevention thing Therefore occur, the target for keeping reservoir area periphery stable.There are many factor for influencing Safety of Tailings Dam operation, including Tailings Dam stockpiling system System, Tailings Dam flood drainage system, tailings storage backwater tapered system, Safety of Tailings Dam management and Tailings Dam once occur caused by dam break Harm etc., each subsystem contains the security performance that several indexs carry out joint effect Tailings Dam entirety again, this is one Typical non-linear, coupling complication system.
The inventors discovered that currently used Tailings Dam Risk-warning scheme is mainly from traditional methods of risk assessment, Single index or a few index are used, the conventional method judged according to actually detected data and threshold value comparison, this It is the assessment to single index, does not account for the multiple information that each achievement data is contained, especially each index institute body Existing time, space and functional information is necessary resource of each index of research to Tailings Dam Risk-warning, it is difficult to Tailings Dam Risk carries out comprehensive quantitative evaluation.Meanwhile Tailings Dam risk is dynamically, only using real-time, accurate and quantitative Evaluation method could effectively control risk, issue warning signal in time, convenient for taking risk prevention system measure.To sum up, current tail The deficiencies of mine library risk data use of information degree is low, risk is difficult to quantitative assessment, early warning real-time is weak.
Summary of the invention
It is an object of the invention to overcome the above-mentioned deficiency in the presence of the prior art, provides and a kind of become Tailings Dam risk Amount carries out scientific classification according to time, space, functional attributes, provides the comprehensive wind of Tailings Dam of the use of information degree of monitoring data Danger quantifies method for early warning.
In order to achieve the above-mentioned object of the invention, the present invention provides following technical schemes:
A kind of Tailings Dam integrated risk quantifies method for early warning, as shown in Figure 1, comprising:
Tailings Dam risk variable is divided into steady-state variable, ensures variable and dynamic variable by step A;The steady-state variable Meet variable quantity of the variable data in scheduled time range and/or spatial dimension less than the first predetermined threshold, and single change It measures related to Risk Results;The guarantee variable meets change of the variable data in scheduled time range and/or spatial dimension Change amount is less than the second predetermined threshold, and the set of several variables is related to Risk Results;The dynamic variable meets variable data The presentation dynamic that changes with time and random character, unitary variant are related to risk structure;
Step B obtains steady-state variable k1,k2,…,ki,…,knThe judgement of 0-1 two-value is carried out to the steady-state variable, 0 is corresponding Variable high risk, 1 corresponding low-risk, calculates steady-state variable early-warning parameters
It obtains and ensures variable and carry out risk numerical value calibration, obtain risk numerical value p1,p2,…,pi,…,pn, fractional value pair High risk is answered, big numerical value corresponds to low-risk, calculates and ensures variable early-warning parametersWherein AiFor risk indicator piIt is right The Risk rated ratio answered;
Real-time monitoring dynamic variable d1,d2,…,di,…,dn, the judgement of the section 0-1 is carried out to the dynamic variable, 0 is corresponding Variable high risk, 1 corresponding low-risk, calculates dynamic variable early-warning parameters
Step C according to the steady-state variable early-warning parameters K, ensures variable early-warning parameters P and dynamic variable early-warning parameters D Calculation risk quantifies early warning value E=K × P × D;
Step D sends pre-warning signal according to the quantifying risk early warning value E.
Wherein, the scheduled time and/or scheduled space can be wanted according to Tailings Dam early warning object and early warning situation Ask adjustment.The steady-state variable and risk have high correlation, keep data relatively stable in opposite space-time unique, Period of waves is relatively long, can work to Risk Governance and leave time enough surplus and spatial margin.The steady-state variable Once failure, i.e. 0-1 determines that result is 0, differentiates that danger source is in high risk state.In specific embodiment, storage capacity, dam The variables such as height, downstream environment, anti-flood drainage system, water seepage drainage facility, dam body status are set as steady-state variable, the standard that 0-1 determines For Tailings Dam design requirement.
The guarantee variable and risk have obvious correlation, typically exhibits the set and risk of such variable data Relationship is more prominent.
Dynamic, stochastic regime is presented in the dynamic variable data, and has direct relation or linear relationship with risk, For the dynamic variable once failing, danger source is in high risk state.Special emphasis is the object tailing as monitoring and early warning After library enters early warning space-time, the key effect of this class variable is dramatically increased, it is necessary to control the data variation of dynamic variable in real time Situation.
Preferably, in step B, when carrying out the judgement of the section 0-1 to the dynamic variable, including at least one buffers decision threshold Value, the buffering decision threshold is between (0,1).Due to dynamic variable for high risk triggering have top when Between sensibility, the monitoring numerical value of the dynamic variable between low-risk and high risk there are large range of waving interval, into The buffering decision threshold is arranged to the waving interval in one step, carries out more fine dynamic variable detected value section distribution and draws Point, be conducive to before high risk pre-warning signal issues, issue pre-tip signal for specific people, is subsequent high risk Sufficient time margin is stopped in pre-warning signal prevention and control.
In specific embodiment, the dynamic variable is dry beach length.It is divided into four using three bundle of lines Tailings Dam risks A state.Three lines: adjusting the dry bank line of flood, the dry bank line of warning, dangerous dry bank line, sets the first threshold for the dry bank line length of the tune flood The dry bank line length of the warning is set second threshold by value, when the dry beach length of real time monitoring is greater than the first threshold, then Dry beach length dynamic variable value is 1;The dry beach length of real time monitoring is less than the first threshold and is greater than the second threshold When, then doing beach length dynamic variable value is 0.7, and it is fixed to be embodied in the risk for the risk contribution of the dynamic variable at this time It measures in early warning value E=K × P × D;When the dry beach length of real time monitoring is less than the second threshold, then beach length dynamic variable is done Value is 0, directly triggering Risk-warning signal.
Preferably, further include step E after step D, into after alert status, continue dynamic variable described in real-time monitoring d1,d2,…,di,…,dnAt least one of in, draw at least one described dynamic variable versus time curve.
Alternatively, the dynamic variable be tailing reservoir level, dam crest to water level superelevation, do beach length, saturation, One or more in displacement structure.
Preferably, it is water level correlative into the dynamic variable for after alert status, continuing real-time monitoring, draws the water level Correlative versus time curve.The water level correlative versus time curve is applied with APP or the side of WEB application Formula is pushed to data terminal in real time, and amplitude, the vibration frequency of water level correlative described in current time are presented in visual form, Convenient for obtaining the peak-peak and fluctuation situation of the water level correlative in time.
Alternatively, the water level correlative is the superelevation or dry beach length of water level, dam crest to water level.Due to doing beach Slope angle can measure to obtain, and the same Tailings Dam can consider that the gradient is constant, do the triangle letter of beach length and superelevation Number relationship can simplify as linear relationship.Based on the water level, superelevation or dry beach length, Tailings Dam can be quickly calculated Interior water.
Preferably, step E further includes the time-domain differential and/or integral for calculating the water level correlative in real time.Pass through reality When calculate water level correlative time-differential and integral, more can profoundly show variation tendency and the stage of water level correlative Property result of variations, including but not limited to the instantaneous value of water level correlative, extreme value, increment change rate, increment change acceleration, time Increment total amount in section.
Preferably, the difference of instantaneous charge for remittance and draining is calculated in real time according to the time-domain differential of the water level correlative, essence The equilibrium state of instantaneous charge for remittance and draining will definitely be gone out.For example, the instantaneous delta of water level is positive, then reflect that instantaneous charge for remittance amount is greater than wink When displacement, risk present increase situation;The instantaneous delta of water level is negative, then reflects that instantaneous charge for remittance amount is less than instantaneous displacement, Risk, which is presented, reduces situation.It should be readily apparent to one skilled in the art that the meter of the calculating conclusion and water level of superelevation or dry beach length It is opposite to calculate conclusion.According to the incremental computations of water level correlative as a result, in conjunction with Tailings Dam plane distribution situation, calculate in real time instantaneous The increment of the instantaneous water of the difference of charge for remittance and draining, i.e. Tailings Dam.
Further, according to the difference and instantaneous water level amount of the instantaneous charge for remittance and draining, it is maximum that Tailings Dam is calculated in real time Allow rainfall.According to the increment of the instantaneous water of Tailings Dam and instantaneous water, the Peak sink of design scheme combining is counted in real time Calculate the maximum allowable rainfall of Tailings Dam.It is notified in advance according to the real-time weather of the maximum allowable rainfall and Tailings Dam part region Breath, can for subsequent risk lasting early warning and timely risk prevention system measure strive for abundance time margin.
Preferably, according to the time volume integration of the water level correlative calculate in designated time period in real time charge for remittance cumulant or Cumulant is drained, the security postures for the Gan Tan that is accurately ranked, sub- dam provide foundation.Product of the water level correlative within the controlled period Point, in conjunction with the planar distribution situation of Tailings Dam, the water increment in the controlled period that can calculate Tailings Dam in real time is tired Accumulated amount.Water buildup of increments amount is positive, then reflects in the controlled period that net increase situation is presented in water, hereafter the dry beach in period, The security risk on sub- dam increases;Water buildup of increments amount is negative, then reflects that net discharge situation is presented in water in the controlled period, this The security risk reduction of the Gan Tan in period, sub- dam afterwards.
Preferably, in step A, the set that the steady-state variable is constituted is the subset for the set that the guarantee variable is constituted; Or there are intersections with the set for ensureing variable composition for the set of the steady-state variable composition.Although the steady-state variable is adopted With mandatory 0-1 decision procedure, the single class variable differentiates that conclusion is directly related with risk.But it is low for being in It is divided into the set for ensureing variable by this class variable of risk status simultaneously, participates in the guarantee variable early warning ginseng The calculating of number P, can further increase the utilization rate for risk variable data, effectively improve the accuracy of Risk-warning.
Preferably, in step B, real-time monitoring dynamic variable d1,d2,…,di,…,dnIf at least one described dynamic becomes The instantaneous rate of change and/or transient change acceleration of amount are more than specified threshold, then directly transmit pre-warning signal.Due to dynamic variable The time attribute occurred with risk is closely bound up, when the dynamic variable does not set out the low-risk threshold value of 0-1 differentiation also, wink When change rate and transient change acceleration often antedating response variation tendency.Pass through the implementing monitoring to variation tendency correlative And calculating, the sending time of Risk-warning signal can be shifted to an earlier date to the maximum extent.
Preferably, according to the corresponding different brackets of Risk-warning numerical value E, the Risk-warning signal of corresponding grade is sent.
Another aspect of the present invention provides a kind of Tailings Dam integrated risk and quantifies prior-warning device, including at least one processing Device, and the memory being connect at least one described processor communication;The memory be stored with can by it is described at least one The instruction that processor executes, described instruction is executed by least one described processor, so that at least one described processor can Above-described Tailings Dam integrated risk quantifies method for early warning.
Compared with prior art, beneficial effects of the present invention:
Tailings Dam integrated risk provided by the invention quantifies method for early warning and differentiates various risks variable data by science Attribute, the information such as time, space and function embodied according to data are divided into important steady-state variable, basic guarantee becomes Amount and crucial dynamic variable three categories, take risk discriminant approach to different classes of variable respectively, to the maximum extent comprehensive benefit The risk relevant information contained with variable data quantitatively calculates Tailings Dam Risk-warning numerical value, according to Risk-warning numerical value pair The different brackets answered sends the Risk-warning signal of corresponding grade.
The present invention has fully considered the importance of crucial dynamic variable after pre-warning signal sending, uses to crucial dynamic variable Round-the-clock real time monitoring, to crucial dynamic variable carry out real-time change tracing analysis, to the evolutionary process of catastrophe carry out continue and When monitoring.
The present invention carries out spatialization, time domain, systematism to many risk variables of Tailings Dam, referred to as " three change ".After three change Data be able to enter classification, adhere to separately, orderly function by different level, realize data management data, deepen artificial intelligence.
Detailed description of the invention:
Fig. 1 is that 1 Tailings Dam integrated risk of the embodiment of the present invention quantifies method for early warning flow chart;
Fig. 2 is that the dry beach length of the embodiment of the present invention 1 implements monitoring data curve graph.
Specific embodiment
Below with reference to test example and specific embodiment, the present invention is described in further detail.But this should not be understood It is all that this is belonged to based on the technology that the content of present invention is realized for the scope of the above subject matter of the present invention is limited to the following embodiments The range of invention.
Embodiment 1
The present embodiment provides a kind of Tailings Dam integrated risks to quantify method for early warning, as shown in Figure 1, comprising:
Tailings Dam risk variable is divided into steady-state variable, ensures variable and dynamic variable by step A;The steady-state variable Meet variable quantity of the variable data in scheduled time range and/or spatial dimension less than the first predetermined threshold, and single change It measures related to Risk Results;The guarantee variable meets change of the variable data in scheduled time range and/or spatial dimension Change amount is less than the second predetermined threshold, and the set of several variables is related to Risk Results;The dynamic variable meets variable data The presentation dynamic that changes with time and random character, unitary variant are related to risk structure;
Step B obtains steady-state variable k1,k2,…,ki,…,kn0-1 judgement, 0 pair of dependent variable are carried out to the steady-state variable High risk, 1 corresponding low-risk, calculates steady-state variable early-warning parameters
It obtains and ensures variable and carry out risk numerical value calibration, obtain risk numerical value p1,p2,…,pi,…,pn, fractional value pair High risk is answered, big numerical value corresponds to low-risk, calculates and ensures variable early-warning parametersWherein AiFor risk indicator piIt is right The Risk rated ratio answered;
Real-time monitoring dynamic variable d1,d2,…,di,…,dn, 0-1 judgement, 0 pair of dependent variable are carried out to the dynamic variable High risk, 1 corresponding low-risk, calculates dynamic variable early-warning parametersAnd real-time waveform is carried out to the dynamic variable Analysis;
Step C according to the steady-state variable early-warning parameters K, ensures variable early-warning parameters P and dynamic variable early-warning parameters D Calculation risk quantifies early warning value E=K × P × D;
Step D sends pre-warning signal according to the quantifying risk early warning value E.
6 indexs such as storage capacity, height of dam, downstream environment, anti-flood drainage system, water seepage drainage facility, dam body status are chosen as stable state Property index steady-state variable, according to design scheme carry out 0-1 judgement, decision process and determine result it is as follows:
1 steady-state variable 0-1 of table determines
Steady-state variable early-warning parameters
The guarantee variable and risk have obvious correlation, typically exhibits the set and risk of such variable data Relationship is more prominent.The risk numerical value calibration for ensureing variable and carrying out the section 1-9 is obtained, risk numerical value p is obtained1,p2,…, pi,…,pn, the physical significance of risk numerical value is the relative risk index for ensureing variable current state relative to design scheme, such as Height of dam is required to be lower than 200 meters design scheme, then less than 30 meters values 9 of height of dam;30~60 meters, value 6.3;60~100 meters, Value 3.6;100~200 meters, value 1.
As shown in table 2, it calculates and ensures variable early-warning parametersWherein AiFor risk indicator piCorresponding risk Weight.Risk rated ratio AiCorrelation according to guarantee variable and Risk Results in previous Tailings Dam Risk-warning engineering practice Statistical analysis obtains.
Table 2 ensures that variable randomization determines
Dynamic, stochastic regime is presented in the dynamic variable data, and has direct relation or linear relationship with risk, For the dynamic variable once failing, danger source is in high risk state.It is divided into four states using three bundle of lines Tailings Dam risks. Three lines: adjusting the dry bank line of flood, the dry bank line of warning, dangerous dry bank line, first threshold is set by the dry bank line length of the tune flood, by institute It states the dry bank line length of warning and is set as second threshold, when the dry beach length of real time monitoring is greater than the first threshold, then dry beach is long Spending dynamic variable value is 1;When the dry beach length of real time monitoring is less than the first threshold and is greater than the second threshold, then do Beach length dynamic variable value is 0.7, and the risk contribution of the dynamic variable has been embodied in the quantifying risk early warning at this time In value E=K × P × D;When the dry beach length of real time monitoring is less than the second threshold, then doing beach length dynamic variable value is 0, directly triggering Risk-warning signal.
Wherein, adjusting the dry bank line of flood is to meet anti-row through flood routing according to high score satellite photo and Tailings Dam health account The dry beach length of big vast demand;Guarding against dry bank line is reservoir level continuous rise in heavy rain, and dry beach length gradually becomes smaller possibility Lead to unrestrained dam accident, meets the dry beach length of Tailings Dam and downstream masses Emergency Preparedness time;Dangerous dry bank line is code requirement Respective level Tailings Dam minimum dry beach length.The relationship of three are as follows: beach <beach tune Hong Gan is done in the dry beach < warning of danger, dry with three Tailings Dam is divided into " blood orange champac " four risk zones by bank line, and highest risk status is " red ", i.e., dry beach length is less than danger Dry beach length, administrative department should start emergency preplan, withdraw downstream personnel and critical facility equipment, closing relative influence region; Risk status is " orange ", i.e., dry beach length is in dangerous dry beach and guards against between dry beach, and administrative department should pay much attention to, and do at any time It is good to prepare starting emergency;Risk status is " Huang ", i.e., dry beach length, which is in, guards against dry beach and adjust between the beach Hong Gan, enterprise watch Member should pay close attention to SEA LEVEL VARIATION at any time;Blue region is safety zone, corresponding to adjust the beach Hong Gan or more.As shown in Fig. 2, for using Beidou position It sets service system and three lines, four area's mode realizes that length of dry sand of tailings reservoir changes real-time monitoring result figure.
Further include step E after step D, into after alert status, continues to do beach length described in real-time monitoring, draw dry Beach length versus time curve.The dry beach length versus time curve is in a manner of APP application or WEB application It is pushed to data terminal in real time, amplitude, the vibration frequency for doing beach length described in current time are presented in visual form, is convenient for The peak-peak and fluctuation situation of the dry beach length are obtained in time.
Since dry beach slope angle can measure to obtain, the same Tailings Dam can consider that the gradient is constant, and it is long to do beach Degree and the trigonometric function relationship of superelevation can simplify as linear relationship.Based on the dry beach length, Tailings Dam is quickly calculated Interior water.
Step E further includes the time-domain differential and/or integral for calculating the dry beach length in real time.It is dry by calculating in real time The time-differential and integral of beach length, more can profoundly show dry beach length variation tendency and phasic Chang as a result, Instantaneous value, extreme value, increment change rate, increment variation acceleration, the increment in the period of including but not limited to dry beach length are total Amount.
The difference for calculating instantaneous charge for remittance and draining in real time according to the time-domain differential of the dry beach length precisely obtains instantaneous The equilibrium state of charge for remittance and draining.The instantaneous delta of dry beach length is positive, then reflects that instantaneous charge for remittance amount is less than instantaneous displacement, wind Danger, which is presented, reduces situation;The instantaneous delta of dry beach length is negative, then reflects that instantaneous charge for remittance amount is greater than instantaneous displacement, risk is presented Increase situation.According to the incremental computations of dry beach length as a result, in conjunction with Tailings Dam plane distribution situation, in real time calculate in real time calculate The difference of instantaneous charge for remittance and draining, the i.e. increment of the instantaneous water of Tailings Dam.
Further, according to the difference and instantaneous water level amount of the instantaneous charge for remittance and draining, it is maximum that Tailings Dam is calculated in real time Allow rainfall.According to the increment of the instantaneous water of Tailings Dam and instantaneous water, the Peak sink of design scheme combining is counted in real time Calculate the maximum allowable rainfall of Tailings Dam.It is notified in advance according to the real-time weather of the maximum allowable rainfall and Tailings Dam part region Breath, can for subsequent risk lasting early warning and timely risk prevention system measure strive for abundance time margin.
Charge for remittance cumulant or draining accumulation in designated time period are calculated in real time according to the time volume integration of the dry beach length Amount, the security postures for the Gan Tan that is accurately ranked, sub- dam provide foundation.Dry integral of the beach length within the controlled period, in conjunction with tail The planar distribution situation in mine library can calculate the water buildup of increments amount in the controlled period of Tailings Dam in real time.Water Buildup of increments amount is positive, then reflects in the controlled period that net increase situation is presented in water, hereafter the Gan Tan in period, sub- dam safety Risk increases;Water buildup of increments amount is negative, then reflects that net discharge situation is presented in water in the controlled period, hereafter period is dry The security risk reduction on beach, sub- dam.
In step A, the set that the steady-state variable is constituted is the subset for the set that the guarantee variable is constituted;Or it is described There are intersections for the set that the set that steady-state variable is constituted is constituted with the guarantee variable, such as storage capacity, height of dam.Although the stable state becomes Amount uses mandatory 0-1 decision procedure, and the single class variable differentiates that conclusion is directly related with risk.But for locating In this class variable of low-risk state, it is divided into simultaneously in the set for ensureing variable, it is pre- to participate in guarantor's quantitative change amount The calculating of alert parameter P, can further increase the utilization rate for risk variable data, effectively improve the accurate of Risk-warning Degree.
In step B, real-time monitoring dynamic variable d1,d2,…,di,…,dnIf at least one described dynamic variable is instantaneous Change rate and/or transient change acceleration are more than specified threshold, then directly transmit pre-warning signal.Since dynamic variable and risk are sent out Raw time attribute is closely bound up, when the dynamic variable does not trigger the low-risk threshold value of 0-1 differentiation also, instantaneous rate of change With transient change acceleration often antedating response variation tendency.By implementing monitoring to variation tendency correlative and calculating, The sending time of Risk-warning signal can be shifted to an earlier date to the maximum extent.
According to the corresponding different brackets of Risk-warning numerical value E, the Risk-warning signal of corresponding grade is sent.Comprehensive and quantitative wind Danger (E) evaluation is mainly made of the evaluation of above-mentioned three parts, comprehensive quantitative evaluation result E=K × P × D, and its risk assessment etc. Grade is divided into 4 grades, wherein 0≤E < 3 are material risk;3≤E < 5 are greater risk;5≤E < 6 are average risk;6≤E≤9 are low Risk.As E < 5, analysis sends Risk-warning signal in real time.
The case where for E < 5, specifically analyzes the reason for causing Risk-warning value relatively low again, takes respectively different types of pre- Alert measure, the Risk-warning value E for caused by due to the steady-state variable is relatively low, issues and forces reform advice, for institute It is relatively low to state Risk-warning value caused by dynamic variable reason, timely enters alert status, formulates emergency preplan.
It will be appreciated by those skilled in the art that: realize that all or part of the steps of above method embodiment can pass through program Relevant hardware is instructed to complete, program above-mentioned can store in computer-readable storage medium, which is executing When, execute step including the steps of the foregoing method embodiments;And storage medium above-mentioned includes: movable storage device, read-only memory The various media that can store program code such as (Read Only Memory, ROM), magnetic or disk.
When the above-mentioned integrated unit of the present invention be realized in the form of SFU software functional unit and as the sale of independent product or In use, also can store in a computer readable storage medium.Based on this understanding, the skill of the embodiment of the present invention Substantially the part that contributes to existing technology can be embodied in the form of software products art scheme in other words, the calculating Machine software product is stored in a storage medium, including some instructions are used so that a computer equipment (can be individual Computer, server or network equipment etc.) execute all or part of each embodiment the method for the present invention.And it is aforementioned Storage medium include: the various media that can store program code such as movable storage device, ROM, magnetic or disk.
The above, the only detailed description of the specific embodiment of the invention, rather than limitation of the present invention.The relevant technologies The technical staff in field is not in the case where departing from principle and range of the invention, various replacements, modification and the improvement made It should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of Tailings Dam integrated risk quantifies method for early warning characterized by comprising
Tailings Dam risk variable is divided into steady-state variable, ensures variable and dynamic variable by step A;The steady-state variable meets Variable quantity of the variable data in scheduled time range and/or spatial dimension less than the first predetermined threshold, and unitary variant with Risk Results are related;The guarantee variable meets variable quantity of the variable data in scheduled time range and/or spatial dimension Less than the second predetermined threshold, and the set of several variables is related to Risk Results;The dynamic variable meets variable data at any time Between variation present dynamic and random character, unitary variant it is related to risk structure;
Step B obtains steady-state variable k1,k2,…,ki,…,knThe judgement of 0-1 two-value, 0 pair of dependent variable are carried out to the steady-state variable High risk, 1 corresponding low-risk, calculates steady-state variable early-warning parameters
It obtains and ensures variable and carry out risk numerical value calibration, obtain risk numerical value p1,p2,…,pi,…,pn, fractional value corresponds to high wind Danger, big numerical value correspond to low-risk, calculate and ensure variable early-warning parametersWherein AiFor risk indicator piIt is corresponding Risk rated ratio;
Real-time monitoring dynamic variable d1,d2,…,di,…,dn, the judgement of the section 0-1,0 pair of dependent variable height are carried out to the dynamic variable Risk, 1 corresponding low-risk, calculates dynamic variable early-warning parameters
Step C according to the steady-state variable early-warning parameters K, ensures that variable early-warning parameters P and dynamic variable early-warning parameters D is calculated Quantifying risk early warning value E=K × P × D;
Step D sends pre-warning signal according to the quantifying risk early warning value E.
2. method for early warning according to claim 1, it is characterised in that: in step B, carry out the area 0-1 to the dynamic variable Between when determining, including at least one buffers decision threshold, and the buffering decision threshold is between (0,1).
3. method for early warning according to claim 1, it is characterised in that: further include step E after step D, into early warning shape After state, continue dynamic variable d described in real-time monitoring1,d2,…,di,…,dnAt least one of in, it is described dynamic to draw at least one State variable versus time curve.
4. method for early warning according to claim 3, it is characterised in that: in step E, into after alert status, continue real-time The dynamic variable of monitoring is water level correlative, draws the water level correlative versus time curve.
5. method for early warning according to claim 4, it is characterised in that: step E further includes calculating the water level correlation in real time The time-domain differential of amount, according to the time-domain differential of the water level correlative calculate in real time instantaneous charge for remittance and draining difference and/ Or integral.
6. method for early warning according to claim 4, it is characterised in that: real according to the time-domain differential of the water level correlative When calculate the difference of instantaneous charge for remittance and draining;And/or when according to the time volume integration of the water level correlative calculating specified in real time Between charge for remittance cumulant or draining cumulant in section.
7. according to the described in any item method for early warning of claim 4-6, it is characterised in that: the water level correlative is water level, dam Push up the superelevation or dry beach length of water level.
8. method for early warning according to claim 1, it is characterised in that: real-time monitoring dynamic variable d in step B1,d2,…, di,…,dnIf the change rate and/or variation acceleration of at least one described dynamic variable are more than specified threshold, directly transmit Pre-warning signal.
9. method for early warning according to claim 1, it is characterised in that: in step A, the set that the steady-state variable is constituted is The subset of the set for ensureing variable composition;Or the collection gathered with the guarantee variable composition that the steady-state variable is constituted There are intersections for conjunction.
10. a kind of Tailings Dam integrated risk quantifies prior-warning device, which is characterized in that including at least one processor, and with institute State the memory of at least one processor communication connection;The memory is stored with can be by the execution of at least one described processor Instruction, described instruction is executed by least one described processor, so that at least one described processor is able to carry out claim 1 To method described in any one of 9.
CN201910083773.3A 2019-01-29 2019-01-29 Tailing pond comprehensive risk quantitative early warning method and device Active CN109816252B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910083773.3A CN109816252B (en) 2019-01-29 2019-01-29 Tailing pond comprehensive risk quantitative early warning method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910083773.3A CN109816252B (en) 2019-01-29 2019-01-29 Tailing pond comprehensive risk quantitative early warning method and device

Publications (2)

Publication Number Publication Date
CN109816252A true CN109816252A (en) 2019-05-28
CN109816252B CN109816252B (en) 2020-06-30

Family

ID=66605553

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910083773.3A Active CN109816252B (en) 2019-01-29 2019-01-29 Tailing pond comprehensive risk quantitative early warning method and device

Country Status (1)

Country Link
CN (1) CN109816252B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110807569A (en) * 2019-09-17 2020-02-18 中国地质大学(武汉) Tailings pond risk evaluation and management method for different interest groups under extreme working conditions
CN112783100A (en) * 2019-11-06 2021-05-11 中国石油化工股份有限公司 Memory, chemical enterprise safety production risk early warning method, equipment and device
CN112883458A (en) * 2021-01-13 2021-06-01 中国安全生产科学研究院 Rapid permeability reducing system and method for inner top pipe of metal mine tailing pond
CN113310515A (en) * 2021-05-25 2021-08-27 上海同禾工程科技股份有限公司 Machine vision-based tailing pond flood drainage facility monitoring system and monitoring method
CN114429308A (en) * 2022-02-08 2022-05-03 河南鑫安利安全科技股份有限公司 Enterprise security risk assessment method and system based on big data
CN115099677A (en) * 2022-07-14 2022-09-23 中国安全生产科学研究院 Tailing pond safety production risk grading early warning method
CN116104052A (en) * 2023-01-19 2023-05-12 中煤科工开采研究院有限公司 Paste alkaline residue safe mining and digging method and dam dismantling method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103488897A (en) * 2013-09-24 2014-01-01 柳州市博源环科科技有限公司 Evaluation method of risk levels of dangerous substances of mining industry
CN104281920A (en) * 2014-09-29 2015-01-14 中南大学 Tailing pond layered index safety assessment and early-warning method and system
CN106600153A (en) * 2016-12-21 2017-04-26 武汉理工大学 Tailing pond dam break risk evaluating method
EP3229186A1 (en) * 2016-04-06 2017-10-11 Honeywell International Inc. Systems and methods for assigning a fire system safety score and for predictive analysis via data mining

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103488897A (en) * 2013-09-24 2014-01-01 柳州市博源环科科技有限公司 Evaluation method of risk levels of dangerous substances of mining industry
CN104281920A (en) * 2014-09-29 2015-01-14 中南大学 Tailing pond layered index safety assessment and early-warning method and system
EP3229186A1 (en) * 2016-04-06 2017-10-11 Honeywell International Inc. Systems and methods for assigning a fire system safety score and for predictive analysis via data mining
CN106600153A (en) * 2016-12-21 2017-04-26 武汉理工大学 Tailing pond dam break risk evaluating method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
谢旭阳等: "尾矿库区域预警指标体系的建立", 《中国安全科学学报》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110807569A (en) * 2019-09-17 2020-02-18 中国地质大学(武汉) Tailings pond risk evaluation and management method for different interest groups under extreme working conditions
CN112783100A (en) * 2019-11-06 2021-05-11 中国石油化工股份有限公司 Memory, chemical enterprise safety production risk early warning method, equipment and device
CN112883458A (en) * 2021-01-13 2021-06-01 中国安全生产科学研究院 Rapid permeability reducing system and method for inner top pipe of metal mine tailing pond
CN112883458B (en) * 2021-01-13 2021-12-14 中国安全生产科学研究院 Rapid permeability reducing system and method for inner top pipe of metal mine tailing pond
CN113310515A (en) * 2021-05-25 2021-08-27 上海同禾工程科技股份有限公司 Machine vision-based tailing pond flood drainage facility monitoring system and monitoring method
CN114429308A (en) * 2022-02-08 2022-05-03 河南鑫安利安全科技股份有限公司 Enterprise security risk assessment method and system based on big data
CN115099677A (en) * 2022-07-14 2022-09-23 中国安全生产科学研究院 Tailing pond safety production risk grading early warning method
CN115099677B (en) * 2022-07-14 2023-04-07 中国安全生产科学研究院 Tailing pond safety production risk grading early warning method
WO2024012552A1 (en) * 2022-07-14 2024-01-18 中国安全生产科学研究院 Graded early-warning method for safety production risks in tailings pond
CN116104052A (en) * 2023-01-19 2023-05-12 中煤科工开采研究院有限公司 Paste alkaline residue safe mining and digging method and dam dismantling method
CN116104052B (en) * 2023-01-19 2023-09-05 中煤科工开采研究院有限公司 Paste alkaline residue safe mining and digging method and dam dismantling method

Also Published As

Publication number Publication date
CN109816252B (en) 2020-06-30

Similar Documents

Publication Publication Date Title
CN109816252A (en) Tailings Dam integrated risk quantifies method for early warning and device
Tiwari et al. Stock market efficiency analysis using long spans of data: A multifractal detrended fluctuation approach
Huaizhi et al. A study of safety evaluation and early-warning method for dam global behavior
CN104954154B (en) The monitoring of operation management platform and Breakdown Maintenance method and system
Hou et al. Evaluating Ecological Vulnerability Using the GIS and Analytic Hierarchy Process (AHP) Method in Yan'an, China.
CN104281920A (en) Tailing pond layered index safety assessment and early-warning method and system
CN112783101A (en) Storage, dangerous chemical tank area safety risk early warning method, equipment and device
CN110132218B (en) Multi-level early warning determination method based on slope stability monitoring
CN109543897A (en) Local government debt risk dynamic evaluation and prediction technique
CN106287233B (en) A kind of pipe network leakage method for early warning and system
CN106779131A (en) Grease hole evaluates phase cumulative production Forecasting Methodology
CN110020760A (en) Petroleum chemical enterprise&#39;s security risk grade quantitative evaluating method
CN104535346B (en) Anti-slip stability detection method for concrete gravity dangerous dam
Alonso et al. A graphical approach to characterize sub-daily flow regimes and evaluate its alterations due to hydropeaking
CN102445396B (en) Apparatus for online detection of use strength and prediction of fatigue based on crane wire rope load measurement, and method thereof
CN111814110B (en) Bridge health monitoring data control chart analysis method
Percic et al. EARLY WARNING SYSTEMS FOR FINANCIAL CRISES-A CRITICAL APPROACH.
CN109726485A (en) Concrete dam point true stress Predicting Reliability analysis method and device
Zhang et al. Real-time burst detection based on multiple features of pressure data
CN101382474B (en) Alarming method for bridge structure safety
CN111222968A (en) Enterprise tax risk management and control method and system
Yang et al. Fuzzy risk analysis of dam overtopping from snowmelt floods in the nonstationarity case of the Manas River catchment, China
Dong et al. Anomaly identification of monitoring data and safety evaluation method of tailings dam
KR100795967B1 (en) Inspection and maintenance system of bridges using extreme distribution analysis
Yang et al. Multistage warning indicators of concrete dam under influences of random factors

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Zhang Yiying

Inventor after: Shi Fuqiang

Inventor after: Wang Lijuan

Inventor after: Shi Diefan

Inventor after: Gong Zhigang

Inventor after: Zhou Shuai

Inventor after: Jiang Yaogang

Inventor after: Guo Wanjia

Inventor after: Liao Xueyan

Inventor before: Shi Fuqiang

Inventor before: Liao Xueyan

Inventor before: Zhang Yiying

Inventor before: Guo Wanjia

Inventor before: Wang Lijuan

Inventor before: Shi Diefan

Inventor before: Gong Zhigang

Inventor before: Zhou Shuai

Inventor before: Jiang Yaogang

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant