CN109811613A - A kind of interim ground installation and its integral construction method - Google Patents

A kind of interim ground installation and its integral construction method Download PDF

Info

Publication number
CN109811613A
CN109811613A CN201910193402.0A CN201910193402A CN109811613A CN 109811613 A CN109811613 A CN 109811613A CN 201910193402 A CN201910193402 A CN 201910193402A CN 109811613 A CN109811613 A CN 109811613A
Authority
CN
China
Prior art keywords
steel frame
module
angle steel
water
floor tile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910193402.0A
Other languages
Chinese (zh)
Other versions
CN109811613B (en
Inventor
江筠
熊海
陈珑
李归
王静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Construction Engineering Co Ltd
Original Assignee
Wuhan Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Construction Engineering Co Ltd filed Critical Wuhan Construction Engineering Co Ltd
Priority to CN201910193402.0A priority Critical patent/CN109811613B/en
Publication of CN109811613A publication Critical patent/CN109811613A/en
Application granted granted Critical
Publication of CN109811613B publication Critical patent/CN109811613B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The invention discloses a kind of interim ground installation and its integral construction methods, combination including angle steel frame module water-permeable brick pavement system, angle steel frame module interior floor tile pavement system and angle steel frame module light vehicle travel pavement system, the angle steel frame module water-permeable brick pavement system includes the rammed earth base being arranged from bottom to top, coarse sand bed course and permeable surface layer;Angle steel frame module interior floor tile pavement system includes the rammed earth base being arranged from bottom to top, coarse sand bed course and indoor tile paved surface;The channel steel frame module light vehicle travel pavement system includes the rammed earth base being arranged from bottom to top, coarse sand bed course and channel steel frame reinforced concrete pavement module supercrust.The present invention is applied widely, and construction efficiency is high, speed is fast, reliable in quality, and modular construction can be achieved in the module of three kinds of pavement systems, and finished product is reusable.

Description

A kind of interim ground installation and its integral construction method
Technical field
The invention belongs to the interim ground construction technical fields in construction site, and in particular to a kind of interim ground installation and one Body construction method.
Background technique
With the promotion of city inhabitants living standard, requirement of the people for quality of life is also higher and higher, for institute The environment of life is completely, neatly most basic requirement;And with the development of the city, government department has also put into effect relevant policies, It is required that construction place keeps clean and tidy, waste must not be brought into city.For this purpose, in construction site Office Area, living area room The laying on ground and surrounding area road surface is particularly important.Construction site ground traditional treatment method is that carriage way pouring is mixed Solidifying soil, either placing concrete or laying common water-permeable brick, flooring are laid with floor tile to Route for pedestrians.This processing method disadvantage Hold a lot of, if concrete road needs to cut after completion of works, can generate many building wastes influences environment;Common water-permeable brick Laying process is complicated;Indoor floor tile service life is short etc..Traditional building site floor treatment mode construction efficiency is low, construction technology is numerous Trivial, material cannot be reused, and the significant wastage of manpower and material resources is caused.
Summary of the invention
The first object of the present invention is to provide that a kind of structural strength is high, laying construction is convenient, does not have to screed-coat, dismounting speed Fastly, repeat the interim ground installation that utilizes of turnover, can by ground temporary facility recycling and reusing, sufficiently meet saving metal material and energy and Environmentally protective requirement.
The second object of the present invention is to provide a kind of interim ground installation integral construction method, and laying construction is convenient, applies Work is high-efficient, speed is fast, reliable in quality, can solve the interim ground installation of construction site Office Area, living area, workspace extensively Mat formation.
To further realize above-mentioned first purpose, the invention adopts the following technical scheme: a kind of interim ground installation, including Angle steel frame module water-permeable brick pavement system, angle steel frame module interior floor tile pavement system and angle steel frame module The combination of light vehicle travel pavement system, in which: the angle steel frame module water-permeable brick pavement system includes under And the thick permeable surface layer of rammed earth base, 50mm thickness coarse sand bed course and 65mm of upper setting, the permeable surface layer includes angle steel Frame water-permeable brick is mated formation module and sand base water-permeable brick;Angle steel frame module interior floor tile pavement system include from lower and The thick indoor tile paved surface of rammed earth base, 50mm thickness coarse sand bed course and the 65-70mm of upper setting, the interior tile paved surface Mat formation module including 60mm thickness floor tile angle steel frame and 5-10mm thickness surface layer floor tile, the floor tile angle steel frame are mated formation in module Pour the armored concrete of 60mm thickness;The channel steel frame module light vehicle travel pavement system include from lower and Rammed earth base, 50mm thickness coarse sand bed course and the 120mm thickness channel steel frame reinforced concrete pavement module road surface of upper setting Layer, the channel steel frame reinforced concrete pavement module supercrust include that channel steel frame is mated formation module and in the channel steel frame The armored concrete of 120mm thickness is poured in module of mating formation.
As an improvement of the above technical solution, in one embodiment of the invention, the coarse sand bed course and the element soil Permeable geotextiles are equipped between compacting base;The angle steel frame water-permeable brick mat formation block length be 1100mm, width is 830mm, bottom is provided with the first support bar of steel of 5mm thickness and middle part is provided with the isolation that 5mm thickness is used as isolation water-permeable brick Item.
Further, first support bar be located at the angle steel frame water-permeable brick mat formation module frame at when, it is wide Degree is 60mm;When first support bar and isolating bar intersect vertically, width 80mm.
Further, the mat formation frame diagonal angle of module of the angle steel frame water-permeable brick is welded with the triangular of 3mm thickness Shape suspension hook plate, the triangle suspension hook plate are the isosceles right triangle of right angle side length 115mm, and being provided with diameter at centroid is The hook on hole of 15mm.
Further, the size of the sand base water-permeable brick is 100mm × 200mm × 60mm, and each angle steel frame is saturating Water brick, which is mated formation, to be put 4 column, 10 row in module and amounts to 40 pieces of sand base water-permeable bricks.
As an improvement of the above technical solution, in one embodiment of the invention, the floor tile angle steel frame is mated formation mould There are the round hole for hoist that a diameter is 30mm, the centers of circle to be located in the middle part of angle steel on four flank side surface of block every side;Each floor tile Angle steel frame mats formation block length for 600 or 800 or 1000mm, and width is 600 or 800 or 1000mm.
As an improvement of the above technical solution, in one embodiment of the invention, the single channel steel frame is mated formation mould Block length is 1500mm, width 1000mm, and channel steel width is 120mm, with a thickness of 5mm.
Further, the mat formation frame diagonal angle of module of the channel steel frame is welded with sunpender, the sunpender and channel steel shape At the isosceles right triangle of right angle side length 115mm, the suspension hook slot of long 100mm, width 50mm, depth 60mm are provided at centroid.
Further, the channel steel frame mat formation module inner concrete pour can take first poured in advance in factory, after At the construction field (site) assembly use or first at the scene lifting channel steel frame mat formation module, after casting concrete at the construction field (site).
To further realize above-mentioned second purpose, the invention adopts the following technical scheme: a kind of interim ground installation one Change construction method, comprising the following steps:
The construction process step of S1, the angle steel frame module water-permeable brick pavement system are as follows:
S101, sundries, the surface dust in rammed earth base are cleaned out, is tamped to compactness not using rammer compacter Less than 93%;
S102, pave one layer of permeable geotextiles, and lap width is not less than 200mm;
S103, pave coarse sand bed course, appropriate to sprinkle water and be sufficiently compacted leveling;
S104, production angle steel frame water-permeable brick are mated formation module, and 40 pieces of sand base water-permeable bricks are divided into 4 column, and to be put into angle steel frame saturating Water brick is mated formation in module;
S105, mated formation in module to coarse sand bed course with suspension hook by hook on hole handling angle steel frame water-permeable brick, band line adjusts Assembly simultaneously controls piece in 1mm;
The construction process step of S2, angle steel frame module interior floor tile pavement system are as follows:
S201, production floor tile angle steel frame are mated formation module;
S202, meet the reinforcing bar of design strength in the setting in module of mating formation of floor tile angle steel frame and pour 60mm thickness coagulation Soil, concrete and floor tile angle steel frame are mated formation, and module is suitable for reading concordant and to receive light smooth;
S203, the surface layer floor tile paving of 5-10mm thickness is formed into indoor floor tile in concrete surface using 903 building adhesives;
The construction process step of S3, the channel steel frame module light vehicle travel pavement system are as follows:
S301, sundries, the surface dust in rammed earth base are cleaned out, is tamped to compactness not using rammer compacter Less than 93%;
S302, pave coarse sand bed course, appropriate to sprinkle water and be sufficiently compacted leveling;
S303, production channel steel frame are mated formation module;
S304, meet the reinforcing bar of design strength in the setting in module of mating formation of channel steel frame and pour 120mm thickness concrete, mix Solidifying soil is suitable for reading concordant with channel steel and to receive light smooth.
Compared with prior art, the invention has the following beneficial effects:
(1) applied widely.The present invention contains angle steel frame module water-permeable brick pavement system, angle steel frame module Indoor floor tile pavement system, channel steel frame module light vehicle travel pavement system, above-mentioned three kinds of pavement systems combine Get up to solve extensively construction site Office Area, living area, workspace interim ground installation mat formation.
(2) construction efficiency is high, speed is fast, reliable in quality.The module of above-mentioned three kinds of pavement systems can be achieved modularization and apply Work, first direct handling is mated formation at the scene after factory is precisely prefabricated, intensity with higher, the smooth beauty of surface layer.
(3) finished product is reusable.In Demolition Construction place when interim ground installation can direct handling earth module, by it Recycling and reusing, energy-saving material-saving are environmentally protective.
Detailed description of the invention
It, below will be to required in embodiment or description of the prior art in order to illustrate more clearly of technical solution of the present invention The attached drawing used is briefly described, it should be apparent that, drawings in the following description are only some embodiments of the invention, right For those of ordinary skill in the art, without creative efforts, it can also be obtained according to these attached drawings Its attached drawing.
Fig. 1 is the structural stratification figure of angle steel frame module water-permeable brick pavement system;
Fig. 2 is that the mat formation plane of module of single angle steel frame water-permeable brick is shown in angle steel frame module water-permeable brick pavement system It is intended to;
Fig. 3 is the structural stratification figure of angle steel frame module interior floor tile pavement system;
Fig. 4 is that the mat formation plane of module of single floor tile angle steel frame is shown in the floor tile pavement system of angle steel frame module interior It is intended to;
Fig. 5 is the structural stratification figure of channel steel frame module light vehicle travel pavement system;
Fig. 6 is that single channel steel frame is mated formation the flat of module in channel steel frame module light vehicle travel pavement system Face schematic diagram.
Wherein: 1- rammed earth base, the permeable geotextiles of 2-, 3- coarse sand bed course, 4- angle steel frame water-permeable brick are mated formation module, 5- sand base water-permeable brick, the first support bar of 6-, 7- isolating bar, 8- triangle suspension hook plate, 9- hole for hoist, 10- floor tile angle steel frame paving Die-filling piece, the second support bar of 11-, 12- armored concrete, 13- surface layer floor tile, 14- circle hole for hoist, 15- channel steel frame mats formation Module, 17- sunpender, 18- suspension hook slot.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art without creative labor it is obtained it is all its His embodiment, shall fall within the protection scope of the present invention.
A kind of interim ground installation provided in an embodiment of the present invention, including angle steel frame module water-permeable brick pavement system, The group of angle steel frame module interior floor tile pavement system and angle steel frame module light vehicle travel pavement system It closes.
As shown in Figs. 1-2, the angle steel frame module water-permeable brick pavement system includes the plain earth rammer being arranged from bottom to top The thick permeable surface layer of real base 1,50mm thickness coarse sand bed course 3 and 65mm, the permeable surface layer includes that angle steel frame water-permeable brick is mated formation Module 4 and sand base water-permeable brick 5;1 compactness of rammed earth base is not less than 93%;The coarse sand bed course 3 and the element Permeable geotextiles 2 are equipped between rammed earth base 1;The coarse sand bed course 3 is 50mm thick, and the angle steel frame water-permeable brick is mated formation 4 length of module is 1100mm, and width 830mm, bottom is provided with the first support bar of steel 6 of 5mm thickness and middle part is provided with 5mm thickness is used as the isolating bar 7 of isolation water-permeable brick;First support bar 6 is located at the angle steel frame water-permeable brick and mats formation module 4 When at frame, width 60mm;When first support bar 6 intersects vertically with isolating bar 7, width 80mm;The angle The mat formation frame diagonal angle of module 4 of steel frame water-permeable brick is welded with the triangular shape suspension hook plate 8 of 3mm thickness, and the triangle is hung Hook plate 8 is the isosceles right triangle of right angle side length 115mm, and the hook on hole 9 that diameter is 15mm is provided at centroid;The sand The size of base water-permeable brick 5 is 100mm × 200mm × 60mm, and each angle steel frame water-permeable brick, which is mated formation, puts 4 column in module 4 10 rows amount to 40 pieces of sand base water-permeable bricks.
As shown in Figure 3-4, angle steel frame module interior floor tile pavement system includes the element soil being arranged from bottom to top The thick indoor tile paved surface of base 1,50mm thickness coarse sand bed course 3 and 65-70mm is tamped, the interior tile paved surface includes 60mm thickness Floor tile angle steel frame is mated formation module 10 and 5-10mm thickness surface layer floor tile 13, further includes second support bar of 40mm wide 11;Describedly Brick angle steel frame, which is mated formation, pours the armored concrete 12 of 60mm thickness in module 10;The floor tile angle steel frame is mated formation module 10 4 There are the round hole for hoist 14 that a diameter is 30mm, the centers of circle to be located in the middle part of angle steel on flank side surface every side;Each floor tile angle Steel frame mat formation 10 length of module be 600, (800,1000) mm, width 600, (800,1000) mm, according to floor tile size It determines.The interior tile paved surface can the floor tile angle steel frames of customized different spread patterns as needed mat formation module.Steel is wide Degree is 60mm, with a thickness of 3mm.
As seen in figs. 5-6, the channel steel frame module light vehicle travel pavement system includes setting from bottom to top Rammed earth base 1,50mm thickness coarse sand bed course 3 and the 120mm thickness channel steel frame reinforced concrete pavement module supercrust set, The channel steel frame reinforced concrete pavement module supercrust includes that channel steel frame is mated formation module 15 and in the channel steel frame The armored concrete 12 of 120mm thickness is poured in module of mating formation 15.1 compactness of rammed earth base is not less than 93%;It is single A channel steel frame mat formation 15 length of module be 1500mm, width 1000mm, channel steel width be 120mm, with a thickness of 5mm. The mat formation frame diagonal angle of module 15 of the channel steel frame is welded with sunpender 17, and it is long that the sunpender 17 and channel steel form right-angle side The isosceles right triangle of 115mm is provided with the suspension hook slot 18 of long 100mm, wide 50mm, depth 60mm at centroid.
Further, can the channel steel frames of customized different spread patterns as needed mat formation module 15, the channel steel Frame mat formation 15 inner concrete of module pour can take first poured in advance in factory, after at the construction field (site) assembly use or first exist On-site hoisting channel steel frame mat formation module, after casting concrete at the construction field (site).
A kind of interim ground installation integral construction method provided in an embodiment of the present invention, comprising the following steps:
The construction process step of step 1, the angle steel frame module water-permeable brick pavement system are as follows:
Step 101 cleans out sundries, the surface dust in rammed earth base 1, is tamped using rammer compacter to compacting Degree is not less than 93%;
Step 102, pave one layer of permeable geotextiles 2, and lap width is not less than 200mm;
Step 103, pave coarse sand bed course 3, appropriate to sprinkle water and be sufficiently compacted leveling;
Step 104, production angle steel frame water-permeable brick are mated formation module 4, and 40 pieces of sand base water-permeable bricks 5 are divided into 4 column and are put into angle steel Frame water-permeable brick is mated formation in module 4;
Step 105 is mated formation in module 4 to coarse sand bed course 3 with suspension hook by 9 handling angle steel frame water-permeable brick of hook on hole, band Line adjustment is assembled and controls piece in 1mm;
The construction process step of step 2, angle steel frame module interior floor tile pavement system are as follows:
Step 201, production floor tile angle steel frame are mated formation module 10;
Step 202 meets the reinforcing bar of design strength and pours 60mm thickness in the setting in module 10 of mating formation of floor tile angle steel frame Concrete, concrete and floor tile angle steel frame are mated formation, and module 10 is suitable for reading concordant and to receive light smooth;
13 paving of 5-10mm thickness surface layer floor tile is formed indoor ground in concrete surface using 903 building adhesives by step 203 Brick;
The construction process step of step 3, the channel steel frame module light vehicle travel pavement system are as follows:
Step 301 cleans out sundries, the surface dust in rammed earth base 1, is tamped using rammer compacter to compacting Degree is not less than 93%;
Step 302, pave coarse sand bed course 3, appropriate to sprinkle water and be sufficiently compacted leveling;
Step 303, production channel steel frame are mated formation module 15;
Step 304 meets the reinforcing bar of design strength and pours 120mm thickness coagulation in the setting in module 15 of mating formation of channel steel frame Soil, concrete is suitable for reading concordant with channel steel and to receive light smooth.
The above is a preferred embodiment of the present invention, cannot limit the right model of the present invention with this certainly It encloses, it is noted that for those skilled in the art, without departing from the principle of the present invention, may be used also To make several improvement and variation, these, which improve and change, is also considered as protection scope of the present invention.

Claims (10)

1. a kind of interim ground installation, which is characterized in that including angle steel frame module water-permeable brick pavement system, angle steel frame mould The combination of block interior floor tile pavement system and angle steel frame module light vehicle travel pavement system, in which:
The angle steel frame module water-permeable brick pavement system includes the rammed earth base being arranged from bottom to top, 50mm thickness coarse sand The thick permeable surface layer of bed course and 65mm, the permeable surface layer include that angle steel frame water-permeable brick is mated formation module and sand base water-permeable brick;
Angle steel frame module interior floor tile pavement system includes the rammed earth base being arranged from bottom to top, 50mm thick thick The thick indoor tile paved surface of sand bedding course and 65-70mm, the interior tile paved surface include that 60mm thickness floor tile angle steel frame is mated formation mould Block and 5-10mm thickness surface layer floor tile, the floor tile angle steel frame, which is mated formation, pours the armored concrete of 60mm thickness in module;
The channel steel frame module light vehicle travel pavement system include the rammed earth base being arranged from bottom to top, 50mm thickness coarse sand bed course and 120mm thickness channel steel frame reinforced concrete pavement module supercrust, the channel steel frame reinforcing bar are mixed Solidifying soil module supercrust of mating formation includes that channel steel frame mats formation and module and mats formation in the channel steel frame and pour 120mm thickness in module Armored concrete.
2. interim ground installation according to claim 1, which is characterized in that the coarse sand bed course and the rammed earth base Permeable geotextiles are equipped between layer;The angle steel frame water-permeable brick mat formation block length be 1100mm, width 830mm, Bottom is provided with the first support bar of steel of 5mm thickness and middle part is provided with the isolating bar that 5mm thickness is used as isolation water-permeable brick.
3. interim ground installation according to claim 2, which is characterized in that first support bar is located at the angle steel side Frame water-permeable brick mat formation module frame at when, width 60mm;It is wide when first support bar and isolating bar intersect vertically Degree is 80mm.
4. interim ground installation according to claim 3, which is characterized in that the angle steel frame water-permeable brick is mated formation module Frame diagonal angle is welded with the triangular shape suspension hook plate of 3mm thickness, and the triangle suspension hook plate is the isosceles of right angle side length 115mm Right angled triangle is provided with the hook on hole that diameter is 15mm at centroid.
5. interim ground installation according to claim 4, which is characterized in that the size of the sand base water-permeable brick is 100mm × 200mm × 60mm, each angle steel frame water-permeable brick, which is mated formation, to be put 4 column, 10 row in module and amounts to 40 pieces of sand base water-permeable bricks.
6. interim ground installation according to claim 1, which is characterized in that the floor tile angle steel frame is mated formation four side of module There are the round hole for hoist that a diameter is 30mm, the centers of circle to be located in the middle part of angle steel for the every side in side;Each floor tile angle steel side Frame mats formation block length for 600 or 800 or 1000mm, and width is 600 or 800 or 1000mm.
7. interim ground installation according to claim 1, which is characterized in that the single channel steel frame is mated formation block length For 1500mm, width 1000mm, channel steel width is 120mm, with a thickness of 5mm.
8. interim ground installation according to claim 7, which is characterized in that the channel steel frame is mated formation the frame pair of module Sunpender is welded at angle, the sunpender and channel steel form the isosceles right triangle of the long 115mm of right-angle side, be provided at centroid The suspension hook slot of long 100mm, width 50mm, depth 60mm.
9. interim ground installation according to claim 7, which is characterized in that the channel steel frame is mated formation module inner concrete Pour can take first poured in advance in factory, after assembly uses at the construction field (site) or first lifting channel steel frame is mated formation mould at the scene Block, after casting concrete at the construction field (site).
10. a kind of interim ground installation integral construction method, which comprises the following steps:
The construction process step of S1, the angle steel frame module water-permeable brick pavement system are as follows:
S101, sundries, the surface dust in rammed earth base are cleaned out, is tamped using rammer compacter to compactness and is not less than 93%;
S102, pave one layer of permeable geotextiles, and lap width is not less than 200mm;
S103, pave coarse sand bed course, appropriate to sprinkle water and be sufficiently compacted leveling;
S104, production angle steel frame water-permeable brick are mated formation module, and 40 pieces of sand base water-permeable bricks are divided into 4 column and are put into angle steel frame water-permeable brick In module of mating formation;
S105, mated formation in module to coarse sand bed course with suspension hook by hook on hole handling angle steel frame water-permeable brick, band line adjustment is assembled And by piece control in 1mm;
The construction process step of S2, angle steel frame module interior floor tile pavement system are as follows:
S201, production floor tile angle steel frame are mated formation module;
S202, meet the reinforcing bar of design strength in the setting in module of mating formation of floor tile angle steel frame and pour 60mm thickness concrete, mix Solidifying soil and floor tile angle steel frame are mated formation, and module is suitable for reading concordant and to receive light smooth;
S203, the surface layer floor tile paving of 5-10mm thickness is formed into indoor floor tile in concrete surface using 903 building adhesives;
The construction process step of S3, the channel steel frame module light vehicle travel pavement system are as follows:
S301, sundries, the surface dust in rammed earth base are cleaned out, is tamped using rammer compacter to compactness and is not less than 93%;
S302, pave coarse sand bed course, appropriate to sprinkle water and be sufficiently compacted leveling;
S303, production channel steel frame are mated formation module;
S304, meet the reinforcing bar of design strength in the setting in module of mating formation of channel steel frame and pour 120mm thickness concrete, concrete It is suitable for reading concordant with channel steel and to receive light smooth.
CN201910193402.0A 2019-03-14 2019-03-14 Temporary ground facility and integrated construction method thereof Active CN109811613B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910193402.0A CN109811613B (en) 2019-03-14 2019-03-14 Temporary ground facility and integrated construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910193402.0A CN109811613B (en) 2019-03-14 2019-03-14 Temporary ground facility and integrated construction method thereof

Publications (2)

Publication Number Publication Date
CN109811613A true CN109811613A (en) 2019-05-28
CN109811613B CN109811613B (en) 2024-03-19

Family

ID=66608879

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910193402.0A Active CN109811613B (en) 2019-03-14 2019-03-14 Temporary ground facility and integrated construction method thereof

Country Status (1)

Country Link
CN (1) CN109811613B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110565488A (en) * 2019-08-31 2019-12-13 上海宝冶集团有限公司 Temporary road macadam paving method
CN111364309A (en) * 2020-03-16 2020-07-03 山西四建集团有限公司 Green construction process for roads on construction site

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100860850B1 (en) * 2008-06-30 2008-09-29 주식회사 누리플랜 Manufacturing method of plate type temporary paving
KR20110132662A (en) * 2010-06-03 2011-12-09 임선우 Asphalt concrete paving block
CN105484132A (en) * 2016-01-04 2016-04-13 上海市政工程设计研究总院(集团)有限公司 Novel construction method of permeable pavement paving
CN105603843A (en) * 2015-12-30 2016-05-25 中国建筑第二工程局有限公司 Assembled reinforced concrete prefabricated pavement slab and construction method thereof
CN209989660U (en) * 2019-03-14 2020-01-24 武汉建工集团股份有限公司 Interim ground facility

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100860850B1 (en) * 2008-06-30 2008-09-29 주식회사 누리플랜 Manufacturing method of plate type temporary paving
KR20110132662A (en) * 2010-06-03 2011-12-09 임선우 Asphalt concrete paving block
CN105603843A (en) * 2015-12-30 2016-05-25 中国建筑第二工程局有限公司 Assembled reinforced concrete prefabricated pavement slab and construction method thereof
CN105484132A (en) * 2016-01-04 2016-04-13 上海市政工程设计研究总院(集团)有限公司 Novel construction method of permeable pavement paving
CN209989660U (en) * 2019-03-14 2020-01-24 武汉建工集团股份有限公司 Interim ground facility

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110565488A (en) * 2019-08-31 2019-12-13 上海宝冶集团有限公司 Temporary road macadam paving method
CN111364309A (en) * 2020-03-16 2020-07-03 山西四建集团有限公司 Green construction process for roads on construction site

Also Published As

Publication number Publication date
CN109811613B (en) 2024-03-19

Similar Documents

Publication Publication Date Title
CN105421188B (en) The construction method of assembled temporary road
CN111676759A (en) Assembly type temporary construction road and construction method
CN202730579U (en) Recyclable prefabricated concrete block for hardening construction plant
CN104405123A (en) Mold subassembly for casting thin-wall rectangular small-section reinforced concrete hollow column in situ and construction method thereof
CN204000523U (en) The prefabricated road surface of a kind of Novel reinforced concrete
CN217150344U (en) Rubble concrete lays structure
CN109811613A (en) A kind of interim ground installation and its integral construction method
CN103334361B (en) Prefabricated hollow steel bar concrete wear resistant road surface plate and pavement construction method
CN204825557U (en) Job site interim construction road combination ground structure
CN206800106U (en) A kind of assembled roads plate
CN209989660U (en) Interim ground facility
CN101929245A (en) Thin webbed girder vertical construction method
CN109853803B (en) Assembled integral floor slab and manufacturing and installing method
CN204299179U (en) Cast-in-situ reinforced concrete thin-wall rectangular small bore open tubular column template assembly
CN217810304U (en) Multifunctional road construction prefabricated slab
CN216973019U (en) Prefabricated assembled temporary parking lot construction structure
CN115387393A (en) Post-cast strip pre-sealing quick construction method
CN105133630A (en) Prefabricated part for constructing foundation forming molds
CN210946354U (en) Temporary road with in-situ prefabricated reinforced concrete prefabricated slab
JPH0611980B2 (en) Construction method of revetment using natural stone
CN210657851U (en) Precast concrete pavement slab capable of being hoisted quickly
CN103334362B (en) Prefabricated steel concrete wear resistant road surface plate and pavement construction method
CN203373624U (en) Bridge prefabricated reinforced concrete hidden beam slab wearproof pavement system
CN203373635U (en) Prefabricated hollow reinforced concrete wearproof pavement slab
CN218147591U (en) Prefabricated sidewalk plate

Legal Events

Date Code Title Description