CN109800944A - A kind of Dispatcher Power Flow calculation method based on cloud computing - Google Patents

A kind of Dispatcher Power Flow calculation method based on cloud computing Download PDF

Info

Publication number
CN109800944A
CN109800944A CN201811517599.0A CN201811517599A CN109800944A CN 109800944 A CN109800944 A CN 109800944A CN 201811517599 A CN201811517599 A CN 201811517599A CN 109800944 A CN109800944 A CN 109800944A
Authority
CN
China
Prior art keywords
trend
user
flow calculation
resource
limit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811517599.0A
Other languages
Chinese (zh)
Other versions
CN109800944B (en
Inventor
杨科
张勇
宁剑
王毅
罗玉春
陆娟娟
闪鑫
彭龙
查国强
彭宗明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NARI Group Corp
North China Grid Co Ltd
Nari Technology Co Ltd
NARI Nanjing Control System Co Ltd
Original Assignee
NARI Group Corp
North China Grid Co Ltd
Nari Technology Co Ltd
NARI Nanjing Control System Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NARI Group Corp, North China Grid Co Ltd, Nari Technology Co Ltd, NARI Nanjing Control System Co Ltd filed Critical NARI Group Corp
Priority to CN201811517599.0A priority Critical patent/CN109800944B/en
Publication of CN109800944A publication Critical patent/CN109800944A/en
Application granted granted Critical
Publication of CN109800944B publication Critical patent/CN109800944B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The Dispatcher Power Flow calculation method based on cloud computing that the invention discloses a kind of, for traditional Dispatcher Power Flow, this method can be according to the computing resource of the automatic allocation schedule person's trend of user information, support multi-user operation and mutually unaffected, calculation of tidal current that can be different according to user information pushing;The information such as out-of-limit, the heavily loaded, transfer of trend that dispatcher pays close attention to are concentrated on a key frame in cloud terminal, inquiry, operation are integrated in same key frame, the operation of equipment, calculated result can be facilitated the functions such as to check when using Load flow calculation function, the application requirement of off-line calculation and the use habit of user are more in line in use habit, therefore perfect in shape and function of this method as Load flow calculation, has a good application prospect.

Description

A kind of Dispatcher Power Flow calculation method based on cloud computing
Technical field
The invention belongs to electric power system tide technical fields, and in particular to a kind of Dispatcher Power Flow calculating based on cloud computing Method.
Background technique
With the development of power industry, the continuous expansion of electrical network capacity.Interconnected power grid quickly forms;Large-sized unit, interconnection The appearance of bulk power grid, super-pressure long-distance transmission line, it is stringenter to the safe and stable of power grid, economical operation requirement, so as to In real time to Operation of Electric Systems carry out automatic data acquisition and monitoring control dispatch automated system (SCADA) meet the tendency of and It is raw.Correlation auxiliary advanced applied software also upgrades therewith.Wherein Dispatcher Power Flow is dispatcher using using in advanced applied software Most one kind and most basic one kind.Dispatcher can correctly use Dispatcher Power Flow function.It is right under its auxiliary Grid operating conditions are analyzed, make correctly judgement and decision so that necessary measure is taken to handle accident and different in time Reason condition.To guaranteeing power system security, economy, reliably run, meaning is very great.
Dispatcher Power Flow module is most basic network analysis tool, operation of the analysis system under the given method of operation State.It changes the method for operation, analyzes the trend distribution of current system by carrying out setting operation under certain method of operation With Load flow calculation characteristic, the calculated result of trend is analyzed, including various heavily loaded monitoring, limit value inspection, Losses Analysis etc..
Dispatcher Power Flow calculate be Power System Analysis basis, guarantee electric grid operating safety and stability, with And it prevents maloperation etc. and all plays a very important role.Existing tidal current computing method has been successfully applied to electric system energy It measures in 1st area of management system.But in IIIth area, the application for simulating trend operation for multi-user delays to be in full swing, a side Face generally requires to do many configurations on a workstation based on the exhibition method of C/S mode framework, and displaying is no simple and clear, separately On the one hand traditional regulator control system supports the resilient expansion of multi-user inadequate.With the further extension of power grid scale, tradition Trend show, method of adjustment efficiency it is too low, in order to which the automation application for improving Load flow calculation is horizontal, there is an urgent need to modern big By each business integration in the trend displaying of network system, realizes and easily dispose, is easy to operate, keynote message is very clear, thus generation For traditional trend methods of exhibiting.
Based on the above analysis, traditional trend displaying, method of adjustment have been unable to meet the needs of current development, need to be changed Into thus this case generates.
Summary of the invention
The purpose of the present invention is, operation not easy, multi-user operation phases inefficient for traditional trend methods of exhibiting The problem of mutually influencing, propose a kind of Dispatcher Power Flow calculation method based on cloud computing.The solution of the present invention is easy to dispose, and shows Mode is straightforward, while can support multi-user while operate and being mutually independent of each other, and has in practical power systems application Condition has a good application prospect.
To achieve the above object, the technical solution adopted by the present invention is that:
A kind of Dispatcher Power Flow calculation method based on cloud computing, includes the following steps,
Step (1), user log in trend homepage, form independent Load flow calculation resource;
Step (2) is embedded with the relevant information of region, plant stand and equipment in trend homepage, is used for user's quick search It with positioning to relevant region, plant stand and equipment, and easily carries out trend mode and adjusts operation, obtain Load flow calculation information;
Step (3) zone of responsibility according to belonging to user and is pushed out use according to out-of-limit rate in trend homepage from high to low Trend within the affiliated zone of responsibility in family is out-of-limit and transinformation;
Step (4), user get over limit information according to the trend of Load flow calculation and are directly viewable out-of-limit adjustable strategies;
Step (5), after trend is not used for a long time or clicks cancellation by user, system discharges the Load flow calculation resource.
Preferably, in step (1), the step of forming independent Load flow calculation resource, is further included steps of
For user before using Load flow calculation, the trend money of on-line operation can be set out in scheduling controlling plateform system Source;User's selection is directly entered Load flow calculation, system according to the non-load balanced case of already existing trend resource and system, Automatically start new trend resource in node and name the trend resource automatically, to guarantee between each user's trend operation not by shadow It rings.
Preferably, in step (1), the step of forming independent Load flow calculation resource, is further included steps of
User selects to create new trend resource, customized name new trend resource, with easy-to-look-up.
Preferably, in step (2), in trend homepage, user is quickly positioned to relevant region, plant stand and equipment and square Just the step of carry out trend mode adjusts operation further includes steps of
(2-1) is directly switch to relevant region, plant stand and equipment in Load flow calculation homepage, does not need to carry out more Secondary switching;
(2-2), user directly adjusts the power output and load in the region on corresponding region pel, alternatively, in administrative division map It is directly switch into the plant stand under the region in member, power output load adjustment, the route master of generator load is carried out in plant stand figure The trend operation that the stoppage in transit of change puts into operation, and carry out Load flow calculation.
Preferably, in step (3), in trend homepage the zone of responsibility according to belonging to user and according to out-of-limit rate from high to low The step of being pushed out the out-of-limit trend within the affiliated zone of responsibility of user and transinformation further includes steps of
After the completion of Load flow calculation, the zone of responsibility information that system is logged according to active user pushes away from high to low according to out-of-limit rate Send out out-of-limit and transfer the Power Flow Information in the user responsibility area.
Preferably, in step (4), user gets over limit information with the trend according to Load flow calculation and is directly viewable out-of-limit adjustable strategies The step of further include steps of
User clicks directly on according to the more limit information of current Load flow calculation and checks the best tune for eliminating the out-of-limit facility information Whole strategy, is rapidly performed by decision.
Preferably, in step (5), after trend is not used for a long time or clicks cancellation by user, system discharges the trend meter The step of calculating resource further includes steps of
Dispatching Control System will record the time of each trend asset creation, if user is more than using the time of trend resource Regulation trend resource longest time or user manually nullify this trend resource, and regulator control system will discharge this trend Resource.
Compared with prior art, it the beneficial effects of the present invention are: 1) technical solution of the present invention is realized based on B/S mode, is somebody's turn to do Method can realize that Power Flow Information browsing, trend mode adjusts and out-of-limit branch adjustable strategies on a homepage, and each It is a scheduling simultaneously operate do not influence respective as a result, simplifying the operating procedure of dispatcher, improve displaying efficiency;2) of the invention Realize that each user uses independent Load flow calculation resource based on cloud computing, trend resource and user, which realize, to be bound, and exhibition is improved Show efficiency;3) technical solution of the present invention is easy to dispose, and exhibition method is straightforward, while can support multi-user while operate And be mutually independent of each other, have the condition in practical power systems application, has a good application prospect.
Detailed description of the invention
Fig. 1 is the flow diagram of the method for the present invention.
Specific embodiment
Below in conjunction with the attached drawing in the present invention, technical solution of the present invention is clearly and completely described, it is clear that Described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Based on the implementation in the present invention Example, those of ordinary skill in the art's all other embodiment obtained under the conditions of not making creative work belong to The scope of protection of the invention.
As shown in Figure 1, the present invention provides a kind of Dispatcher Power Flow calculation method based on cloud computing, include the following steps,
Step (1), user log in trend homepage, form independent Load flow calculation resource.
Further, for user before using Load flow calculation, on-line operation can be set out in scheduling controlling plateform system Trend resource;User's selection is directly entered Load flow calculation, and system is equal according to the load of already existing trend resource and system Weigh situation, starts new trend resource automatically in node and names the trend resource automatically, to guarantee each user's trend operation Between it is unaffected.Alternatively, user can also be after logging in trend homepage, customized one new trend resource name, with It is easy-to-look-up.New trend resource is mutually indepedent with existing trend resource.
Step (2) is embedded with the relevant information of region, plant stand and equipment in trend homepage, is used for user's quick search It with positioning to relevant region, plant stand and equipment, and easily carries out trend mode and adjusts operation, obtain Load flow calculation information.
Further, it can be directly switch to region, plant stand and equipment in Load flow calculation homepage, do not need to carry out more Secondary switching.
On corresponding region pel, user can check the power output and load of current region, and user can on this basis The power output and load in the region are adjusted with the size of direct pull pel, and the area can also be directly switch into the pel of region In plant stand catalogue under domain, the stoppage in transit that the power output load adjustment, route main transformer of generator load are carried out in plant stand figure puts into operation Trend operation, and carry out Load flow calculation.
Step (3) zone of responsibility according to belonging to user and is pushed out use according to out-of-limit rate in trend homepage from high to low Trend within the affiliated zone of responsibility in family is out-of-limit and transinformation.After the completion of Load flow calculation, duty that system is logged according to active user Appoint area's information, out-of-limit and transfer the Power Flow Information being pushed out from high to low in the user responsibility area according to out-of-limit rate.Here Out-of-limit rate refers to the out-of-limit severity of trend.
Step (4), user get over limit information according to the trend of Load flow calculation and are directly viewable out-of-limit adjustable strategies.User according to The more limit information of current Load flow calculation clicks directly on the optimum apjustment strategy checked and eliminate the out-of-limit facility information, is rapidly performed by Decision.
Step (5), after trend is not used for a long time or clicks cancellation by user, system discharges the Load flow calculation resource.It adjusts Degree control system will record the time of each trend asset creation, if user is more than that regulation trend provides using the time of trend resource Source longest time or user manually nullify this trend resource, and regulator control system will discharge this trend resource.
The present invention carries out the information of Load flow calculation acquisition after adjusting according to trend mode, directly list whole in homepage The trend in region is out-of-limit and power flow transfer information, the trend of user's affiliated area get over clicked on limit information can check it is out-of-limit Adjustable strategies need to switch in layer page lookup, effectively raise dispatching efficiency compared with traditional trend.
The present invention provides a kind of Dispatcher Power Flow calculation method based on cloud computing, should for traditional Dispatcher Power Flow Method can support multi-user operation and mutually not by shadow according to the computing resource of the automatic allocation schedule person's trend of user information It rings, calculation of tidal current that can be different according to user information pushing;It is out-of-limit, again in trend that cloud terminal pays close attention to dispatcher The information such as load, transfer concentrate on a key frame, and inquiry, operation are integrated in same key frame, are using Load flow calculation The operation of equipment, calculated result can be facilitated the functions such as to check when function, off-line calculation is more in line in use habit The use habit of application requirement and user, therefore perfect in shape and function of this method as Load flow calculation, have a good application prospect.
Basic principles and main features and advantage of the invention have been shown and described above.The technical staff of the industry should Understand, the present invention is not limited to the above embodiments, and the above embodiments and description only describe originals of the invention Reason, without departing from the spirit and scope of the present invention, various changes and improvements may be made to the invention, these changes and improvements It all fall within the protetion scope of the claimed invention.The claimed scope of the invention is by appended claims and its equivalent circle It is fixed.

Claims (7)

1. a kind of Dispatcher Power Flow calculation method based on cloud computing, which is characterized in that include the following steps,
Step (1), user log in trend homepage, form independent Load flow calculation resource;
Step (2) is embedded with the relevant information of region, plant stand and equipment in trend homepage, for user's quick search and fixed Position easily carries out trend mode and adjusts operation to relevant region, plant stand and equipment, obtains Load flow calculation information;
Step (3) zone of responsibility according to belonging to user and is pushed out user institute according to out-of-limit rate in trend homepage from high to low Belong within zone of responsibility trend is out-of-limit and transinformation;
Step (4), user get over limit information according to the trend of Load flow calculation and are directly viewable out-of-limit adjustable strategies;
Step (5), after trend is not used for a long time or clicks cancellation by user, system discharges the Load flow calculation resource.
2. a kind of Dispatcher Power Flow calculation method based on cloud computing according to claim 1, which is characterized in that step (1) in, the step of forming independent Load flow calculation resource, is further included steps of
For user before using Load flow calculation, the trend resource of on-line operation can be set out in scheduling controlling plateform system;With Family selection is directly entered Load flow calculation, and system is according to the non-load balanced case of already existing trend resource and system, in node In start new trend resource automatically and name the trend resource automatically, it is unaffected between each user's trend operation to guarantee.
3. a kind of Dispatcher Power Flow calculation method based on cloud computing according to claim 1, which is characterized in that step (1) in, the step of forming independent Load flow calculation resource, is further included steps of
User selects to create new trend resource, customized name new trend resource, with easy-to-look-up.
4. a kind of Dispatcher Power Flow calculation method based on cloud computing according to claim 1, which is characterized in that step (2) in, in trend homepage, user quickly positions to relevant region, plant stand and equipment and easily carries out trend mode tune The step of whole operation, further includes steps of
(2-1) is directly switch to relevant region, plant stand and equipment in Load flow calculation homepage, does not need repeatedly to be cut It changes;
(2-2), user directly adjusts the power output and load in the region on corresponding region pel, alternatively, in the pel of region It is directly switch into the plant stand under the region, power output load adjustment, the route main transformer of generator load is carried out in plant stand figure The trend to put into operation of stopping transport operates, and carries out Load flow calculation.
5. a kind of Dispatcher Power Flow calculation method based on cloud computing according to claim 1, which is characterized in that step (3) zone of responsibility according to belonging to user and it is pushed out the affiliated responsibility of user from high to low according to out-of-limit rate in, in trend homepage The step of trend within area is out-of-limit and transinformation further includes steps of
After the completion of Load flow calculation, the zone of responsibility information that system is logged according to active user is pushed out from high to low according to out-of-limit rate Out-of-limit and transfer Power Flow Information in the user responsibility area.
6. a kind of Dispatcher Power Flow calculation method based on cloud computing according to claim 1, which is characterized in that step (4) in, user with the trend according to Load flow calculation get over the step of limit information is directly viewable out-of-limit adjustable strategies further comprise with Lower step:
User clicks directly on according to the more limit information of current Load flow calculation and checks the optimum apjustment plan for eliminating the out-of-limit facility information Slightly, it is rapidly performed by decision.
7. a kind of Dispatcher Power Flow calculation method based on cloud computing according to claim 1, which is characterized in that step (5) in, after trend is not used for a long time or clicks and nullifies by user, the step of system discharges the Load flow calculation resource, is further wrapped Include following steps:
Dispatching Control System will record the time of each trend asset creation, if user is more than regulation using the time of trend resource Trend resource longest time or user manually nullify this trend resource, and regulator control system will discharge this trend resource.
CN201811517599.0A 2018-12-12 2018-12-12 Dispatcher load flow calculation method based on cloud calculation Active CN109800944B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811517599.0A CN109800944B (en) 2018-12-12 2018-12-12 Dispatcher load flow calculation method based on cloud calculation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811517599.0A CN109800944B (en) 2018-12-12 2018-12-12 Dispatcher load flow calculation method based on cloud calculation

Publications (2)

Publication Number Publication Date
CN109800944A true CN109800944A (en) 2019-05-24
CN109800944B CN109800944B (en) 2022-09-02

Family

ID=66556629

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811517599.0A Active CN109800944B (en) 2018-12-12 2018-12-12 Dispatcher load flow calculation method based on cloud calculation

Country Status (1)

Country Link
CN (1) CN109800944B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113703649A (en) * 2021-08-12 2021-11-26 深圳供电局有限公司 Method and tool for adjusting tidal current output and load of simulation power grid

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103530813A (en) * 2013-09-30 2014-01-22 广东电网公司佛山供电局 Method and system for automatically evaluating dispatcher load flow calculation precision in real time
CN104836329A (en) * 2015-04-14 2015-08-12 国网上海市电力公司 Local-level dispatch supporting system capable of improving analyzing and processing capability of dispatcher during accident generation
CN104835077A (en) * 2015-04-14 2015-08-12 国网上海市电力公司 Static safety analysis system with dispatcher accident prediction supporting function
CN104835078A (en) * 2015-04-14 2015-08-12 国网上海市电力公司 Power flow determining method in static safety analysis system in view of operation of automatic switching device of standby power supply
CN104835376A (en) * 2015-04-14 2015-08-12 国网上海市电力公司 Dispatcher training simulation system with automatic switching device of standby power supply automatic safety device operation simulating function
CN106385034A (en) * 2016-11-02 2017-02-08 国电南瑞科技股份有限公司 Power grid dynamic partition calculating method based on N-1 security checking

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103530813A (en) * 2013-09-30 2014-01-22 广东电网公司佛山供电局 Method and system for automatically evaluating dispatcher load flow calculation precision in real time
CN104836329A (en) * 2015-04-14 2015-08-12 国网上海市电力公司 Local-level dispatch supporting system capable of improving analyzing and processing capability of dispatcher during accident generation
CN104835077A (en) * 2015-04-14 2015-08-12 国网上海市电力公司 Static safety analysis system with dispatcher accident prediction supporting function
CN104835078A (en) * 2015-04-14 2015-08-12 国网上海市电力公司 Power flow determining method in static safety analysis system in view of operation of automatic switching device of standby power supply
CN104835376A (en) * 2015-04-14 2015-08-12 国网上海市电力公司 Dispatcher training simulation system with automatic switching device of standby power supply automatic safety device operation simulating function
CN106385034A (en) * 2016-11-02 2017-02-08 国电南瑞科技股份有限公司 Power grid dynamic partition calculating method based on N-1 security checking

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113703649A (en) * 2021-08-12 2021-11-26 深圳供电局有限公司 Method and tool for adjusting tidal current output and load of simulation power grid

Also Published As

Publication number Publication date
CN109800944B (en) 2022-09-02

Similar Documents

Publication Publication Date Title
Bebic Power system planning: emerging practices suitable for evaluating the impact of high-penetration photovoltaics
Speer et al. Role of smart grids in integrating renewable energy
CN105427039A (en) Efficient processing method of distribution network repair work orders based on responsibility areas
CN109327323B (en) New energy grid-connected power communication network planning and optimizing method and system
CN102593829A (en) Method and device for determining transmission section in consideration of key branch circuit
CN102495850A (en) Method for splicing multi-stage multi-region interconnected power grid relay protection model
Lyon et al. Market implications and pricing of dynamic reserve policies for systems with renewables
CN103297505A (en) Multi-energy online control method and system for data center under dynamic cloud service request
CN105429297A (en) Multi-operation mode controlling and switching method for micro-grid
Antoniadou-Plytaria et al. Chalmers campus as a testbed for intelligent grids and local energy systems
Hao et al. Locational marginal pricing in the campus power system at the power distribution level
CN110046790A (en) A kind of low-voltage platform area receiving distributed photovoltaic power generation merit rating method
CN107133870B (en) Electric power spot transaction security check method based on 30-second period static analysis
Layden et al. Integrating security constraints in optimal power flow studies
CN104268668A (en) Low-carbon optimized dispatching method for closed loop
Nawaz et al. Risk-aware distributed optimal power flow in coordinated transmission and distribution system
CN109586272A (en) A kind of generation method and system of power grid continuous operation emulation section
Yang et al. Distribution locational marginal pricing based equilibrium optimization strategy for data center park with spatial-temporal demand-side resources
CN109800944A (en) A kind of Dispatcher Power Flow calculation method based on cloud computing
Taft et al. A reference model for distribution grid control in the 21st century
CN106651136B (en) Day-ahead power generation plan compiling method and device for bilateral transaction
Romero Dynamic power system load-estimation of parameters from operational data
CN106451565B (en) A kind of power plant's optimization submitting on-line analysis based on perturbation theory
CN107332232B (en) A kind of preferred method of the homochronousness phase modifier of large size city power grid
CN102789603B (en) A kind ofly take into account the provincial scheduling active power adjustment method that load draws road model

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant