CN109797659A - 一种波形钢腹板连续梁桥移动支架异步施工方法 - Google Patents
一种波形钢腹板连续梁桥移动支架异步施工方法 Download PDFInfo
- Publication number
- CN109797659A CN109797659A CN201910215931.6A CN201910215931A CN109797659A CN 109797659 A CN109797659 A CN 109797659A CN 201910215931 A CN201910215931 A CN 201910215931A CN 109797659 A CN109797659 A CN 109797659A
- Authority
- CN
- China
- Prior art keywords
- bracket
- construction
- segment
- wavelike steel
- steel webplate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种波形钢腹板连续梁桥移动支架异步施工方法,该方法包括三个过程:0#块施工、典型节段施工和合龙段施工,三个过程依次进行。所述典型节段施工包括三个工作面,即第n‑1节段顶板混凝土施工、第n节段底板混凝土施工和第n+1节段波形钢腹板施工,此外,还可以进行第n‑2节段的支架拆除和第n+1节段的支架搭设。本发明的优点:将传统支架施工的一个工作面扩大到三个,在第n节段混凝土等强期间安装第n‑1节段的波形钢腹板,同时通过拆除已完成节段支架,循环利用支架,能够有效地缩短工期、降低成本,施工的技术难度较小,工程质量和安全也能够得到满足。
Description
技术领域
本发明涉及一种波形钢腹板连续梁桥移动支架异步施工方法,属于建筑工程技术领域。
背景技术
波形钢腹板预应力混凝土箱梁是一种新型的钢—混凝土组合结构,其重要特点是:利用波形钢板作为腹板;采用体内外预应力相结合的预应力体系;混凝土和钢腹板之间设置抗剪、抗拉拔的连接件。正是由于在结构上的这种改良,使其具备很多优良的性能。与传统的预应力混凝土桥梁相比,这种结构在减轻自重、降低造价、缩短工期、提高结构效率等方面有着很好地表现,同时避免了混凝土腹板开裂问题,波形钢腹板的褶皱效应也提高了预应力效率,近年来在国内外受到广泛关注。
当前,波形钢腹板预应力混凝土箱梁桥常用的传统施工方法主要有满堂支架现浇、挂篮悬浇、顶推等施工工艺。尽管挂篮悬浇法使用较为普遍,但是在施工条件允许的情况下,有针对性地采用支架现浇法施工也能带来便利性和经济性的双重收益。然而,传统的满堂支架施工,对于支架的需求量大,一次性占用施工场地大,施工效率不足。近年来,逐渐发展应用的移动支架逐段现浇技术也只是把施工工作面局限在一个断面上,没有充分发挥波形钢腹板预应力混凝土箱梁的独特优势,钢腹板的安装需要单独占用一定的施工时间,且同一节段的顶底板施工也会相会干扰,从而使得整个节段的施工周期大大延长。
发明内容
技术问题:本发明要解决的技术问题,在于提供一种波形钢腹板连续梁桥移动支架异步施工方法,既保留了移动支架法节约支架的特点,又可扩大原有的单一工作面,使得工期缩短,施工效率大大提高。
技术方案:本发明的波形钢腹板连续梁桥移动支架异步施工方法通过下述方案实现:
本发明的波形钢腹板连续梁桥移动支架异步施工方法包括三个过程:0#块施工、典型节段施工和合龙段施工,三个过程依次进行。所述典型节段施工包括三个工作面,即第n-1节段顶板混凝土施工、第n节段底板混凝土施工和第n+1节段波形钢腹板施工,此外,还可以进行第n-2节段的支架拆除和第n+1节段的支架搭设,实现支架的循环利用。
所述典型节段施工包括以下步骤:
步骤一:在支架上进行第n节段底板和第n-1节段顶板的立模,绑扎钢筋,安装预应力管道,浇筑顶底板混凝土;
步骤二:混凝土养生,第n+1节段波形钢腹板的吊装;
步骤三:混凝土强度满足要求后,第n-1节段的预应力束进行张拉,孔道压浆;
步骤四:第n-2节段支架进行拆除,第n+1节段支架进行搭设,并按要求进行堆载预压。
波形钢腹板的吊装,提前到第n节段混凝土浇筑之后,与第n节段混凝土养生共用同一施工周期。
波形钢腹板的吊装,应通过空间坐标进行精确定位,并通过普通螺栓进行临时固定,然后进行焊接,波形钢腹板之间采用圆钢竖向剪刀撑和12#槽钢上下水平剪刀撑进行横向临时连接。
第n-2节段支架进行拆除,第n+1节段支架进行搭设,实现了支架的循环利用。
所述0#块施工步骤为: 绑扎钢筋,安装波纹管,
所述合龙段施工步骤为: 绑扎钢筋, 边拆除合龙段支架,边撤除悬臂端配重。
合龙段施工采用先边跨、再中跨的顺序进行,边跨合龙后,拆除墩梁临时固结,体系由超静定结构转变为静定结构,中跨合龙后体系由静定结构转变为超静定结构。
焊接劲性骨架前,对于T构的悬臂端应松动支架,然后根据合龙段重量,合理地在悬臂端设置配重。
合龙段施工完成,边拆除合龙段支架,边撤除悬臂端配重,保证悬臂端在施工过程中受力保持不变。
有益效果:本发明的有益效果在于:这种波形钢腹板连续梁桥移动支架异步施工方法能够充分利用这种结构类型桥梁的自身特点,把波形钢腹板、混凝土顶板以及混凝土底板的施工区分开来,互不干扰,将传统施工中的一个工作平面扩大到三个,从而大幅度缩短工期。该方法中,混凝土在支架上浇筑、养生,外伸波形钢腹板采用横向临时连接,结构的稳定性强,减少了施工过程中薄弱位置的出现。该方法采用移动支架施工,支架材料用量小,周转率高。因此,这种波形钢腹板连续梁桥移动支架异步施工方法具有操作简单、实用高效、线形可控、质量可靠和安全系数高等优点,能够加快桥梁施工进度,降低施工造价,有效地保证了施工的安全和质量。
附图说明
为了使本发明的目的、技术方案和有益效果更加清楚,本发明提供如下附图进行说明:
图1为本发明典型节段施工工艺流程图;
图2为本发明典型节段施工工艺示意图;
图3为本发明合龙段施工工艺流程图。
附图标记:桥墩1,支座2,墩梁临时固结3,0#块4,第n-2节段5,第n-1节段顶板混凝土6,第n节段底板混凝土7,第n+1节段波形钢腹板8,第n-2节段支架9,第n-1节段支架10,第n节段支架11。
具体实施方式
以下结合附图1-3对本发明做进一步说明。
本发明的波形钢腹板连续梁桥移动支架异步施工方法包括三个过程:0#块施工、典型节段施工和合龙段施工,三个过程依次进行。典型节段施工包括三个工作面,即第n-1节段顶板混凝土施工、第n节段底板混凝土施工和第n+1节段波形钢腹板施工,此外,还可以进行第n-2节段的支架拆除和第n+1节段的支架搭设,实现支架的循环利用。
典型节段施工包括以下步骤:
步骤一:在支架上进行第n节段底板和第n-1节段顶板的立模,绑扎钢筋,安装预应力管道,浇筑顶底板混凝土;
步骤二:混凝土养生,第n+1节段波形钢腹板的吊装;
步骤三:混凝土强度满足要求后,第n-1节段的预应力束进行张拉,孔道压浆;
步骤四:第n-2节段支架进行拆除,第n+1节段支架进行搭设,并按要求进行堆载预压。
第n+1节段波形钢腹板的吊装,提前到第n节段混凝土浇筑之后,与第n节段混凝土养生共用同一施工周期。
波形钢腹板的吊装,通过空间坐标进行精确定位,并通过普通螺栓进行临时固定,然后进行焊接,波形钢腹板之间采用圆钢竖向剪刀撑和12#槽钢上下水平剪刀撑进行横向临时连接。
第n-2节段支架进行拆除,第n+1节段支架进行搭设,实现了支架的循环利用。
0#块施工步骤为: 绑扎钢筋,安装波纹管,
合龙段施工步骤为: 绑扎钢筋, 边拆除合龙段支架,边撤除悬臂端配重。
合龙段施工采用先边跨、再中跨的顺序进行,边跨合龙后,拆除墩梁临时固结,体系由超静定结构转变为静定结构,中跨合龙后体系由静定结构转变为超静定结构。
焊接劲性骨架前,对于T构的悬臂端应松动支架,然后根据合龙段重量,合理地在悬臂端设置配重。
合龙段施工完成,边拆除合龙段支架,边撤除悬臂端配重,保证悬臂端在施工过程中受力保持不变。
最后需要说明的是,以上所述实施方式仅用于说明本发明的技术方案而非限制,尽管通过上述实施方式已经对本发明进行了详细的描述,但本领域技术人员应当理解,可以在形式上和细节上对其作出各种各样的改变,而不偏离本发明权利要求书所限定的范围。
Claims (10)
1.一种波形钢腹板连续梁桥移动支架异步施工方法,其特征在于:该方法包括三个过程:0#块施工、典型节段施工和合龙段施工,三个过程依次进行;所述典型节段施工包括三个工作面,即第n-1节段顶板混凝土施工、第n节段底板混凝土施工和第n+1节段波形钢腹板施工,此外,还可以进行第n-2节段的支架拆除和第n+1节段的支架搭设,实现支架的循环利用。
2.根据权利要求1所述的一种波形钢腹板连续梁桥移动支架异步施工方法,其特征在于:所述典型节段施工包括以下步骤:
步骤一:在支架上进行第n节段底板和第n-1节段顶板的立模,绑扎钢筋,安装预应力管道,浇筑顶底板混凝土;
步骤二:混凝土养生,第n+1节段波形钢腹板的吊装;
步骤三:混凝土强度满足要求后,第n-1节段的预应力束进行张拉,孔道压浆;
步骤四:第n-2节段支架进行拆除,第n+1节段支架进行搭设,并按要求进行堆载预压。
3.根据权利要求2所述的一种波形钢腹板连续梁桥移动支架异步施工方法,其特征在于:所述波形钢腹板的吊装,提前到第n节段混凝土浇筑之后,与第n节段混凝土养生共用同一施工周期。
4.根据权利要求2所述的一种波形钢腹板连续梁桥移动支架异步施工方法,其特征在于:所述波形钢腹板的吊装,应通过空间坐标进行精确定位,并通过普通螺栓进行临时固定,然后进行焊接,波形钢腹板之间采用圆钢竖向剪刀撑和12#槽钢上下水平剪刀撑进行横向临时连接。
5.根据权利要求2所述的一种波形钢腹板连续梁桥移动支架异步施工方法,其特征在于:所述第n-2节段支架进行拆除,第n+1节段支架进行搭设,实现支架的循环利用。
6.根据权利要求1所述的一种波形钢腹板连续梁桥移动支架异步施工方法,其特征在于:所述0#块施工步骤为: 绑扎钢筋,安装波纹管, 进行相应的纵、横、
7.根据权利要求1所述的一种波形钢腹板连续梁桥移动支架异步施工方法,其特征在于:所述合龙段施工步骤为: 绑扎钢筋, 边拆除合龙段支架,边撤除悬臂端配重。
8.根据权利要求7所述的一种波形钢腹板连续梁桥移动支架异步施工方法,其特征在于:所述合龙段施工采用先边跨、再中跨的顺序进行,边跨合龙后,拆除墩梁临时固结,体系由超静定结构转变为静定结构,中跨合龙后体系由静定结构转变为超静定结构。
9.根据权利要求7所述的一种波形钢腹板连续梁桥移动支架异步施工方法,其特征在于:所述焊接劲性骨架,在此之前对于T构的悬臂端应松动支架,然后根据合龙段重量,合理地在悬臂端设置配重。
10.根据权利要求7所述的一种波形钢腹板连续梁桥移动支架异步施工方法,其特征在于:所述合龙段施工完成,边拆除合龙段支架,边撤除悬臂端配重,保证悬臂端在施工过程中受力保持不变。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910215931.6A CN109797659A (zh) | 2019-03-21 | 2019-03-21 | 一种波形钢腹板连续梁桥移动支架异步施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910215931.6A CN109797659A (zh) | 2019-03-21 | 2019-03-21 | 一种波形钢腹板连续梁桥移动支架异步施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109797659A true CN109797659A (zh) | 2019-05-24 |
Family
ID=66563719
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910215931.6A Pending CN109797659A (zh) | 2019-03-21 | 2019-03-21 | 一种波形钢腹板连续梁桥移动支架异步施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109797659A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111119072A (zh) * | 2020-02-13 | 2020-05-08 | 中铁二十三局集团有限公司 | 一种山区高墩桥梁台阶错位施工方法 |
CN111119071A (zh) * | 2020-01-16 | 2020-05-08 | 中建七局安装工程有限公司 | 混凝土预制节段箱梁拼装施工方法 |
CN111893884A (zh) * | 2020-07-06 | 2020-11-06 | 湖北工业大学 | 一种全预制拼装施工波形钢腹板桥异步施工方法 |
CN112342916A (zh) * | 2020-10-15 | 2021-02-09 | 中交二公局第三工程有限公司 | 波形钢腹板预应力混凝土组合桥梁合拢段同步施工方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003313811A (ja) * | 2002-04-26 | 2003-11-06 | Ps Mitsubishi Construction Co Ltd | 波形鋼板ウエブを備えた桁の応力緩和方法 |
CN102154992A (zh) * | 2011-04-28 | 2011-08-17 | 中交第二公路工程局有限公司 | 波形钢腹板错位安装方法 |
CN103422437A (zh) * | 2013-07-18 | 2013-12-04 | 杭州博数土木工程技术有限公司 | 波形钢腹板桥梁台阶式施工工艺 |
CN205062678U (zh) * | 2015-10-09 | 2016-03-02 | 中交第二航务工程局有限公司 | 应用于波形钢腹板结构的箱梁的施工挂篮 |
CN108914785A (zh) * | 2018-09-26 | 2018-11-30 | 中铁四局集团有限公司 | 一种多室波形钢腹板连续梁桥的挂篮悬臂浇筑施工工法 |
CN109098100A (zh) * | 2018-09-26 | 2018-12-28 | 中铁四局集团有限公司 | 波形钢腹板连续梁桥悬臂浇筑中的腹板超前安装施工工法 |
-
2019
- 2019-03-21 CN CN201910215931.6A patent/CN109797659A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003313811A (ja) * | 2002-04-26 | 2003-11-06 | Ps Mitsubishi Construction Co Ltd | 波形鋼板ウエブを備えた桁の応力緩和方法 |
CN102154992A (zh) * | 2011-04-28 | 2011-08-17 | 中交第二公路工程局有限公司 | 波形钢腹板错位安装方法 |
CN103422437A (zh) * | 2013-07-18 | 2013-12-04 | 杭州博数土木工程技术有限公司 | 波形钢腹板桥梁台阶式施工工艺 |
CN205062678U (zh) * | 2015-10-09 | 2016-03-02 | 中交第二航务工程局有限公司 | 应用于波形钢腹板结构的箱梁的施工挂篮 |
CN108914785A (zh) * | 2018-09-26 | 2018-11-30 | 中铁四局集团有限公司 | 一种多室波形钢腹板连续梁桥的挂篮悬臂浇筑施工工法 |
CN109098100A (zh) * | 2018-09-26 | 2018-12-28 | 中铁四局集团有限公司 | 波形钢腹板连续梁桥悬臂浇筑中的腹板超前安装施工工法 |
Non-Patent Citations (2)
Title |
---|
原创力文档: "挂篮合龙段施工工艺应用", 《HTTPS://MAX.BOOK118.COM/HTML/2017/1210/143558568.SHTM》 * |
豆丁建筑: "大跨度连续梁桥加长节段支架法施工关键技术", 《HTTP://JZ.DOCIN.COM/P-1504634910.HTML》 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111119071A (zh) * | 2020-01-16 | 2020-05-08 | 中建七局安装工程有限公司 | 混凝土预制节段箱梁拼装施工方法 |
CN111119072A (zh) * | 2020-02-13 | 2020-05-08 | 中铁二十三局集团有限公司 | 一种山区高墩桥梁台阶错位施工方法 |
CN111893884A (zh) * | 2020-07-06 | 2020-11-06 | 湖北工业大学 | 一种全预制拼装施工波形钢腹板桥异步施工方法 |
CN112342916A (zh) * | 2020-10-15 | 2021-02-09 | 中交二公局第三工程有限公司 | 波形钢腹板预应力混凝土组合桥梁合拢段同步施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109797659A (zh) | 一种波形钢腹板连续梁桥移动支架异步施工方法 | |
CN106677049B (zh) | 装配式钢-混凝土组合结构桥梁及施工方法 | |
CN101994293B (zh) | 一种高墩盖梁施工方法 | |
CN208151833U (zh) | 一种新型rc—砌体组合拱桥的构造 | |
CN208415270U (zh) | 一种深基坑装配式可回收钢支撑结构 | |
CN103147385B (zh) | 双拼式矮塔斜拉桥 | |
CN102154992A (zh) | 波形钢腹板错位安装方法 | |
CN104831639B (zh) | 一种超宽变截面连续梁0#块固结及解除施工方法 | |
CN106049289A (zh) | 贝雷梁临时便桥改造为钢混组合永久桥的施工方法 | |
CN205421019U (zh) | 一种预张拉钢混叠合梁桥面板 | |
CN107090908A (zh) | 一种新型竖向预制构件节点连接方法 | |
CN105781142A (zh) | 用于建筑结构顶层抽柱的加固结构及加固方法 | |
CN210395128U (zh) | 一种桥梁加宽中空心板梁连接结构 | |
CN205531016U (zh) | 一种预制混凝土柱构件及连接节点 | |
CN110130233A (zh) | 一种适用于双曲拱桥拱上建筑的改造方法 | |
CN206769199U (zh) | 后穿式后张法竖向预应力现浇混凝土柱结构 | |
CN109469242A (zh) | 一种压型钢板-再生混凝土组合楼板及其施工方法 | |
CN103205930B (zh) | 一种既有简支空心板梁桥连续化改造的结构及其施工方法 | |
CN204780635U (zh) | 一种超宽变截面连续梁0#块固结及解除施工结构 | |
CN215052265U (zh) | 钢筋混凝土薄壁墙身加固结构 | |
CN107100322A (zh) | 后张法竖向预应力现浇混凝土柱结构及施工方法 | |
CN104032741B (zh) | 一种水利工程大体积温控的快速施工方法 | |
CN102936953A (zh) | “大”字型劲钢结构模板施工方法 | |
CN208472958U (zh) | 一种部分预制装配式型钢混凝土巨型框架结构 | |
CN102092642B (zh) | 筒体混合结构群塔附臂、顶升装置及其施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |