CN109787092A - Modularization power distribution station for data center - Google Patents
Modularization power distribution station for data center Download PDFInfo
- Publication number
- CN109787092A CN109787092A CN201910141965.5A CN201910141965A CN109787092A CN 109787092 A CN109787092 A CN 109787092A CN 201910141965 A CN201910141965 A CN 201910141965A CN 109787092 A CN109787092 A CN 109787092A
- Authority
- CN
- China
- Prior art keywords
- power distribution
- distribution station
- subframe
- connector
- station according
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P80/00—Climate change mitigation technologies for sector-wide applications
- Y02P80/10—Efficient use of energy, e.g. using compressed air or pressurized fluid as energy carrier
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Abstract
This application discloses a kind of modularization power distribution stations for data center.The power distribution station includes: fixed frame, the fixed frame includes: one or more subframe customized in advance in factory, with the electrical equipment and its auxiliary auxiliary facility being arranged in the subframe, it is provided with the first connector and the second connector on the subframe, is connected between the subframe by first connector;The subframe is connected by second connector with concrete room.Present application addresses due to electromechanical installation amount live during Constructing data center it is big, caused by low efficiency, technical problem long in time limit.
Description
Technical field
This application involves data center fields, in particular to a kind of modularization power distribution station for data center.
Background technique
By development over several years, Mechatronic Systems overall architecture, design scheme gradually standardize data center's industry.
The service object of data center is extensive, and different industries client has different want to the Mechatronic Systems of data center
It asks.Compatibility delivers speed as the focal point of current line in the industry.Electro-mechanical parts are the core of the mating auxiliary equipment of data center
Center portion point, compatibility deliver speed for two big focal points.
Under normal conditions, data center's electro-mechanical parts are installed again after completion is built in civil engineering part, the duration
Longer, this is just needed through prefabricated modularization power distribution station, and by data center's distribution section, integrated, commercialization, is adapted to not
Same scene, client, and by prefabricated mode, maximum electromechanical installation section will be influenced on data center's construction speed in work
Factory is prefabricated, parallel with the civil construction at scene, achievees the purpose that shorten the construction period.
It is big for electromechanical installation amount live during Constructing data center in the related technology, caused by low efficiency, work
The technical problem of phase length, currently no effective solution has been proposed.
Summary of the invention
The main purpose of the application is to provide a kind of modularization power distribution station for data center, to solve process of construction
Middle scene electromechanical installation amount is big, caused by low efficiency, technical problem long in time limit,.
To achieve the goals above, according to the one aspect of the application, a kind of modularization for data center is provided
Power distribution station.
It include: fixed frame according to the modularization power distribution station for data center of the application, the fixed frame includes:
One or more is on the preparatory customized subframe of factory, and the electrical equipment being arranged in the subframe, the subframe
It is provided with the first connector and the second connector, is connected between the subframe by first connector;The subframe
It is connected by second connector with concrete room.
Further, the electrical equipment includes: low-voltage distribution apparatus, no-break power unit or close-coupled UPS equipment
And its auxiliary auxiliary facility.
Further, the length of multiple subframes is identical with height, of different size.
Further, the length and width of multiple subframes is identical, and height is different.
Further, the width of multiple subframes is identical with height, and length is different.
Further, first connector include: form the subframe Vierendeel girder or frame column it is outwardly extending
Outwardly extending portion.
Further, the outwardly extending portion is located at top side and bottom side, and/or is located at left and right side, and/or before being located at
Side and rear side.
Further, terrace is arranged in the bottom of the subframe.
Further, the close-coupled UPS equipment includes: incoming line cabinet, transformer, bus connection switch, compensation circuit, UPS function
Rate module, input and output cabinet, maintenance bypass and feeder cabinet.
Further, the subframe further include: detachable rod piece.
In the embodiment of the present application, using modular mode, electrical equipment is arranged by subframe, passes through the first connection
Part splices multiple subframes and forms power distribution station, and the power distribution station of formation is spliced to the concrete room of civil engineering by the second connector
In, reach prefabricated power distribution station, and be fixed to the purpose in concrete room, assembly is simple, assembly efficiency is high, contracting to realize
The technical effect of casual labourer's phase, and then solve during Constructing data center that live electromechanical installation amount is big, caused by efficiency
Technical problem low, long in time limit.
Detailed description of the invention
The attached drawing constituted part of this application is used to provide further understanding of the present application, so that the application's is other
Feature, objects and advantages become more apparent upon.The illustrative examples attached drawing and its explanation of the application is for explaining the application, not
Constitute the improper restriction to the application.In the accompanying drawings:
Fig. 1 is one of the modularization power distribution station structural schematic diagram according to the embodiment of the present application;
Fig. 2 is the modularization power distribution station second structural representation according to the embodiment of the present application;
Fig. 3 is the sub-frame structures schematic diagram according to the embodiment of the present application;
Fig. 4 is the inside electric appliance schematic diagram according to the embodiment of the present application.
Appended drawing reference
1, fixed frame;2, subframe;3, electrical equipment;4, the first connector;5, the second connector;6, extend outwardly
Portion;7, terrace;8, incoming line cabinet;9, transformer;10, bus connection switch;11, compensation circuit;12, UPS power module;13, it inputs defeated
It offers for sale;14, maintenance bypass;15, feeder cabinet;16, Vierendeel girder;17, frame column;18, detachable rod piece.
Specific embodiment
In order to make those skilled in the art more fully understand application scheme, below in conjunction in the embodiment of the present application
Attached drawing, the technical scheme in the embodiment of the application is clearly and completely described, it is clear that described embodiment is only
The embodiment of the application a part, instead of all the embodiments.Based on the embodiment in the application, ordinary skill people
Member's every other embodiment obtained without making creative work, all should belong to the model of the application protection
It encloses.
It should be noted that the description and claims of this application and term " first " in above-mentioned attached drawing, "
Two " etc. be to be used to distinguish similar objects, without being used to describe a particular order or precedence order.It should be understood that using in this way
Data be interchangeable under appropriate circumstances, so as to embodiments herein described herein.In addition, term " includes " and " tool
Have " and their any deformation, it is intended that cover it is non-exclusive include, for example, containing a series of steps or units
Process, method, system, product or equipment those of are not necessarily limited to be clearly listed step or unit, but may include without clear
Other step or units listing to Chu or intrinsic for these process, methods, product or equipment.
In this application, term " on ", "lower", "left", "right", "front", "rear", "top", "bottom", "inner", "outside",
" in ", "vertical", "horizontal", " transverse direction ", the orientation or positional relationship of the instructions such as " longitudinal direction " be orientation based on the figure or
Positional relationship.These terms are not intended to limit indicated dress primarily to better describe the present invention and embodiment
Set, element or component must have particular orientation, or constructed and operated with particular orientation.
Also, above-mentioned part term is other than it can be used to indicate that orientation or positional relationship, it is also possible to for indicating it
His meaning, such as term " on " also are likely used for indicating certain relations of dependence or connection relationship in some cases.For ability
For the those of ordinary skill of domain, the concrete meaning of these terms in the present invention can be understood as the case may be.
In addition, term " installation ", " setting ", " being equipped with ", " connection ", " connected ", " socket " shall be understood in a broad sense.For example,
It may be a fixed connection, be detachably connected or monolithic construction;It can be mechanical connection, or electrical connection;It can be direct phase
It even, or indirectly connected through an intermediary, or is two connections internal between device, element or component.
For those of ordinary skills, the specific meanings of the above terms in the present invention can be understood according to specific conditions.
It should be noted that in the absence of conflict, the features in the embodiments and the embodiments of the present application can phase
Mutually combination.The application is described in detail below with reference to the accompanying drawings and in conjunction with the embodiments.
As shown in Figs 1-4, this application involves a kind of modularization power distribution station for data center, which includes: solid
Determine frame 1, the fixed frame 1 includes: one or more subframe 2 customized in advance in factory, and is arranged in the sub- frame
Electrical equipment 3 in frame 2, is provided with the first connector 4 and the second connector 5 on the subframe 2, between the subframe 2
It is connected by first connector 4;The subframe 2 is connected by second connector 5 with concrete room.
Specifically, fixed frame 1 is the framework of power distribution station, mutually splice directly as room entirety with civil engineering part and solid
It is fixed;Preferably, at least one side of fixed frame 1 is filled by concrete or other construction materials;This process is before factory,
Through completing, refilled when without to assembled in situ.Fixed frame 1 can be a subframe 2 and form, in each subframe 2
Electrical equipment 3 is set, it is only necessary to which the subframe 2 with electrical equipment 3 is assembled to concrete room by the second connector 5
In can form the power distribution station of small area;Fixed frame 1 is also possible to multiple subframes 2 and forms, each with electrical equipment 3
The power distribution station of large area, i.e. a son can be spliced to form between subframe 2 by the first about 4 connector, left and right or front and back
Frame 2 is only one of power distribution unit, and multiple power distribution units combine and form power distribution station;In the present embodiment, a subframe 2
Size length be no more than 15m*4.5m*6m, weight be no more than 55 tons, can convenient for assembly, can also improve dress as far as possible
With efficiency.As preferably, first connector 4 includes: the Vierendeel girder 16 or frame for forming the subframe 2 in the present embodiment
The outwardly extending outwardly extending portion 6 of trestle 17;Subframe 2 is connected formation by Vierendeel girder 16 with frame column 17, Vierendeel girder 16
Or the outwardly extending outwardly extending portion 6 of frame column 17 refers to Vierendeel girder 16 or 17 both ends of frame column for being connected between subframe 2
Part;Between Vierendeel girder 16 and frame column 17 before factory, subframe 2 is formed using welding technique, according still further to the mixed of civil engineering
Specification splices multiple subframes 2 between solidifying abode house, forms fixed frame 1, the form of splicing can be construction site welding or
The bolt connection of construction site is also possible to through outwardly extending portion 6 (overhanging bracket) mutually clamping matching;Preferably bolt connects
It connects, connects firm, convenient disassembly.Optionally, the outwardly extending portion 6 is located at top side and bottom side, and/or is located at left side and the right side
Side, and/or it is located at front side and rear side;Can by overhanging bracket in the top side of subframe 2 and bottom side and/or left side and
Right side and/or front side connect another subframe 2 with rear side, achieve the purpose that be spliced into fixed frame 1.It is more in electrical equipment 3
A circuit integration is highly integrated to together, having achieved the purpose that.As preferred in the present embodiment, as shown in figure 3, described electrical
Equipment 3 includes: low-voltage distribution apparatus, no-break power unit, HVDC Equipments or close-coupled UPS equipment;It is preferably compact
Formula UPS equipment, close-coupled UPS controller switching equipment can meet needed for the data center of different capabilities with electricity demanding, such as capacity
2500kVA, 2000kVA, 1600kVA etc.;Internal mating independent, integrated auxiliary equipment, can be used as separate modular splicing.
It can be seen from the above description that the application realizes following technical effect:
In the embodiment of the present application, using modular mode, electrical equipment 3 is arranged by subframe 2, is connected by first
Fitting 4 splices multiple subframes 2 and forms power distribution station, and the power distribution station of formation is spliced to the coagulation of civil engineering by the second connector 5
In between abode house, prefabricated power distribution station is reached, and be fixed to the purpose in concrete room, assembly is simple, assembles effect to realize
The technical effect that rate is high, shortens the construction period, and then solve since electromechanical installation amount live during Constructing data center is big,
Caused by low efficiency, technical problem long in time limit.
As preferably, the length of multiple subframes 2 is identical with height, of different size in the present embodiment.It can be real
Existing forward and backward splicing subframe 2, reaches and is spliced into large area power distribution station, to adapt to the requirement of different data centers.
As preferred in the present embodiment, the length and width of multiple subframes 2 is identical, and height is different.It can be real
Now splice subframe 2 above and below, reaches the power distribution station for being spliced into multilayer, to adapt to the requirement of different data centers.
As preferred in the present embodiment, the width of multiple subframes 2 is identical with height, and length is different.It can be real
Existing left and right splicing subframe 2, reaches and is spliced into large area power distribution station, to adapt to the requirement of different data centers.
In the present embodiment, it is preferred that the length of multiple subframes 2, width and height are all the same.Before may be implemented
Afterwards, left and right, up and down splicing subframe 2, achieve the purpose that comprehensive enlarged-area, so as to be spliced into large area power distribution station,
To adapt to the requirement of different data centers.
As preferred in the present embodiment, the bottom setting terrace 7 of the subframe 2.Carrying can be reached by terrace 7
The purpose of electrical equipment 3 preferably uses concrete floor 7, is also possible to other terraces 7 in the prior art.
As preferably, the close-coupled UPS equipment includes: incoming line cabinet 8, transformer 9, bus connection switch in the present embodiment
10, compensation circuit 11, UPS power module Unit 12, input and output cabinet 13, maintenance bypass 14 and feeder cabinet 15;Specifically, logical
Cross the integration of controller switching equipment arrangement, the densification of realization bulk supply unit, integrated arrangement.It arranges in sequence: incoming line cabinet
8, transformer 9, inlet wire and bus connection switch 10, compensation circuit 11, UPS power unit, UPS input and output cabinet 13, UPS power list
Member, UPS input and output cabinet 13, maintenance bypass 14, feeder cabinet 15.As shown in Figure 4.Compact solution mainly passes through UPS power module
12 inputs, the integration of output switching circuitry, are connected using busbar inside controller switching equipment, reduce low-voltage distribution cabinet to UPS power
Cable length and distance between module 12 realize integrated, the densification of device configuration in single steel structure module, in turn
After reducing module splicing, the workload of wiring, improves working efficiency between module.
As preferred in the present embodiment, the subframe 2 further include: detachable rod piece 18.Set a roof beam in place with frame column 17 by
Non-removable rod piece and dismountable rod piece composition, specifically, removably can be rod piece is cross bar, vertical bar, it can also be with
Brace, by this rod piece and set a roof beam in place, the combination of frame column 17 can guarantee the stability of integrated steel-structure frame, assembling
After the completion, these braces can be dismantled.
The foregoing is merely preferred embodiment of the present application, are not intended to limit this application, for the skill of this field
For art personnel, various changes and changes are possible in this application.Within the spirit and principles of this application, made any to repair
Change, equivalent replacement, improvement etc., should be included within the scope of protection of this application.
Claims (10)
1. a kind of modularization power distribution station for data center characterized by comprising fixed frame, the fixed frame packet
It includes: one or more subframes customized in advance in factory, and the electrical equipment being arranged in the subframe, the sub- frame
It is provided with the first connector and the second connector on frame, is connected between the subframe by first connector;The son
Frame is connected by second connector with concrete room.
2. modularization power distribution station according to claim 1, which is characterized in that the electrical equipment electrically sets to be integrated
It is standby;The electrical equipment includes: low-voltage distribution apparatus, no-break power unit or close-coupled UPS equipment and its auxiliary with being arranged
It applies.
3. modularization power distribution station according to claim 1, which is characterized in that the length and height phase of multiple subframes
Together, of different size.
4. modularization power distribution station according to claim 1, which is characterized in that the length and width phase of multiple subframes
Together, height is different.
5. modularization power distribution station according to claim 1, which is characterized in that the width and height phase of multiple subframes
Together, length is different.
6. modularization power distribution station according to claim 1, which is characterized in that first connector includes: described in composition
The outwardly extending outwardly extending portion of Vierendeel girder or frame column of subframe.
7. modularization power distribution station according to claim 1, which is characterized in that the outwardly extending portion is located at top side and bottom
Side, and/or it is located at left and right side, and/or be located at front side and rear side.
8. modularization power distribution station according to claim 1, which is characterized in that terrace is arranged in the bottom of the subframe.
9. modularization power distribution station according to claim 2, which is characterized in that the close-coupled UPS equipment includes: inlet wire
Cabinet, transformer, bus connection switch, compensation circuit, UPS power module, input and output cabinet, maintenance bypass and feeder cabinet.
10. modularization power distribution station according to claim 1, which is characterized in that the subframe further include: removable link
Part.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910141965.5A CN109787092A (en) | 2019-02-26 | 2019-02-26 | Modularization power distribution station for data center |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910141965.5A CN109787092A (en) | 2019-02-26 | 2019-02-26 | Modularization power distribution station for data center |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109787092A true CN109787092A (en) | 2019-05-21 |
Family
ID=66487087
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910141965.5A Pending CN109787092A (en) | 2019-02-26 | 2019-02-26 | Modularization power distribution station for data center |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109787092A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117878738A (en) * | 2023-12-21 | 2024-04-12 | 广东博瑞天成能源技术有限公司 | Integrated power supply equipment for data center |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN205502248U (en) * | 2016-02-02 | 2016-08-24 | 华德宝机械(昆山)有限公司 | Assembled steel structure module and adopt assembled steel house room of this module |
CN107806176A (en) * | 2017-12-01 | 2018-03-16 | 贵州精正检测有限公司 | Steel construction assembled architecture and its construction method based on BIM |
CN207252112U (en) * | 2017-05-10 | 2018-04-17 | 腾讯科技(深圳)有限公司 | A kind of data center apparatus and system |
CN108930423A (en) * | 2017-05-26 | 2018-12-04 | 华为技术有限公司 | Data center |
CN209487943U (en) * | 2019-02-26 | 2019-10-11 | 财拓云计算(上海)有限公司 | Modularization power distribution station for data center |
-
2019
- 2019-02-26 CN CN201910141965.5A patent/CN109787092A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN205502248U (en) * | 2016-02-02 | 2016-08-24 | 华德宝机械(昆山)有限公司 | Assembled steel structure module and adopt assembled steel house room of this module |
CN207252112U (en) * | 2017-05-10 | 2018-04-17 | 腾讯科技(深圳)有限公司 | A kind of data center apparatus and system |
CN108930423A (en) * | 2017-05-26 | 2018-12-04 | 华为技术有限公司 | Data center |
CN107806176A (en) * | 2017-12-01 | 2018-03-16 | 贵州精正检测有限公司 | Steel construction assembled architecture and its construction method based on BIM |
CN209487943U (en) * | 2019-02-26 | 2019-10-11 | 财拓云计算(上海)有限公司 | Modularization power distribution station for data center |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117878738A (en) * | 2023-12-21 | 2024-04-12 | 广东博瑞天成能源技术有限公司 | Integrated power supply equipment for data center |
CN117878738B (en) * | 2023-12-21 | 2024-08-06 | 广东博瑞天成能源技术有限公司 | Integrated power supply equipment for data center |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103597700B (en) | Electrical charge transfer apparatus and related management method | |
CN104242349B (en) | The photovoltaic system of anti-potential induction attenuation and photovoltaic DC-to-AC converter | |
DE4032569A1 (en) | Photovoltaic system coupled to mains network - has individual modules incorporating respective DC-AC converter for direct supply of mains network | |
DE102009025363A1 (en) | Starting source inverter | |
CN101938139B (en) | Variable frequency transformer having multiple horizontal rotary transformers and method thereof | |
CN209487943U (en) | Modularization power distribution station for data center | |
CN102066745A (en) | Wind energy system comprising busbars | |
CN102652388A (en) | Apparatus, system and method employing ups | |
CN105356304A (en) | Output power distribution module and power distribution cabinet | |
CN109787092A (en) | Modularization power distribution station for data center | |
CN106329377A (en) | Compact switch cabinet | |
CN111463830A (en) | Local area power grid networking method and application system thereof | |
DE69834554T2 (en) | ELECTRIC SCHOOL EQUIPMENT | |
CN206878358U (en) | Multi-functional charging pile system based on box-type substation | |
RU2219630C1 (en) | Method for erecting modular distribution transformer substation | |
CN216648859U (en) | Low-voltage switchgear cabinet body frame convenient to installation | |
CN106549325A (en) | A kind of new structure pre-installed transformer sub-station that quickly can be arranged and its installation method | |
CN201742156U (en) | Station power supply based on backdrop technology | |
CN105762926A (en) | Combined power distribution system for data center | |
CN1333507C (en) | Parallel uninterrupted power source system and starting method thereof | |
CN110258855A (en) | A kind of assembled wall of built-in electric wire | |
CN219717697U (en) | GIS and marine booster station | |
CN106486948B (en) | Emergent female structure of arranging of low pressure bypass | |
CN201584725U (en) | Horizontal elbow structure for busway | |
CN204668734U (en) | Compact-type high-pressure metering cabinet |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |