CN109787092A - Modularization power distribution station for data center - Google Patents

Modularization power distribution station for data center Download PDF

Info

Publication number
CN109787092A
CN109787092A CN201910141965.5A CN201910141965A CN109787092A CN 109787092 A CN109787092 A CN 109787092A CN 201910141965 A CN201910141965 A CN 201910141965A CN 109787092 A CN109787092 A CN 109787092A
Authority
CN
China
Prior art keywords
power distribution
distribution station
subframe
connector
station according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910141965.5A
Other languages
Chinese (zh)
Inventor
陈亮
王晓磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Caituo Cloud Computing (shanghai) Co Ltd
Original Assignee
Caituo Cloud Computing (shanghai) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Caituo Cloud Computing (shanghai) Co Ltd filed Critical Caituo Cloud Computing (shanghai) Co Ltd
Priority to CN201910141965.5A priority Critical patent/CN109787092A/en
Publication of CN109787092A publication Critical patent/CN109787092A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P80/00Climate change mitigation technologies for sector-wide applications
    • Y02P80/10Efficient use of energy, e.g. using compressed air or pressurized fluid as energy carrier

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

This application discloses a kind of modularization power distribution stations for data center.The power distribution station includes: fixed frame, the fixed frame includes: one or more subframe customized in advance in factory, with the electrical equipment and its auxiliary auxiliary facility being arranged in the subframe, it is provided with the first connector and the second connector on the subframe, is connected between the subframe by first connector;The subframe is connected by second connector with concrete room.Present application addresses due to electromechanical installation amount live during Constructing data center it is big, caused by low efficiency, technical problem long in time limit.

Description

Modularization power distribution station for data center
Technical field
This application involves data center fields, in particular to a kind of modularization power distribution station for data center.
Background technique
By development over several years, Mechatronic Systems overall architecture, design scheme gradually standardize data center's industry.
The service object of data center is extensive, and different industries client has different want to the Mechatronic Systems of data center It asks.Compatibility delivers speed as the focal point of current line in the industry.Electro-mechanical parts are the core of the mating auxiliary equipment of data center Center portion point, compatibility deliver speed for two big focal points.
Under normal conditions, data center's electro-mechanical parts are installed again after completion is built in civil engineering part, the duration Longer, this is just needed through prefabricated modularization power distribution station, and by data center's distribution section, integrated, commercialization, is adapted to not Same scene, client, and by prefabricated mode, maximum electromechanical installation section will be influenced on data center's construction speed in work Factory is prefabricated, parallel with the civil construction at scene, achievees the purpose that shorten the construction period.
It is big for electromechanical installation amount live during Constructing data center in the related technology, caused by low efficiency, work The technical problem of phase length, currently no effective solution has been proposed.
Summary of the invention
The main purpose of the application is to provide a kind of modularization power distribution station for data center, to solve process of construction Middle scene electromechanical installation amount is big, caused by low efficiency, technical problem long in time limit,.
To achieve the goals above, according to the one aspect of the application, a kind of modularization for data center is provided Power distribution station.
It include: fixed frame according to the modularization power distribution station for data center of the application, the fixed frame includes: One or more is on the preparatory customized subframe of factory, and the electrical equipment being arranged in the subframe, the subframe It is provided with the first connector and the second connector, is connected between the subframe by first connector;The subframe It is connected by second connector with concrete room.
Further, the electrical equipment includes: low-voltage distribution apparatus, no-break power unit or close-coupled UPS equipment And its auxiliary auxiliary facility.
Further, the length of multiple subframes is identical with height, of different size.
Further, the length and width of multiple subframes is identical, and height is different.
Further, the width of multiple subframes is identical with height, and length is different.
Further, first connector include: form the subframe Vierendeel girder or frame column it is outwardly extending Outwardly extending portion.
Further, the outwardly extending portion is located at top side and bottom side, and/or is located at left and right side, and/or before being located at Side and rear side.
Further, terrace is arranged in the bottom of the subframe.
Further, the close-coupled UPS equipment includes: incoming line cabinet, transformer, bus connection switch, compensation circuit, UPS function Rate module, input and output cabinet, maintenance bypass and feeder cabinet.
Further, the subframe further include: detachable rod piece.
In the embodiment of the present application, using modular mode, electrical equipment is arranged by subframe, passes through the first connection Part splices multiple subframes and forms power distribution station, and the power distribution station of formation is spliced to the concrete room of civil engineering by the second connector In, reach prefabricated power distribution station, and be fixed to the purpose in concrete room, assembly is simple, assembly efficiency is high, contracting to realize The technical effect of casual labourer's phase, and then solve during Constructing data center that live electromechanical installation amount is big, caused by efficiency Technical problem low, long in time limit.
Detailed description of the invention
The attached drawing constituted part of this application is used to provide further understanding of the present application, so that the application's is other Feature, objects and advantages become more apparent upon.The illustrative examples attached drawing and its explanation of the application is for explaining the application, not Constitute the improper restriction to the application.In the accompanying drawings:
Fig. 1 is one of the modularization power distribution station structural schematic diagram according to the embodiment of the present application;
Fig. 2 is the modularization power distribution station second structural representation according to the embodiment of the present application;
Fig. 3 is the sub-frame structures schematic diagram according to the embodiment of the present application;
Fig. 4 is the inside electric appliance schematic diagram according to the embodiment of the present application.
Appended drawing reference
1, fixed frame;2, subframe;3, electrical equipment;4, the first connector;5, the second connector;6, extend outwardly Portion;7, terrace;8, incoming line cabinet;9, transformer;10, bus connection switch;11, compensation circuit;12, UPS power module;13, it inputs defeated It offers for sale;14, maintenance bypass;15, feeder cabinet;16, Vierendeel girder;17, frame column;18, detachable rod piece.
Specific embodiment
In order to make those skilled in the art more fully understand application scheme, below in conjunction in the embodiment of the present application Attached drawing, the technical scheme in the embodiment of the application is clearly and completely described, it is clear that described embodiment is only The embodiment of the application a part, instead of all the embodiments.Based on the embodiment in the application, ordinary skill people Member's every other embodiment obtained without making creative work, all should belong to the model of the application protection It encloses.
It should be noted that the description and claims of this application and term " first " in above-mentioned attached drawing, " Two " etc. be to be used to distinguish similar objects, without being used to describe a particular order or precedence order.It should be understood that using in this way Data be interchangeable under appropriate circumstances, so as to embodiments herein described herein.In addition, term " includes " and " tool Have " and their any deformation, it is intended that cover it is non-exclusive include, for example, containing a series of steps or units Process, method, system, product or equipment those of are not necessarily limited to be clearly listed step or unit, but may include without clear Other step or units listing to Chu or intrinsic for these process, methods, product or equipment.
In this application, term " on ", "lower", "left", "right", "front", "rear", "top", "bottom", "inner", "outside", " in ", "vertical", "horizontal", " transverse direction ", the orientation or positional relationship of the instructions such as " longitudinal direction " be orientation based on the figure or Positional relationship.These terms are not intended to limit indicated dress primarily to better describe the present invention and embodiment Set, element or component must have particular orientation, or constructed and operated with particular orientation.
Also, above-mentioned part term is other than it can be used to indicate that orientation or positional relationship, it is also possible to for indicating it His meaning, such as term " on " also are likely used for indicating certain relations of dependence or connection relationship in some cases.For ability For the those of ordinary skill of domain, the concrete meaning of these terms in the present invention can be understood as the case may be.
In addition, term " installation ", " setting ", " being equipped with ", " connection ", " connected ", " socket " shall be understood in a broad sense.For example, It may be a fixed connection, be detachably connected or monolithic construction;It can be mechanical connection, or electrical connection;It can be direct phase It even, or indirectly connected through an intermediary, or is two connections internal between device, element or component. For those of ordinary skills, the specific meanings of the above terms in the present invention can be understood according to specific conditions.
It should be noted that in the absence of conflict, the features in the embodiments and the embodiments of the present application can phase Mutually combination.The application is described in detail below with reference to the accompanying drawings and in conjunction with the embodiments.
As shown in Figs 1-4, this application involves a kind of modularization power distribution station for data center, which includes: solid Determine frame 1, the fixed frame 1 includes: one or more subframe 2 customized in advance in factory, and is arranged in the sub- frame Electrical equipment 3 in frame 2, is provided with the first connector 4 and the second connector 5 on the subframe 2, between the subframe 2 It is connected by first connector 4;The subframe 2 is connected by second connector 5 with concrete room.
Specifically, fixed frame 1 is the framework of power distribution station, mutually splice directly as room entirety with civil engineering part and solid It is fixed;Preferably, at least one side of fixed frame 1 is filled by concrete or other construction materials;This process is before factory, Through completing, refilled when without to assembled in situ.Fixed frame 1 can be a subframe 2 and form, in each subframe 2 Electrical equipment 3 is set, it is only necessary to which the subframe 2 with electrical equipment 3 is assembled to concrete room by the second connector 5 In can form the power distribution station of small area;Fixed frame 1 is also possible to multiple subframes 2 and forms, each with electrical equipment 3 The power distribution station of large area, i.e. a son can be spliced to form between subframe 2 by the first about 4 connector, left and right or front and back Frame 2 is only one of power distribution unit, and multiple power distribution units combine and form power distribution station;In the present embodiment, a subframe 2 Size length be no more than 15m*4.5m*6m, weight be no more than 55 tons, can convenient for assembly, can also improve dress as far as possible With efficiency.As preferably, first connector 4 includes: the Vierendeel girder 16 or frame for forming the subframe 2 in the present embodiment The outwardly extending outwardly extending portion 6 of trestle 17;Subframe 2 is connected formation by Vierendeel girder 16 with frame column 17, Vierendeel girder 16 Or the outwardly extending outwardly extending portion 6 of frame column 17 refers to Vierendeel girder 16 or 17 both ends of frame column for being connected between subframe 2 Part;Between Vierendeel girder 16 and frame column 17 before factory, subframe 2 is formed using welding technique, according still further to the mixed of civil engineering Specification splices multiple subframes 2 between solidifying abode house, forms fixed frame 1, the form of splicing can be construction site welding or The bolt connection of construction site is also possible to through outwardly extending portion 6 (overhanging bracket) mutually clamping matching;Preferably bolt connects It connects, connects firm, convenient disassembly.Optionally, the outwardly extending portion 6 is located at top side and bottom side, and/or is located at left side and the right side Side, and/or it is located at front side and rear side;Can by overhanging bracket in the top side of subframe 2 and bottom side and/or left side and Right side and/or front side connect another subframe 2 with rear side, achieve the purpose that be spliced into fixed frame 1.It is more in electrical equipment 3 A circuit integration is highly integrated to together, having achieved the purpose that.As preferred in the present embodiment, as shown in figure 3, described electrical Equipment 3 includes: low-voltage distribution apparatus, no-break power unit, HVDC Equipments or close-coupled UPS equipment;It is preferably compact Formula UPS equipment, close-coupled UPS controller switching equipment can meet needed for the data center of different capabilities with electricity demanding, such as capacity 2500kVA, 2000kVA, 1600kVA etc.;Internal mating independent, integrated auxiliary equipment, can be used as separate modular splicing.
It can be seen from the above description that the application realizes following technical effect:
In the embodiment of the present application, using modular mode, electrical equipment 3 is arranged by subframe 2, is connected by first Fitting 4 splices multiple subframes 2 and forms power distribution station, and the power distribution station of formation is spliced to the coagulation of civil engineering by the second connector 5 In between abode house, prefabricated power distribution station is reached, and be fixed to the purpose in concrete room, assembly is simple, assembles effect to realize The technical effect that rate is high, shortens the construction period, and then solve since electromechanical installation amount live during Constructing data center is big, Caused by low efficiency, technical problem long in time limit.
As preferably, the length of multiple subframes 2 is identical with height, of different size in the present embodiment.It can be real Existing forward and backward splicing subframe 2, reaches and is spliced into large area power distribution station, to adapt to the requirement of different data centers.
As preferred in the present embodiment, the length and width of multiple subframes 2 is identical, and height is different.It can be real Now splice subframe 2 above and below, reaches the power distribution station for being spliced into multilayer, to adapt to the requirement of different data centers.
As preferred in the present embodiment, the width of multiple subframes 2 is identical with height, and length is different.It can be real Existing left and right splicing subframe 2, reaches and is spliced into large area power distribution station, to adapt to the requirement of different data centers.
In the present embodiment, it is preferred that the length of multiple subframes 2, width and height are all the same.Before may be implemented Afterwards, left and right, up and down splicing subframe 2, achieve the purpose that comprehensive enlarged-area, so as to be spliced into large area power distribution station, To adapt to the requirement of different data centers.
As preferred in the present embodiment, the bottom setting terrace 7 of the subframe 2.Carrying can be reached by terrace 7 The purpose of electrical equipment 3 preferably uses concrete floor 7, is also possible to other terraces 7 in the prior art.
As preferably, the close-coupled UPS equipment includes: incoming line cabinet 8, transformer 9, bus connection switch in the present embodiment 10, compensation circuit 11, UPS power module Unit 12, input and output cabinet 13, maintenance bypass 14 and feeder cabinet 15;Specifically, logical Cross the integration of controller switching equipment arrangement, the densification of realization bulk supply unit, integrated arrangement.It arranges in sequence: incoming line cabinet 8, transformer 9, inlet wire and bus connection switch 10, compensation circuit 11, UPS power unit, UPS input and output cabinet 13, UPS power list Member, UPS input and output cabinet 13, maintenance bypass 14, feeder cabinet 15.As shown in Figure 4.Compact solution mainly passes through UPS power module 12 inputs, the integration of output switching circuitry, are connected using busbar inside controller switching equipment, reduce low-voltage distribution cabinet to UPS power Cable length and distance between module 12 realize integrated, the densification of device configuration in single steel structure module, in turn After reducing module splicing, the workload of wiring, improves working efficiency between module.
As preferred in the present embodiment, the subframe 2 further include: detachable rod piece 18.Set a roof beam in place with frame column 17 by Non-removable rod piece and dismountable rod piece composition, specifically, removably can be rod piece is cross bar, vertical bar, it can also be with Brace, by this rod piece and set a roof beam in place, the combination of frame column 17 can guarantee the stability of integrated steel-structure frame, assembling After the completion, these braces can be dismantled.
The foregoing is merely preferred embodiment of the present application, are not intended to limit this application, for the skill of this field For art personnel, various changes and changes are possible in this application.Within the spirit and principles of this application, made any to repair Change, equivalent replacement, improvement etc., should be included within the scope of protection of this application.

Claims (10)

1. a kind of modularization power distribution station for data center characterized by comprising fixed frame, the fixed frame packet It includes: one or more subframes customized in advance in factory, and the electrical equipment being arranged in the subframe, the sub- frame It is provided with the first connector and the second connector on frame, is connected between the subframe by first connector;The son Frame is connected by second connector with concrete room.
2. modularization power distribution station according to claim 1, which is characterized in that the electrical equipment electrically sets to be integrated It is standby;The electrical equipment includes: low-voltage distribution apparatus, no-break power unit or close-coupled UPS equipment and its auxiliary with being arranged It applies.
3. modularization power distribution station according to claim 1, which is characterized in that the length and height phase of multiple subframes Together, of different size.
4. modularization power distribution station according to claim 1, which is characterized in that the length and width phase of multiple subframes Together, height is different.
5. modularization power distribution station according to claim 1, which is characterized in that the width and height phase of multiple subframes Together, length is different.
6. modularization power distribution station according to claim 1, which is characterized in that first connector includes: described in composition The outwardly extending outwardly extending portion of Vierendeel girder or frame column of subframe.
7. modularization power distribution station according to claim 1, which is characterized in that the outwardly extending portion is located at top side and bottom Side, and/or it is located at left and right side, and/or be located at front side and rear side.
8. modularization power distribution station according to claim 1, which is characterized in that terrace is arranged in the bottom of the subframe.
9. modularization power distribution station according to claim 2, which is characterized in that the close-coupled UPS equipment includes: inlet wire Cabinet, transformer, bus connection switch, compensation circuit, UPS power module, input and output cabinet, maintenance bypass and feeder cabinet.
10. modularization power distribution station according to claim 1, which is characterized in that the subframe further include: removable link Part.
CN201910141965.5A 2019-02-26 2019-02-26 Modularization power distribution station for data center Pending CN109787092A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910141965.5A CN109787092A (en) 2019-02-26 2019-02-26 Modularization power distribution station for data center

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910141965.5A CN109787092A (en) 2019-02-26 2019-02-26 Modularization power distribution station for data center

Publications (1)

Publication Number Publication Date
CN109787092A true CN109787092A (en) 2019-05-21

Family

ID=66487087

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910141965.5A Pending CN109787092A (en) 2019-02-26 2019-02-26 Modularization power distribution station for data center

Country Status (1)

Country Link
CN (1) CN109787092A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117878738A (en) * 2023-12-21 2024-04-12 广东博瑞天成能源技术有限公司 Integrated power supply equipment for data center

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205502248U (en) * 2016-02-02 2016-08-24 华德宝机械(昆山)有限公司 Assembled steel structure module and adopt assembled steel house room of this module
CN107806176A (en) * 2017-12-01 2018-03-16 贵州精正检测有限公司 Steel construction assembled architecture and its construction method based on BIM
CN207252112U (en) * 2017-05-10 2018-04-17 腾讯科技(深圳)有限公司 A kind of data center apparatus and system
CN108930423A (en) * 2017-05-26 2018-12-04 华为技术有限公司 Data center
CN209487943U (en) * 2019-02-26 2019-10-11 财拓云计算(上海)有限公司 Modularization power distribution station for data center

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205502248U (en) * 2016-02-02 2016-08-24 华德宝机械(昆山)有限公司 Assembled steel structure module and adopt assembled steel house room of this module
CN207252112U (en) * 2017-05-10 2018-04-17 腾讯科技(深圳)有限公司 A kind of data center apparatus and system
CN108930423A (en) * 2017-05-26 2018-12-04 华为技术有限公司 Data center
CN107806176A (en) * 2017-12-01 2018-03-16 贵州精正检测有限公司 Steel construction assembled architecture and its construction method based on BIM
CN209487943U (en) * 2019-02-26 2019-10-11 财拓云计算(上海)有限公司 Modularization power distribution station for data center

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117878738A (en) * 2023-12-21 2024-04-12 广东博瑞天成能源技术有限公司 Integrated power supply equipment for data center
CN117878738B (en) * 2023-12-21 2024-08-06 广东博瑞天成能源技术有限公司 Integrated power supply equipment for data center

Similar Documents

Publication Publication Date Title
CN103597700B (en) Electrical charge transfer apparatus and related management method
CN104242349B (en) The photovoltaic system of anti-potential induction attenuation and photovoltaic DC-to-AC converter
DE4032569A1 (en) Photovoltaic system coupled to mains network - has individual modules incorporating respective DC-AC converter for direct supply of mains network
DE102009025363A1 (en) Starting source inverter
CN101938139B (en) Variable frequency transformer having multiple horizontal rotary transformers and method thereof
CN209487943U (en) Modularization power distribution station for data center
CN102066745A (en) Wind energy system comprising busbars
CN102652388A (en) Apparatus, system and method employing ups
CN105356304A (en) Output power distribution module and power distribution cabinet
CN109787092A (en) Modularization power distribution station for data center
CN106329377A (en) Compact switch cabinet
CN111463830A (en) Local area power grid networking method and application system thereof
DE69834554T2 (en) ELECTRIC SCHOOL EQUIPMENT
CN206878358U (en) Multi-functional charging pile system based on box-type substation
RU2219630C1 (en) Method for erecting modular distribution transformer substation
CN216648859U (en) Low-voltage switchgear cabinet body frame convenient to installation
CN106549325A (en) A kind of new structure pre-installed transformer sub-station that quickly can be arranged and its installation method
CN201742156U (en) Station power supply based on backdrop technology
CN105762926A (en) Combined power distribution system for data center
CN1333507C (en) Parallel uninterrupted power source system and starting method thereof
CN110258855A (en) A kind of assembled wall of built-in electric wire
CN219717697U (en) GIS and marine booster station
CN106486948B (en) Emergent female structure of arranging of low pressure bypass
CN201584725U (en) Horizontal elbow structure for busway
CN204668734U (en) Compact-type high-pressure metering cabinet

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination