CN109763483A - A kind of thick 4th is buried excavation collapse broken formation upstriker segmenting slip casting technique - Google Patents

A kind of thick 4th is buried excavation collapse broken formation upstriker segmenting slip casting technique Download PDF

Info

Publication number
CN109763483A
CN109763483A CN201910058885.3A CN201910058885A CN109763483A CN 109763483 A CN109763483 A CN 109763483A CN 201910058885 A CN201910058885 A CN 201910058885A CN 109763483 A CN109763483 A CN 109763483A
Authority
CN
China
Prior art keywords
slip casting
grouting pipe
pipe
upstriker
thick
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910058885.3A
Other languages
Chinese (zh)
Other versions
CN109763483B (en
Inventor
刘小平
李宁
刘新星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian University of Technology
Original Assignee
Xian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian University of Technology filed Critical Xian University of Technology
Priority to CN201910058885.3A priority Critical patent/CN109763483B/en
Publication of CN109763483A publication Critical patent/CN109763483A/en
Application granted granted Critical
Publication of CN109763483B publication Critical patent/CN109763483B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

It is buried excavation collapse broken formation upstriker segmenting slip casting technique the invention discloses a kind of thick 4th, specifically: first, pore-forming, drilling open pore size is Φ 150mm, mud off is used in Quaternary loose soils, it is drilled into stable basement rock or less 5m, cement paste is poured into bottom hole by orifice tube, by orifice tube down toward stablizing basement rock or less 5m before cement slurry initial set, using slurry processes fixed orifice pipe is sat, first time variable diameter is carried out, rock section is crept into using clear water, continue to be drilled into water flowing fractured zone bottom, carries out second of variable diameter;After pore-forming, tripping in Grouting Pipe welds in aperture by ring flange;Lower section slip casting is carried out by Grouting Pipe, after lower section slip casting, carries out upper section slip casting from orifice tube and Grouting Pipe gap, until reaching the standard of end hole, slip casting terminates.By segmenting slip casting, the compactness of goaf filling can be significantly increased, improves slip casting uniformity, improves drilling utilization efficiency, it is ensured that goaf harnessing engineering quality.

Description

A kind of thick 4th is buried excavation collapse broken formation upstriker segmenting slip casting technique
Technical field
The invention belongs to goaf grouting technical fields, and in particular to a kind of thick 4th is buried excavation collapse broken formation Upstriker segmenting slip casting technique.
Background technique
With the rapid development of our country's economy, infrastructure construction constantly improve, and land resource accelerates in short supply.Especially in mine Area, land resource growing tension, more and more highways, railway, bridge, tunnel, dam and the construction of work China Democratic National Construction Association are inevitable Encounter goaf ground.
Goaf ground itself is unstable, is easy to happen buckling deformation under the factors such as weight stress, earthquake and underground water; After earth's surface builds buildings or structures, under imposed load effect, it is possible to break the original equilibrium state in goaf, it is again " living Change " goaf, accelerate goaf foundation deformation, so that buildings or structures be caused to destroy.
The method of goaf harnessing mainly has perfusion filling method, passes through/cross over method, masonry method, shell backfill method of digging, is strong at present 6 kinds of rammer method, preloading methods.Wherein, most common method is perfusion filling method.In general, goaf harnessing is using " primary Pore-forming, full section slip casting " construction technology.
In the 4th system covering thickness, buried, stratum crushing, the construction of multilayer goaf harnessing engineering, stratum cranny development Degree is uneven and drilling is easily collapsed, and using " one-step pore-creating, full section slip casting " construction technology, be easy to cause slip casting section collapse hole, is caving Band is full of leakiness, causes slip casting uneven, and drilling utilization rate reduces, and construction quality is difficult to ensure.
Summary of the invention
It is buried excavation collapse broken formation upstriker segmenting slip casting technique the object of the present invention is to provide a kind of thick 4th, Solve the problems, such as that the prior art easy collapse hole of slip casting section, caving zone filling leakiness and slip casting in slip casting are non-uniform.
The technical scheme adopted by the invention is that a kind of thick 4th is buried excavation collapse broken formation upstriker segmentation note Sizing process is specifically implemented according to the following steps:
Step 1, pore-forming, drilling open pore size are Φ 150mm, use mud off in Quaternary loose soils, are drilled into stabilization 5m below basement rock pours into 1:1.5 cement paste to bottom hole by orifice tube by Φ 127mm orifice tube down toward away from bottom hole 10m, By orifice tube down toward basement rock or less 5m is stablized before cement slurry initial set, using seat slurry processes fixed orifice pipe, Gu the pipe time is no less than 24h;
Step 2, after sitting slurry, first time variable diameter is carried out, variable diameter aperture is Φ 110mm, and rock section is crept into using clear water, Continue to be drilled into water flowing fractured zone bottom, carry out second of variable diameter, variable diameter aperture is Φ 91mm, within the scope of the whole above 20m of hole bottom hole Take core;
Step 3, after pore-forming, rapid tripping in Grouting Pipe, Grouting Pipe pipe outer wall binds conduit, corresponding second of the variable diameter of Grouting Pipe Steel tray is installed in position, and for steel tray to weld floral tube more than seat earth, 3~5m of steel tray top pours into 1 by pipeline: 1.5 cement pastes, finally, soldered vias pipe flange and Grouting Pipe screw connector, aperture is wrapped up to slip casting;
Step 4, when slip casting, lower section slip casting is carried out by Grouting Pipe first, after lower section slip casting, from orifice tube and slip casting Pipe gap carries out upper section slip casting, until reaching the standard of end hole, slip casting terminates.
The features of the present invention also characterized in that
In step 1, before cement slurry initial set by orifice tube in hole, using seat slurry processes fixed orifice pipe, setting time No less than for 24 hours, the height that pours of cement paste is 10m.
In step 1, the aperture Φ of orifice tube is 127mm;Orifice tube 20cm above ground level.
In step 3, the aperture Φ of Grouting Pipe is 48mm, Grouting Pipe 50cm above ground level.
In step 3, the slip casting pipe outer wall positioned at steel tray lower part covers rubber stoping flowing pulp plug, and rubber stoping flowing pulp plug is close to steel support Disk.
The internal diameter of steel tray is 50mm, outer diameter 100mm;Rubber stoping flowing pulp plug is truncated cone, big mouth diameter 100mm, Osculum diameter 90mm, height 100mm.
In step 3, the diameter of conduit is 20mm, and the spacing between conduit bottom and steel tray is 5m.
The beneficial effects of the present invention are:
By segmenting slip casting, the compactness of goaf filling can be significantly increased, improves slip casting uniformity, drilling is improved and utilizes Efficiency, it is ensured that goaf harnessing engineering quality.
Detailed description of the invention
Fig. 1 is that the present invention a kind of thick 4th is pore-forming in buried excavation collapse broken formation upstriker segmenting slip casting technique Structural schematic diagram;
Fig. 2 is middle and lower sections slip casting schematic diagram of the embodiment of the present invention;
Fig. 3 is upper section slip casting schematic diagram in the embodiment of the present invention.
In figure, 1. Quaternary loose soils, 2. basement rock;3. water flowing fractured zone, 4. caving zones, 5. coal columns, 6. goafs, 7. coals Layer bottom plate, 8. screw connectors, 9. Grouting Pipes, 10. conduits, 11. ring flanges, 12. orifice tubes, 13.1:1.5 cement slurry, 14. steel supports Disk, 15. rubber stoping flowing pulp plugs, 16. floral tubes, 17. pipe collars, 18. relief valves, 19. pressure gauges, 20. grouting pipes, 21. gaskets.
Specific embodiment
The following describes the present invention in detail with reference to the accompanying drawings and specific embodiments.
The present invention a kind of thick 4th is buried excavation collapse broken formation upstriker segmenting slip casting technique, such as at pore structure Shown in Fig. 1, it is specifically implemented according to the following steps:
Step 1, pore-forming, drilling open pore size are Φ 150mm, use mud off in Quaternary loose soils 1, are drilled into stabilization 2 or less 5m of basement rock pours into 1:1.5 cement paste 13 to bottom hole by orifice tube, in water by orifice tube 12 down toward away from bottom hole 10m By orifice tube 12 down toward basement rock or less 5m is stablized before mud initial set, using seat slurry processes fixed orifice pipe 12, Gu the pipe time is no less than 24h;
The aperture Φ of orifice tube is 127mm, orifice tube 20cm above ground level;
The length that pours of cement paste 13 is 10m;
Step 2, after sitting slurry, first time variable diameter is carried out, variable diameter aperture is Φ 110mm, creeps into using clear water, continues to bore To 3 bottom of water flowing fractured zone, second of variable diameter is carried out, variable diameter aperture is Φ 91mm, takes rock within the scope of the whole above 20m of hole bottom hole Core;
Step 3, after pore-forming, rapid tripping in Grouting Pipe 9,9 pipe outer wall of Grouting Pipe binds conduit 10, Grouting Pipe 9 corresponding second Steel tray 14 is installed in secondary variable diameter position, and 9 outer wall of Grouting Pipe positioned at 14 lower part of steel tray covers rubber stoping flowing pulp plug 15, and rubber is only starched Plug 15 is close to steel tray 14, and to weld floral tube 16 down toward 7 or more seat earth, 14 3~5m of top of steel tray passes through steel tray 14 Conduit 10 pours into 1:1.5 cement paste 13, finally, soldered vias pipe flange 11 and Grouting Pipe screw connector 8, aperture wrapping to Slip casting;
The aperture Φ of Grouting Pipe 9 is 48mm, the 50cm above ground level of Grouting Pipe 9;Connected between every two Grouting Pipe 9 using pipe collar 17 It connects;
The diameter of conduit 10 is 20mm, and the spacing between 10 bottom of conduit and steel tray 14 is 5m;
The internal diameter of steel tray 14 is 50mm, outer diameter 100mm;
Rubber stoping flowing pulp plug 15 is truncated cone, big mouth diameter 100mm, osculum diameter 90mm, height 100mm;
Step 4, when slip casting, first by Grouting Pipe 9 carry out lower section slip casting, after lower section slip casting, from orifice tube 12 with 9 gap of Grouting Pipe carries out upper section slip casting, until reaching the standard of end hole, slip casting terminates.
Embodiment
Goaf harnessing engineering under certain super-huge highway bridge, goaf are formed by fully mechanized mining, are mined one layer, roof control side Formula is freely to be caving formula, and goaf is averaged buried depth 274m, and be averaged mining height 2.5m, and the 4th system buried depth that is averaged is more than 100m, the 4th system There are one layer of layer of sand and two layers of boulder beds for coating lower part.Goaf " three bands " development, stratum crushing.Inlet well is divided into curtain Hole, bridge pier injected hole and general injected hole three classes.Construction sequencing are as follows: first curtain hole, rear abutment injected hole, note as last Starch hole;First two sequences after a sequence.Using " one-step pore-creating is divided to two sections of upward groutings " technique, specific implementation step is as follows:
(1) drilling construction: it include fixed point, drilling machine installation, aperture drilling, pour orifice tube, pore-forming, pour Grouting Pipe, Seven steps of filling adaptor are installed;
1. pinpointing;Inlet well should using the measuring instruments such as RTK or total station according to engineering design hole location coordinate carry out by Design position 1.0m is not to be exceeded in point setting-out on the spot, drilling physical location in principle;
2. rigging up;Smooth location, rigging up, level rack, body, prepare drilling tool, get ready casing, drill bit and The equipment such as drilling rod, core barrel;
3. aperture is crept into;Using Φ 150mm aperture, mud off is used in Quaternary loose soils 1, drilling is bored using three wings Head is followed by core barrel, increases stiffness of twist drill, it is ensured that borehole perpendicularity is drilled into stable 2 or less 5m of basement rock;By Φ 127mm orifice tube 12 down toward away from bottom hole 10m, and using profusely welding between orifice tube 12, when welding is measured using horizontal ruler, it is ensured that is hung down between orifice tube Straight degree, pours into 1:1.5 cement paste 13 to bottom hole by pipeline, and pouring height is 10m, by orifice tube 12 before cement slurry initial set Under away from bottom hole 10m, manage and (is not less than for 24 hours) admittedly using slurry processes are sat;
5. pore-forming;After sitting slurry, variable diameter is Φ 110mm (variable diameter), is crept into using clear water, continues to be drilled into water guide and split 3 bottom of gap band, final variable diameter are Φ 91mm (secondary variable diameter), and last 20m takes core;
6. pouring Grouting Pipe;After pore-forming, tripping in Φ 48mm Grouting Pipe 9,9 pipe outer wall of Grouting Pipe binds conduit 10, conduit 10 Diameter be 20mm, the corresponding secondary variable diameter position of Grouting Pipe 9 installs steel tray 14, is located at steel tray 14) outside the Grouting Pipe 9 of lower part Wall covers rubber stoping flowing pulp plug 15, and rubber stoping flowing pulp plug 15 is close to steel tray 14;It is connected between Grouting Pipe 9 using pipe collar 17, steel tray 14 To weld floral tube 16 down toward 7 or more seat earth, 14 top 5m of steel tray pours into 1:1.5 cement paste 13 by pipeline;Conduit Spacing between 10 bottoms and steel tray 14 is 5m;
7. installing filling adaptor;Under complete Grouting Pipe 9,9 screw connector 8 of soldered vias pipe flange 11 and Grouting Pipe, drilling It checks and accepts, aperture is wrapped up to slip casting;
(2) mortar depositing construction;
1. lower section slip casting;As shown in Fig. 2, carrying out lower section slip casting, Grouting Pipe 9 and slip casting by Grouting Pipe 9 first when slip casting It is connected between pipeline 20 using pipe collar 17;Water-solid ratio uses 1:1.2, and when pressure gauge 19 reaches 2MPa, pump amount is less than 50L/min, More than 15min, which terminates, and opens relief valve 18;
2. upper section slip casting;As shown in figure 3, carrying out upper section note from orifice tube 12 and 9 gap of Grouting Pipe after lower section slip casting Slurry, upper section slip casting are connected by ring flange, clip pad piece 21 between two ring flanges, it is ensured that and good seal, water-solid ratio use 1:1, when When reaching design slip casting ending standard, which terminates.
Grouting serous fluid is cement and flying ash grout, and grout coordinate ratio is as follows: bridge pier curtain hole, cement: flyash match ratio is 2: 8, and the accelerator of cement weight 3%~5% is added;Bridge pier injected hole, cement: flyash match ratio is 3:7;General slip casting Hole, cement: flyash match ratio is 2:8;Slip casting ending standard is that grouting pressure reaches 2MPa, and pump amount is less than 50L/min, is more than 15min。
In the method for the present invention, goaf upstriker segmenting slip casting technology, ring flange, can to use floral tube down toward seat earth Influence of the collapse hole to lower section slip casting is effectively avoided, drilling utilization efficiency is improved.
Core barrel is followed by using three-wing bit, borehole perpendicularity can be increased, makes orifice tube smoothly down toward projected depth;Using Sit slurry processes, it can be ensured that good seal between orifice tube and hole wall avoids slurries when upper section slip casting from being lost from the line of demarcation Tu Yan.
Since the 4th is that overburden cover is larger, core barrel drilling (increasing stiffness of twist drill) is followed by using three-wing bit, really Protect borehole perpendicularity;Using profusely (screwed connection can also be directlyed adopt) is welded between orifice tube, measured using horizontal ruler when welding, Ensure verticality between orifice tube;Drilling is vertical, orifice tube is vertical, just can guarantee orifice tube smoothly down toward projected depth.
Grouting Pipe can be stuck in using ring flange, stop grouting plug by secondary variable diameter position and realize segmentation, water is injected by conduit Mud can further strengthen solid pipe and segmentation, it is ensured that implementation result.
Ring flange can effectively avoid influence of the collapse hole to lower section slip casting to use floral tube down toward seat earth, improve drilling Utilization efficiency.
The last 20m of bottom hole takes core, and the purpose for taking core is to avoid rock powder precipitating blocking slip casting channel, disclose key Stratum and evaluation slip casting effect.
By segmenting slip casting, the compactness of goaf filling can be significantly increased, improves slip casting uniformity, drilling is improved and utilizes Efficiency, it is ensured that goaf harnessing engineering quality.

Claims (7)

1. a kind of thick 4th is buried excavation collapse broken formation upstriker segmenting slip casting technique, which is characterized in that specifically according to Following steps are implemented:
Step 1, pore-forming, drilling open pore size are Φ 150mm, use mud off in Quaternary loose soils, are drilled into stable basement rock Following 5m pours into 1:1.5 cement paste to bottom hole by orifice tube, in cement by Φ 127mm orifice tube down toward away from bottom hole 10m By orifice tube down toward basement rock or less 5m is stablized before slurry initial set, using seat slurry processes fixed orifice pipe, Gu the pipe time is no less than for 24 hours;
Step 2, after sitting slurry, first time variable diameter is carried out, variable diameter aperture is Φ 110mm, and rock section is crept into using clear water, is continued It is drilled into water flowing fractured zone bottom, carries out second of variable diameter, variable diameter aperture is Φ 91mm, is taken within the scope of the whole above 20m of hole bottom hole Core;
Step 3, after pore-forming, rapid tripping in Grouting Pipe, Grouting Pipe pipe outer wall binds conduit, corresponding second of the variable diameter position of Grouting Pipe Steel tray is installed, for steel tray to weld floral tube more than seat earth, 3~5m of steel tray top pours into 1:1.5 by pipeline Cement paste, finally, soldered vias pipe flange and Grouting Pipe screw connector, aperture is wrapped up to slip casting;
Step 4, when slip casting, lower section slip casting is carried out by Grouting Pipe first, it is empty from orifice tube and Grouting Pipe after lower section slip casting Gap carries out upper section slip casting, until reaching the standard of end hole, slip casting terminates.
2. the according to claim 1 a kind of thick 4th is buried excavation collapse broken formation upstriker segmenting slip casting technique, It is characterized in that, before cement slurry initial set by orifice tube in hole, using slurry processes fixed orifice pipe is sat, being coagulated in the step 1 Gu the time is no less than for 24 hours, the height that pours of cement paste is 10m.
3. the according to claim 1 a kind of thick 4th is buried excavation collapse broken formation upstriker segmenting slip casting technique, It is characterized in that, the aperture Φ of orifice tube is 127mm in the step 1;Orifice tube 20cm above ground level.
4. the according to claim 1 a kind of thick 4th is buried excavation collapse broken formation upstriker segmenting slip casting technique, It is characterized in that, the aperture Φ of Grouting Pipe is 48mm, Grouting Pipe 50cm above ground level in the step 3.
5. the according to claim 1 a kind of thick 4th is buried excavation collapse broken formation upstriker segmenting slip casting technique, It is characterized in that, the slip casting pipe outer wall positioned at steel tray lower part covers rubber stoping flowing pulp plug, and rubber stoping flowing pulp plug is tight in the step 3 Paste steel tray.
6. the according to claim 5 a kind of thick 4th is buried excavation collapse broken formation upstriker segmenting slip casting technique, It is characterized in that, the internal diameter of steel tray is 50mm, outer diameter 100mm;Rubber stoping flowing pulp plug is truncated cone, big mouth diameter 100mm, osculum diameter 90mm, height 100mm.
7. the according to claim 1 a kind of thick 4th is buried excavation collapse broken formation upstriker segmenting slip casting technique, It is characterized in that, the diameter of conduit is 20mm in the step 3, the spacing between conduit bottom and steel tray is 5m.
CN201910058885.3A 2019-01-22 2019-01-22 Up-going type sectional grouting process for thick fourth-system deep-buried mining cave-in broken stratum Expired - Fee Related CN109763483B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910058885.3A CN109763483B (en) 2019-01-22 2019-01-22 Up-going type sectional grouting process for thick fourth-system deep-buried mining cave-in broken stratum

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910058885.3A CN109763483B (en) 2019-01-22 2019-01-22 Up-going type sectional grouting process for thick fourth-system deep-buried mining cave-in broken stratum

Publications (2)

Publication Number Publication Date
CN109763483A true CN109763483A (en) 2019-05-17
CN109763483B CN109763483B (en) 2021-04-23

Family

ID=66455046

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910058885.3A Expired - Fee Related CN109763483B (en) 2019-01-22 2019-01-22 Up-going type sectional grouting process for thick fourth-system deep-buried mining cave-in broken stratum

Country Status (1)

Country Link
CN (1) CN109763483B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110617029A (en) * 2019-09-16 2019-12-27 中国矿业大学 Drilling segmented retreating type grouting method
CN111238327A (en) * 2020-02-28 2020-06-05 白银有色集团股份有限公司 Method for drilling blast holes in hard rock and blasting by using blast holes
CN111663918A (en) * 2020-07-10 2020-09-15 中勘资源勘探科技股份有限公司 Coal mining ground grouting process and grouting structure
CN112282640A (en) * 2020-10-21 2021-01-29 重庆市地质矿产勘查开发局南江水文地质工程地质队 Broken stratum bare hole drilling method
CN112593543A (en) * 2020-12-18 2021-04-02 中国矿业大学(北京) Well lattice type reinforcing method for building foundation in shallow-buried thick quicksand layer subsidence area
CN114108609A (en) * 2021-09-29 2022-03-01 华北水利水电大学 Goaf multistage subsection precise filling deep pile-forming construction process and method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5992522A (en) * 1997-08-12 1999-11-30 Steelhead Reclamation Ltd. Process and seal for minimizing interzonal migration in boreholes
CN103603689A (en) * 2013-11-04 2014-02-26 葛洲坝集团基础工程有限公司 Curtain grouting construction method for treating mined-out areas
CN103924945A (en) * 2014-05-08 2014-07-16 中煤科工集团西安研究院有限公司 High-pressure grouting process of water-rich weathering fracture rock formation below thick unconsolidated formation for coal mine
CN205895289U (en) * 2016-08-19 2017-01-18 泰安振声科技工程有限公司 Slip casting anchor rope with double -deck thick liquid and spiral stirring function of ending

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5992522A (en) * 1997-08-12 1999-11-30 Steelhead Reclamation Ltd. Process and seal for minimizing interzonal migration in boreholes
CN103603689A (en) * 2013-11-04 2014-02-26 葛洲坝集团基础工程有限公司 Curtain grouting construction method for treating mined-out areas
CN103924945A (en) * 2014-05-08 2014-07-16 中煤科工集团西安研究院有限公司 High-pressure grouting process of water-rich weathering fracture rock formation below thick unconsolidated formation for coal mine
CN205895289U (en) * 2016-08-19 2017-01-18 泰安振声科技工程有限公司 Slip casting anchor rope with double -deck thick liquid and spiral stirring function of ending

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
任政: "高速公路桥梁穿越煤矿采空区基础处理措施", 《桥梁与隧道工程》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110617029A (en) * 2019-09-16 2019-12-27 中国矿业大学 Drilling segmented retreating type grouting method
CN111238327A (en) * 2020-02-28 2020-06-05 白银有色集团股份有限公司 Method for drilling blast holes in hard rock and blasting by using blast holes
CN111663918A (en) * 2020-07-10 2020-09-15 中勘资源勘探科技股份有限公司 Coal mining ground grouting process and grouting structure
CN112282640A (en) * 2020-10-21 2021-01-29 重庆市地质矿产勘查开发局南江水文地质工程地质队 Broken stratum bare hole drilling method
CN112593543A (en) * 2020-12-18 2021-04-02 中国矿业大学(北京) Well lattice type reinforcing method for building foundation in shallow-buried thick quicksand layer subsidence area
CN112593543B (en) * 2020-12-18 2021-10-08 中国矿业大学(北京) Well lattice type reinforcing method for building foundation in shallow-buried thick quicksand layer subsidence area
CN114108609A (en) * 2021-09-29 2022-03-01 华北水利水电大学 Goaf multistage subsection precise filling deep pile-forming construction process and method
CN114108609B (en) * 2021-09-29 2023-03-10 华北水利水电大学 Construction method for multistage segmented precise filling and deep pile forming in goaf

Also Published As

Publication number Publication date
CN109763483B (en) 2021-04-23

Similar Documents

Publication Publication Date Title
CN109763483A (en) A kind of thick 4th is buried excavation collapse broken formation upstriker segmenting slip casting technique
AU2020101047A4 (en) Method for filling underground cavity in bedrock by grouting and hydraulic filling device
CN108060908B (en) Long-distance horizontal directional drilling and grouting reinforcement process for water-rich sand layer under building group
CN103334770B (en) One is grown up reverse-slope tunnel ultra high water pressure rich water zone of fracture construction method
CN103821544B (en) Tunneling and underground engineering high-pressure high-flow is dashed forward Water outburst treatment method
CN101624910B (en) Method for reinforcing concealed tunnel
CN103628912B (en) The construction method of filling grouting is processed in a kind of goaf
CN109594990B (en) Large-section jacking pipe construction method for complex stratum
CN109139052B (en) Grouting hole device based on high-pressure deep hole grouting and construction method
CN103899351B (en) A kind of filling reinforcement means of processing complicated cavity
CN103603670A (en) Construction method of ultra-deep-earthed shield crossing complex formations
CN105155563A (en) Reinforcing and treating method for water burst of soft-flow muddy stratum of foundation pit
CN101793154A (en) Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes
CN106522981B (en) Pass through the method for protecting support in goaf tunnel
WO2021098444A1 (en) Technique for controlling tunneling parameters of shielded tunneling machine for rocky region at shielded tunneling launch point
CN112482364A (en) Construction process of rotary digging cast-in-place pile under strong corrosive soft geological conditions in coastal region
CN107905796A (en) A kind of tunnels in soil Guan Peng operating rooms construction method
CN111379573B (en) Connecting system for connecting shield tunnel in middle of oil and gas pipeline
WO2022117124A1 (en) Construction method for outward expansion pipe in drill hole in goaf
CN108180018A (en) A kind of shallow embedding collapsible loess tunnel Core Soil and glass bolt anchorage construction method
CN102031795A (en) Short pile reinforcing technology in narrow space
CN203161250U (en) Deep hole grouting reinforcing system for tunnel
CN105065774B (en) A kind of underground piping branch connects construction method
CN114737979B (en) Construction method for continuously passing large-diameter water conveying pipeline downwards in shield region
CN102979105A (en) Underground water control method of wellhole grouting and seepage insulation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210423

CF01 Termination of patent right due to non-payment of annual fee