CN109750684A - A kind of multi-purpose precipitation well construction and preparation method thereof - Google Patents

A kind of multi-purpose precipitation well construction and preparation method thereof Download PDF

Info

Publication number
CN109750684A
CN109750684A CN201910162465.XA CN201910162465A CN109750684A CN 109750684 A CN109750684 A CN 109750684A CN 201910162465 A CN201910162465 A CN 201910162465A CN 109750684 A CN109750684 A CN 109750684A
Authority
CN
China
Prior art keywords
well
drainage
pipe
relief
screen
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910162465.XA
Other languages
Chinese (zh)
Other versions
CN109750684B (en
Inventor
瞿成松
毛喜云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Changkai Geotechnical Engineering Co Ltd
Original Assignee
Shanghai Changkai Geotechnical Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Changkai Geotechnical Engineering Co Ltd filed Critical Shanghai Changkai Geotechnical Engineering Co Ltd
Priority to CN201910162465.XA priority Critical patent/CN109750684B/en
Publication of CN109750684A publication Critical patent/CN109750684A/en
Application granted granted Critical
Publication of CN109750684B publication Critical patent/CN109750684B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The present invention relates to a kind of multi-purpose precipitation well construction, pipe, decompression well screen are cylindrical in shape relief well in fact, same to diameter, and are sequentially connected from top to bottom, constitute relief well well casing;Pipe, drainage well screen are cylindrical in shape drainage well in fact, same to diameter, and are sequentially connected from top to bottom;Drainage well is managed in fact, the connector of drainage well screen is set in outside relief well reality pipe, and is fixedly connected with relief well reality pipe, and the annulus between relief well well casing constitutes drainage well well casing;In the wellhole opened up, the periphery in drainage well reality tube top portion is equipped with clay, drainage well screen bottom welded seal steel plate group back cover, sealing steel plate group lower part setting layering sealing material, is located at around relief well chimney filter and relief well reality pipe equipped with gravel material, layering sealing material lower part between clay and layering sealing material and is also provided with gravel material;Clay, layering sealing material, gravel material fully support wellhole.The present invention can extract multi-layer Underground Water in one-step pore-creating Cheng Jinghou hierarchical control.

Description

A kind of multi-purpose precipitation well construction and preparation method thereof
Technical field
The present invention relates to a kind of dewatering wells more particularly to a kind of multi-purpose precipitation well construction and preparation method thereof.
Background technique
At present dewatering well diving be mostly drainage well, artesian water is relief well, diving with pressure-bearing water stratification at times respectively into Row precipitation;Another kind is that combined shaft diving draws water simultaneously with artesian water.Former approach needs to carry out at well larger workload Multiple Cheng Jing, the construction period is longer, higher cost;Later approach precipitation is larger especially need to draw water to artesian water in advance, drop Water, which causes to cheat all surface subsidence, to be affected.
Summary of the invention
The object of the present invention is to provide a kind of multi-purpose precipitation well construction, one-step pore-creating reaches diving and pressure-bearing water stratification point Period is separately turned on the function of carrying out precipitation, and construction cost is smaller;It is particularly suitable for excavation face and approaches or expose artesian aquifer Top plate, the biggish engineering project of artesian water precipitation range.
The present invention takes following technical scheme:
A kind of multi-purpose precipitation well construction, including relief well reality pipe 3, drainage well reality pipe 1, drainage well screen 2, decompression well screen 4;The relief well reality pipe 3, decompression well screen 4 are cylindrical in shape, same to diameter, and are sequentially connected from top to bottom, and relief well well casing is constituted; The drainage well reality pipe 1, drainage well screen 2 are cylindrical in shape, same to diameter, and are sequentially connected from top to bottom;Drainage well reality pipe 1, drainage The connector of well screen 2 is set in outside relief well reality pipe 3, and is fixedly connected with relief well reality pipe 3, between relief well well casing Annulus constitute drainage well well casing;In the wellhole opened up, the periphery at 1 top of drainage well reality pipe is equipped with clay 7, dredges 2 bottom welded seal steel plate group of dry-well chimney filter, 6 back cover, 6 lower part of sealing steel plate group setting layering sealing material, clay 7 and layering It is located at around relief well chimney filter 4 and relief well reality pipe 3 between sealing material equipped with gravel material 8, layering sealing material lower part and also sets Set gravel material 8;Clay 7, layering sealing material, gravel material 8 fully support the wellhole.
Further, 4 lower end of decompression well screen is also connect with equal diameter sediment tube 5, is also set around sediment tube 5 There is the gravel material 8.
Further, institute's layering sealing material is sealing clay 9.
Further, water pump 10 is equipped in the decompression well screen 4, water pump 10 connects pump line 11, and pump line 11 stretches out upwards Relief well reality pipe 3.
Further, the drainage well reality pipe 1 and drainage well screen 2 protrude into air inlet 14, outlet pipe 12 from top to bottom, Air inlet 14 connects outer fan, and outlet pipe 12 is connect with vacuum tube 12, and vacuum tube 12 and the external device for providing negative pressure connect It connects.
Further, the vacuum tube 12 is also directly connected to the drainage well reality pipe 1.
A kind of production method of above-mentioned multi-purpose precipitation well construction, comprising the following steps: S1, drainage well reality pipe 1 and drainage well Chimney filter 2 is successively welded according to design length, constitutes the drainage well well casing of outer layer;Drainage well casing caliber is greater than relief well well casing caliber 50mm or more;S2, relief well reality pipe 3, decompression well screen 4 are successively welded with sediment tube 5 according to design length, constitute subtracting for internal layer Kill-job well casing;S3, the relief well well casing of the drainage well well casing of outer layer and internal layer is fixed every 2-3m, and in drainage well screen 2 6 back cover of tube bottom welded seal steel plate group, assembly welding complete entirely multi-purpose well well casing structure;S4, pore-forming, borehole cleaning, aperture are greater than The drainage well well casing caliber 100mm or more of outer layer, borehole cleaning put down the multi-purpose well well casing structure after the completion;S5, projected depth is pressed Gravel material 8 is inserted, gravel material 8 inserts 4m or more sealing clay 9 after being filled above the position of decompression well screen 4;Gravel material 8 is successively filled again And clay 7, until earth's surface;S6, drainage well well casing and relief well well casing install pumping equipment respectively, be separately turned on as needed into Capable operation of drawing water.
Further, in step S5, segmentation is stood when filling out gravel material and filling out clay, to one section of gravel material 8,7 completely densified of clay Shi Fangke carries out the filling of next section of gravel material, clay.
Further, sealing plus vacuum between inside and outside two layers of well casing, are drawn water using vacuum;Or make to be formed in drainage well Vacuum environment with air compressor machine or is put water in the small small water pump extraction phreatic aquifer of bore, is placed in the relief well well casing of internal layer Water pump 10 extract artesian aquifer in water, thus from a well difference layering carry out draw water.
Further, air inlet 14 and outlet pipe 13, air inlet 14 and outer fan are installed in drainage well screen 2 Connection, outlet pipe 13 are connect with external vacuum pump.
When the present invention is implemented: the double-deck well casing and chimney filter are set in dewatering well, and internal layer is decompression well construction, and outer layer is drainage Well construction fills sand and sealing clay according to water-bearing layer position between two layers of well casing, installs Grouting Pipe, clay in the middle part of sealing part After being backfilled to design thickness half, Grouting Pipe 2 are installed in borehole wall two sides, is symmetrically installed.Slip casting bottom of the tube is in clay backfilling thickness It spends at half, on grouting tube top to clay backfilling elevation of top face.Clay sealing layer will have certain thickness and intensity.Two Pass through the same equipment of air compressor machine well-flushing between layer well casing or put the small water pump of bore and extract water in phreatic aquifer, is put in internal layer pipe well It sets water pump and extracts water in artesian aquifer, carry out purpose of drawing water to reach and can distinguish layering from a well.Shallow-layer drainage Diving can seal plus vacuum, drawn water using vacuum or drainage well in form vacuum environment, with the same equipment of air compressor machine well-flushing Or it puts the small water pump of bore and extracts water in phreatic aquifer.
The beneficial effects of the present invention are:
1) multi-layer Underground Water can be extracted in one-step pore-creating Cheng Jinghou hierarchical control.
2) high reliablity;It is ingenious in design.
Detailed description of the invention
Fig. 1 is the schematic diagram of the multi-purpose precipitation well construction of the present invention.
Fig. 2 is A-A ' cross-sectional view in Fig. 1.
Fig. 3 is B-B ' cross-sectional view in Fig. 1.
Fig. 4 is C-C ' cross-sectional view in Fig. 1.
Fig. 5 is D-D ' cross-sectional view in Fig. 1.
Fig. 6 is the partial enlarged view of Fig. 1.
Fig. 7 is another form of implementation of the invention: using more filter structure drainage well schematic diagrames.
Fig. 8 is the manufacturing process schematic diagram of the multi-purpose precipitation well construction of the present invention.
In figure, 1. drainage wells are managed in fact, and 2. drainage well screens, 3. relief wells are managed in fact, 4. decompression well screens, 5. sediments tube, and 6. 7. clay of sealing steel plate, 8. gravel material, 9. sealing clays, 10. water pumps, 11. pump lines, 12. vacuum tubes, 13. outlet pipes, 14. air inlets Air hose.
Specific embodiment
Present invention will be further explained below with reference to the attached drawings and specific examples.
Referring to Fig. 1-Fig. 8, a kind of multi-purpose precipitation well construction, including relief well reality pipe 3, drainage well reality pipe 1, drainage well screen 2, well screen 4 is depressurized;The relief well reality pipe 3, decompression well screen 4 are cylindrical in shape, same to diameter, and are sequentially connected from top to bottom, structure At relief well well casing;The drainage well reality pipe 1, drainage well screen 2 are cylindrical in shape, same to diameter, and are sequentially connected from top to bottom;Drainage Well reality pipe 1, drainage well screen 2 connector be set in outside relief well reality pipe 3, and be fixedly connected, and subtract with relief well reality pipe 3 Annulus between kill-job well casing constitutes drainage well well casing;In the wellhole opened up, the periphery at 1 top of drainage well reality pipe Equipped with clay 7,2 bottom welded seal steel plate group of drainage well screen, 6 back cover, the setting of 6 lower part of sealing steel plate group is layered sealing material, Gravel material 8 is equipped between clay 7 and layering sealing material, layering sealing material lower part is located at relief well chimney filter 4 and relief well reality pipe 3 Around be also provided with gravel material 8;Clay 7, layering sealing material, gravel material 8 fully support the wellhole.
In this embodiment, referring to Fig. 1,4 lower end of decompression well screen is also connect with equal diameter sediment tube 5, precipitating The gravel material 8 also is provided with around pipe 5.
Referring to Fig. 1 and Fig. 7, institute's layering sealing material is sealing clay 9.
Referring to Fig. 1, water pump 10 is equipped in the decompression well screen 4, water pump 10 connects pump line 11, and pump line 11 stretches out upwards to be subtracted Kill-job reality pipe 3.
Referring to Fig. 1 and Fig. 6, the drainage well reality pipe 1 and drainage well screen 2 protrude into air inlet 14, water outlet from top to bottom Pipe 12, air inlet 14 connect outer fan, and outlet pipe 12 is connect with vacuum tube 12, the dress of vacuum tube 12 and external offer negative pressure Set connection.
Referring to Fig. 1 and Fig. 6, the vacuum tube 12 is also directly connected to the drainage well reality pipe 1.
It is detailed in Fig. 8: the production of multi-purpose precipitation well construction, comprising the following steps:
1. drainage well reality pipe 1 is successively welded with drainage well screen 2 according to design length, outer layer drainage well well casing is constituted;For The guarantee effect drainage well casing diameter that draws water should be greater than relief well caliber 50mm or more.
2. relief well reality pipe 3, decompression well screen 4 are successively welded with sediment tube 5 according to design length, internal layer drainage well is constituted Well casing;
3. fixing outer layer drainage well well casing and internal layer relief well well casing every 2-3m, and welded in 2 tube bottom of drainage well screen 6 back cover of sealing steel plate group is connect, assembly welding completes entirely multi-purpose well well casing structure;
4. pore-forming, and carry out borehole cleaning.Aperture is greater than outer layer well casing caliber 100mm or more.Downhole pipe after the completion of borehole cleaning;
5. inserting gravel material 8 by projected depth, 4m or more sealing clay 9 is inserted after the completion of the filling of gravel material 8;Gravel is successively filled again Material 8 and clay 7, until earth's surface.It need to be segmented standing when filling out gravel, next section can be carried out when gravel material (or clay) completely densified and filled out Gravel (or clay) filling.
6. installing pumping equipment, it is separately turned on carries out operation of drawing water as needed.It can be sealed between two layers of well casing and add vacuum, Drawn water using vacuum or drainage well in form vacuum environment, with the same equipment of air compressor machine well-flushing or put the small water pump of bore and take out Take water in phreatic aquifer.Water pump is placed in internal layer pipe well extracts water in artesian aquifer, it can from a well to reach Difference layering carries out purpose of drawing water.
Fig. 7 is another form of implementation of the invention: using more filter structure drainage wells, drainage well screen 2 and drainage well The setting of the real interval of pipe 1.
Similarly, for multi-layered aquifer, using three layers or even more layers similar structures well casing, layered clay ball pressurization slurry Sealing, is layered embedded filter, and observation draws water or recharge etc..
For multilayer soil layer, rock stratum etc., using multilayer similar structures well casing, shape is not limited to circle, and material is not limited to steel Pipe, is layered sealing material and mode is not limited to clay ball pressurization slurry sealing, is layered embedded Multi-channel filtering device, observation, layering Recharge etc. is drawn water or be layered, can carry out, can also implement step by step according to plan simultaneously.And so on, it is more also to can achieve a well Purpose.
It is the preferred embodiment of the present invention above, those of ordinary skill in the art can also carry out various changes on this basis It changes or improves, under the premise of not departing from the present invention total design, these transformation or improve all should belong to that the present invention claims guarantors Within the scope of shield.

Claims (10)

1. a kind of multi-purpose precipitation well construction, it is characterised in that:
Including relief well pipe (3), drainage well pipe (1), drainage well screen (2), decompression well screen (4) in fact in fact;
Pipe (3), decompression well screen (4) are cylindrical in shape the relief well in fact, same to diameter, and are sequentially connected from top to bottom, and decompression is constituted Well well casing;
Pipe (1), drainage well screen (2) are cylindrical in shape the drainage well in fact, same to diameter, and are sequentially connected from top to bottom;Drainage well is real Pipe (1), drainage well screen (2) connector be set in relief well pipe (3) be external in fact, and pipe (3) is fixedly connected in fact with relief well, Annulus between relief well well casing constitutes drainage well well casing;
In the wellhole opened up, the periphery that the drainage well manages at the top of (1) in fact is equipped with clay (7), the weldering of drainage well screen (2) bottom Connect sealing steel plate group (6) back cover, sealing steel plate group (6) lower part setting layering sealing material, clay (7) and layering sealing material it Between be equipped with gravel material (8), layering sealing material lower part is located at real manage of relief well chimney filter (4) and relief well and is also provided with gravel around (3) Expect (8);
Clay (7), layering sealing material, gravel material (8) fully support the wellhole.
2. multi-purpose precipitation well construction as described in claim 1, it is characterised in that: decompression well screen (4) lower end also with phase Equal diameter sediment tube (5) connects, and also is provided with the gravel material (8) around sediment tube (5).
3. multi-purpose precipitation well construction as described in claim 1, it is characterised in that: the layering sealing material is sealing clay (9)。
4. multi-purpose precipitation well construction as described in claim 1, it is characterised in that: be equipped with water pump in the decompression well screen (4) (10), water pump (10) connection pump line (11), pump line (11) stretch out relief well pipe (3) in fact upwards.
5. multi-purpose precipitation well construction as described in claim 1, it is characterised in that: drainage well pipe (1) and the filter of drainage well in fact Pipe (2) protrudes into air inlet (14), outlet pipe (12) from top to bottom, and air inlet (14) connects outer fan, outlet pipe (12) It is connect with vacuum tube (12), vacuum tube (12) is connect with the external device for providing negative pressure.
6. multi-purpose precipitation well construction as claimed in claim 4, it is characterised in that: the vacuum tube (12) is also directly dredged with described Dry-well pipe (1) connection in fact.
7. a kind of production method of precipitation well construction multi-purpose as described in claim 1, which comprises the following steps:
Pipe (1) is successively welded with drainage well screen (2) according to design length in fact for S1, drainage well, constitutes the drainage well well casing of outer layer; Drainage well casing caliber is greater than relief well well casing caliber 50mm or more;
Pipe (3), decompression well screen (4) are successively welded with sediment tube (5) according to design length in fact for S2, relief well, constitute internal layer Relief well well casing;
S3, the relief well well casing of the drainage well well casing of outer layer and internal layer is fixed every 2-3m, and in drainage well screen (2) tube bottom Welded seal steel plate group (6) back cover, assembly welding complete entirely multi-purpose well well casing structure;
S4, pore-forming, borehole cleaning, aperture are greater than the drainage well well casing caliber 100mm or more of outer layer, put down after the completion of borehole cleaning described multi-purpose Well well casing structure;
S5, gravel material (8) are inserted by projected depth, filling 4m or more stops after gravel material (8) is filled above the position of decompression well screen (4) Water clay (9);Gravel material (8) and clay (7) are successively filled again, until earth's surface;
S6, drainage well well casing and relief well well casing install pumping equipment respectively, are separately turned on carry out operation of drawing water as needed.
8. the production method of multi-purpose precipitation well construction as claimed in claim 6, it is characterised in that: in step S5, fill out gravel material and When filling out clay segmentation is stood, and next section of gravel material can be carried out when one section of gravel material (8), clay (7) completely densified, clay is filled out It fills.
9. the production method of multi-purpose precipitation well construction as claimed in claim 6, it is characterised in that: close between inside and outside two layers of well casing Envelope plus vacuum, are drawn water using vacuum;Or make to form vacuum environment in drainage well, with air compressor machine or put the small small water pump pumping of bore Water in phreatic aquifer is taken, water pump (10) is placed in the relief well well casing of internal layer and extracts water in artesian aquifer, thus from flatly Difference layering draw water in well.
10. the production method of multi-purpose precipitation well construction as claimed in claim 8, it is characterised in that: peace in drainage well screen (2) Dress air inlet (14) and outlet pipe (13), air inlet (14) are connect with outer fan, outlet pipe (13) and external vacuum pump Connection.
CN201910162465.XA 2019-03-05 2019-03-05 Multipurpose dewatering well structure and manufacturing method thereof Active CN109750684B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910162465.XA CN109750684B (en) 2019-03-05 2019-03-05 Multipurpose dewatering well structure and manufacturing method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910162465.XA CN109750684B (en) 2019-03-05 2019-03-05 Multipurpose dewatering well structure and manufacturing method thereof

Publications (2)

Publication Number Publication Date
CN109750684A true CN109750684A (en) 2019-05-14
CN109750684B CN109750684B (en) 2024-03-26

Family

ID=66406786

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910162465.XA Active CN109750684B (en) 2019-03-05 2019-03-05 Multipurpose dewatering well structure and manufacturing method thereof

Country Status (1)

Country Link
CN (1) CN109750684B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112983428A (en) * 2021-02-20 2021-06-18 上海市政工程设计研究总院(集团)有限公司 Method for building underground water environment monitoring well
CN115305901A (en) * 2022-08-16 2022-11-08 中交第四公路工程局有限公司 Directional recharge and emergency pumping well

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102518141A (en) * 2011-12-19 2012-06-27 同济大学 Deep foundation pit dewatering and decompressing combination well controlled in subsection manner
JP2012241383A (en) * 2011-05-18 2012-12-10 Penta Ocean Construction Co Ltd Ground improvement method and decompression container
CN202809629U (en) * 2012-08-29 2013-03-20 上海长凯岩土工程有限公司 Pressure-reduction and dewatering supplementary well completion structure in disturbance stratum inside foundation pit
CN107489159A (en) * 2017-08-03 2017-12-19 中国电建集团铁路建设有限公司 Deep & thick silt matter Soft Soil Layer vacuum tube well dewatering construction structure and its construction
CN210140838U (en) * 2019-03-05 2020-03-13 上海长凯岩土工程有限公司 Multi-purpose precipitation well structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012241383A (en) * 2011-05-18 2012-12-10 Penta Ocean Construction Co Ltd Ground improvement method and decompression container
CN102518141A (en) * 2011-12-19 2012-06-27 同济大学 Deep foundation pit dewatering and decompressing combination well controlled in subsection manner
CN202809629U (en) * 2012-08-29 2013-03-20 上海长凯岩土工程有限公司 Pressure-reduction and dewatering supplementary well completion structure in disturbance stratum inside foundation pit
CN107489159A (en) * 2017-08-03 2017-12-19 中国电建集团铁路建设有限公司 Deep & thick silt matter Soft Soil Layer vacuum tube well dewatering construction structure and its construction
CN210140838U (en) * 2019-03-05 2020-03-13 上海长凯岩土工程有限公司 Multi-purpose precipitation well structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112983428A (en) * 2021-02-20 2021-06-18 上海市政工程设计研究总院(集团)有限公司 Method for building underground water environment monitoring well
CN112983428B (en) * 2021-02-20 2023-03-14 上海市政工程设计研究总院(集团)有限公司 Method for building underground water environment monitoring well
CN115305901A (en) * 2022-08-16 2022-11-08 中交第四公路工程局有限公司 Directional recharge and emergency pumping well
CN115305901B (en) * 2022-08-16 2024-05-28 中交第四公路工程局有限公司 Directional recharging and emergency pumping well

Also Published As

Publication number Publication date
CN109750684B (en) 2024-03-26

Similar Documents

Publication Publication Date Title
CN100480475C (en) Controllable one-well lamina precipitation construction method
CN100464055C (en) Construction method of shallow buried underground excavating tunnel super large section using PBA method
CN103031850B (en) Low-permeability sludge claypan ultra-vacuum dual-pipe unwatering well and construction technology
CN205369282U (en) Well point dewatering of sluice construction usefulness
CN104594327B (en) A kind of Ground Water Pumping during Excavation Bao Quan recharges integrated apparatus
CN102383412A (en) Construction method by adopting dewatering and water recharging to control sedimentation surrounding deep foundation pit
CN110318410A (en) A kind of deep basal pit chance artesian water is prominent to gush decompression drought stress construction method
CN110055987A (en) A kind of rich water mobile sand layer foundation pit tool-type dewatering well device
CN109750684A (en) A kind of multi-purpose precipitation well construction and preparation method thereof
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN206438526U (en) Deep basal pit tube well dewatering equipment
CN114606964A (en) Foundation pit dewatering method used under complex geological condition
CN109441355A (en) Silt or sand bed pipe well high pressure water flushing fast pore-creating construction method
CN205502044U (en) Be applied to precipitation structure in grittiness water -bearing stratum under building
CN206129244U (en) Colliery water resources regionalization is mining system in advance
CN203007963U (en) Ultra-high vacuum double-pipe drained well at low-permeability silt clay course
CN110130377A (en) Combined shaft and application are shared for the double plate water isolation types of foundation pit drainage-decompression inward turning
CN210140838U (en) Multi-purpose precipitation well structure
CN110878557B (en) Layered bidirectional drainage method for foundation pit dewatering
CN106894429B (en) Base pit engineering soft soil foundation is layered dewatering construction structure and construction method
CN106988330A (en) Soft soil foundation is layered dewatering construction structure and construction method
CN207211172U (en) Deep & thick silt matter Soft Soil Layer vacuum tube well dewatering construction structure
CN111851548A (en) Dewatering inclined shaft in deep foundation pit and construction method thereof
CN219219076U (en) Light well point dewatering well structure integrating pumping pipe well and well sealing section
CN102304924B (en) Non-resource-exploitation dewatering construction method and dewatering well

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant