CN109736175A - A kind of factories and miness rock salt road and its construction method - Google Patents

A kind of factories and miness rock salt road and its construction method Download PDF

Info

Publication number
CN109736175A
CN109736175A CN201811593704.9A CN201811593704A CN109736175A CN 109736175 A CN109736175 A CN 109736175A CN 201811593704 A CN201811593704 A CN 201811593704A CN 109736175 A CN109736175 A CN 109736175A
Authority
CN
China
Prior art keywords
rock salt
road
roadbed
road surface
rock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811593704.9A
Other languages
Chinese (zh)
Inventor
马宝财
赵得元
王占录
冯博博
崔国强
张红玉
李章峰
王林青
郭付平
鲍虎
黄志刚
王辉军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qinghai Salt Lake Industry Co Ltd
Original Assignee
Qinghai Salt Lake Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qinghai Salt Lake Industry Co Ltd filed Critical Qinghai Salt Lake Industry Co Ltd
Priority to CN201811593704.9A priority Critical patent/CN109736175A/en
Publication of CN109736175A publication Critical patent/CN109736175A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Road Paving Structures (AREA)

Abstract

The present invention provides a kind of factories and miness rock salt road and its construction method, including, original ground is rolled into smooth S1;It is laid with rock salt on the original ground and rolls, to form rock salt roadbed S2;It is laid with rock salt at the top of the rock salt roadbed and rolls, to form rock salt road surface S3.According to the technique and scheme of the present invention, road is built using rock salt, gathered materials on the spot, reduce road construction and the investment of raw material and cost;The rock salt road performance built is stablized, and is not easy to collapse, and safety is good, and safeguards simple;Rock salt road after construction meets construction reference, and application effect is preferable, meets actual shipment needs.

Description

A kind of factories and miness rock salt road and its construction method
Technical field
This patent disclosure relates generally to constructing road fields, build technology more particularly, to a kind of factories and miness rock salt road.
Background technique
The soil property in the Cha Er Han Salt Lake area in the Caidamu Basin is chlorine saline soil soil property, object in the mining area to guarantee this area The transport of the resources such as money, mineral products needs to build reliable, safe factories and mines road.Qinghai Salt Lake Industry Co., Ltd. mining area Positioned at this area, mining area area is up to 5856 sq-kms, and mining area area is big, the distribution of Area Mining (adopting halogen) point is more, so Sand-gravel surface is built on big area or asphalt concrete pavement investment is too high.And the roadbed of Cha Er Han is chlorine saline soil Soil property, roadbed is unstable after building asphalt concrete pavement above the chlorine saline soil, and after encountering fresh water, fresh water is by villaumite stain Soil dissolution finally results in roadbed collapse.When carrying out roadbed filling according to materials such as slabstone, rubble, cobble, sand horsestones, this work Journey amount is bigger, and it is beyond measure to transport the above material progress construction road cost of investment apart from Golmud 60km for Cha Er Han. There is problem above mostly positioned at the mining area of Salt Lake Area, therefore, it is particularly significant to build reliable and stable road.
Summary of the invention
Based on problem above, it is an object of the invention to overcome in the prior art, Salt Lake Area constructing road is at high cost, road The defects of base easily collapses provides a kind of factories and miness rock salt road and its construction method.
According to the first aspect of the invention, a kind of construction method of factories and miness rock salt road is provided, including, original ground is ground Flatten S1;It is laid with rock salt on the original ground and rolls, to form rock salt roadbed S2;It is spread at the top of the rock salt roadbed If rock salt simultaneously rolls, to form rock salt road surface S3.
Optionally, the rock salt is derived from the rock salt of 0~100cm of salt lake earth's surface or less;By the rock salt be broken into partial size≤ The salt block of 15cm is used for laying road.
Optionally, described smooth S1 is rolled on original road surface to further include, solution cavity rock salt is backfilled and pressed after finding solution cavity It is real.
It is optionally, described that smooth S1 is rolled on original road surface includes original ground compacting factor >=92%.
Optionally, be laid with and rock salt and roll on the original ground, include to form rock salt roadbed S2, carry out one layer or Rock salt described in multilayer is laid with;Loose laying depth≤50cm of every layer of rock salt, is then rolled, to form the rock salt road Base;Rock salt subgrade compaction coefficient >=93%.
Optionally, every layer of rock salt spills saturated bittern consolidation after the completion of rolling, and spills saturated bittern at least 3 times;Until grinding Pressure thickness reaches 80~100cm.
Optionally, it is laid with rock salt at the top of the rock salt roadbed and rolls, includes to form rock salt road surface S3, in the salt Loose laying depth is the rock salt of 30~50cm at the top of rock roadbed, and is rolled and shaping;It is described to roll compacting factor >=93%;It is whole Saturated bittern is spilt after the completion of shape to be conserved, and is spilt saturated bittern at least 5 times, to form the rock salt road surface;The rock salt road surface Hard shell rock salt road surface is formed after spontaneous nucleation on the 7th.
Optionally, side slope is built in the two sides on the rock salt roadbed and the rock salt road surface, by the slope of the side slope than control It is made as 1:1.5~1:3S4.
Optionally, road shoulder is built at the both sides edge on the rock salt road surface, on the original road of rock salt roadbed two sides Banket, gutter S5 are built on face.
Optionally, the width of the road shoulder is 0.2m;Width >=2m of the banket.
According to the second aspect of the invention, a kind of factories and miness rock salt road, including rock salt roadbed, rock salt road surface are provided, it is described Rock salt roadbed is layed on original ground;The rock salt road surfacing is in rock salt roadbed top.
Optionally, the rock salt road surface by one of rock salt and saturated bittern or a variety of forms;The rock salt roadbed by At least one layer of one of rock salt and the saturated bittern or a variety of compositions;The thickness of the rock salt roadbed reaches 80~ 100cm。
Optionally, the rock salt is derived from the rock salt of 0~100cm of salt lake earth's surface or less;The rock salt be broken into partial size≤ The salt block of 15cm, for being laid with the rock salt roadbed or the rock salt road surface.
Optionally, the rock salt road surface is hard shell rock salt road surface.
It optionally, further include side slope, the side slope is built in the two sides of the rock salt roadbed and the rock salt road surface;It is described The slope ratio of side slope is 1:1.5~1:3.
It optionally, further include road shoulder, banket, gutter, the road shoulder is located at the both sides edge on the rock salt road surface, The width of the road shoulder is 0.2m;The banket is built on the original road surface of the two sides of the rock salt roadbed, the slope protection Width >=the 2m in road;It builds on the original road surface beside the banket in the gutter.
The present invention has the advantages that
1) according to the technique and scheme of the present invention, build road using rock salt, gather materials on the spot, reduce road construction investment and Cost;
2) the rock salt road performance according to the technique and scheme of the present invention, built is stablized, and is not easy to collapse, and safeguards simple.
Detailed description of the invention
Fig. 1 shows a kind of schematic diagram of factories and miness rock salt road according to the present invention.
Fig. 2 shows a kind of flow charts of the construction method of factories and miness rock salt road according to the present invention.
Fig. 3 shows solution cavity schematic diagram according to the present invention.
Fig. 4 shows the schematic diagram that a kind of build according to the present invention has the factories and miness rock salt road of side slope.
Fig. 5 shows a kind of flow chart of the construction method of factories and miness rock salt road as shown in Figure 4.
Fig. 6 shows a kind of embodiment flow chart of the construction method of factories and miness rock salt road according to the present invention.
Fig. 7 shows a kind of embodiment schematic diagram of factories and miness rock salt road according to the present invention.
Specific embodiment
The preferred embodiments of the present invention will be described in detail with reference to the accompanying drawing, and reference label refers to the group in the present invention Part, technology, realizing under appropriate circumstances so as to advantages and features of the invention can be easier to be understood.Following description is pair The materialization of the claims in the present invention, and other specific implementations not clearly stated relevant to claim also belong to power The range that benefit requires.
Fig. 1 shows a kind of schematic diagram of factories and miness rock salt road according to the present invention.
It may include rock salt roadbed 1, rock salt road surface 2, the rock salt as shown in Figure 1, providing a kind of factories and miness rock salt road Roadbed 1 is layed on original ground 3;The rock salt road surface 2 is layed in 1 top of rock salt roadbed.
The original ground 3 refers to the dirt road without filling or excavating.Roadbed is straight by what is fill or excavated and formed Connect the structure of supporting track, also referred to as route substructure.The material of traditional construction roadbed, no matter filling out or digging, mainly native stone Class discrete material is often subject to the invasion and destruction of the variation of the natural conditions such as geology, water, rainfall, weather, earthquake, resistivity Difference.Therefore, roadbed should have enough robustnesses, stability and durability.Road surface refers to various road-making material makings in road The structure of vehicular load is directly born on the roadbed of road.The second best in quality road surface should have enough intensity and good stability, Its surface should reach smooth, closely knit and antiskid requirement.
A kind of embodiment according to the present invention, the rock salt road surface 2 can by one of rock salt and saturated bittern or A variety of compositions;The rock salt roadbed 1 by least one layer of one of the rock salt and the saturated bittern or a variety of can form. For example, the rock salt road surface 2 can only include rock salt, it also may include rock salt and saturated bittern composition.The rock salt roadbed 1 can To be made of one layer of rock salt or one layer of rock salt and the saturated bittern;It can also be made of multilayer, every layer all includes The rock salt or every layer all include that the rock salt and the saturated bittern form.Optionally, the thickness of the rock salt roadbed 1 It can achieve 80~100cm.
The rock salt refers to that strong evaporation from land, the plate that saturated brine Step crystallization is formed are passed through in salt lake for a long time Shape crystalline solid is the distinctive substance in Salt Lake Area.The saturated bittern refers to that, by being concentrated by evaporation, density reaches 1199.5kg/ m3~1209.6kg/m3Aqueous solution;Its main chemical compositions be include K+、Na+、Mg+、Cl-—H2The quaternary water salt of O composition is flat Weighing apparatus system.
Optionally, the rock salt is derived from the rock salt of 0~100cm of salt lake earth's surface or less;The rock salt be broken into partial size≤ The salt block of 15cm, for being laid with the rock salt roadbed 1 or the rock salt road surface 2.The rock salt roadbed 1 or the rock salt road surface 2 Total salinity >=75% of the rock salt of filler.The rock salt can first use Mechanical Crushing, including automation is crushed or hand Dynamic Mechanical Crushing, crushing plant may include jaw crusher, gyratory crusher, gyratory crusher, hammer mill, roll-type Crusher, impact breaker, impact crusher etc..The rock salt facilitates use by being broken into partial size≤15cm salt block In required road laying or fill.
A kind of embodiment according to the present invention, the rock salt road surface 2 are hard shell rock salt road surface.Hard shell rock salt road surface Hardness is larger, bearing capacity is strong, performance is stable, and safeguards simple.
Fig. 2 shows a kind of flow charts of the construction method of factories and miness rock salt road according to the present invention.
As shown in Fig. 2, a kind of construction method of factories and miness rock salt road is provided, including, original ground is rolled into smooth S1;? It is laid with rock salt on the original ground and rolls, to form rock salt roadbed S2;It is laid with rock salt at the top of the rock salt roadbed and grinds Pressure, to form rock salt road surface S3.
A kind of construction method of factories and miness rock salt road according to the present invention, first can by original ground, such as dirt road, into Row rolls, and can roll repeatedly, to achieve the purpose that surfacing and construction reference.Optionally, rolling to original ground can be with Reach original ground compacting factor >=92%, at this point it is possible to meet construction reference, to lay a solid foundation to pave the way.To primitively Rolling for face is the basis paved the way, and subsequent step of paving the way will be unfolded on this basis, therefore, rolls matter to original road surface Amount is directly related to the roadbed paved the way the even quality on road surface.
Described roll refers to through external force change object form, certain object is made to generate the deformed state of " flat ".For example, can To carry out grinding operation by road roller, vibrated roller, bull-dozer, sheep-foot roller etc..The basic principle rolled can be first light It shakes after heavy afterwards, first quiet, first low rear high, first slow rear fast, wheelmark is overlapped.The method rolled can be using roll, vibratile compacter Tool rolls, shakes and make that foundation soil is closely knit, intensity improves, compressibility reduces, back and forth thus the one kind for handling ground Densification process.
Then it can be gathered materials using bull-dozer, i.e., concentrated the filler of each size, to prevent thickness from isolating;Then make Feeding is carried out to roadbed with excavator.Optionally, roadbed filling can be using the rock salt of 0~100cm below the earth's surface of salt lake;It can be with The rock salt is broken into partial size≤15cm salt block, is used for laying road.The rock salt of the laying road filler always contains Salt amount >=75%.The broken method and apparatus of the rock salt has been combined Fig. 1 and is illustrated, and details are not described herein again.
Optionally, it is laid with rock salt on the original ground and rolls, may include carrying out one to form rock salt roadbed S2 Rock salt described in layer or multilayer is laid with;Loose laying depth≤50cm of every layer of rock salt, is then rolled, to form the rock salt Roadbed;Rock salt subgrade compaction coefficient >=93%.
The rock salt roadbed can be one layer of rock salt of progress and be laid with, that is, pine one layer of rock salt of paving, Song Puhou Then degree can be rolled with≤50cm, form the rock salt roadbed when rolling compacting factor >=93%.
The rock salt roadbed can also carry out being laid with for rock salt described in multilayer.Wherein, after every layer of rock salt of pine paving, It is rolled, then carries out the pine paving of next layer rock salt again, rolled again;It repeats operation after being laid with multilayer rock salt Reach construction reference, to form the rock salt roadbed, rock salt subgrade compaction coefficient >=93%.Wherein, every layer of rock salt Loose laying depth can be with≤50cm, loose laying depth is excessive to be not easy to be compacted, and the too small needs of loose laying depth, which increase, is laid with the number of plies, influences to apply Work efficiency fruit and efficiency.
The pine paving refers to the laying of the material without compacting.According to the technique and scheme of the present invention, the pine paving refers to straight It connects and is laid with the rock salt, piled up without operation, the rock salt such as rolling in fluffy.The loose laying depth refers to without compacting Layer thickness.With various distinct methods pave any material when, compactness is often significantly less than reaching after rolling Provide compactness.
The compacting factor refers to dry density of the roadbed through actually reaching with the sample that is obtained by compaction test most The ratio K of big dry density.The compaction quality of roadbed is indicated with construction compaction K (%).Compacting factor shows to be compacted closer to 1 Quality requirement is higher.It is optimum moisture content there are also being exactly the corresponding water content of maximum dry density, rather than minimum moisture content.Pressure The effect of real soil matrix is to improve the compactness of the soil body, reduces the water penetration of the soil body, reduce the lifting height of capillary water, to prevent Moisture accumulation causes soil matrix to soften with corroding, or causes inhomogeneous deformation because slurry is swollen.Compaction theory is to utilize machinery Method come change soil structure, with achieve the purpose that improve soil matrix strength and stability.Compacting to soil matrix is by rolling behaviour What work was realized.
Optionally, every layer of rock salt spills saturated bittern consolidation after the completion of rolling, and spills saturated bittern at least 3 times;Until grinding Pressure thickness reaches 80~100cm.
The rock salt roadbed either passes through one layer of rock salt and is laid with, or be laid with by rock salt described in multilayer and At, saturated bittern can be spilt after the completion of every layer of rock salt rolls, so that this layer of rock salt consolidation, and every layer is spilt saturated bittern Number be at least 3 times.The composition of the saturated bittern is illustrated in conjunction with Fig. 1, and details are not described herein again.
When carrying out the laying of rock salt described in multilayer, the laying of every layer of rock salt may pass through pine and spread, rolls, spill saturation halogen The step of water, until forming rock salt roadbed when rock salt thickness described in multilayer after rolling reaches 80~100cm, meeting construction mark Until quasi- and requirement.
Or according to construction requirement and road construction demand, it is only necessary to it is laid with one layer of rock salt roadbed, spread, roll by pine, Spill saturated bittern consolidation, rock salt subgrade compaction coefficient >=93%.Loose laying depth can be with≤50cm, after the rolling of formation Roadbed thickness≤50cm;It can also be larger so that rolling rear thickness disposably reaches 80~100cm.
The consolidation refers to the process of that unconsolidated sediment is changed into consolidated rock, also known as consolidation.Spilling saturated bittern makes Rock salt roadbed consolidation is realized by recrystallization.The recrystallization refers to that mineralogical composition borrows dissolution, local dissolution And the effects of solid diffusion and rearrange the process of combination.Recrystallization can make soft deposit be transformed into consolidation Rock, the primary structure construction of deposit can be destroyed, form new structure construction.Granular size, shape such as deposit And arrangement mode etc., it can go to pot because of recrystallization, thin thin stratification can also disappear because mineral recrystallize, to increase institute State the hardness and stability of rock salt roadbed.
Optionally, it is laid with rock salt at the top of the rock salt roadbed and rolls, may include to form rock salt road surface S3, in institute It states loose laying depth at the top of rock salt roadbed and is the rock salt of 30~50cm, and rolled and shaping;It is described roll compacting factor >= 93%;Saturated bittern is spilt after the completion of shaping to be conserved, and is spilt saturated bittern at least 5 times, to form the rock salt road surface;The salt Rock road surface forms hard shell rock salt road surface after spontaneous nucleation on the 7th.
After the completion of the rock salt roadbed is built, rock salt road surface can be built at the top of the rock salt roadbed.Specific side Method includes that the pine paving rock salt at the top of the rock salt roadbed, loose laying depth is 30~50cm.Road surface is generally smaller than the thickness of roadbed, Therefore the loose laying depth used is 30~50cm.Then it is rolled, carries out shaping after rolling compacting factor >=93%, shaping is complete Saturated bittern is spilt after to be conserved.The shaping refer to fragmentary rock salt without compacting or other sundries in road pavement etc. into Row cleaning, and road pavement is struck off and edge is renovated etc., so that road surface keeps smooth.Spill saturated bittern at least 5 The secondary consolidation effect to guarantee the rock salt road surface.The rock salt road surface can also be spread by multilayer rock salt according to actual needs If every layer of rock salt, which is laid with, repeats aforesaid operations.The rock salt road surface can form hard shell after spontaneous nucleation by least 7 days Rock salt road surface.Hard shell rock salt road surface has the characteristics that bearing capacity is strong, stable and firm, and safeguards simply, such as need to only spill full It is conserved with brine.
According to the technique and scheme of the present invention, adaptation to local conditions, gather materials on the spot, raw material and construction cost are lower, the salt after construction Rock road effect is preferable, meets construction reference, meets actual shipment needs.
Fig. 3 shows solution cavity schematic diagram according to the present invention.
Before building factories and miness rock salt road according to the present invention, it usually needs soil investigation, soil exploration is carried out, if in soil investigation, soil exploration Find that perhaps lapies 4 can be by 4 top of the solution cavity or lapies just like solution cavity shown in Fig. 3 under original road surface 3 in the process Road surface excavates, and backfills solution cavity or lapies 4 with rock salt and is compacted, then carries out the construction of rock salt roadbed 1 and rock salt road surface 2 again. If solution cavity or lapies 4 do not backfill, it may cause the serious consequence of Subgrade Subsidence, directly affect road quality and safety.Institute It states solution cavity or lapies 4 refers to road surface part cavity formed below.
During building rock salt roadbed 1 and road surface 2, if it has also been found that the rock salt roadbed 1 or the rock salt road There are solution cavity or lapies 4 in face 2, also should backfill and be compacted in time, to guarantee road quality and safety.
Fig. 4 shows the schematic diagram that a kind of build according to the present invention has the factories and miness rock salt road of side slope.
As shown in figure 4, a kind of factories and miness rock salt road according to the present invention can also include side slope 5, the side slope 5 build in The two sides of the rock salt roadbed 1 and the rock salt road surface 2;The slope ratio of the side slope 5 is 1:1.5~1:3.
The side slope 5 refers to guarantee subgrade stability, in the slope surface with certain slope that roadbed two sides are made into.Side slope 5 can be needed to build sloping by construction, can also build into stairstepping.
The gradient of the side slope 5 refers to the ratio between height and the width 5 of side slope 5.
Fig. 5 shows a kind of flow chart of the construction method of factories and miness rock salt road as shown in Figure 4.
As shown in figure 5, a kind of construction method of factories and miness rock salt road as shown in Figure 4, can also be included in the rock salt Side slope 5 is built in the two sides on roadbed 1 and the rock salt road surface 2, and the slope ratio of the side slope 5 is controlled as 1:1.5~1:3S4.
It in the rock salt roadbed 1 and after the completion of building of the rock salt road surface 2, caves in order to prevent, guarantees construction safety, When filling height is more than certain limit, the side slope 5 with certain slope can be made at its edge.The side slope 5 can be used Rock salt is filled, and can also be consolidated and be conserved spilling saturated bittern after overcompaction.
The gradient is too small, increases expenditure;It is excessive and dangerous.So the gradient of side slope 5 should be according to filling height, filler material Fact with underground water is determined.According to actual practice experience, the rock salt road built according to the technique and scheme of the present invention, such as Fruit builds side slope 5, and slope ratio, which may be controlled to 1:1.5~1:3, to be advisable.It both ensure that the stabilization of roadbed and the safety of road in this way, Also it controls and builds spending.
Fig. 6 shows a kind of embodiment flow chart of the construction method of factories and miness rock salt road according to the present invention.
As shown in fig. 6, a kind of embodiment of the construction method of factories and miness rock salt road according to the present invention, can also include Road shoulder is built at both sides edge on the rock salt road surface, built on the original road surface of the rock salt roadbed two sides banket, Gutter S5.
The road shoulder refers to that being located at driveway outer rim has the band-like portions of one fixed width to pavement edge, including hard Road shoulder and protectiveness road shoulder, to keep function and the temporary parking of driveway to use, and the lateral support as road surface.Build road The main function of shoulder may include: the stabilization for protecting the primary structures such as runway;For generation mechanical breakdown or an emergency situation is encountered Vehicle need temporary parking provide position;Lateral clearance is provided, safety is conducive to, increases comfort;For pedestrian, bicycle It is current;Position is provided for setting road facility;Work-yard as maintenance operations;Under the premise of not damaging highway construction, Also it can be used as the position of embedded underground installation;Improve the bend sighting distance in excavation section, promotes traffic safety etc..Optionally, described The width of road shoulder can be 0.2m.
Banket is that rock salt roadbed is protected by normal erosion, not guarantee a kind of measure of the rock salt subgrade stability, can be with It builds on the original road surface of rock salt roadbed bottom, along the line to the platform for retaining or building up one fixed width.It can also work as When side slope is built in the two sides of the rock salt roadbed, to guarantee stability of slope, between original road surface and side slope slope foot, or in side slope Banket is built in slope surface.Setting can widen side slope transfer in this way, slow down side slope mean inclination.Banket is wider, more favorably In stability of slope, but project amount increases therewith.The rock salt road built according to the technique and scheme of the present invention, to guarantee the rock salt The safety and stabilization of roadbed or the side slope, the width of the banket can be set to >=2m.
The gutter refers to that the water for collecting place low-lying near roadbed guides the ditch other than roadbed into.The gutter The original road surface that the both ends or lower one end in banket can be built, can be built in a manner of excavation, to exclude cannot The rainwash of receiving.The terminal in the gutter can connect reservoir or free drainage road.
Fig. 7 shows a kind of embodiment schematic diagram of factories and miness rock salt road according to the present invention.
As shown in fig. 7, a kind of embodiment of factories and miness rock salt road according to the present invention, can also include road shoulder 6, slope protection Road 7, gutter 8, the road shoulder 6 are located at the both sides edge on the rock salt road surface 2, and the width of the road shoulder 6 is 0.2m;It is described Banket 7 is built on the original road surface 3 of the two sides of the rock salt roadbed 1, width >=2m of the banket 7;The draining Ditch 8 is built on the original road surface 3 on 7 side of banket.
The factories and miness rock salt road of the embodiment has combined the construction method of Fig. 6 to be illustrated, and details are not described herein again.
Embodiment 1: building a kind of factories and miness rock salt road as shown in Figure 7, and specific construction method is as follows: by original ground 3 Roll smooth, 3 compacting factor >=92% of original ground;Multilayer rock salt is laid on the original ground 3, every layer of rock salt Loose laying depth≤50cm, is then rolled, rock salt subgrade compaction coefficient >=93%, after the completion of every layer of rock salt rolls Saturated bittern consolidation is spilt, is spilt saturated bittern at least 3 times, until rolling thickness reaches 80~100cm, to form rock salt roadbed 1;? The 1 top loose laying depth of rock salt roadbed is the rock salt of 30~50cm, and is rolled, and carries out after rolling compacting factor >=93% Shaping is spilt saturated bittern after the completion of shaping and is conserved, spilt saturated bittern at least 5 times, to form the rock salt road surface 2;It is described Rock salt road surface 2 forms hard shell rock salt road surface after spontaneous nucleation on the 7th;The two of the rock salt roadbed 1 and the rock salt road surface 2 Side slope 5 is built in side, and the slope ratio of the side slope 5 is controlled as 1:1.5~1:3;It builds at both sides edge on the rock salt road surface 2 Road shoulder 6, the width of the road shoulder 6 are 0.2m;Banket 7 and draining are built on the original road surface 3 of 1 two sides of rock salt roadbed Ditch 8, width >=2m of the banket 7.The rock salt is derived from the rock salt of 0~100cm of salt lake earth's surface or less;The rock salt is broken It is broken into partial size≤15cm salt block, is used for laying road;Total salinity >=75% of the rock salt.
Table 1
Table 2
Table 1 shows a kind of construction for the factories and miness rock salt road as shown in Figure 7 built according to the construction method of embodiment 1 Qualitative data and standard scale, table 2 show subgrade compaction data and standard scale.The factories and miness built according to the technique and scheme of the present invention Rock salt road, either construction quality or subgrade compaction data meet construction reference, and road application effect is preferable
The present invention has the advantages that
1) road according to the technique and scheme of the present invention, is built using rock salt, is gathered materials on the spot, road construction and original are reduced The investment and cost of material;
2) the rock salt road performance according to the technique and scheme of the present invention, built is stablized, and is not easy to collapse, and safety is good, and ties up Shield is simple;
3) the hard shell rock salt road surface that the rock salt road according to the technique and scheme of the present invention, built is formed have bearing capacity it is strong, It consolidates, conserve the features such as simple;
4) according to the technique and scheme of the present invention, the rock salt road after construction meets construction reference, and application effect is preferable, meets Actual shipment needs.
It should be noted that the above-mentioned embodiments illustrate rather than limit the invention, and this Field technical staff can be designed alternative embodiment without departing from the scope of the appended claims.In claim In, any reference symbol between parentheses should not be configured to limitations on claims.

Claims (10)

1. a kind of construction method of factories and miness rock salt road, including,
Original ground is rolled into smooth (S1);
It is laid with rock salt on the original ground and rolls, to form rock salt roadbed (S2);
It is laid with rock salt at the top of the rock salt roadbed and rolls, to form rock salt road surface (S3).
2. according to the method described in claim 1, wherein, rock salt being laid on the original ground and is rolled, to form rock salt Roadbed (S2) includes,
One or more layers described rock salt is carried out to be laid with;
Loose laying depth≤50cm of every layer of rock salt, is then rolled, to form the rock salt roadbed;
Rock salt subgrade compaction coefficient >=93%.
3. according to the method described in claim 2, further include,
Every layer of rock salt spills saturated bittern consolidation after the completion of rolling, spill saturated bittern at least 3 times;
Until rolling thickness reaches 80~100cm.
4. according to the method described in claim 1, wherein, rock salt being laid at the top of the rock salt roadbed and is rolled, with forming salt (S3) includes on rock road surface,
Loose laying depth is the rock salt of 30~50cm at the top of the rock salt roadbed, and is rolled and shaping;
It is described to roll compacting factor >=93%;
Saturated bittern is spilt after the completion of shaping to be conserved, and is spilt saturated bittern at least 5 times, to form the rock salt road surface;
The rock salt road surface forms hard shell rock salt road surface after spontaneous nucleation on the 7th.
5. according to the method described in claim 1, further comprise,
Build side slope in the two sides on the rock salt roadbed and the rock salt road surface, by the slope of the side slope than control for 1:1.5~ 1:3(S4)。
6. according to the method described in claim 1, further comprise,
Road shoulder is built at both sides edge on the rock salt road surface,
Banket, gutter (S5) are built on the original road surface of rock salt roadbed two sides.
7. a kind of factories and miness rock salt road, including rock salt roadbed, rock salt road surface,
The rock salt roadbed is layed on original ground;
The rock salt road surfacing is in rock salt roadbed top.
8. a kind of factories and miness rock salt road according to claim 7, wherein
The rock salt road surface is by one of rock salt and saturated bittern or a variety of forms;
The rock salt roadbed is by least one layer of one of the rock salt and the saturated bittern or a variety of forms;
The thickness of the rock salt roadbed reaches 80~100cm.
9. a kind of factories and miness rock salt road according to claim 7, further includes side slope,
The side slope is built in the two sides of the rock salt roadbed and the rock salt road surface;
The slope ratio of the side slope is 1:1.5~1:3.
It further include road shoulder, banket, gutter 10. a kind of factories and miness rock salt road according to claim 7,
The road shoulder is located at the both sides edge on the rock salt road surface, and the width of the road shoulder is 0.2m;
The banket is built on the original road surface of the two sides of the rock salt roadbed, width >=2m of the banket;
It builds on the original road surface beside the banket in the gutter.
CN201811593704.9A 2018-12-25 2018-12-25 A kind of factories and miness rock salt road and its construction method Pending CN109736175A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811593704.9A CN109736175A (en) 2018-12-25 2018-12-25 A kind of factories and miness rock salt road and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811593704.9A CN109736175A (en) 2018-12-25 2018-12-25 A kind of factories and miness rock salt road and its construction method

Publications (1)

Publication Number Publication Date
CN109736175A true CN109736175A (en) 2019-05-10

Family

ID=66359900

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811593704.9A Pending CN109736175A (en) 2018-12-25 2018-12-25 A kind of factories and miness rock salt road and its construction method

Country Status (1)

Country Link
CN (1) CN109736175A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112160221A (en) * 2020-09-17 2021-01-01 青海省能源发展(集团)有限责任公司 Method for hardening pavement of transportation road in mining area by using brine

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103603251A (en) * 2013-11-26 2014-02-26 中铁西北科学研究院有限公司 Method for reinforcing railroad bed of salt lake by using saturated brine clay slurry
CN103628375A (en) * 2012-08-24 2014-03-12 新疆交通建设(集团)有限责任公司 Rock salt roadbed construction method
CN107100047A (en) * 2017-03-14 2017-08-29 新疆维吾尔自治区交通规划勘察设计研究院 Suitable for the rock salt bittern road structure and construction method in playa area

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103628375A (en) * 2012-08-24 2014-03-12 新疆交通建设(集团)有限责任公司 Rock salt roadbed construction method
CN103603251A (en) * 2013-11-26 2014-02-26 中铁西北科学研究院有限公司 Method for reinforcing railroad bed of salt lake by using saturated brine clay slurry
CN107100047A (en) * 2017-03-14 2017-08-29 新疆维吾尔自治区交通规划勘察设计研究院 Suitable for the rock salt bittern road structure and construction method in playa area

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
周斌: "浅谈岩盐路基施工工艺", 《黑龙江交通科技》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112160221A (en) * 2020-09-17 2021-01-01 青海省能源发展(集团)有限责任公司 Method for hardening pavement of transportation road in mining area by using brine

Similar Documents

Publication Publication Date Title
Keller Application of geosynthetics on low-volume roads
CN111893827A (en) Construction process of urban trunk road
CN102747662A (en) Construction method for sand-filling subgrade
CN105297571A (en) Mudstone filled roadbed structure and construction method thereof
CN106522074A (en) Construction technology for gravel-pebble-soil roadbed of expressway
CN108978385A (en) A kind of roadbed construction method on the road Tong Cun
CN104264680A (en) Foundation treatment method of collapsible loess slope cut-and-fill joint part
CN107119505A (en) The general fast railway bed filling construction method of desert area
CN113250025A (en) Island-shaped frozen soil roadbed structure of high-latitude forest area and construction method
Lee et al. Assessing slope protection methods for weak rock slopes in Southwestern Taiwan
CN110761137B (en) Non-damage layered rolling construction method using cement-modified fine silt as roadbed filler
Zumrawi Pavement design for roads on expansive clay subgrades
Uge Performance, problems and remedial measures for roads constructed on expansive soil in Ethiopia–a review
CN109736175A (en) A kind of factories and miness rock salt road and its construction method
CN216514911U (en) High fill roadbed structure
Węgliński et al. Ground improvement and rebuild of a district roadin complex geotechnical-engineering conditions–case study
CN106400643B (en) With the cutting stereoscopic protective structure of high polymer grouting reinforcement waterproof
CN214245168U (en) Use urban road of mud-bonded rubble as bed filler of leaving road to reform transform road bed
CN211142675U (en) Roadbed structure of expressway filled with muck type construction waste
CN106436725A (en) Construction method of road cutting stereoscopic protection structure achieving high polymer grouting reinforcement and water prevention
CN113005839A (en) Treatment process of bad soil roadbed
CN106192645A (en) A kind of wind field road construction method
CN111304986A (en) Construction method for treating soft foundation settlement in plateau frozen soil area
CN116876280B (en) Construction method of high embankment
CN219527612U (en) Roadbed processing structure used under soft foundation geological conditions

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190510