CN109723384A - With pipe at well dewatering construction engineering method - Google Patents

With pipe at well dewatering construction engineering method Download PDF

Info

Publication number
CN109723384A
CN109723384A CN201910083167.1A CN201910083167A CN109723384A CN 109723384 A CN109723384 A CN 109723384A CN 201910083167 A CN201910083167 A CN 201910083167A CN 109723384 A CN109723384 A CN 109723384A
Authority
CN
China
Prior art keywords
well
pipe
well casing
dewatering
drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910083167.1A
Other languages
Chinese (zh)
Other versions
CN109723384B (en
Inventor
陈小羊
黄琪
王超
翟德瑞
吝江海
徐桃
胡连超
金阳
范保鑫
李雪瑞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Transportation Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Construction Development Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN201910083167.1A priority Critical patent/CN109723384B/en
Publication of CN109723384A publication Critical patent/CN109723384A/en
Application granted granted Critical
Publication of CN109723384B publication Critical patent/CN109723384B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Earth Drilling (AREA)

Abstract

The present invention provides with pipe, at well dewatering construction engineering method, easy to operate, quickly, dewatering effect is good, securely and reliably, greatly accelerates the construction speed of bored tunnel, reduces the construction cost of bored tunnel for construction;The present invention provides a kind of construction by the way that slot is as water seepage hole in well casing tube wall (chimney filter section), and at water seepage hole wide 2mm, long 20cm, circumferentially disposed 3, longitudinal pitch 60cm, whole well casings arrange that water seepage hole carries out slot processing;Shoe is welded in head section well casing bottom, and head section well casing bottom is covered on expansion bit by shoe;Well casing declines with drill bit drilling when construction, stops drilling when head section well casing drops to certain altitude, installs second well casing, it is welded to connect between well casing by pipe sleeve, second well casing continues to creep into after installing, so circulation pipe-following drilling, until designed elevation, forms well;Well casing is wrapped up using the coarse granule of wellhole periphery remnants as filtrate;Operation of the present invention is easy, and construction is quick.

Description

With pipe at well dewatering construction engineering method
Technical field
The present invention relates to underground construction technology fields, especially with pipe at well dewatering construction engineering method.
Background technique
With expanding rapidly for China's city size, the city for building subway engineering is more and more, and Subway Tunnel is common to be applied Work method has cut and cover method, subsurface excavation method and shield method, and subsurface excavation method is still being widely used as the main method that section is constructed.But tunneling Underground water is frequently encountered when construction, is especially encountered that granular media shape is severely-weathered and the unfavorable geological conditions such as completely weathered granite, is met water Phenomena such as easily softening, disintegration, intensity drastically reduce, and easy unstability occurs chip off-falling, collapses, the presence of underground water considerably increases tunneling Difficulty of construction and security risk when operation, if underground water dropped to before tunneling starts operation tunnel bottom or less 0.5-1m with Under, guarantee anhydrous excavation operation, then can greatly speed up engineering construction progress, greatly reduction security risk, while work can be improved again Civilized construction degree in journey construction quality and hole;If level of ground water control not can guarantee below tunnel bottom safe and normal Construction, control it is improper will cause tunnel vault collapse, face gush the serious consequences such as mud.Dewatering has to meet building work Journey foundation pit technical specification related code requirement with subterranean railway engineering.
Existing some dewatering construction engineering methods are complex, and constructional difficulties can tie down construction period.
Summary of the invention
For above situation, for the defect for overcoming the prior art, the present invention provides, at well dewatering construction engineering method, grasp with pipe Make simplicity, quickly, dewatering effect is good, securely and reliably, greatly accelerates the construction speed of bored tunnel, reduces tunneling tunnel for construction The construction cost in road.
The present invention provides a kind of construction and includes the following steps;1, according to geotechnical investigation geological conditions, dewatering well is determined Quantity, depth, spacing and horizontal layout.
2, the location of well;According to the position for the well location map that dewatering design scheme provides, field lofting determines well location and well spacing. Well location deviation≤50mm under normal circumstances, if well location need to be adjusted by meeting special circumstances (such as underground obstacle, ground or aerial barrage) When, it, should appropriate adjustment according to field condition in the case where guaranteeing dewatering effect.
3, drilling machine is in place: being bored using crawler type, adjusts the flatness of drilling machine after drilling machine is in place by four hydraulic legs With the verticality of boring tower, hydraulic locking precisely is carried out after contraposition, to guarantee that drilling machine installation is steady.
4, creep into and follow up well casing;
4.1, first to well casing, (well casing uses 168 steel pipe of φ, wall thickness 3mm, length 6m, slot on tube wall (chimney filter section) before construction As water seepage hole, at water seepage hole wide 2mm, long 20cm, circumferentially disposed 3, longitudinal pitch 60cm, whole well casings arrange water seepage hole) Slot processing is carried out, is processed connecting pipe box (prefabricated spare);
4.2, shoe is welded in head section well casing bottom, and head section well casing bottom is covered on expansion bit by shoe, top is logical Connector is crossed to be fixed on drilling rod;Well casing declines with drill bit drilling when construction, when head section well casing drops to certain altitude Stopping drilling, second well casing is installed, is welded to connect between well casing by pipe sleeve, second well casing continues to creep into after installing, So circulation pipe-following drilling, until designed elevation, forms well;
4.3, well casing is wrapped up using the coarse granule of wellhole periphery remnants as filtrate;Should follow up quantity in drilling process according to well casing Record well depth, final well depth are measured with lining rope in time, and well depth should be not less than projected depth.
5, water pump and water pipe are installed;Lift is selected to be not less than 6m not less than 60m, displacement3The water pump of/h, water pipe select not PVC water supplying pipe less than 50mm, inspection comprehensively before installing, can even running after guarantee installation;Water pump bottom distance is not less than 3m, uses Steel wire hang is fixed.
6, start precipitation;Examination pumping is first carried out after being installed, mud pump drainage in well is clean, and knot is taken out in examination when water outlet change is clear Beam starts to carry out formal precipitation;Dewatering well answers continuous pumpage after coming into operation, and should not be interrupted halfway, and need repairing more water-change pump When, it should carry out one by one, while increasing the monitoring frequency of SEA LEVEL VARIATION.It draws water after beginning, should check whether drainage pipeline is smooth one by one It is logical, whether there is or not leakage phenomenon, as joint or drainpipe leakage should do over again or repair.
Operation of the present invention is easy, and quickly, dewatering effect is good, securely and reliably, greatly accelerates the construction of bored tunnel for construction Progress reduces the construction cost of bored tunnel, and whole economic efficiency and social benefit are significant, and construction technology has reached industry Advanced level.
Detailed description of the invention
Fig. 1 is drilling well of the present invention with pipe schematic diagram.
Fig. 2 is construction process flow diagram of the present invention.
Fig. 3 is water pump scheme of installation of the present invention.
Fig. 4 is well casing side wall expanded view of the present invention.
Specific embodiment
Below in conjunction with attached drawing 1-4, specific embodiments of the present invention will be described in further detail.
This engineering method is suitable for suitable for grittiness clay layer, strong (complete) weathered rock formation of granular media shape, strong (complete) decomposed rock of cataclastic shape Precipitation in layer.
This engineering method uses following steps:
1, according to geotechnical investigation geological conditions, quantity, depth, spacing and the horizontal layout of dewatering well are determined.
2, the location of well;According to the position for the well location map that dewatering design scheme provides, field lofting determines well location and well spacing. Well location deviation≤50mm under normal circumstances, if well location need to be adjusted by meeting special circumstances (such as underground obstacle, ground or aerial barrage) When, it, should appropriate adjustment according to field condition in the case where guaranteeing dewatering effect.
3, drilling machine is in place: being bored using crawler type, adjusts the flatness of drilling machine after drilling machine is in place by four hydraulic legs With the verticality of boring tower, hydraulic locking precisely is carried out after contraposition, to guarantee that drilling machine installation is steady.
4, creep into and follow up well casing 2;
4.1,168 steel pipe of φ first is used to well casing 2(well casing 2 before construction, wall thickness 3mm, length 6m are cut on tube wall (chimney filter section) It stitches and is used as water seepage hole 4, at water seepage hole 4 width 2mm, long 20cm, circumferentially disposed 3, longitudinal pitch 60cm, whole well casings 2 arrange infiltration Water hole 4) slot processing is carried out, it processes connecting pipe box (prefabricated spare);
4.2, shoe 3 is welded in head section 2 bottom of well casing, and head is saved into 2 bottom of well casing by 3 sets of shoe on expansion bit 1, top Portion is fixed on drilling rod by connector;Well casing 2 declines with the drilling of drill bit 1 when construction, when head section well casing 2 drops to centainly Stop drilling when height, second well casing 2 is installed, is welded to connect between well casing 2 by pipe sleeve, after second well casing 2 installs Continue to creep into, so circulation pipe-following drilling, until designed elevation, forms well;
4.3, well casing 2 is wrapped up using the coarse granule of wellhole periphery remnants as filtrate;Should follow up number in drilling process according to well casing 2 Record well depth, final well depth are measured amount with lining rope in time, and well depth should be not less than projected depth.
5, water pump and water pipe are installed;Lift is selected to be not less than 6m not less than 60m, displacement3The water pump of/h, water pipe select not PVC water supplying pipe less than 50mm, inspection comprehensively before installing, can even running after guarantee installation;Water pump bottom is not less than apart from shaft bottom 3m is fixed with steel wire hang.
6, start precipitation;Examination pumping is first carried out after being installed, mud pump drainage in well is clean, and knot is taken out in examination when water outlet change is clear Beam starts to carry out formal precipitation;Dewatering well answers continuous pumpage after coming into operation, and should not be interrupted halfway, and need repairing more water-change pump When, it should carry out one by one, while increasing the monitoring frequency of SEA LEVEL VARIATION.It draws water after beginning, should check whether drainage pipeline is smooth one by one It is logical, whether there is or not leakage phenomenon, as joint or drainpipe leakage should do over again or repair.
This engineering method in specific application, 1, according to geotechnical investigation geological conditions, determine the quantity, depth, spacing of dewatering well And horizontal layout;Scene need to carry out the preparation of personnel, mechanical equipment and material in advance;It will be in advance by every mouthful before wellbore construction Well casing 2 completes the process.
Material selection φ 168mm steel pipe, wall thickness 3mm, joint length 6m, quantity are stocked up according to design well total depth, and It is appropriate more than needed;Steel sleeve is processed, length 20cm using the 168mm steel pipe scene φ, and quantity is processed according to scene;Pipe Boots 3, be finished product accessory, matched with steel pipe, internal diameter be φ 140mm, outer diameter top is 1mm smaller than pipe diameter, lower part with Outer diameter of steel pipes is consistent, and quantity is equipped with according to live dewatering well design quantity, and each dewatering well is equipped with 1 shoe 3.
2, the location of well;According to the position for the well location map that dewatering design scheme provides, field lofting determines well location and well spacing; Well location deviation≤50mm under normal circumstances, if well location need to be adjusted by meeting special circumstances (such as underground obstacle, ground or aerial barrage) When, it, should appropriate adjustment according to field condition in the case where guaranteeing dewatering effect.
3, drilling machine is in place: being bored using crawler type, adjusts the flatness of drilling machine after drilling machine is in place by four hydraulic legs With the verticality of boring tower, hydraulic locking precisely is carried out after contraposition, to guarantee that drilling machine installation is steady.
4, creep into and follow up well casing;
In drilling process, three-way pipeline is installed in drilling rod upper end, high-pressure blast and work are realized by the three-way pipeline on drilling rod top The synchronous supply of journey water, supplying water carries out that suitably wet (water supply is not generate dust in drilling process but not to the soil body Formed subject to mud), air compressor machine is sent high-pressure blast to foot of hole by air supply tube, by fine graineds such as powder clays in hole along well Gap blowout between pipe 2 and the borehole wall, and coarse granule (quartz sand etc.) package 2 periphery of well casing is left, automatically form dewatering well Filter layer.
The powder clay on 2 periphery of well casing, fine grained must all be blown out when drilling, cannot blindly accelerate rate of penetration;Sternly Lattice control hole diameter, well depth and well spacing by design requirement;A well is often broken into, Yao Jinhang quality examination is checked and accepted, Aperture deviation≤ 10cm, perpendicularity deviation≤5%, well depth deviation≤20cm.
5, water pump and water pipe are installed;Lift is selected to be not less than 6m not less than 60m, displacement3The water pump of/h, water pipe select not PVC water supplying pipe less than 50mm, inspection comprehensively before installing, can even running after guarantee installation;Water pump bottom is not less than apart from shaft bottom 3m is fixed with steel wire hang.
6, start precipitation;Examination pumping is first carried out after being installed, mud pump drainage in well is clean, and knot is taken out in examination when water outlet change is clear Beam starts to carry out formal precipitation;Dewatering well answers continuous pumpage after coming into operation, and should not be interrupted halfway, and need repairing more water-change pump When, it should carry out one by one, while increasing the monitoring frequency of SEA LEVEL VARIATION.It draws water after beginning, should check whether drainage pipeline is smooth one by one It is logical, whether there is or not leakage phenomenon, as joint or drainpipe leakage should do over again or repair.
Running check drinking-water pipe and water pump is answered to have fault-free during drawing water, one it is found that should repair or replace in time, and answer Running check is drawn water situation, prevent it is anhydrous burn out water pump, influence dewatering effect.
There must be special messenger to be responsible in all well-diggings and pump process, carry out into well record and the record that draws water is to guarantee into well It quality and draws water normal.
Well pumping test must be carried out before large-area precipitation, whether verifying precipitation scheme is reasonable, and whether dewatering effect is obvious, Otherwise precipitation scheme should be adjusted in time.
Surface subsidence caused by prevent from taking out of stratum thin particulate matter because of pumping underground water, will carry out sand content to the water of extraction Detection: coarse sand content < 1/50000, middle sand content < 1/20000, fine content < 1/10000.It (draws water for the first time normal rear) for the first time After sand content detection is qualified, sand content detection is periodically carried out by no more than 3 moon interval time during drawing water, is answered under abnormal conditions According to circumstances encryption detection number.It draws water after beginning, should check water yield of well, water outlet sand content one by one.When sand content is excessive, Water pump can above be mentioned, if sand content is still larger, Ying Chongxin well-flushing is discarded when still undesirable after well-flushing, digs a well again.
This engineering method construction equipment is simple, easy to operate, and construction technology is simple, and construction efficiency is high, and well casing 2 does not have to wrap up close mesh Net, does not have to special setting rubble loaded filter, and construction efficiency is high.Common setting sand, rubble loaded filter dewatering well general 3 days or so at A well, the engineering method at 1 ~ 2 mouthful of well, are not easy plugging, dewatering effect is good, and construction area is few, and environmental pollution is small, environment protecting daily It is good.
This engineering method pore-forming is dry drill method, does not need pulping in work progress, does not need to carry out mud circulation and outward transport processing; High-pressure blast is supplied by three-way pipeline in drilling process and uses water on a small quantity, and water mainly plays the wet drilling soil body, prevents Dust polluting environment is generated in drilling process and influences the health of operating worker.Therefore this engineering method construction area is few, environment Pollute small, operating condition is good, and whole environment protecting is good.
Operation of the present invention is easy, and quickly, dewatering effect is good, securely and reliably, greatly accelerates the construction of bored tunnel for construction Progress reduces the construction cost of bored tunnel, and whole economic efficiency and social benefit are significant, and construction technology has reached industry Advanced level.

Claims (6)

1. one kind is with pipe at well dewatering construction engineering method, comprising the following steps:
Step 1: determining quantity, depth, spacing and the horizontal layout of dewatering well according to geotechnical investigation geological conditions;
Step 2: the location of well;According to the position for the well location map that dewatering design scheme provides, field lofting is determined between well location and well Away from,
Well location deviation≤50mm under normal circumstances, if meeting special circumstances (such as underground obstacle, ground or aerial barrage) needs to adjust It, should appropriate adjustment according to field condition in the case where guaranteeing dewatering effect when well location;
Step 3: drilling machine is in place: being bored using crawler type, adjust the flatness of drilling machine after drilling machine is in place by four hydraulic legs With the verticality of boring tower, hydraulic locking precisely is carried out after contraposition, to guarantee that drilling machine installation is steady;
Step 4: drilling and follow-up well casing (2);
Slot processing first is carried out to well casing (2) before construction, is processed connecting pipe box (prefabricated spare);
It is covered by shoe (3) in expansion bit in head section well casing (2) bottom welding shoe (3), and by section well casing (2) bottom head (1) on, top is fixed on drilling rod by connector;Well casing (2) declines with drill bit (1) drilling when construction, when head saves well Pipe (2) stops drilling when dropping to certain altitude, installs second well casing (2), is welded to connect between well casing (2) by pipe sleeve, Second well casing (2) continues to creep into after installing, so circulation pipe-following drilling, until designed elevation, forms well;
Well casing (2) are wrapped up using the coarse granule of wellhole periphery remnants as filtrate;Should follow up number in drilling process according to well casing (2) Record well depth, final well depth are measured amount with lining rope in time, and well depth should be not less than projected depth;
Step 5: installation water pump and water pipe;
Step 6: starting precipitation;Examination pumping is first carried out after being installed, mud pump drainage in well is clean, and examination is taken out when water outlet change is clear Terminate, starts to carry out formal precipitation;Dewatering well answers continuous pumpage after coming into operation, and should not be interrupted halfway, need repairing and replace water When pump, it should carry out one by one, while increasing the monitoring frequency of SEA LEVEL VARIATION;It draws water after beginning, whether should check drainage pipeline one by one It is unimpeded, whether there is or not leakage phenomenon, as joint or drainpipe leakage should do over again or repair.
2. one kind according to claim 1 is with pipe at well dewatering construction engineering method, which is characterized in that the well casing (2) is adopted With 168 steel pipe of φ, wall thickness 3mm, length 6m, slot is as water seepage hole (4) on tube wall (chimney filter section), water seepage hole (4) width 2mm, Long 20cm, at circumferentially disposed 3, longitudinal pitch 60cm, whole well casings (2) arrange water seepage hole (4).
3. one kind according to claim 1 is with pipe at well dewatering construction engineering method, which is characterized in that the pump suction sump is raised Journey is not less than 6m not less than 60m, displacement3The water pump of/h, water pipe selection are not less than the PVC water supplying pipe of 50mm, before installing comprehensively It checks, guarantees energy even running after installation;Water pump bottom is not less than 3m apart from shaft bottom, is fixed with steel wire hang.
4. one kind according to claim 1 is with pipe at well dewatering construction engineering method, which is characterized in that the steel sleeve, benefit It is processed with the 168mm steel pipe scene φ, length 20cm, quantity is processed according to scene.
5. one kind according to claim 1 is with pipe at well dewatering construction engineering method, which is characterized in that the shoe (3) is Finished product accessory is matched with well casing (2), and internal diameter is φ 140mm, and outer diameter top is 1mm smaller than pipe diameter, lower part and steel pipe Outer diameter is consistent, and quantity is equipped with according to live dewatering well design quantity, and each dewatering well is equipped with 1 shoe (3).
6. one kind according to claim 1 is with pipe at well dewatering construction engineering method, which is characterized in that necessary when the described drilling The powder clay on well casing (2) periphery, fine grained are all blown out, rate of penetration cannot be blindly accelerated;Strictly controlled by design requirement Good hole diameter, well depth and well spacing;A well is often broken into, Yao Jinhang quality examination is checked and accepted, Aperture deviation≤10cm, perpendicularity deviation≤ 5%, well depth deviation≤20cm.
CN201910083167.1A 2019-01-29 2019-01-29 Pipe-following well-forming dewatering construction method Active CN109723384B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910083167.1A CN109723384B (en) 2019-01-29 2019-01-29 Pipe-following well-forming dewatering construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910083167.1A CN109723384B (en) 2019-01-29 2019-01-29 Pipe-following well-forming dewatering construction method

Publications (2)

Publication Number Publication Date
CN109723384A true CN109723384A (en) 2019-05-07
CN109723384B CN109723384B (en) 2021-03-16

Family

ID=66301066

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910083167.1A Active CN109723384B (en) 2019-01-29 2019-01-29 Pipe-following well-forming dewatering construction method

Country Status (1)

Country Link
CN (1) CN109723384B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112227944A (en) * 2020-08-31 2021-01-15 中铁十六局集团有限公司 Dewatering well construction process applied to tunnel construction
CN114319403A (en) * 2022-01-21 2022-04-12 中水华通工程有限公司 Construction method for quick well formation of quicksand geological formations

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101736732A (en) * 2009-12-17 2010-06-16 上海隧道工程股份有限公司 Pressure and water reduction construction method of ultra-deep foundation pit confined water
US20110168443A1 (en) * 2010-01-13 2011-07-14 Peter Paul Smolka Bitless Drilling System
CN102912806A (en) * 2012-09-27 2013-02-06 中交三航局第二工程有限公司 Construction method of precipitation well
CN103147450A (en) * 2013-03-19 2013-06-12 成军 Construction method for plugging partial steel pipe dewatering well by using flange plates for excavation of deep foundation pit
CN107476322A (en) * 2017-08-10 2017-12-15 魏玉建 Well-points dewatering automatic servo compensation technique
CN207892652U (en) * 2018-02-05 2018-09-21 云南工程建设总承包股份有限公司 A kind of dewatering device of tunnel rich water section
CN109137888A (en) * 2018-08-08 2019-01-04 中国二十冶集团有限公司 The dewatering construction method of prefabricated concrete pipe pile supporting construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101736732A (en) * 2009-12-17 2010-06-16 上海隧道工程股份有限公司 Pressure and water reduction construction method of ultra-deep foundation pit confined water
US20110168443A1 (en) * 2010-01-13 2011-07-14 Peter Paul Smolka Bitless Drilling System
CN102912806A (en) * 2012-09-27 2013-02-06 中交三航局第二工程有限公司 Construction method of precipitation well
CN103147450A (en) * 2013-03-19 2013-06-12 成军 Construction method for plugging partial steel pipe dewatering well by using flange plates for excavation of deep foundation pit
CN107476322A (en) * 2017-08-10 2017-12-15 魏玉建 Well-points dewatering automatic servo compensation technique
CN207892652U (en) * 2018-02-05 2018-09-21 云南工程建设总承包股份有限公司 A kind of dewatering device of tunnel rich water section
CN109137888A (en) * 2018-08-08 2019-01-04 中国二十冶集团有限公司 The dewatering construction method of prefabricated concrete pipe pile supporting construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112227944A (en) * 2020-08-31 2021-01-15 中铁十六局集团有限公司 Dewatering well construction process applied to tunnel construction
CN114319403A (en) * 2022-01-21 2022-04-12 中水华通工程有限公司 Construction method for quick well formation of quicksand geological formations

Also Published As

Publication number Publication date
CN109723384B (en) 2021-03-16

Similar Documents

Publication Publication Date Title
CN106369223B (en) A kind of silt stratum pipe jacking construction method
CN106402490B (en) Silt stratum push pipe jacking construction method based on steel bushing head tool pipe
CN108560541B (en) Rotary drilling full-casing follow-up rock face drilling construction method
CN105715296B (en) Sand blowing, backfilling and grouting construction method for tunnel to penetrate through coal mine goaf
CN112502777B (en) Method for treating tunnel inrush roof collapse and door closing
CN109594564A (en) A kind of anti-collapse construction method of Metro Deep Excavation open cut
CN110593254A (en) Construction method of cast-in-situ bored pile in stratum with karst cave in joint zone
CN112160324A (en) Construction method for deep foundation pit support
CN111395322A (en) Construction method for rotary digging cast-in-place pile under karst landform
CN109723384A (en) With pipe at well dewatering construction engineering method
JP7292772B2 (en) External expansion pipe construction method for drilling in the mining zone
CN101832137A (en) Pre-embedding method for coal seam roof strut
CN102235010A (en) Treatment method for hanging sinking stop due to expansive soil in well sinking
CN112962579B (en) Construction method of underground continuous wall of coastal push-filling area
CN113266019B (en) Construction method of foundation pit steel pipe support system
CN114250801A (en) Pipe well and light well point combined dewatering construction method
CN114991774A (en) Ground subsection descending type grouting method for crushed andesite basalt stratum
CN104060636B (en) Pressure release anti-float method during high water level regional architecture foundation construction and device
CN114575746A (en) Construction method for natural gas pipeline reverse well drilling crossing
CN117248962B (en) Method for treating presbyopia water among small kiln roadway column type residual coal pillars
Paulatto et al. Rock grouting in Copenhagen limestone–The Cityringen Experience
CN203834529U (en) Pressure-relieving anti-floating device for building foundation construction in high-water-level district
CN116906049B (en) Construction method for breaking large boulder of jacking pipe through mechanical splitting
CN108533270A (en) A kind of method that underground deep layer flexible pipe line is removed in rich water soft soil layer
Sinna Application of trenchless construction technology in construction of water supply and drainage in urban road construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: No.267, 15th Street, Jingkai, Zhengzhou, Henan Province, 450000

Applicant after: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd.

Address before: 450000 No. 116 Chengdong Road, Jinshui District, Henan, Zhengzhou

Applicant before: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd.

CB02 Change of applicant information
CB03 Change of inventor or designer information

Inventor after: Hou Shunping

Inventor after: Hu Lianchao

Inventor after: Jin Yang

Inventor after: Fan Baoxin

Inventor after: Li Xuerui

Inventor after: Tian Zhijie

Inventor after: Chen Xiaoyang

Inventor after: Huang Qi

Inventor after: Wu Jingjiang

Inventor after: Wang Chao

Inventor after: Zhai Derui

Inventor after: Laijiang and Haihai

Inventor after: Xu Tao

Inventor before: Chen Xiaoyang

Inventor before: Li Xuerui

Inventor before: Huang Qi

Inventor before: Wang Chao

Inventor before: Zhai Derui

Inventor before: Laijiang and Haihai

Inventor before: Xu Tao

Inventor before: Hu Lianchao

Inventor before: Jin Yang

Inventor before: Fan Baoxin

CB03 Change of inventor or designer information
TA01 Transfer of patent application right

Effective date of registration: 20210222

Address after: No.267, 15th Street, Jingkai, Zhengzhou, Henan Province, 450000

Applicant after: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd.

Applicant after: China Construction Seventh Bureau Transportation Construction Co.,Ltd.

Applicant after: China Construction Seventh Bureau Construction Development Co.,Ltd.

Address before: No.267, 15th Street, Jingkai, Zhengzhou, Henan Province, 450000

Applicant before: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant