CN109706955A - One kind being suitable for III class stake of cast-in-situ bored pile and cushion cap connection type - Google Patents

One kind being suitable for III class stake of cast-in-situ bored pile and cushion cap connection type Download PDF

Info

Publication number
CN109706955A
CN109706955A CN201811628193.XA CN201811628193A CN109706955A CN 109706955 A CN109706955 A CN 109706955A CN 201811628193 A CN201811628193 A CN 201811628193A CN 109706955 A CN109706955 A CN 109706955A
Authority
CN
China
Prior art keywords
pile
stake
cast
extension
cushion cap
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811628193.XA
Other languages
Chinese (zh)
Inventor
王亚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU XINGSHA CONSTRUCTION ENGINEERING GROUP Co Ltd
Original Assignee
JIANGSU XINGSHA CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU XINGSHA CONSTRUCTION ENGINEERING GROUP Co Ltd filed Critical JIANGSU XINGSHA CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority to CN201811628193.XA priority Critical patent/CN109706955A/en
Publication of CN109706955A publication Critical patent/CN109706955A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

The present invention relates to architectural design technical fields, it is in particular a kind of to be suitable for III class stake of cast-in-situ bored pile and cushion cap connection type, comprising the following steps: Step 1: extending with the stake side of former III class stake of cast-in-situ bored pile, to clear up soil property, and on the basis of cutting pile beacon height, soil is taken downwards;Step 2: the length after the extension of stake side is radius, again formwork pile extension using the former III class stake center of circle of cast-in-situ bored pile as the center of circle, the stake top after pile extension stretches to cushion cap, and the pile concrete of pile extension uses slightly expanded concrete;Step 3: former III class stake body reinforcing bar of cast-in-situ bored pile stretches in cushion cap;Step 4: pile extension pile body vertical reinforcement stretches in cushion cap.Quick construction of the present invention is convenient, short construction period, is not influenced by the limitation of site facility and former stake spacing, the a large amount of time can not only be saved for engineering, improve working efficiency, progress is fast, the problems in practice of construction is quickly solved, while also reducing the unnecessary expense in part.

Description

One kind being suitable for III class stake of cast-in-situ bored pile and cushion cap connection type
Technical field
The present invention relates to architectural design technical fields, specially a kind of to connect suitable for III class stake of cast-in-situ bored pile with cushion cap Mode.
Background technique
Bored concrete pile system refers in engineering site through means such as machine drilling, steel pipe soil compaction or manpower excavations in foundation soil Stake holes is formed, and places steel reinforcement cage, concrete perfusion and the stake being made into it, according to forming hole method difference, bored concrete pile again may be used It is divided into several classes such as driven cast-in-place pile, cast-in-situ bored pile and digging hole filling pile, during foundation excavation, due to construction site The influence of limitation and former stake spacing, basic soil timely cannot go out fortune and accumulate at the scene, lotus when former stake is by mound product Load causes pile body to be destroyed, and cannot reach former design bearing requirements, in consideration of it, it is proposed that a kind of be suitable for cast-in-situ bored pile III Class stake and cushion cap connection type.
Summary of the invention
The purpose of the present invention is to provide one kind to be suitable for III class stake of cast-in-situ bored pile and cushion cap connection type, on solving State the problem of proposing in background technique.
To achieve the above object, the invention provides the following technical scheme:
One kind being suitable for III class stake of cast-in-situ bored pile and cushion cap connection type, comprising the following steps:
Step 1: extending with the stake side of former III class stake of cast-in-situ bored pile, soil property is cleared up, and on the basis of cutting pile beacon height, is taken downwards Soil;
Step 2: the length after the extension of stake side is radius, and formwork connects again using the former III class stake center of circle of cast-in-situ bored pile as the center of circle , the stake top after pile extension stretches to cushion cap, and the pile concrete of pile extension uses slightly expanded concrete;
Step 3: former III class stake body reinforcing bar of cast-in-situ bored pile stretches in cushion cap;
Step 4: pile extension pile body vertical reinforcement stretches in cushion cap;
Step 5: backfill conserves pile extension pile body after the completion of the construction of pile extension pile body, Soil Surrounding is cleared up, completes cushion construction;
It is wanted Step 6: determining that original III class stake body reinforcing bar of cast-in-situ bored pile and pile extension pile body vertical reinforcement anchor into cushion cap length and reach It asks and after pile extension pile body built-in length reaches requirement, carries out foundation platform construction.
As a preference of the present invention, the length of the stake side extension in step 1 with former III class stake of cast-in-situ bored pile is 150mm, Take the depth of soil not less than 600mm downwards.
As a preference of the present invention, using the former III class stake center of circle of cast-in-situ bored pile as the center of circle in step 2, after the extension of stake side Radius is 150mm, and it is 50mm that the stake top after pile extension, which stretches to the depth in cushion cap, and the grade of the pile concrete of pile extension is C40, When pouring pile extension pile concrete, vibration compacting, it is ensured that pile extension pile body is complete.
As a preference of the present invention, cast-in-situ bored pile III class stake body reinforcing bar in step 3 Central Plains stretches to the length in cushion cap For 35D, the III class stake body reinforcing bar of former cast-in-situ bored pile in cushion cap is protruded into without any bending.
As a preference of the present invention, it is 35D, pile extension that pile extension pile body vertical reinforcement, which stretches to the length in cushion cap, in step 4 Pile body vertical reinforcement grade is grade III steel, and specification 12, arrangement spacing is 250mm, and the pile body transverse steel of pile extension is grade III steel, Specification is 8, and arrangement spacing is 100mm.
As a preference of the present invention, cushion construction uses grade for the concrete of C20 in step 5, construction with a thickness of 10mm。
Compared with prior art, beneficial effects of the present invention:
Quick construction of the present invention is convenient, short construction period, is not influenced by the limitation of site facility and former stake spacing, not only It can be that engineering saves a large amount of time, improve working efficiency, progress is fast, quickly solves the problems in practice of construction, while also subtracting The unnecessary expense of small part.
Detailed description of the invention
Fig. 1 is overall structure diagram of the invention;
Fig. 2 is the bottom view of the present invention former cast-in-situ bored pile III class stake and pile extension.
In figure: former III class stake 1 of cast-in-situ bored pile, pile extension 2, III class stake body reinforcing bar 3 of former cast-in-situ bored pile, pile extension pile body are perpendicular To reinforcing bar 4, bed course 5, cushion cap 6.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
In the description of the present invention, it is to be understood that, term " center ", " longitudinal direction ", " transverse direction ", " length ", " width ", " thickness ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside", " up time The orientation or positional relationship of the instructions such as needle ", " counterclockwise " is to be based on the orientation or positional relationship shown in the drawings, and is merely for convenience of The description present invention and simplified description, rather than the equipment of indication or suggestion meaning or element must have a particular orientation, with spy Fixed orientation construction and operation, therefore be not considered as limiting the invention.
Embodiment 1
One kind being suitable for III class stake of cast-in-situ bored pile and cushion cap connection type, comprising the following steps:
Step 1: extending with the stake side of former III class stake 1 of cast-in-situ bored pile, soil property is cleared up, and on the basis of cutting pile beacon height, is taken downwards Soil;
Step 2: the length after the extension of stake side is radius, and formwork connects again using former III class stake of cast-in-situ bored pile, 1 center of circle as the center of circle Stake 2, the stake top after pile extension 2 stretch to cushion cap 6, and the pile concrete of pile extension 2 uses slightly expanded concrete;
Step 3: former III class stake body reinforcing bar 3 of cast-in-situ bored pile stretches in cushion cap;
Step 4: pile extension pile body vertical reinforcement 4 stretches in cushion cap;
Step 5: backfill conserves 2 pile body of pile extension after the completion of the construction of 2 pile body of pile extension, Soil Surrounding is cleared up, bed course 5 is completed and applies Work;
Step 6: determining that original III class stake body reinforcing bar 3 of cast-in-situ bored pile and pile extension pile body vertical reinforcement 4 anchor into 6 length of cushion cap and reach To requiring and after 2 pile body built-in length of pile extension reaches requirement, carry out foundation platform 6 and construct.
In the present embodiment, the length of the stake side extension in step 1 with former III class stake 1 of cast-in-situ bored pile is 150mm, downwards The depth for taking soil is 600mm.
In the present embodiment, using former III class stake of cast-in-situ bored pile, 1 center of circle as the center of circle in step 2, the radius after the extension of stake side is 150mm, it is 50mm that the stake top after pile extension 2, which stretches to the depth in cushion cap 6, and the grade of the pile concrete of pile extension 2 is C40, is poured When building 2 pile concrete of pile extension, vibration compacting, it is ensured that 2 pile body of pile extension is complete.
In the present embodiment, the length that cast-in-situ bored pile III class stake body reinforcing bar 3 in step 3 Central Plains stretches in cushion cap 6 is 35D protrudes into the III class stake body reinforcing bar 3 of former cast-in-situ bored pile in cushion cap 6 without any bending.
It is 35D, pile extension pile body that pile extension pile body vertical reinforcement 4, which stretches to the length in cushion cap 6, in the present embodiment, in step 4 4 grade of vertical reinforcement is grade III steel, and specification 12, arrangement spacing is 250mm, and the pile body transverse steel of pile extension is grade III steel, rule Lattice are 8, and arrangement spacing is 100mm.
In the present embodiment, the construction of bed course 5 uses grade for the concrete of C20 in step 5, constructs with a thickness of 10mm.
Embodiment 2
One kind being suitable for III class stake of cast-in-situ bored pile and cushion cap connection type, comprising the following steps:
Step 1: extending with the stake side of former III class stake 1 of cast-in-situ bored pile, soil property is cleared up, and on the basis of cutting pile beacon height, is taken downwards Soil;
Step 2: the length after the extension of stake side is radius, and formwork connects again using former III class stake of cast-in-situ bored pile, 1 center of circle as the center of circle Stake 2, the stake top after pile extension 2 stretch to cushion cap 6, and the pile concrete of pile extension 2 uses slightly expanded concrete;
Step 3: former III class stake body reinforcing bar 3 of cast-in-situ bored pile stretches in cushion cap;
Step 4: pile extension pile body vertical reinforcement 4 stretches in cushion cap;
Step 5: backfill conserves 2 pile body of pile extension after the completion of the construction of 2 pile body of pile extension, Soil Surrounding is cleared up, bed course 5 is completed and applies Work;
Step 6: determining that original III class stake body reinforcing bar 3 of cast-in-situ bored pile and pile extension pile body vertical reinforcement 4 anchor into 6 length of cushion cap and reach To requiring and after 2 pile body built-in length of pile extension reaches requirement, carry out foundation platform 6 and construct.
In the present embodiment, the length of the stake side extension in step 1 with former III class stake 1 of cast-in-situ bored pile is 150mm, downwards The depth for taking soil is 625mm.
In the present embodiment, using former III class stake of cast-in-situ bored pile, 1 center of circle as the center of circle in step 2, the radius after the extension of stake side is 150mm, it is 50mm that the stake top after pile extension 2, which stretches to the depth in cushion cap 6, and the grade of the pile concrete of pile extension 2 is C40, is poured When building 2 pile concrete of pile extension, vibration compacting, it is ensured that 2 pile body of pile extension is complete.
In the present embodiment, the length that cast-in-situ bored pile III class stake body reinforcing bar 3 in step 3 Central Plains stretches in cushion cap 6 is 35D protrudes into the III class stake body reinforcing bar 3 of former cast-in-situ bored pile in cushion cap 6 without any bending.
It is 35D, pile extension pile body that pile extension pile body vertical reinforcement 4, which stretches to the length in cushion cap 6, in the present embodiment, in step 4 4 grade of vertical reinforcement is grade III steel, and specification 12, arrangement spacing is 250mm, and the pile body transverse steel of pile extension is grade III steel, rule Lattice are 8, and arrangement spacing is 100mm.
In the present embodiment, the construction of bed course 5 uses grade for the concrete of C20 in step 5, constructs with a thickness of 10mm.
Embodiment 3
One kind being suitable for III class stake of cast-in-situ bored pile and cushion cap connection type, comprising the following steps:
Step 1: extending with the stake side of former III class stake 1 of cast-in-situ bored pile, soil property is cleared up, and on the basis of cutting pile beacon height, is taken downwards Soil;
Step 2: the length after the extension of stake side is radius, and formwork connects again using former III class stake of cast-in-situ bored pile, 1 center of circle as the center of circle Stake 2, the stake top after pile extension 2 stretch to cushion cap 6, and the pile concrete of pile extension 2 uses slightly expanded concrete;
Step 3: former III class stake body reinforcing bar 3 of cast-in-situ bored pile stretches in cushion cap;
Step 4: pile extension pile body vertical reinforcement 4 stretches in cushion cap;
Step 5: backfill conserves 2 pile body of pile extension after the completion of the construction of 2 pile body of pile extension, Soil Surrounding is cleared up, bed course 5 is completed and applies Work;
Step 6: determining that original III class stake body reinforcing bar 3 of cast-in-situ bored pile and pile extension pile body vertical reinforcement 4 anchor into 6 length of cushion cap and reach To requiring and after 2 pile body built-in length of pile extension reaches requirement, carry out foundation platform 6 and construct.
In the present embodiment, the length of the stake side extension in step 1 with former III class stake 1 of cast-in-situ bored pile is 150mm, downwards The depth for taking soil is 650mm.
In the present embodiment, using former III class stake of cast-in-situ bored pile, 1 center of circle as the center of circle in step 2, the radius after the extension of stake side is 150mm, it is 50mm that the stake top after pile extension 2, which stretches to the depth in cushion cap 6, and the grade of the pile concrete of pile extension 2 is C40, is poured When building 2 pile concrete of pile extension, vibration compacting, it is ensured that 2 pile body of pile extension is complete.
In the present embodiment, the length that cast-in-situ bored pile III class stake body reinforcing bar 3 in step 3 Central Plains stretches in cushion cap 6 is 35D protrudes into the III class stake body reinforcing bar 3 of former cast-in-situ bored pile in cushion cap 6 without any bending.
It is 35D, pile extension pile body that pile extension pile body vertical reinforcement 4, which stretches to the length in cushion cap 6, in the present embodiment, in step 4 4 grade of vertical reinforcement is grade III steel, and specification 12, arrangement spacing is 250mm, and the pile body transverse steel of pile extension is grade III steel, rule Lattice are 8, and arrangement spacing is 100mm.
In the present embodiment, the construction of bed course 5 uses grade for the concrete of C20 in step 5, constructs with a thickness of 10mm.
The basic principles, main features and advantages of the present invention have been shown and described above.The technology of the industry For personnel it should be appreciated that the present invention is not limited to the above embodiments, described in the above embodiment and specification is only the present invention Preference, be not intended to limit the invention, without departing from the spirit and scope of the present invention, the present invention also has various Changes and improvements, these changes and improvements all fall within the protetion scope of the claimed invention.The claimed scope of the invention is by institute Attached claims and its equivalent thereof.

Claims (6)

1. one kind is suitable for III class stake of cast-in-situ bored pile and cushion cap connection type, it is characterised in that: the following steps are included:
Step 1: extending with the stake side of former III class stake (1) of cast-in-situ bored pile, soil property is cleared up, and on the basis of cutting pile beacon height, downwards Take soil;
Step 2: the length after the extension of stake side is radius, again formwork using former III class stake (1) center of circle of cast-in-situ bored pile as the center of circle Pile extension (2), the stake top after pile extension (2) stretch to cushion cap (6), and the pile concrete of pile extension (2) uses slightly expanded concrete;
Step 3: former III class stake body reinforcing bar (3) of cast-in-situ bored pile stretches in cushion cap;
Step 4: pile extension pile body vertical reinforcement (4) stretches in cushion cap;
Step 5: backfill conserves pile extension (2) pile body after the completion of the construction of pile extension (2) pile body, Soil Surrounding is cleared up, completes pad Layer (5) construction;
Step 6: determining that original III class stake body reinforcing bar (3) of cast-in-situ bored pile and pile extension pile body vertical reinforcement (4) anchor into cushion cap (6) Length reaches requirement and after pile extension (2) pile body built-in length reaches requirement, carries out foundation platform (6) construction.
2. according to claim 1 be suitable for III class stake of cast-in-situ bored pile and cushion cap connection type, it is characterised in that: step The length extended in one with the stake side of former III class stake (1) of cast-in-situ bored pile takes downwards the depth of soil not less than 600mm for 150mm.
3. according to claim 1 be suitable for III class stake of cast-in-situ bored pile and cushion cap connection type, it is characterised in that: step Using former III class stake (1) center of circle of cast-in-situ bored pile as the center of circle in two, the radius after the extension of stake side is 150mm, the stake top after pile extension (2) The depth stretched in cushion cap (6) is 50mm, and the grade of the pile concrete of pile extension (2) is C40, and it is mixed to pour pile extension (2) pile body When solidifying soil, vibration compacting, it is ensured that pile extension (2) pile body is complete.
4. according to claim 1 be suitable for III class stake of cast-in-situ bored pile and cushion cap connection type, it is characterised in that: step It is 35D that three Central Plains cast-in-situ bored piles, III class stake body reinforcing bar (3), which stretches to the length in cushion cap (6), protrudes into the original in cushion cap (6) III class stake body reinforcing bar (3) of cast-in-situ bored pile is without any bending.
5. according to claim 1 be suitable for III class stake of cast-in-situ bored pile and cushion cap connection type, it is characterised in that: step It is 35D that pile extension pile body vertical reinforcement (4), which stretches to the length in cushion cap (6), in four, and pile extension pile body vertical reinforcement (4) grade is three Grade steel, specification 12, arrangement spacing are 250mm, and the pile body transverse steel of pile extension is grade III steel, specification 8, and spacing of arranging is 100mm。
6. according to claim 1 be suitable for III class stake of cast-in-situ bored pile and cushion cap connection type, it is characterised in that: step Bed course (5) construction uses grade for the concrete of C20 in five, constructs with a thickness of 10mm.
CN201811628193.XA 2018-12-28 2018-12-28 One kind being suitable for III class stake of cast-in-situ bored pile and cushion cap connection type Pending CN109706955A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811628193.XA CN109706955A (en) 2018-12-28 2018-12-28 One kind being suitable for III class stake of cast-in-situ bored pile and cushion cap connection type

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811628193.XA CN109706955A (en) 2018-12-28 2018-12-28 One kind being suitable for III class stake of cast-in-situ bored pile and cushion cap connection type

Publications (1)

Publication Number Publication Date
CN109706955A true CN109706955A (en) 2019-05-03

Family

ID=66258119

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811628193.XA Pending CN109706955A (en) 2018-12-28 2018-12-28 One kind being suitable for III class stake of cast-in-situ bored pile and cushion cap connection type

Country Status (1)

Country Link
CN (1) CN109706955A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111254815A (en) * 2020-03-04 2020-06-09 东南大学 Self-resetting prefabricated pier structure for single-pile foundation and assembling method thereof
CN115354651A (en) * 2022-02-23 2022-11-18 中国五冶集团有限公司 Construction method for pile extension of rotary drilling cast-in-place pile

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203200771U (en) * 2013-01-30 2013-09-18 苏州工业园区设计研究院股份有限公司 Connection structure for pile extension top and bearing platform
CN205712153U (en) * 2015-12-31 2016-11-23 上海建工五建集团有限公司 Foundation pile structure
CN206538779U (en) * 2017-02-23 2017-10-03 华西能源工程有限公司 A kind of rotary digging bored concrete pile pile splicing structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203200771U (en) * 2013-01-30 2013-09-18 苏州工业园区设计研究院股份有限公司 Connection structure for pile extension top and bearing platform
CN205712153U (en) * 2015-12-31 2016-11-23 上海建工五建集团有限公司 Foundation pile structure
CN206538779U (en) * 2017-02-23 2017-10-03 华西能源工程有限公司 A kind of rotary digging bored concrete pile pile splicing structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111254815A (en) * 2020-03-04 2020-06-09 东南大学 Self-resetting prefabricated pier structure for single-pile foundation and assembling method thereof
CN115354651A (en) * 2022-02-23 2022-11-18 中国五冶集团有限公司 Construction method for pile extension of rotary drilling cast-in-place pile

Similar Documents

Publication Publication Date Title
CN106958256B (en) A kind of placement layer by layer, the open caisson construction technique repeatedly sunk
CN201148621Y (en) Miniature anti-slide pile composite structure
CN103334439A (en) Long-span reinforced concrete inner support structure of rectangular deep foundation pit and construction method of structure
CN106088127A (en) Open caisson construction method
CN107338804B (en) A kind of hollow independent composite pile foundation of super-large diameter and its method of construction
CN103696784A (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN205242436U (en) Supplementary soleplate traded interim bearing structure who props during system was gone along with sb. to guard him to underground complex
CN203782684U (en) Anti-skid pile provided with crossbeam
CN105545323A (en) Construction method for open cut tunnel lining
CN102864780A (en) Supporting structure and supporting method of foundation pit
CN111441343A (en) Mountain photovoltaic support micropore cast-in-place pile foundation system, construction method and application
CN203411993U (en) Simple and fast retaining wall
CN109706955A (en) One kind being suitable for III class stake of cast-in-situ bored pile and cushion cap connection type
CN108360535A (en) Foundation pit supporting construction based on campshed and inner support and its construction method
CN106013834B (en) Device and method for basement increasing layer
CN105804101B (en) Reduce off-loading supporting and retaining system system and construction method and the application of retaining structure stress
CN107034894A (en) Post-tensioned prestressed tension beam recoverable pattern foundation pit supporting structure prefabricated pile and preparation method thereof and construction method
CN111810185B (en) Tunnel bottom pre-reinforcement construction method
CN105484270B (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN209555962U (en) One kind being suitable for III class stake of cast-in-situ bored pile and cushion cap connection structure
CN106120853B (en) A kind of inverted construction method of frame bridge
CN206220558U (en) Old City Wall door opening ruggedized construction
CN214993788U (en) Assembled cement soil composite pile
CN104805876B (en) A kind of method for inclining the vertical pushing tow correction of independent bent columns
CN204780943U (en) H type precast concrete pile and excavation supporting device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190503