CN109667591A - A kind of construction method of the sharp radius curve section of shield tunnel - Google Patents

A kind of construction method of the sharp radius curve section of shield tunnel Download PDF

Info

Publication number
CN109667591A
CN109667591A CN201811615852.6A CN201811615852A CN109667591A CN 109667591 A CN109667591 A CN 109667591A CN 201811615852 A CN201811615852 A CN 201811615852A CN 109667591 A CN109667591 A CN 109667591A
Authority
CN
China
Prior art keywords
shield
tunnel
distance
curve section
radius curve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811615852.6A
Other languages
Chinese (zh)
Other versions
CN109667591B (en
Inventor
孙林
韩根福
黄炜焱
方华
张峥
林海骏
戚晓东
王振峰
赵培
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Mechanized Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Group Co Ltd filed Critical Shanghai Mechanized Construction Group Co Ltd
Priority to CN201811615852.6A priority Critical patent/CN109667591B/en
Publication of CN109667591A publication Critical patent/CN109667591A/en
Application granted granted Critical
Publication of CN109667591B publication Critical patent/CN109667591B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0621Shield advancing devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/385Sealing means positioned between adjacent lining members
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/003Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/093Control of the driving shield, e.g. of the hydraulic advancing cylinders

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a kind of construction methods of the sharp radius curve section of shield tunnel, during shield tunnel construction, the every propulsion certain distance of shield machine, the automatic measurement system of shield machine is checked using minor radius measurement check method, the deviation between the shield attitude of shield machine and the design centre line in tunnel is controlled, and so that the shield attitude of shield machine is tended to the design centre line of the shield tunnel by shield correction.The present invention passes through the deviation between the shield attitude of control shield machine and the design centre line in tunnel, the deviation is set to meet national acceptance specification, simultaneously by reducing the deviation between shield attitude and the design centre line in tunnel, guarantee shield gap, waterstop is set according to tunnel curvilinear wedge amount, solves the quality problems of section of jurisdiction fragmentation, percolating water.

Description

A kind of construction method of the sharp radius curve section of shield tunnel
Technical field
The present invention relates to shield method tunnel construction technical fields, more particularly, to a kind of sharp radius curve section of shield tunnel Construction method.
Background technique
As long as the exploitation of the underground space and the construction of subway have many decades, Urban Underground new subway is by more and more Existing underground building object space hinders, the tunnel-type that some subterranean tunnel routes are had to using sharp radius curve within 250m Formula avoids existing underground building object group, and minor radius tunnel is following subway construction form in need of consideration, but due to existing The restriction of metro shield technology, this form be not common.In the common Shield Construction Technique of subway construction, within 350 meters Turning radius can be referred to as tight turn radius, generally using articulated shield machine come construction tunnel, due to tunnel turning radius Small, the power of shield is that its main jack is withstood on the tunnel formed, and curve turning in minor radius tunnel is more anxious, and shield is very heavy The thrust and tunnel contact of a curve on top, so cannot be born completely by tunnel, it can be with tunnel toward lateral offset, so existing Tight turn radius misalignment of axe is big in shield technique, and since misalignment of axe is big, and shield correction is more when bad with posture, So the common quality defect of section of jurisdiction fragmentation, percolating water is serious.
Summary of the invention
The purpose of the present invention is to provide a kind of construction methods of the sharp radius curve section of shield tunnel, to control minor radius The deviation of curved tunnel axis solves the problems, such as the section of jurisdiction fragmentation occurred in shield tunnel construction, leakage.
In order to achieve the above object, the present invention provides a kind of construction method of the sharp radius curve section of shield tunnel, During shield tunnel construction, the every propulsion certain distance of shield machine checks oneself of shield machine using minor radius measurement check method Dynamic measuring system controls the deviation between the shield attitude of shield machine and the design centre line in tunnel, and is made by shield correction The shield attitude of shield machine tends to the design centre line of the shield tunnel.
Optionally, the minor radius measurement check method, which refers to, introduces measure traverse line described in shield tunnel check from ground The automatic measurement system of shield machine, the measure traverse line include multiple conducting wire transmitting points, between two neighboring conducting wire transmitting point Line is intervisibility sight, when the intervisibility line-of-sight distance tunnel inner wall is close to 1.5 meters of curve center of circle side, according to plane curve The distance between the two neighboring conducting wire transmitting point that internal diameter simulation calculates in tunnel maximum value, and according to two neighboring described The distance between conducting wire transmitting point maximum value is arranged the conducting wire and transmits point.
Optionally, the measure traverse line further includes the hanging basket point for installing hanging basket, high according to the shield trolley in shield tunnel Degree, shield tunnel diameter and the practical center axis are simulated visual between the automatic measurement system and hanging basket point Range, in the visual range, the minimum distance of the hanging basket point and the automatic measurement system is first distance, described to hang The maximum distance of basket point and the automatic measurement system is second distance.
Optionally, a hanging basket point setting is being at the first distance position apart from the automatic measurement system, with The shield machine promote, when the distance between the hanging basket point and the automatic measurement system increase to the second distance When, the Bluepoint of hanging is moved to apart from the automatic measurement system as at the first distance position.
Optionally, when the sharp radius curve section of the shield tunnel passes through bed shallow covering, using the shield of the shield machine Structure posture predeformation method controls the deviation between the actual center line and design centre line of shield tunnel, and the shield attitude is pre- It is pre- partially to the sharp radius curve section center of circle while deformation method refers to that the head of the shield machine, tail portion are pre- inclined downwards.
Optionally, when the sharp radius curve section of the shield tunnel passes through bed shallow covering, by adjusting the shield machine The grouting amount of the synchronous grouting pipe of different location, the grouting amount for infusing the synchronous grouting pipe above the shield tunnel are greater than The grouting amount of synchronous grouting pipe note below the shield tunnel, and the synchronization in the center of circle far from sharp radius curve section The grouting amount of Grouting Pipe note is greater than the grouting amount of the synchronous grouting pipe note close to the center of circle of sharp radius curve section, shallow to overcome Earthing region tunnel is easy to float, the defect that tunnel is deviated outward by shield thrust when minor-circle turn tunneling shield is constructed.
Optionally, the gap of the shield tail between shield tail and section of jurisdiction is calculated, and by between the shield correction adjustment shield tail Gap makes between the shield tail and the section of jurisdiction without interference.
Optionally, when the gap of the shield tail is less than 1 centimetre, the shield machine promotes 1 endless tube piece distance to adjust the shield Structure posture makes to state gap of the shield tail greater than 1 centimetre and carries out the shield correction again.
Optionally, the shield correction includes powerful small by adjusting the propelling cylinder hydraulic oil pressure of shield machine, makes shield The shield attitude of machine tends to the design centre line of the shield tunnel.
Optionally, when carrying out shield correction, the semi-ring of side is opened in gap between the section of jurisdiction of the shield tunnel Stick on waterstop in the section of jurisdiction.
In a kind of construction method of the sharp radius curve section of shield tunnel provided by the invention, in shield tunnel construction mistake Cheng Zhong, the every propulsion certain distance of shield machine check the automatic measurement system of shield machine, control using minor radius measurement check method Deviation between the shield attitude of shield machine and the design centre line in tunnel, and the shield attitude of shield machine is made by shield correction Tend to the design centre line of the shield tunnel.The included automatic measurement system of shield machine is the metrical information by input and pushes away Into when parameter calculate axis, it can not calculate shield machine and misalignment of axe when tunnel itself shifts, so It needs that measure traverse line is manually introduced tunnel from ground and checks shield machine automatic measurement system, and rectified a deviation by shield and control shield Deviation between the line of posture and tunnel design centre makes the deviation meet national acceptance specification, while by reducing shield Deviation between structure posture and the design centre line in tunnel guarantees shield gap, and waterstop is arranged according to tunnel curvilinear wedge amount, Solve the quality problems of section of jurisdiction fragmentation, percolating water.
Detailed description of the invention
Fig. 1 is the measure traverse line transmission figure that one embodiment of the invention provides;
Fig. 2 is the measure traverse line shield trolley section transmitting sectional view that one embodiment of the invention provides;
Fig. 3 is the measure traverse line shield trolley section transmitting main view that one embodiment of the invention provides;
Fig. 4 is the measure traverse line shield trolley section transmitting top view that one embodiment of the invention provides;
Fig. 5 is the pre- inclined schematic diagram of axis that one embodiment of the invention provides;
Fig. 6 is the synchronous grouting schematic diagram that one embodiment of the invention provides;
Fig. 7 is the gap of the shield tail schematic diagram that one embodiment of the invention provides;
Wherein: the section of jurisdiction 10-, 20- shield trolley, 30- hanging basket, 40- total station, 50- automatic measurement system, 60- shield machine, 71- the first synchronous grouting pipe, the one or two synchronous grouting pipe of 72-, 73- third synchronous grouting pipe, the 4th synchronous grouting pipe of 74-.
Specific embodiment
A specific embodiment of the invention is described in more detail below in conjunction with schematic diagram.According to following description and Claims, advantages and features of the invention will become apparent from.It should be noted that attached drawing is all made of very simplified form and Using non-accurate ratio, only for the purpose of facilitating and clarifying the purpose of the embodiments of the invention.
One embodiment of the invention provides a kind of construction method of the sharp radius curve section of shield tunnel, in shield tunnel construction In the process, the every propulsion certain distance of shield machine checks the automatic measurement system of shield machine, control using minor radius measurement check method Deviation between the shield attitude of shield machine processed and the design centre line in tunnel, and the shield appearance of shield machine is made by shield correction State tends to the design centre line of the shield tunnel, makes the shield attitude of the shield machine and the design centre of the shield tunnel Deviation between line meets national acceptance specification.Shield attitude is in the work progress of shield tunnel, to meet shield machine The construction of driving needs, and by measurement or calculates obtained shield machine deviation shield tunnel design centre by automatic measurement system The state of line, major parameter have horizontal departure, vertical missing and rotation angle.Shield correction refers to that shield attitude deviates tunnel Design centre line, shield driver small makes shield appearance by adjusting shield driving oil cylinder hydraulic oil pressure is powerful in shield tunneling process State tends to the process of the design centre line in tunnel.Shield correction is actually the mistake that shield is turned according to certain sweep Journey, the sweep of shield correction turning and the design centre line for being less than tunnel.
As preferable embodiment, Fig. 1 is the measure traverse line transmission figure that one embodiment of the invention provides, as shown in Figure 1, The minor radius measurement check method, which refers to, introduces the automatic survey that shield tunnel checks the shield machine from ground for measure traverse line Amount system, the measure traverse line include multiple conducting wire transmitting points, and the line between two neighboring conducting wire transmitting point is intervisibility sight, When the intervisibility line-of-sight distance tunnel inner wall is close to 1.5 meters of curve center of circle side, simulated according to internal diameter in plane curve tunnel The distance between the two neighboring conducting wire transmitting point (being conducting wire transmitting point A and conducting wire transmitting point B respectively) calculated maximum value, And the conducting wire is arranged according to the distance between two neighboring conducting wire transmitting point maximum value and transmits point.The smaller part of shield tunnel Sighting condition difference limits the arrangement of the polygon control survey point in diametal curve section, and the shield tunnel is generally every in straightway subway It lays the conducting wire for 200 meters or so and transmits point, lay the conducting wire for every 150 meters of general curve section and transmit point, at this In embodiment, for the radius of the sharp radius curve section less than 250 meters, the sighting condition of the sharp radius curve section is poor, therefore adjacent Distance is calculated by internal diameter simulation in plane curve tunnel between two conducting wire transmitting points.
As preferable embodiment, Fig. 2 is that the measure traverse line shield trolley section transmitting that one embodiment of the invention provides is cutd open Face figure, Fig. 3 are the measure traverse line shield trolley section transmitting main views that one embodiment of the invention provides, and Fig. 4 is that the present invention one is implemented The measure traverse line shield trolley section that example provides transmits top view, and as in Figure 2-4, the hanging basket 30 for being equipped with total station 40, which is hung, to be located at The section of jurisdiction inner wall of shield tunnel, and between shield trolley 20 and fast section of jurisdiction 10 of binding.The measure traverse line further includes installation The hanging basket point of hanging basket 30, according to 20 height of shield trolley, shield tunnel diameter and the mandrel in practice in shield tunnel Line simulates the visual range between the automatic measurement system 50 and hanging basket point, in the visual range, the hanging basket The minimum distance of point 30 and the automatic measurement system 50 is first distance, the hanging basket point 30 and the automatic measurement system 50 Maximum distance be second distance.One setting of hanging basket point 30 is being the first distance apart from the automatic measurement system 50 At position, as the shield machine promotes, when the distance between the hanging basket point 30 and the automatic measurement system 50 increase to When the second distance, the Bluepoint 30 of hanging is moved to apart from the automatic measurement system as at the first distance position.
As preferable embodiment, when the sharp radius curve section of the shield tunnel passes through bed shallow covering, using institute State the deviation between the actual center line and design centre line of the shield attitude predeformation method control shield tunnel of shield machine, institute State shield attitude predeformation method refer to the shield machine head downwards it is pre- inclined while, to the curve center of circle it is pre- partially.In this reality It applies in example, the shield machine 60 is articulated shield machine, selects articulated shield machine, bed shallow covering tunnel is easy to float, small Tunnel is deviated by shield thrust to far from the center of curve when radius curve tunneling shield is constructed, by the head of shield machine to leaning on Nearly sharp radius curve section center of circle direction deviates 20~30 millimeters, while offseting downward 20~30 millimeters, by the tail of shield machine Portion deviates 20~30 millimeters to close to sharp radius curve section center of circle direction, while offseting downward 40~50 millimeters, in shield Tunnel is so tested in specification by the axle power offset successor generated under the influence of small-radius shield thrust and the buoyancy of shallow earthing tunnel Within the scope of the misalignment of axe of receipts.Fig. 5 is the pre- inclined schematic diagram of axis that one embodiment of the invention provides, as shown in figure 5, L3 is shield The propulsion center line of machine 60, L2 are the actual center line of shield tunnel, and L1 is the design centre line of shield tunnel, final shield tunnel The actual center line L2 in road tends to the design centre line L1 of shield tunnel, and deviation meets national acceptance specification.
Make as preferable embodiment by adjusting the grouting amount of the synchronous grouting pipe of the shield machine different location The grouting amount of synchronous grouting pipe note above the shield tunnel is greater than the synchronous grouting below the shield tunnel The grouting amount of pipe note, and the grouting amount of the synchronous grouting pipe note in the center of circle far from sharp radius curve section is greater than close to minor radius The grouting amount of the synchronous grouting pipe note in the center of circle of curved section, to overcome bed shallow covering tunnel to be easy to float, minor radius turns The defect that tunnel is deviated outward by shield thrust when curved tunneling shield is constructed.Fig. 6 is the synchronous note that one embodiment of the invention provides Schematic diagram is starched, as shown in fig. 6, in this embodiment, the curve center of circle C is located on the left of shield machine, the synchronous grouting pipe includes Second synchronous grouting pipe, 72,225 ° of sides in 71,135 ° of directions of the first synchronous grouting pipe of 45 ° of directions (being positive in a counterclockwise direction) To third synchronous grouting pipe 73 and 315 ° of directions the 4th synchronous grouting pipe 74, slip casting ratio be 44%:38%:9%: 9%.
As preferable embodiment, the section of jurisdiction fragmentation is mainly the interference between the shield tail of shield machine and the section of jurisdiction It causes, calculates the gap of the shield tail between the shield tail and the section of jurisdiction, and the gap of the shield tail is adjusted by shield correction, Make between the shield tail and the section of jurisdiction without interference.Guarantee shield gap and waterstop, solution are arranged according to tunnel curvilinear wedge amount Determined section of jurisdiction fragmentation, percolating water quality problems.
Fig. 7 is the gap of the shield tail schematic diagram that one embodiment of the invention provides, as shown in fig. 7, close to the shield machine 60 80 endface position of section of jurisdiction to measure gap between the shield tail and the section of jurisdiction be R1+R2, shield attitude head Horizontal departure is △ h, and shield attitude tail portion horizontal departure is △ t (being negative close to the curve center of circle, be positive far from the curve center of circle), institute Stating shield machine overall length is D1, and it is D2 that the section of jurisdiction, which enters the shield tail length,.Then the gap of the shield tail is R0:
R0=R2- (△ h- △ t) × D2/D1+R1+ (△ h- △ t) × D2/D1.
When the gap of the shield tail is less than 1 centimetre, the shield machine promotes 1 endless tube piece distance to adjust the shield attitude, Make to state gap of the shield tail and carries out the shield correction again greater than 1 centimetre.
As preferable embodiment, the shield correction includes the propelling cylinder hydraulic oil pressure by adjusting shield machine Size makes the shield attitude of shield machine tend to the design centre line of the shield tunnel.It is adjacent when carrying out shield correction Gap is opened between two semi-ring sections of jurisdiction, and section of jurisdiction described in the semi-ring of side is opened in gap between the section of jurisdiction of the shield tunnel and is added Waterstop is pasted, prevents original waterstop from not having Effective Compaction, water-stagnating effect weakens and causes to leak.
In conclusion during shield tunnel construction, the every propulsion certain distance of shield machine is measured using minor radius and is checked Method checks the automatic measurement system of shield machine, controls inclined between the shield attitude of shield machine and the design centre line in tunnel Difference, and so that the shield attitude of shield machine is tended to the design centre line of the shield tunnel by shield correction, make the shield of shield machine Deviation between structure posture and the design centre line of the shield tunnel meets national acceptance specification.
The above is only a preferred embodiment of the present invention, does not play the role of any restrictions to the present invention.Belonging to any Those skilled in the art, in the range of not departing from technical solution of the present invention, to the invention discloses technical solution and Technology contents make the variation such as any type of equivalent replacement or modification, belong to the content without departing from technical solution of the present invention, still Within belonging to the scope of protection of the present invention.

Claims (10)

1. a kind of construction method of the sharp radius curve section of shield tunnel, during shield tunnel construction, the every propulsion of shield machine Certain distance is checked the automatic measurement system of shield machine using minor radius measurement check method, controls the shield attitude of shield machine Deviation between the design centre line in tunnel, and so that the shield attitude of shield machine is tended to the shield tunnel by shield correction Design centre line.
2. the construction method of the sharp radius curve section of shield tunnel according to claim 1, which is characterized in that the smaller part Diameter measurement check method, which refers to, introduces the automatic measurement system that shield tunnel checks the shield machine, institute from ground for measure traverse line Stating measure traverse line includes multiple conducting wire transmitting points, and the line between two neighboring conducting wire transmitting point is intervisibility sight, described logical When depending on line-of-sight distance tunnel inner wall close to 1.5 meters of curve center of circle side, according to the phase that internal diameter simulation calculates in plane curve tunnel The distance between adjacent two conducting wire transmitting points maximum value, and most according to the distance between two neighboring described conducting wire transmitting point Big value is arranged the conducting wire and transmits point.
3. the construction method of the sharp radius curve section of shield tunnel according to claim 2, which is characterized in that the measurement Conducting wire further includes the hanging basket point for installing hanging basket, according to the shield trolley height in shield tunnel, shield tunnel diameter and described Practical center axis simulates the visual range between the automatic measurement system and hanging basket point, in the visual range, The minimum distance of the hanging basket point and the automatic measurement system is first distance, the hanging basket point and the automatic measurement system Maximum distance be second distance.
4. the construction method of the sharp radius curve section of shield tunnel according to claim 3, which is characterized in that hung described in one The setting of basket point is being at the first distance position, as the shield machine promotes, when described apart from the automatic measurement system When the distance between hanging basket point and the automatic measurement system increase to the second distance, the Bluepoint of hanging is moved to distance The automatic measurement system is at the first distance position.
5. the construction method of the sharp radius curve section of shield tunnel according to claim 1, which is characterized in that the shield When the sharp radius curve section in tunnel passes through bed shallow covering, shield is controlled using the shield attitude predeformation method of the shield machine Deviation between the actual center line and design centre line in tunnel, the shield attitude predeformation method refer to the shield machine It is pre- partially to the sharp radius curve section center of circle while head, tail portion are pre- inclined downwards.
6. the construction method of the sharp radius curve section of shield tunnel according to claim 1 or 5, which is characterized in that described When the sharp radius curve section of shield tunnel passes through bed shallow covering, by adjusting the synchronous grouting pipe of the shield machine different location Grouting amount, the grouting amount for infusing the synchronous grouting pipe above the shield tunnel be greater than the shield tunnel below institute The grouting amount of synchronous grouting pipe note is stated, and the grouting amount of the synchronous grouting pipe note in the center of circle far from sharp radius curve section is greater than Close to the grouting amount of the synchronous grouting pipe note in the center of circle of sharp radius curve section, to overcome bed shallow covering tunnel to be easy Defect floating, that tunnel is deviated outward by shield thrust when minor-circle turn tunneling shield is constructed.
7. the construction method of the sharp radius curve section of shield tunnel according to claim 1, which is characterized in that calculate shield tail Gap of the shield tail between section of jurisdiction, and the gap of the shield tail is adjusted by shield correction, make the shield tail and the section of jurisdiction Between without interference.
8. the construction method of the sharp radius curve section of shield tunnel according to claim 7, which is characterized in that when the shield When tail gap is less than 1 centimetre, the shield machine promotes 1 endless tube piece distance to adjust the shield attitude, makes to state gap of the shield tail greater than 1 Centimetre the shield correction is carried out again.
9. the construction method of the sharp radius curve section of shield tunnel according to claim 1, which is characterized in that the shield Correction include it is powerful small by adjusting the propelling cylinder hydraulic oil pressure of shield machine, so that the shield attitude of shield machine is tended to the shield The design centre line in tunnel.
10. the construction method of the sharp radius curve section of shield tunnel according to claim 1, which is characterized in that carrying out When the shield is rectified a deviation, waterstop is sticked in section of jurisdiction described in the semi-ring of gap opening side between the section of jurisdiction of the shield tunnel.
CN201811615852.6A 2018-12-27 2018-12-27 Construction method of small-radius curve segment of shield tunnel Active CN109667591B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811615852.6A CN109667591B (en) 2018-12-27 2018-12-27 Construction method of small-radius curve segment of shield tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811615852.6A CN109667591B (en) 2018-12-27 2018-12-27 Construction method of small-radius curve segment of shield tunnel

Publications (2)

Publication Number Publication Date
CN109667591A true CN109667591A (en) 2019-04-23
CN109667591B CN109667591B (en) 2020-10-23

Family

ID=66146950

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811615852.6A Active CN109667591B (en) 2018-12-27 2018-12-27 Construction method of small-radius curve segment of shield tunnel

Country Status (1)

Country Link
CN (1) CN109667591B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110130910A (en) * 2019-05-22 2019-08-16 重庆大学 Earth pressure balanced shield, EPBS small curve radius tunneling shield driving method
CN111101955A (en) * 2019-11-11 2020-05-05 中铁隧道局集团有限公司 Construction method for ultra-large diameter shield to penetrate through small-radius curve tunnel section
CN114183152A (en) * 2021-12-07 2022-03-15 中铁隧道局集团有限公司 Method for controlling shield attitude in small-radius multi-curve subway shield construction

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2441554A1 (en) * 1973-12-17 1975-06-19 Continental Oil Co METHOD OF REMOVING A MINERAL DEPOSIT
CN104655092A (en) * 2013-11-25 2015-05-27 天津城建隧道股份有限公司 Triangular single well directional measurement method used in subway shield construction
CN204591286U (en) * 2015-04-27 2015-08-26 浙江大学城市学院 A kind of small curvature radius tunneling shield cardan shaft line traffic control mechanism
CN106382121A (en) * 2016-12-05 2017-02-08 中交第三航务工程局有限公司 Measuring method for subway tunnel shield excavation

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2441554A1 (en) * 1973-12-17 1975-06-19 Continental Oil Co METHOD OF REMOVING A MINERAL DEPOSIT
CN104655092A (en) * 2013-11-25 2015-05-27 天津城建隧道股份有限公司 Triangular single well directional measurement method used in subway shield construction
CN204591286U (en) * 2015-04-27 2015-08-26 浙江大学城市学院 A kind of small curvature radius tunneling shield cardan shaft line traffic control mechanism
CN106382121A (en) * 2016-12-05 2017-02-08 中交第三航务工程局有限公司 Measuring method for subway tunnel shield excavation

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110130910A (en) * 2019-05-22 2019-08-16 重庆大学 Earth pressure balanced shield, EPBS small curve radius tunneling shield driving method
CN111101955A (en) * 2019-11-11 2020-05-05 中铁隧道局集团有限公司 Construction method for ultra-large diameter shield to penetrate through small-radius curve tunnel section
CN114183152A (en) * 2021-12-07 2022-03-15 中铁隧道局集团有限公司 Method for controlling shield attitude in small-radius multi-curve subway shield construction
CN114183152B (en) * 2021-12-07 2023-09-12 中铁隧道局集团有限公司 Method for controlling shield posture in small-radius multi-curve subway shield construction

Also Published As

Publication number Publication date
CN109667591B (en) 2020-10-23

Similar Documents

Publication Publication Date Title
CN109667591A (en) A kind of construction method of the sharp radius curve section of shield tunnel
CN107120120B (en) Vehicle frame walking shield tunnel grouting behind shaft or drift lining testing equipment
CN106934159B (en) A kind of duct pieces of shield tunnel assembly point bit digitizing type selecting assembling method
CN103322989A (en) Measuring device and method of dynamic real-time measurement of position and posture of pipe pushing jack
CN109372532A (en) Jacking construction engineering method under multiplexed address environment
CN209444350U (en) Shield launching wears existing shield tunnel barrel vault advanced support structure under being
CN101598023A (en) The control method of the shield tunnel axis when closing on the side underground structure being arranged
CN207215039U (en) A kind of double track scanning system of tunnel surrounding and constructional aspect
CN101737058A (en) Small-radius shield tunnel construction technology
CN106703819A (en) Small-radius shield curve launching construction method for super-shallow-buried large-section tunnel
CN103711492B (en) A kind of jacking-type cable sleeve channel construction method
CN102635362B (en) Secondary reception constructing method for shield arrival
CN110130910A (en) Earth pressure balanced shield, EPBS small curve radius tunneling shield driving method
CN203961994U (en) Under balancing earth-pressure shielding machine, wear the concealed tunneling structure of having runed shield tunnel
CN108625866A (en) Shield machine based on steel bushing device crosses ventilating shaft method
CN104389615A (en) Small-radius curve large-slope shield construction method in coastal soft soil stratum
CN106223969A (en) One closely upper and lower overlap or shield tunnel construction method of closely intersecting
CN206346737U (en) A kind of supporting major diameter curve pipe curtain
CN104389613B (en) Slurry balance shield passes through the construction method of jeopardously underground pipelines
CN208685678U (en) A kind of float Structure of subway station
CN205134343U (en) Steel-pipe pile cofferdam structure
CN208220811U (en) A kind of inverted arch support component suitable for the tunnel shield formula TBM prefabricated pipe section liner structure
CN111677521B (en) High-pressure gas pipe settlement control method for subway interval tunnel construction
CN112922610A (en) Construction method for special railway line for downward passing freight by using shield tunneling machine
CN203239355U (en) Jacking type cable sleeve channel structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant