CN109664226A - A kind of large-scale air cleaning equipment pipeline centralising device - Google Patents

A kind of large-scale air cleaning equipment pipeline centralising device Download PDF

Info

Publication number
CN109664226A
CN109664226A CN201811588786.8A CN201811588786A CN109664226A CN 109664226 A CN109664226 A CN 109664226A CN 201811588786 A CN201811588786 A CN 201811588786A CN 109664226 A CN109664226 A CN 109664226A
Authority
CN
China
Prior art keywords
damping
pipeline
bottom plate
fixed
centralising device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811588786.8A
Other languages
Chinese (zh)
Other versions
CN109664226B (en
Inventor
赵城广
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taizhou JINDA Electronic Technology Co., Ltd
Original Assignee
Shengzhou Kaifeng Textile Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shengzhou Kaifeng Textile Machinery Co Ltd filed Critical Shengzhou Kaifeng Textile Machinery Co Ltd
Priority to CN201811588786.8A priority Critical patent/CN109664226B/en
Publication of CN109664226A publication Critical patent/CN109664226A/en
Application granted granted Critical
Publication of CN109664226B publication Critical patent/CN109664226B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B25HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
    • B25BTOOLS OR BENCH DEVICES NOT OTHERWISE PROVIDED FOR, FOR FASTENING, CONNECTING, DISENGAGING OR HOLDING
    • B25B11/00Work holders not covered by any preceding group in the subclass, e.g. magnetic work holders, vacuum work holders
    • B25B11/02Assembly jigs
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B25HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
    • B25BTOOLS OR BENCH DEVICES NOT OTHERWISE PROVIDED FOR, FOR FASTENING, CONNECTING, DISENGAGING OR HOLDING
    • B25B27/00Hand tools, specially adapted for fitting together or separating parts or objects whether or not involving some deformation, not otherwise provided for

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Joints Allowing Movement (AREA)

Abstract

The invention discloses a kind of large-scale air cleaning equipment pipeline centralising devices, including fixed bracket and cushion socket, fixed bracket includes fixed bottom plate and side stand, cushion socket includes damping bottom plate and damping casing, the front and rear sides of damping damping bottom plate are provided with sliding shoe, it is extended transversely through in sliding shoe and is provided with sliding bar, adjusting bracket is provided between two damping casings, the basal sliding of adjusting bracket is connected on the top surface of damping bottom plate.The present invention can effectively ensure the centering precision between two pipelines, to the horizontal connection and fixation between subsequent two pipelines of being more convenient for, close performance after improving pipeline connection, the centralising device can also play damping effect simultaneously, there is good isolation effect to the mechanical oscillation of pipeline transmitting, there is obvious action to the noise reduced inside pipeline, and the cushioning effect of centralising device can also avoid pipeline in pipeline docking operation from shaking and the serious misalignment that causes pipeline to interface, reduce the operation difficulty of pipeline docking.

Description

A kind of large-scale air cleaning equipment pipeline centralising device
Technical field
The present invention relates to air purification fields, and in particular to a kind of large-scale air cleaning equipment pipeline centralising device.
Background technique
Air cleaning facility (also known as " air cleaner equipment ", air cleaner) is to refer to filter out or kill air pollution Object, the product for effectively improving air cleanliness are with the household and business air cleaning equipment of removing room air pollution at present It is main.Pipeline is one of necessary component in equipment in large-scale air cleaning equipment.It is all needed substantially in the installation process of pipeline Pipeline docked and be fixed, need manually to use hand fixed -piping in pipeline docking operation in the prior art and by two pipelines pair Interface alignment, and due to pipeline it is excessive, it is too long be not easy to dock it, fix, increase artificial docking difficulty.And it is artificial Pipeline is easy to happen shaking in fixed docking operation, causes the serious misalignment between pipeline, reduces docking effect.
Summary of the invention
Present invention aims at provide a kind of large-scale air cleaning equipment pipeline for deficiency of the prior art Centralising device, smart structural design is reasonable, easy to use and operate, can effectively ensure the centering precision between two pipelines, To the horizontal connection and fixation between subsequent two pipelines of being more convenient for, the close performance after pipeline connects is improved, while this is right Middle device can also play damping effect, so that the use of pipeline is more steady, have to the mechanical oscillation of pipeline transmitting good Good isolation effect has obvious action to the noise reduced inside pipeline, and the cushioning effect of centralising device can also be kept away Exempt from the serious misalignment that pipeline in pipeline docking operation shakes and causes pipeline to interface, the operation for reducing pipeline docking is difficult Degree, the operating time for saving pipeline docking.
In order to solve the above-mentioned technical problem, the present invention adopts the following technical scheme:
A kind of large-scale air cleaning equipment pipeline centralising device, it is characterised in that: fixed including fixed bracket and cushion socket Bracket includes fixed bottom plate and side stand, is provided with clamped sliding slot on the top surface of fixed bottom plate, side stand is symmetricly set on fixation The left and right sides of bottom plate, for shock-absorbing seat in the top of fixed bottom plate, cushion socket includes damping bottom plate and damping casing, damping bottom plate Bottom surface on be provided with clamped piece, clamped piece matches with clamped sliding slot, and clamped piece is connected in clamped sliding slot, damping bottom plate Front and rear sides are provided with sliding shoe, extend transversely through in sliding shoe and are provided with sliding bar, the both ends of sliding bar respectively with two sides Bracket is connected, and sliding shoe is fixed by the first holding screw and sliding bar limit, and there are two damping casing settings, two dampings The casing top arranged in parallel in damping bottom plate is respectively provided on the opposite face of two damping casings there are two fixture block, two Adjusting bracket is provided between damping casing, fixture block is connected and fixed with adjusting bracket, and the basal sliding of adjusting bracket is connected to damping bottom plate Top surface on.
Further, side stand includes limit sleeve and supporting leg, and the side of limit sleeve is provided with limiting slot and circle hole groove, fixed Bottom plate matches with limiting slot, and the left and right ends of fixed bottom plate are connected in limiting slot, and sliding bar matches with circle hole groove, sliding The end of bar is connected in circle hole groove, and supporting leg is uniformly arranged on the other side of limit sleeve, and the design of limit sleeve can be in order to limiting The design of position slot can simplify installing and dismounting step by limiting slot in order to connecting and fixing between side stand and fixed bottom plate, The design of circle hole groove can be in order to connecting and fixing between sliding bar and side stand on limit sleeve, and the design of supporting leg can be in order to Fixed bracket support is fixed, is fixed so that entire centralising device be supported.
Further, supporting leg includes the first strut and the second strut, and the first strut is fixedly connected with limit sleeve, the second strut Top be connected in the regulating tank of the first strut bottom surface, and the second strut by the second holding screw and the first strut limit consolidate Fixed, the bottom of the second strut is connect with bridge screw, and the design of the first strut and the second strut is more ingenious reasonable, Ke Yigen According to the height of actual demand adjustment supporting leg, consolidate to will entirely fix the supports such as bracket and equipment, ground by supporting leg It is fixed, it is ensured that centralising device firmly installs performance, and pressing plate ensures the bottom surface of the second strut in same level, thus after being more convenient for The continuous adjustment to support leg length is passed through by unscrewing the second holding screw on the supporting leg of the same side, then horizontal stretch pressing plate Pressing plate drives the adjustment of the second strut upper-lower height, changes intubating length of second strut in the regulating tank of the first strut, until Supporting leg is adjusted to suitable height, then tightens the second holding screw, overall construction design compact and reasonable, letter easy to use It is single.
Further, it is connected by consolidating bar between the front end of two damping casings and the rear end of two damping casings, Consolidate in the middle part of bar and be provided with elastic stretching section, elastic stretching section is an integral molding structure with bar is consolidated, and the design for consolidating bar can To realize the connection between two damping casings, so that the structure of cushion socket more firm stable, so that the damping of cushion socket Effect is more preferable, while the design of elastic stretching section meets the design of two damping casings or so fine tuning again, and whole design is reasonable, bullet Property stretch section and consolidate the design that bar is an integral molding structure and may insure to consolidate the structural strength of bar.
Further, adjusting bracket includes card frame and cap ned, and the front and rear sides of cap ned upper end are provided with card frame, card frame Left and right ends are provided with card slot, and fixture block matches with card slot, and fixture block is connected in card slot, and fixture block passes through third holding screw It limits and fixes with card frame, the design of card frame can be in order to the connection between adjusting bracket and two damping casings, and the design of card slot can In order to the clamping between fixture block and card frame, and the intubating length by adjusting fixture block in corresponding card slot, it can be to correspondence The left-right position of damping casing carry out the fine tuning of small distance, so that it is guaranteed that pipeline in each damping casing and corresponding pipeline Between accurate centering, the leakproofness after improving pipeline connection prevents pipeline dislocation from influencing connection between subsequent pipeline, I-shaped The design of frame can be fixed in order to the installation between adjusting bracket and damping bottom plate, so that it is guaranteed that the stable structure of adjusting bracket, more just Clamping between damping casing and adjusting bracket improves the structural stability of damping casing, the design of third holding screw indirectly It is more ingenious to be rationally convenient for actual operation and use, after the completion of damping casing fine tuning, by tightening third holding screw It is fixed being limited between fixture block and card frame, so that it is guaranteed that can not be moved after damping casing fine tuning, it is ensured that the knot of entire centralising device Structure strength and stability.
Further, damping casing includes shock ring and connecting plate, and shock ring is provided at least three, and connecting plate is symmetrical arranged In the left and right sides of shock ring, shock ring is uniformly arranged between two connecting plates, and shock ring is welded and fixed with connecting plate, fixture block It is fixedly connected with connecting plate, the socket area between damping casing and pipeline may insure by the design of multiple shock rings, from And ensure the secured performance of socket of the pipeline in damping casing, so that the pipeline configuration in damping casing is more secured, and It can also be improved the damping effect of damping casing by the design of multiple shock rings, have so that damping casing vibrates Management of Pipeline Mechanical Equipment There is good isolation, while significantly reducing the mechanical noise in pipeline use process, shock ring may be implemented in the design of connecting plate Between be connected and fixed, improve the overall structural strength of damping casing, extend the service life of damping casing, it is ensured that each damping The ring heart of ring is on the same line, it is ensured that the levelness of damping casing, so that it is guaranteed that the straight line for the pipeline being socketed in damping casing Property, the leakproofness convenient for the centering between subsequent two pipelines, after improving two pipe level docking.
Further, the first reinforcing rod, the first reinforcing rod are provided with below the connecting plate on two damping casing opposite faces Bottom end be provided with reinforcement head, the bottom for reinforcing head is provided with inserted block, the lower section of the connecting plate on two damping casing opposing faces It is provided with the second reinforcing rod, the second reinforcing rod is fixedly connected with head is reinforced, and fine tuning sliding slot is provided on the top surface of damping bottom plate, is inserted Block matches with fine tuning sliding slot, and inserted block is connected in fine tuning sliding slot, and the design of the first reinforcing rod and the second reinforcing rod can be with tune Section frame matches, and plays the role of further resilient support to damping casing, so that the structure of damping casing is more firm Gu it is reliable, so that it is guaranteed that the structural stability can for the pipeline being arranged in damping casing, the essence for actual pipeline centering of being also more convenient for Certainly position, improves centering precision, and the design for reinforcing head can be further improved the structural strength of the first reinforcing rod, reinforce simultaneously The design of head can also be in order to being connected and fixed between the second reinforcing rod and the first reinforcing rod, and the design for reinforcing head can also be with Convenient for the setting of inserted block, by the design of inserted block and fine tuning sliding slot can the left-right position to two damping casings carry out it is individual Fine tuning, it is ensured that the levelness during the adjustment of two damping casings, so that it is guaranteed that pipeline in each damping casing can with it is right The interface precise positioning for the pipeline connected answered, the centering connection between pipeline of being more convenient for, avoids the shadow that misplaces between pipeline Sealing performance and service life after the docking of speaking pipe road.
Further, flexible gasket ring is provided in shock ring, the design of flexible gasket ring is so that the annular distance inside shock ring has Certain deformation quantity, the socket being more convenient between pipeline and damping casing, and can subtract again with pipeline with after damping casing socket Fitting closely between shake ring and pipeline lateral wall, while flexible gasket ring can also protect the lateral wall of pipeline, avoid Rigid friction between pipeline lateral wall and shock ring inner sidewall, protects pipeline.
The present invention is by adopting the above-described technical solution, have the advantages that
Smart structural design of the invention is reasonable, the adjustment twice to pipeline left-right position may be implemented, first to pipeline Left-right position is significantly adjusted, to pipeline is moved adjacent at docked pipeline, then to the left and right position of pipeline It sets and is finely adjusted, it is ensured that the pipeline in damping casing is positioned with the centering of the casing docked, to effectively improve pipeline docking Accuracy afterwards, the docking between pipeline of being more convenient for are fixed, pipeline are socketed in damping casing first, and it is tight then to unscrew first Determine screw, sliding shoe is significantly moved along sliding bar or so, to change the damping casing on damping bottom plate Left-right position, until the pipeline in damping casing is generally moved to and at the position of the multipair pipeline connect, then tightens the One holding screw, so that pipeline location at mobile position, then unscrews third holding screw, tune of the adjustment fixture block in card frame The length in slot is saved, the inserted block for reinforcing head bottom while fixture block adjusts is slided along the fine tuning sliding slot on damping bottom plate, thus The levelness for ensuring damping casing or so adjustment avoids damping casing itself from tilting and cause inclining to interface for internal pipeline Tiltedly, so that the docking for influencing subsequent pipeline is fixed, by adjusting fixture block until the pipeline in damping casing is moved to and institute The pipeline precise positioning of docking, so that it is guaranteed that the centring property between two pipelines, and successively to the shock-absorbing sleeve of the left and right sides The left-right position of pipe is adjusted separately, so that it is guaranteed that the pipeline that can be docked with itself of the pipeline in two damping casings it Between accurate centering, the docking between subsequent pipeline of being more convenient for fixes, avoid pipeline to interface dislocation, inclination and increase pipeline docking Difficulty causes the leakproofness at pipeline docking poor.
Support and installation positioning to entire centralising device may be implemented by support bracket fastened design in the present invention, thus Ensure the structural stability and secured performance of entire centralising device, while fixed bracket can also carry out the adjustment of oneself height, By combining with the step of pipeline left-right position adjustment, the precision of pipeline centering is further increased, subsequent pipeline of being more convenient for Between docking fix, improve the service life of pipeline entirety after docking, and consolidate entire centralising device by fixation bracket The mechanical oscillation of centralising device can be reduced after fixed, and then lower the mechanical oscillation of pipeline itself, so that pipeline and pipeline, equipment Between connection it is more secured, and by the ingehious design of cushion socket specific structure, so that cushion socket both can be in order to right The mechanical of pipeline transmitting is shaken in the socket of pipeline and the adjustment of pipeline left-right position, and the good damping effect of cushion socket itself It is dynamic that there is good buffer action, there is remarkable effect to structural noise is reduced, so as to improve environment, improves the use of pipeline and equipment Service life.
The configuration of the present invention is simple, practical, smart structural design is reasonable, easy to use and operate, can effectively ensure two Centering precision between a pipeline, so that horizontal connection and fixation between subsequent two pipelines of being more convenient for, improve pipeline and connect Close performance after connecing, while the centralising device can also play damping effect, so that the use of pipeline is more steady, to pipe The mechanical oscillation of road transmitting have good isolation effect, have obvious action, and centering to the noise reduced inside pipeline The cushioning effect of device can also avoid pipeline in pipeline docking operation from shaking and the serious misalignment that causes pipeline to interface, It reduces the operation difficulty of pipeline docking, save the operating time of pipeline docking.
Detailed description of the invention
The present invention will be further explained below with reference to the attached drawings:
Fig. 1 is a kind of structural schematic diagram of large-scale air cleaning equipment pipeline centralising device of the present invention;
Fig. 2 is the structural schematic diagram of cushion socket in the present invention;
Fig. 3 is the mounting structure schematic diagram for consolidating bar and damping casing in the present invention;
Fig. 4 is the structural schematic diagram of adjusting bracket in the present invention;
Fig. 5 is the structural schematic diagram of side stand in the present invention;
Fig. 6 is the structural schematic diagram of damping bottom plate in the present invention.
In figure: the fixed bracket of 1-;2- cushion socket;3- fixes bottom plate;4- side stand;5- damping bottom plate;6- damping casing;7- Clamped piece;The clamped sliding slot of 8-;9- sliding shoe;10- sliding bar;The first holding screw of 11-;12- fixture block;13- adjusting bracket;14- limit Position set;15- supporting leg;16- limiting slot;17- circle hole groove;The first strut of 18-;The second strut of 19-;The second holding screw of 20-; 21- pressing plate;22- consolidates bar;23- elastic stretching section;24- card frame;25- cap ned;26- card slot;27- third holding screw;28- Shock ring;29- connecting plate;The first reinforcing rod of 30-;31- reinforces head;The second reinforcing rod of 32-;33- inserted block;34- finely tunes sliding slot; 35- flexibility gasket ring.
Specific embodiment
It as shown in Figures 1 to 6, is a kind of large-scale air cleaning equipment pipeline centralising device of the present invention, including fixed bracket 1 With cushion socket 2, fixed bracket 1 includes fixed bottom plate 3 and side stand 4, is provided with clamped sliding slot 8 on the top surface of fixed bottom plate 3.
Side stand 4 is symmetricly set on the left and right sides of fixed bottom plate 3, and side stand 4 includes limit sleeve 14 and supporting leg 15, limit The side of position set 14 is provided with limiting slot 16 and circle hole groove 17, and fixed bottom plate 3 matches with limiting slot 16, a left side for fixed bottom plate 3 Right both ends are connected in limiting slot 16, and sliding bar 10 matches with circle hole groove 17, and the end of sliding bar 10 is connected to circle hole groove 17 Interior, supporting leg 15 is uniformly arranged on the other side of limit sleeve 14, and the design of limit sleeve 14 can lead in order to the design of limiting slot 16 Installing and dismounting step, limit sleeve 14 can be simplified in order to connecting and fixing between side stand 4 and fixed bottom plate 3 by crossing limiting slot 16 The design of upper circle hole groove 17 can be in order to connecting and fixing between sliding bar 10 and side stand 4, and the design of supporting leg 15 can be so as to It fixes in the support of bracket 1 will be fixed, is fixed so that entire centralising device be supported.
Supporting leg 15 includes the first strut 18 and the second strut 19, and the first strut 18 is fixedly connected with limit sleeve 14, and second The top of strut 19 is connected in the regulating tank of 18 bottom surface of the first strut, and the second strut 19 passes through the second holding screw 20 and the The limit of one strut 18 is fixed, and the bottom of the second strut 19 connect with 21 screw of pressing plate, and the first strut 18 and the second strut 19 are set Meter is more ingenious rationally can to adjust the height of supporting leg 15 according to actual demand, thus will be entire by supporting leg 15 The fixed supports such as bracket 1 and equipment, ground are fixed, it is ensured that centralising device firmly installs performance, and pressing plate 21 ensures the second strut 19 Bottom surface in same level, thus the subsequent adjustment to 15 length of supporting leg of being more convenient for, by unscrewing the same side supporting leg The second holding screw 20 on 15, then horizontal stretch pressing plate 21 drive the adjustment of 19 upper-lower height of the second strut by pressing plate 21, change Become intubating length of second strut 19 in the regulating tank of the first strut 18, until supporting leg 15 is adjusted to suitable height, The second holding screw 20 is tightened again, and overall construction design compact and reasonable is simple and easy to use.
Cushion socket 2 is located at the top of fixed bottom plate 3, and cushion socket 2 includes damping bottom plate 5 and damping casing 6, damping bottom plate 5 Bottom surface on be provided with clamped piece 7, clamped piece 7 matches with clamped sliding slot 8, and clamped piece 7 is connected in clamped sliding slot 8, damping The front and rear sides of bottom plate 5 are provided with sliding shoe 9, extend transversely through in sliding shoe 9 and are provided with sliding bar 10, the both ends of sliding bar 10 It is connected respectively with two side stands 4, sliding shoe 9 is fixed by the first holding screw 11 and the limit of sliding bar 10.
There are two the settings of damping casing 6, logical between the front end of two damping casings 6 and the rear end of two damping casings 6 It crosses and consolidates bar 22 and be connected, the middle part for consolidating bar 22 is provided with elastic stretching section 23, elastic stretching section 23 and to consolidate bar 22 be one Forming structure, connection between two damping casings 6 may be implemented in the design for consolidating bar 22, so that the structure of cushion socket 2 is more The firm stable added, so that the damping effect of cushion socket 2 is more preferable, while the design of elastic stretching section 23 meets two shock-absorbing sleeves again The design that pipe 6 or so is finely tuned, whole design is reasonable, elastic stretching section 23 with consolidate design that bar 22 is an integral molding structure can be with Ensure to consolidate the structural strength of bar 22.
Two damping casings 6 top arranged in parallel in damping bottom plate 5, on the opposite face of two damping casings 6 Setting is provided with adjusting bracket 13 between two damping casings 6 there are two fixture block 12, and fixture block 12 is connected and fixed with adjusting bracket 13, tune The basal sliding of section frame 13 is connected on the top surface of damping bottom plate 5, and adjusting bracket 13 includes card frame 24 and cap ned 25, cap ned 25 The front and rear sides of upper end are provided with card frame 24, and the left and right ends of card frame 24 are provided with card slot 26, fixture block 12 and 26 phase of card slot Matching, fixture block 12 are connected in card slot 26, and fixture block 12 is fixed by third holding screw 27 and the limit of card frame 24, card frame 24 Design can be in order to the connection between adjusting bracket 13 and two damping casings 6, and the design of card slot 26 can be in order to fixture block 12 and card Clamping between frame 24, and the intubating length by adjusting fixture block 12 in corresponding card slot 26, can be to corresponding shock-absorbing sleeve The left-right position of pipe 6 carries out the fine tuning of small distance, so that it is guaranteed that essence between the pipeline and corresponding pipeline in each damping casing 6 Quasi- centering, the leakproofness after improving pipeline connection, prevents pipeline dislocation from influencing the connection between subsequent pipeline, cap ned 25 Design can be fixed in order to the installation between adjusting bracket 13 and damping bottom plate 5, so that it is guaranteed that the stable structure of adjusting bracket 13, more just Clamping between damping casing 6 and adjusting bracket 13 improves the structural stability of damping casing 6, third holding screw 27 indirectly Design more it is ingenious rationally, be convenient for actual operation and use, when damping casing 6 fine tuning after the completion of, by tightening third Holding screw 27 will be limited between fixture block 12 and card frame 24 and be fixed, so that it is guaranteed that damping casing 6 can not move after finely tuning, it is ensured that whole The structural strength and stability of a centralising device.
Damping casing 6 includes shock ring 28 and connecting plate 29, and shock ring 28 is provided at least three, setting in shock ring 28 Flexible gasket ring 35, the design of flexible gasket ring 35 is so that the annular distance inside shock ring 28 has certain deformation quantity, pipe of being more convenient for Socket between road and damping casing 6, and after can be socketed with pipeline and damping casing 6 again, shock ring 28 and pipeline lateral wall Between fit closely, while flexible gasket ring 35 can also protect the lateral wall of pipeline, avoid pipeline lateral wall and subtract The rigid friction between 28 inner sidewall of ring is shaken, pipeline is protected, connecting plate 29 is symmetricly set on the left and right two of shock ring 28 Side, shock ring 28 are uniformly arranged between two connecting plates 29, and shock ring 28 is welded and fixed with connecting plate 29, fixture block 12 with connect Plate 29 is fixedly connected, and may insure the socket area between damping casing 6 and pipeline by the design of multiple shock rings 28, thus Ensure the secured performance of socket of the pipeline in damping casing 6, so that the pipeline configuration in damping casing 6 is more secured, and It can also be improved the damping effect of damping casing 6 by the design of multiple shock rings 28, so that damping casing 6 shakes to Management of Pipeline Mechanical Equipment It is dynamic that there is good isolation, while the mechanical noise in pipeline use process is significantly reduced, the design of connecting plate 29 may be implemented Being connected and fixed between shock ring 28 improves the overall structural strength of damping casing 6, extends the service life of damping casing 6, really Protect the ring heart of each shock ring 28 on the same line, it is ensured that the levelness of damping casing 6, so that it is guaranteed that 6 inner sleeve of damping casing The linearity of the pipeline connect, the leakproofness convenient for the centering between subsequent two pipelines, after improving two pipe level docking.
The lower section of connecting plate 29 on two 6 opposite faces of damping casing is provided with the first reinforcing rod 30, the first reinforcing rod 30 Bottom end be provided with reinforce head 31, reinforce head 31 bottom be provided with inserted block 33, the connecting plate on two 6 opposing faces of damping casing 29 lower section is provided with the second reinforcing rod 32, and the second reinforcing rod 32 is fixedly connected with head 31 is reinforced, sets on the top surface of damping bottom plate 5 It is equipped with fine tuning sliding slot 34, inserted block 33 matches with fine tuning sliding slot 34, and inserted block 33 is connected in fine tuning sliding slot 34, the first reinforcing rod 30 Design with the second reinforcing rod 32 can be matched with adjusting bracket 13, play the role of further resilient support to damping casing 6, So that the structure of damping casing 6 is more solid and reliable, so that it is guaranteed that the stable structure for the pipeline being arranged in damping casing 6 Performance, the precise positioning for actual pipeline centering of being also more convenient for improve centering precision, and the design for reinforcing head 31 can be further The structural strength of the first reinforcing rod 30 is improved, while reinforcing first 31 design to reinforce in order to the second reinforcing rod 32 and first Being connected and fixed between bar 30, and reinforce first 31 design and can also pass through inserted block 33 and fine tuning in order to the setting of inserted block 33 The design of sliding slot 34 can the left-right position to two damping casings 6 individually finely tuned, it is ensured that the adjustment of two damping casings 6 Levelness in the process, so that it is guaranteed that the pipeline in each damping casing 6 can be with the interface of corresponding connected pipeline Precise positioning, the centering connection between pipeline of being more convenient for, avoid between pipeline dislocation influence the sealing performance after pipeline docking and Service life.
Smart structural design of the invention is reasonable, the adjustment twice to pipeline left-right position may be implemented, first to pipeline Left-right position is significantly adjusted, to pipeline is moved adjacent at docked pipeline, then to the left and right position of pipeline It sets and is finely adjusted, it is ensured that the pipeline in damping casing 6 is positioned with the centering of the casing docked, to effectively improve pipeline docking Accuracy afterwards, the docking between pipeline of being more convenient for are fixed, pipeline are socketed in damping casing 6 first, then unscrews first Holding screw 11 moves sliding shoe 9 significantly along sliding bar 10 or so, to change on damping bottom plate 5 The left-right position of damping casing 6, until by the pipeline in damping casing 6 generally move to at the position of the multipair pipeline connect, Then the first holding screw 11 is tightened, so that pipeline location at mobile position, then unscrews third holding screw 27, adjustment Length of the fixture block 12 in the regulating tank of card frame 24 reinforces the inserted block 33 of 31 bottom of head along damping bottom while fixture block 12 adjusts Fine tuning sliding slot 34 on plate 5 slides, so that it is guaranteed that the levelness that damping casing 6 or so adjusts, avoids damping casing 6 itself from tilting And cause the inclination to interface of internal pipeline, so that the docking for influencing subsequent pipeline is fixed, by adjusting fixture block 12 until By the pipeline in damping casing 6 be moved to the pipeline precise positioning that is docked, so that it is guaranteed that between two pipelines to neutrality Can, and successively the left-right position of the damping casing 6 of the left and right sides is adjusted separately, so that it is guaranteed that two damping casings 6 Accurate centering between the pipeline that interior pipeline can be docked with itself, the docking between subsequent pipeline of being more convenient for are fixed, are avoided Pipeline misplaces to interface, tilts and increases pipeline docking difficulty, causes the leakproofness at pipeline docking poor.
Support and installation positioning to entire centralising device may be implemented by the design of fixed bracket 1 in the present invention, from And ensure the structural stability and secured performance of entire centralising device, while fixed bracket 1 can also carry out the tune of oneself height It is whole, by combining the step of pipeline left-right position adjusts, the precision of pipeline centering is further increased, subsequent pipe of being more convenient for Docking between road is fixed, and improves the service life of pipeline entirety after docking, and by fixing bracket 1 for entire centralising device It can reduce the mechanical oscillation of centralising device after fixation, and then lower the mechanical oscillation of pipeline itself, so that pipeline and pipeline, setting Connection between standby is more secured, and passes through the ingehious design of 2 specific structure of cushion socket, so that cushion socket 2 both can be so as to In the adjustment of socket and pipeline left-right position to pipeline, and the good damping effect of cushion socket 2 itself, to the machine of pipeline transmitting Tool vibration has good buffer action, has remarkable effect to structural noise is reduced, and so as to improve environment, improves pipeline and equipment Service life.
The configuration of the present invention is simple, practical, smart structural design is reasonable, easy to use and operate, can effectively ensure two Centering precision between a pipeline, so that horizontal connection and fixation between subsequent two pipelines of being more convenient for, improve pipeline and connect Close performance after connecing, while the centralising device can also play damping effect, so that the use of pipeline is more steady, to pipe The mechanical oscillation of road transmitting have good isolation effect, have obvious action, and centering to the noise reduced inside pipeline The cushioning effect of device can also avoid pipeline in pipeline docking operation from shaking and the serious misalignment that causes pipeline to interface, It reduces the operation difficulty of pipeline docking, save the operating time of pipeline docking.
The above is only specific embodiments of the present invention, but technical characteristic of the invention is not limited thereto.It is any with this hair Based on bright, to realize essentially identical technical effect, made ground simple change, equivalent replacement or modification etc. are all covered Among protection scope of the present invention.

Claims (8)

1. a kind of large-scale air cleaning equipment pipeline centralising device, it is characterised in that: described solid including fixed bracket and cushion socket Fixed rack includes fixed bottom plate and side stand, is provided with clamped sliding slot on the top surface of the fixed bottom plate, the side stand is symmetrical The left and right sides of the fixed bottom plate is set, and the shock-absorbing seat includes in the top of the fixed bottom plate, the cushion socket Damping bottom plate and damping casing, are provided with clamped piece on the bottom surface of the damping bottom plate, described clamped piece with the clamped sliding slot Match, described clamped piece is connected in the clamped sliding slot, and the front and rear sides of the damping bottom plate are provided with sliding shoe, institute It states to extend transversely through in sliding shoe and is provided with sliding bar, the both ends of the sliding bar are connected with two side stands respectively, institute It states sliding shoe to fix by the first holding screw and sliding bar limit, there are two the damping casing settings, described in two The damping casing top arranged in parallel in the damping bottom plate is provided with two on the opposite face of two damping casings A fixture block is provided with adjusting bracket between two damping casings, and the fixture block is connected and fixed with the adjusting bracket, the adjusting The basal sliding of frame is connected on the top surface of the damping bottom plate.
2. a kind of large-scale air cleaning equipment pipeline centralising device according to claim 1, it is characterised in that: described collateral Frame includes limit sleeve and supporting leg, and the side of the limit sleeve is provided with limiting slot and circle hole groove, the fixed bottom plate with it is described Limiting slot matches, and the left and right ends of the fixed bottom plate are connected in the limiting slot, the sliding bar and the circle hole groove Match, the end of the sliding bar is connected in the circle hole groove, and the supporting leg is uniformly arranged on the another of the limit sleeve Side.
3. a kind of large-scale air cleaning equipment pipeline centralising device according to claim 2, it is characterised in that: the support Leg includes the first strut and the second strut, and first strut is fixedly connected with the limit sleeve, the top of second strut It is connected in the regulating tank of first strut bottom surface, and second strut passes through the second holding screw and first strut Limit is fixed, and the bottom of second strut is connect with bridge screw.
4. a kind of large-scale air cleaning equipment pipeline centralising device according to claim 1, it is characterised in that: described in two It is connected by consolidating bar between the front end of damping casing and the rear end of two damping casings, the middle part for consolidating bar It is provided with elastic stretching section, the elastic stretching section is an integral molding structure with the bar of consolidating.
5. a kind of large-scale air cleaning equipment pipeline centralising device according to claim 1, it is characterised in that: the adjusting Frame includes card frame and cap ned, and the front and rear sides of the cap ned upper end are provided with the card frame, the left and right two of the card frame End is provided with card slot, and the fixture block matches with the card slot, and the fixture block is connected in the card slot, and the fixture block is logical It crosses third holding screw and card frame limit is fixed.
6. a kind of large-scale air cleaning equipment pipeline centralising device according to claim 1, it is characterised in that: the damping Casing includes shock ring and connecting plate, and the shock ring is provided at least three, and the connecting plate is symmetricly set on the damping The left and right sides of ring, the shock ring are uniformly arranged between two connecting plates, and the shock ring and the connecting plate weld Fixation is connect, the fixture block is fixedly connected with the connecting plate.
7. a kind of large-scale air cleaning equipment pipeline centralising device according to claim 6, it is characterised in that: described in two The first reinforcing rod is provided with below the connecting plate on damping casing opposite face, the bottom end of first reinforcing rod is provided with Reinforce head, the bottom for reinforcing head is provided with inserted block, the lower section of the connecting plate on two damping casing opposing faces It is provided with the second reinforcing rod, second reinforcing rod is fixedly connected with the reinforcement head, is arranged on the top surface of the damping bottom plate There is fine tuning sliding slot, the inserted block matches with the fine tuning sliding slot, and the inserted block is connected in the fine tuning sliding slot.
8. a kind of large-scale air cleaning equipment pipeline centralising device according to claim 6, it is characterised in that: the damping Flexible gasket ring is provided in ring.
CN201811588786.8A 2018-12-25 2018-12-25 Large-scale air purification equipment pipeline centering device Active CN109664226B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811588786.8A CN109664226B (en) 2018-12-25 2018-12-25 Large-scale air purification equipment pipeline centering device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811588786.8A CN109664226B (en) 2018-12-25 2018-12-25 Large-scale air purification equipment pipeline centering device

Publications (2)

Publication Number Publication Date
CN109664226A true CN109664226A (en) 2019-04-23
CN109664226B CN109664226B (en) 2020-11-17

Family

ID=66146854

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811588786.8A Active CN109664226B (en) 2018-12-25 2018-12-25 Large-scale air purification equipment pipeline centering device

Country Status (1)

Country Link
CN (1) CN109664226B (en)

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2136113Y (en) * 1992-03-23 1993-06-16 徐桂中 Multifunctional portable cutting machine
JPH0839345A (en) * 1994-07-26 1996-02-13 Tadashi Ikeda Pipe cutter
CN1145833A (en) * 1995-07-07 1997-03-26 布莱克-德克尔公司 Adjustable fence for compound miter saw
CN1206364A (en) * 1996-10-31 1999-01-27 布莱克和戴克公司 Guard and control apparatus for sliding compound miter saw
US20050173853A1 (en) * 2004-02-06 2005-08-11 Maes Roger V. Portable vise
CN201432147Y (en) * 2009-05-08 2010-03-31 浙江工业职业技术学院 Automatic pipe cutting machine
CN202922639U (en) * 2012-11-15 2013-05-08 福建兢辉环保科技有限公司 Rotary cutting machine
CN203390980U (en) * 2013-06-29 2014-01-15 广东联塑科技实业有限公司 Equipment for longitudinally cutting large-caliber electric melting pipe
CN104084966A (en) * 2014-06-25 2014-10-08 福建省雾精灵环境科技有限公司 Rapid tube cutter
CN204471453U (en) * 2015-03-13 2015-07-15 天津旭迪聚氨酯保温防腐设备有限公司 A kind of planetary cutting saw and a kind of tubing diced system
CN104802037A (en) * 2014-01-29 2015-07-29 广东威德力机械实业股份有限公司 Double-station numerical control machining center
CN105965575A (en) * 2016-07-01 2016-09-28 成都佼佼胶粘制品有限公司 Rubber tube cutting equipment capable of avoid saw web damage
CN106994708A (en) * 2017-04-26 2017-08-01 无锡市明骥智能机械有限公司 The small-sized pipe cutting machine of standby cutter is installed
CN206393704U (en) * 2016-12-29 2017-08-11 蜀源(天津)科技发展股份有限公司 A kind of auto parts machinery electric slicer
CN107571308A (en) * 2017-09-29 2018-01-12 贵州省从江县润田复合材料有限公司 A kind of glass reinforced plastic pipe cutter device

Patent Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2136113Y (en) * 1992-03-23 1993-06-16 徐桂中 Multifunctional portable cutting machine
JPH0839345A (en) * 1994-07-26 1996-02-13 Tadashi Ikeda Pipe cutter
CN1145833A (en) * 1995-07-07 1997-03-26 布莱克-德克尔公司 Adjustable fence for compound miter saw
CN1206364A (en) * 1996-10-31 1999-01-27 布莱克和戴克公司 Guard and control apparatus for sliding compound miter saw
CN1077820C (en) * 1996-10-31 2002-01-16 布莱克和戴克公司 Guard and control apparatus for sliding compound miter saw
US20050173853A1 (en) * 2004-02-06 2005-08-11 Maes Roger V. Portable vise
CN201432147Y (en) * 2009-05-08 2010-03-31 浙江工业职业技术学院 Automatic pipe cutting machine
CN202922639U (en) * 2012-11-15 2013-05-08 福建兢辉环保科技有限公司 Rotary cutting machine
CN203390980U (en) * 2013-06-29 2014-01-15 广东联塑科技实业有限公司 Equipment for longitudinally cutting large-caliber electric melting pipe
CN104802037A (en) * 2014-01-29 2015-07-29 广东威德力机械实业股份有限公司 Double-station numerical control machining center
CN104084966A (en) * 2014-06-25 2014-10-08 福建省雾精灵环境科技有限公司 Rapid tube cutter
CN204471453U (en) * 2015-03-13 2015-07-15 天津旭迪聚氨酯保温防腐设备有限公司 A kind of planetary cutting saw and a kind of tubing diced system
CN105965575A (en) * 2016-07-01 2016-09-28 成都佼佼胶粘制品有限公司 Rubber tube cutting equipment capable of avoid saw web damage
CN206393704U (en) * 2016-12-29 2017-08-11 蜀源(天津)科技发展股份有限公司 A kind of auto parts machinery electric slicer
CN106994708A (en) * 2017-04-26 2017-08-01 无锡市明骥智能机械有限公司 The small-sized pipe cutting machine of standby cutter is installed
CN107571308A (en) * 2017-09-29 2018-01-12 贵州省从江县润田复合材料有限公司 A kind of glass reinforced plastic pipe cutter device

Also Published As

Publication number Publication date
CN109664226B (en) 2020-11-17

Similar Documents

Publication Publication Date Title
CN106764077B (en) Petroleum pipeline damping base and its working method
CN207179055U (en) A kind of motor base of good damping effect
CN109664226A (en) A kind of large-scale air cleaning equipment pipeline centralising device
CN108899054A (en) A kind of computer hardware installing mechanism damping device
CN208112407U (en) A kind of motor mounting rack with shock-absorbing function
CN110425340A (en) A kind of tube support arrangement for drainage system
CN208587604U (en) A kind of adjustable natural gas line support frame
CN208457514U (en) A kind of safety monitoring equipment mounting bracket
CN208082838U (en) Vibrating screening machine
CN209488685U (en) A kind of device increasing solar powered WiFi camera stability
CN209691528U (en) A kind of transformer quake-proof supporting structure
CN108612961A (en) A kind of damping type engine support
CN208527285U (en) A kind of sandstone used by oscillating screen damping device
CN108167158A (en) A kind of damping air press
CN208237348U (en) A kind of combined anti-seismic bracket
CN109798322A (en) A kind of gas pressure adjustable damper
KR102498190B1 (en) Automobile antifreeze recovery device
CN219131969U (en) Shot blasting machine with support mechanism
CN108155578A (en) A kind of adjustable distribution box support plate in shock type position
CN213328071U (en) Adjusting mechanism of upper frame of textile machine
CN210920716U (en) Shock absorption support for radiator
CN216101126U (en) Damping base for printing machine
CN211600141U (en) Balance calibration device for mounting electromechanical equipment
CN221034679U (en) Noise reduction device for pump of water supply machine
CN208533584U (en) One kind putting sedimentation tubular pole model

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20201103

Address after: 7-5-b-32, 8 Xingguo Road, Gaogang District, Taizhou City, Jiangsu Province 225300

Applicant after: Taizhou JINDA Electronic Technology Co., Ltd

Address before: 312400 No. 41, Wang Jia Shu'ao Village, Sanjie Town, Shengzhou City, Shaoxing City, Zhejiang Province

Applicant before: SHENGZHOU KAIFENG TEXTILE MACHINERY Co.,Ltd.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant