CN109653225A - Steel sheet-pile cofferdam and its construction method - Google Patents

Steel sheet-pile cofferdam and its construction method Download PDF

Info

Publication number
CN109653225A
CN109653225A CN201811645414.4A CN201811645414A CN109653225A CN 109653225 A CN109653225 A CN 109653225A CN 201811645414 A CN201811645414 A CN 201811645414A CN 109653225 A CN109653225 A CN 109653225A
Authority
CN
China
Prior art keywords
pile
steel sheet
leading truck
cofferdam
casting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811645414.4A
Other languages
Chinese (zh)
Other versions
CN109653225B (en
Inventor
薛斌
肖必忠
吕荣海
李斌
姚光群
冯嘉佳
李艾梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Road and Bridge Engineering Co Ltd
Original Assignee
Anhui Road and Bridge Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Road and Bridge Engineering Co Ltd filed Critical Anhui Road and Bridge Engineering Co Ltd
Priority to CN201811645414.4A priority Critical patent/CN109653225B/en
Publication of CN109653225A publication Critical patent/CN109653225A/en
Application granted granted Critical
Publication of CN109653225B publication Critical patent/CN109653225B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The present invention relates to steel sheet-pile cofferdams, including the interim casting platform of steel sheet-pile cofferdam leading truck, steel sheet-pile cofferdam and steel sheet-pile cofferdam systems stabilisation;The steel sheet-pile cofferdam systems stabilisation includes steel pile casting, cross-brace, longitudinal bracing, balance sand pocket, hoist engine and hangs peaceful;The steel sheet-pile cofferdam leading truck includes interior leading truck, outer leading truck and leading truck support system;The interim casting platform of steel sheet-pile cofferdam includes fixed rack, casting platform and pours device.The beneficial effects of the present invention are: fixed rack is fixed at the top of steel pile casting by the present invention, then casting platform is chimeric with fixed rack, and platform sliding wheel is set on platform, slide casting platform along fixed rack, in addition pouring device can slide along the pipe slideway that pours on casting platform, and final back cover range can cover entire cofferdam place.

Description

Steel sheet-pile cofferdam and its construction method
Technical field
The invention belongs to cofferdam field more particularly to a kind of steel sheet-pile cofferdam and its construction methods.
Background technique
Cofferdam refers in hydraulic engineering construction, to build permanent water conservancy projects, the provisional building enclosure built.Its Effect is to prevent water and soil from building position into building, so that in cofferdam internal drainage, excavation pit builds building.One As be mainly used in waterwork, except as formal building a part in addition to, cofferdam is generally removed after being finished.Cofferdam height Higher than the peak level being likely to occur in the construction time.Traditional cofferdam often deflects during beating steel sheet pile, thus needs The hole being adapted with steel sheet pile size is excavated in advance, steel sheet pile is hung in hole using crane, to ensure steel sheet pile not Run-off the straight, however this method have the defects that it is certain, if the heatable adobe sleeping platform size excavated in advance is inaccurate, it is less than normal can not will Steel sheet pile is put into, and steel sheet pile bigger than normal still can run-off the straight.In addition in coffering it is general all can back cover, traditional construction method will Pour pipe to be passed through at back cover position, then concrete perfusion, to a construction section after, then move the device into next apply Workshop section.This method efficiency is lower, during back cover, if cofferdam region is larger, repeatedly movement is needed to pour device, and pours Device volume is larger, needs to expend a large amount of manpower and material resources;The mode of fine sand is inserted in engineering in cofferdam two sides to improve cofferdam Shock resistance, although this method can effectively improve the impact resistance in cofferdam, the fine sand of filling is being constructed After be not easily recycled.
It can ensure that steel sheet pile sets verticality, efficient back cover and cofferdam can be improved in conclusion needing to invent one kind at present The steel sheet-pile cofferdam and its construction method of impact capacity.
Summary of the invention
The purpose of the present invention is overcoming deficiency in the prior art, a kind of steel sheet-pile cofferdam and its construction method are provided.
This steel sheet-pile cofferdam, including the interim casting platform of steel sheet-pile cofferdam leading truck, steel sheet-pile cofferdam and steel sheet pile enclose Weir systems stabilisation;
The steel sheet-pile cofferdam systems stabilisation include steel pile casting, cross-brace, longitudinal bracing, balance sand pocket, hoist engine and Peaceful is hung, setting cross-brace and longitudinal bracing at the top of cofferdam, vertically and horizontally support lower section is equipped with steel pile casting, the steel of edge Casing is equipped with gusseted, and gusseted is equipped with guide table, is equipped at the top of guide table and hangs peaceful, hang on peaceful platform Hoist engine is placed, balance sand pocket is placed on cofferdam two sides by hanging peaceful by hoist engine;Cofferdam is formed by Larsen steel sheet pile spelling, Closed up on four angles in cofferdam by profile iron sheet pile;
The steel sheet-pile cofferdam leading truck includes interior leading truck, outer leading truck and leading truck support system, leading truck support It is supported by leading truck in system, leading truck is divided into interior leading truck and outer leading truck, opposite one on interior leading truck and outer leading truck Side is equipped with internal layer slideway;Leading truck includes positioning fixture, universal wheel, connecting plate, cylindrical bar and cylindrical slide, under positioning fixture Side is equipped with universal wheel, and positioning fixture is equipped with cylindrical slide by connecting plate connecting cylinder bar, cylindrical bar inside, and positioning fixture is being led It is slided on the internal layer slideway of frame;The leading truck support system include the gusseted being fixed on steel pile casting and be located at guiding The guide support frame of frame bottom;
The interim casting platform of steel sheet-pile cofferdam includes fixed rack, casting platform and pours device;Fixed rack is solid It is scheduled at the top of steel pile casting, casting platform is fixed on fixed rack, is placed on casting platform and is poured device, casting platform is in fixation It is slided on sliding rail, pours device and slided on casting platform.
As preferred: being connected between Larsen steel sheet pile by connector, close up between the Larsen steel sheet pile at place and deformed steel flats is arranged Stake, profile iron sheet pile are connect with Larsen steel sheet pile by connector;Guide table is connected by bearing diagonal.
As preferred: being connected with lifting rope on balance sand pocket, lifting rope one end connects hoist engine;Hang peaceful by hoist engine track and A liter mouth composition is hung, lifting rope is pierced by from a liter mouth is hung.
As preferred: the gusseted includes support plate, diagonal brace and casing connecting plate, and casing connecting plate is welded on steel shield On cylinder, it is provided with support plate on casing connecting plate, is welded with diagonal brace between casing connecting plate and support plate.
As preferred: guide support frame is made of support platform, vertical supporting and bridging.
As preferred: being equipped on the outside of positioning fixture and be oriented to sharp rib, Larsen steel sheet pile is placed along sharp rib is oriented to, Larsen steel plate Stake is matched with sharp rib is oriented to.
As preferred: sliding rail preformed groove is reserved in the casting platform bottom, is provided with platform at the top of sliding rail preformed groove and slides Wheel, platform sliding wheel are fitted and fixed with sliding rail.
As preferred: the device that pours placed on the casting platform includes pouring hopper, sliding wheel, pouring pipe and back cover Plate, back cover plate, which is bolted, is pouring bottom of the tube, and junction is equipped with splice plate and screw hole;Pour pipe upper end connection pouring material Bucket pours hopper lower part equipped with sliding wheel;Pipe and sliding wheel is poured to match with the pipe slideway that pours of casting platform.
The construction method of this steel sheet-pile cofferdam, comprising the following steps:
1) prefabricated steel pile casting;Prefabricated steel pile casting, and gusseted is welded for branch on the casing for partially having support function Support leading truck;
2) steel pile casting is constructed;Steel pile casting is lifted to construction site using crane;
3) leading truck is placed;In leading truck corresponding position, vertical supporting is set, vertical supporting is spliced with steel pipe, and Bridging is set on adjacent steel pipe;Then interior leading truck and outer leading truck are placed in support platform and gusseted;
4) bearing diagonal is constructed;One of bearing diagonal is set on adjacent leading truck, twice guide table is made to link together;
5) cofferdam construction;Larsen steel sheet pile is hung using crane and rises to position corresponding to inside and outside leading truck, then sliding is led Positioning fixture on frame, Larsen steel sheet pile is along the guiding point rib slide downward on positioning fixture, to Larsen steel sheet pile construction After the completion, it pushes the cylindrical bar on positioning fixture to cylindrical slide, inside contracts positioning fixture, be detached from Larsen steel sheet pile, then move It moves the next position and cylindrical bar is pushed outwardly exposing positioning fixture, carry out the construction of next Larsen steel sheet pile;
6) casting platform is constructed;Fixed rack is fixed on the steel pile casting at both ends, then by the sliding rail of casting platform Preformed groove is chimeric with fixed rack, and the two is made to be stitched together;
7) device installation is poured;Device will be poured using crane to transfer along the pipe slideway that pours on casting platform, makes to pour Hopper clamping connection is built on casting platform, then back cover plate is connected to and pours bottom of the tube;
8) back cover;By concrete along pouring hopper and pour pipe and be cast in place bottom;
9) vertically and horizontally Construction of Supporting;It is arranged at the top of cofferdam and vertically and horizontally supports;
10) balance sand pocket construction;It is placed at the top of leading truck and hangs peaceful, and place hoist engine on hanging peaceful platform, benefit Balance sand pocket is placed in cofferdam two sides with hoist engine, the lifting or decline of balance sand pocket are controlled by hoist engine.
The beneficial effects of the present invention are:
(1) present invention places sand pocket in cofferdam two sides to improve the impact resistance in cofferdam, controls sand pocket using hoist engine Rising and decline, can be improved shock resistance, but also not only convenient for recycling.
(2) fixed rack is fixed at the top of steel pile casting by the present invention, then that casting platform is chimeric with fixed rack, and Platform sliding wheel is set on platform, slides casting platform along fixed rack, in addition pouring device can be along pouring The pipe slideway that pours on platform slides, and final back cover range can cover entire cofferdam place.
(3) present invention devises steel sheet pile leading truck, and steel sheet pile can be transferred along the positioning fixture on leading truck, positioning Fixture may insure the verticality of steel sheet pile, and simplify work progress.
Detailed description of the invention
Fig. 1 is steel sheet-pile cofferdam overall top view;
Fig. 2 is the steel sheet-pile cofferdam systems stabilisation schematic diagram in Fig. 1;
Fig. 3 is detail drawing at A in Fig. 2;
Fig. 4 is detail drawing at B in Fig. 2;
Fig. 5 is the profile iron sheet pile schematic diagram in Fig. 3;
Fig. 6 is the Section A-A figure in Fig. 2;
Fig. 7 is the steel sheet-pile cofferdam leading truck schematic diagram in Fig. 1;
Fig. 8 is the leading truck top view in Fig. 7;
Fig. 9 is the leading truck front view in Fig. 7;
Figure 10 is the leading truck side view in Fig. 7;
Figure 11 is the section B-B figure in Fig. 7;
Figure 12 is the interim casting platform schematic diagram of steel sheet-pile cofferdam in Fig. 1;
Figure 13 is the C-C sectional view in Figure 12;
Figure 14 is to pour schematic device in Figure 12;
Figure 15 is detail drawing at C in Figure 14.
Description of symbols: 1-Larsen steel sheet pile;2-profile iron sheet piles;3-connectors;4-steel pile castings;5-bearing diagonals; 6-cross-braces;7-longitudinal bracings;8-guide tables;9-guide support framves;10-lifting ropes;11-hang peaceful;12— Hang a liter mouth;13-balance sand pockets;14-hoist engines;15-support plates;16-outer leading trucks;17-interior leading trucks;18-internal layers Slideway;19-positioning fixtures;20-universal wheels;21-connecting plates;22-cylindrical bars;23-cylindrical slides;24-vertical supportings; 25-bridgings;26-support platforms;27-fixed racks;28-pour hopper;29-casting platforms;30-, which pour pipe, slides Road;31-pour pipe;32-sliding wheels;33-sliding rail preformed grooves;34-screw holes;35-splice plates;36-cofferdam;37-tiltedly Support;38-casing connecting plates;39-are oriented to sharp rib;40-hoist engine tracks;41-back cover plates;42-platform sliding wheels.
Specific embodiment
The present invention is described further below with reference to embodiment.The explanation of following embodiments is merely used to help understand this Invention.It should be pointed out that for those skilled in the art, without departing from the principle of the present invention, also Can be with several improvements and modifications are made to the present invention, these improvement and modification also fall into the protection scope of the claims in the present invention It is interior.
The steel sheet-pile cofferdam, including the interim casting platform of steel sheet-pile cofferdam leading truck, steel sheet-pile cofferdam and steel sheet pile Cofferdam systems stabilisation;
The steel sheet-pile cofferdam systems stabilisation includes steel pile casting 4, cross-brace 6, longitudinal bracing 7, balance sand pocket 13, elevator Machine 14 and hanging peaceful 11, setting cross-brace 6 and longitudinal bracing 7 at the top of cofferdam, vertically and horizontally support lower section is equipped with steel pile casting 4, The steel pile casting 4 of edge is equipped with gusseted, and gusseted is equipped with guide table 8, is equipped at the top of guide table 8 and hangs liter Platform 11, hangs placement hoist engine 14 on peaceful 11, and balance sand pocket 13 is placed on cofferdam 36 by hanging peaceful 11 by hoist engine 14 Two sides improve the protecting against shock ability in cofferdam, improve the stability in cofferdam;Cofferdam is formed by 1 spelling of Larsen steel sheet pile, and the four of cofferdam Closed up on a angle by profile iron sheet pile 2;
The steel sheet-pile cofferdam leading truck includes interior leading truck 17, outer leading truck 16 and leading truck support system, leading truck Leading truck is supported by support system, leading truck is divided into interior leading truck 17 and outer leading truck 16, interior leading truck 17 and outer leading truck Opposite side is equipped with internal layer slideway 18 on 16;Leading truck includes positioning fixture 19, universal wheel 20, connecting plate 21, cylindrical bar 22 and cylindrical slide 23, be equipped with universal wheel 20 below positioning fixture 19, positioning fixture 19 by 21 connecting cylinder bar 22 of connecting plate, Cylindrical slide 23 is equipped on the inside of cylindrical bar 22, positioning fixture 19 slides on the internal layer slideway 18 of leading truck;The leading truck branch Support body system includes the gusseted being fixed on steel pile casting 4 and the guide support frame 9 positioned at leading truck bottom;
The interim casting platform of steel sheet-pile cofferdam includes fixed rack 27, casting platform 29 and pours device;It is fixed to slide Rail 27 is fixed on 4 top of steel pile casting, and casting platform 29 is fixed on fixed rack 27, places on casting platform 29 and pour device, Casting platform 29 slides on fixed rack 27, pours device and slides on casting platform 29, therefore the interim casting platform Entire cofferdam can be covered by pouring range.
It is connected between Larsen steel sheet pile 1 by connector 3, closes up setting profile iron sheet pile 2 between the Larsen steel sheet pile 1 at place, it is different Shape steel sheet pile 2 is connect with Larsen steel sheet pile 1 by connector 3;Guide table 8 is connected by bearing diagonal 5, improves guide table 8 Stability.
Lifting rope 10 is connected on balance sand pocket 13,10 one end of lifting rope connects hoist engine 14;Peaceful 11 is hung by hoist engine track 40 form with liter mouth 12 is hung, and lifting rope 10 is pierced by from liter mouth 12 is hung.
Gusseted includes support plate 15, diagonal brace 37 and casing connecting plate 38, and casing connecting plate 38 is welded on steel pile casting 4 On, it is provided with support plate 15 on casing connecting plate 38, diagonal brace 37 is welded between casing connecting plate 38 and support plate 15.
Guide support frame 9 is made of support platform 26, vertical supporting 24 and bridging 25.
It is equipped on the outside of positioning fixture 19 and is oriented to sharp rib 39, Larsen steel sheet pile 1 is placed along sharp rib 39 is oriented to, Larsen steel sheet pile 1 matches with sharp rib 39 is oriented to.
Sliding rail preformed groove 33 is reserved in 29 bottom of casting platform, is provided with platform sliding wheel at the top of sliding rail preformed groove 33 42, platform sliding wheel 42 is fitted and fixed with sliding rail 27.
The device that pours placed on the casting platform 29 includes pouring hopper 28, sliding wheel 32, pouring pipe 31 and back cover Plate 41, back cover plate 41, which is bolted, is pouring 31 bottom of pipe, and junction is equipped with splice plate 35 and screw hole 34, it can be ensured that pours The concrete horizontal back cover built;It pours the connection of 31 upper end of pipe and pours hopper 28, pour 28 lower part of hopper equipped with sliding wheel 32;It pours Pipe 31 and sliding wheel 32 are matched with the pipe slideway 30 that pours of casting platform 29.
The construction method of the steel sheet-pile cofferdam, comprising the following steps:
1) prefabricated steel pile casting 4;Prefabricated steel pile casting 4, and weld gusseted on the casing for partially having support function and be used for Support guide frame;
2) steel pile casting 4 is constructed;Steel pile casting 4 is lifted to construction site using crane, the position of steel pile casting 4 need to be with design side Case is corresponding;
3) leading truck is placed;In leading truck corresponding position, vertical supporting 24 is set, vertical supporting 24 is spliced with steel pipe, And bridging 25 is set on adjacent steel pipe;Then interior leading truck 17 and outer leading truck 16 are placed on support platform 26 and triangle In support;
4) bearing diagonal 5 is constructed;One of bearing diagonal 5 is set on adjacent leading truck, twice guide table 8 is made to be connected to one It rises;
5) cofferdam 36 is constructed;Larsen steel sheet pile 1 is hung using crane and rises to position corresponding to inside and outside leading truck, is then slided Positioning fixture 19 on leading truck, Larsen steel sheet pile 1 is along 39 slide downward of guiding point rib on positioning fixture 19, to Larsen steel After the completion of sheet pile 1 is constructed, pushes the cylindrical bar 22 on positioning fixture 19 to cylindrical slide 23, inside contract positioning fixture 19, be detached from Larsen steel sheet pile 1 then moves to the next position and is pushed outwardly cylindrical bar 22 and expose positioning fixture 19, carries out next drawing The construction of gloomy steel sheet pile 1;
6) casting platform 29 is constructed;Fixed rack 27 is fixed on the steel pile casting 4 at both ends, then by casting platform 29 Sliding rail preformed groove 33 it is chimeric with fixed rack 27, both make to be stitched together;
7) device installation is poured;Device will be poured using crane to transfer along the pipe slideway 30 that pours on casting platform 29, Make to pour 28 clamping connection of hopper on casting platform 29, then back cover plate 41 is connected to and pours 31 bottom of pipe;
8) back cover;By concrete along pouring hopper 28 and pour pipe 31 and be cast in place bottom;
9) vertically and horizontally Construction of Supporting;It is arranged at the top of cofferdam 36 and vertically and horizontally supports, improves the stability in cofferdam 36;
10) balance sand pocket 13 is constructed;It is placed at the top of leading truck and hangs peaceful 11, and place elevator on hanging peaceful 11 Machine 14, using hoist engine 14 36 two sides of cofferdam place balance sand pocket 13, by hoist engine 36 control balance sand pocket 13 lifting or Decline.

Claims (9)

1. a kind of steel sheet-pile cofferdam, which is characterized in that including steel sheet-pile cofferdam leading truck, the interim casting platform of steel sheet-pile cofferdam and Steel sheet-pile cofferdam systems stabilisation;
The steel sheet-pile cofferdam systems stabilisation include steel pile casting (4), cross-brace (6), longitudinal bracing (7), balance sand pocket (13), It hoist engine (14) and hangs peaceful (11), setting cross-brace (6) and longitudinal bracing (7) at the top of cofferdam, vertically and horizontally support lower section Equipped with steel pile casting (4), the steel pile casting (4) of edge is equipped with gusseted, and gusseted is equipped with guide table (8), leads It is equipped at the top of to platform (8) and hangs peaceful (11), hang placement hoist engine (14) on peaceful (11), hoist engine (14) is by hanging liter Platform (11) will balance sand pocket (13) and be placed on cofferdam (36) two sides;Cofferdam is formed by Larsen steel sheet pile (1) spelling, and four of cofferdam Closed up on angle by profile iron sheet pile (2);
The steel sheet-pile cofferdam leading truck includes interior leading truck (17), outer leading truck (16) and leading truck support system, leading truck It is supported by leading truck on support system, leading truck is divided into interior leading truck (17) and outer leading truck (16), interior leading truck (17) and outer Opposite side is equipped with internal layer slideway (18) on leading truck (16);Leading truck includes positioning fixture (19), universal wheel (20), connects Fishplate bar (21), cylindrical bar (22) and cylindrical slide (23), positioning fixture (19) lower section are equipped with universal wheel (20), positioning fixture (19) By connecting plate (21) connecting cylinder bar (22), cylindrical slide (23) are equipped on the inside of cylindrical bar (22), positioning fixture (19) is being led It is slided on the internal layer slideway (18) of frame;The leading truck support system include the gusseted that is fixed on steel pile casting (4) and Guide support frame (9) positioned at leading truck bottom;
The interim casting platform of steel sheet-pile cofferdam includes fixed rack (27), casting platform (29) and pours device;It is fixed to slide Rail (27) is fixed at the top of steel pile casting (4), and casting platform (29) is fixed on fixed rack (27), and casting platform is placed on (29) Device is poured, casting platform (29) slides on fixed rack (27), pours device and slides on casting platform (29).
2. steel sheet-pile cofferdam according to claim 1, which is characterized in that between Larsen steel sheet pile (1) even by connector (3) It connects, closes up setting profile iron sheet pile (2) between the Larsen steel sheet pile (1) at place, profile iron sheet pile (2) passes through with Larsen steel sheet pile (1) Connector (3) connection;Guide table (8) is connected by bearing diagonal (5).
3. steel sheet-pile cofferdam according to claim 1, which is characterized in that be connected with lifting rope (10) in balance sand pocket (13), hang Rope (10) one end connection hoist engine (14);Peaceful (11) are hung by hoist engine track (40) and hangs a liter mouth (12) and forms, lifting rope (10) it is pierced by from hanging a liter mouth (12).
4. steel sheet-pile cofferdam according to claim 1, which is characterized in that the gusseted include support plate (15), tiltedly Support (37) and casing connecting plate (38), casing connecting plate (38) are welded on steel pile casting (4), and casing connecting plate is provided on (38) Support plate (15) is welded with diagonal brace (37) between casing connecting plate (38) and support plate (15).
5. steel sheet-pile cofferdam according to claim 1, which is characterized in that guide support frame (9) is by support platform (26), perpendicular It is formed to support (24) and bridging (25).
6. steel sheet-pile cofferdam according to claim 1, which is characterized in that be equipped on the outside of positioning fixture (19) and be oriented to sharp rib (39), Larsen steel sheet pile (1) is placed along sharp rib (39) is oriented to, and Larsen steel sheet pile (1) is matched with sharp rib (39) is oriented to.
7. steel sheet-pile cofferdam according to claim 1, which is characterized in that it is pre- that sliding rail is reserved in casting platform (29) bottom It stays slot (33), is provided with platform sliding wheel (42) at the top of sliding rail preformed groove (33), platform sliding wheel (42) is fitted and fixed with sliding rail (27)。
8. steel sheet-pile cofferdam according to claim 1, which is characterized in that places on the casting platform (29) pours dress It sets including pouring hopper (28), sliding wheel (32), pouring pipe (31) and back cover plate (41), back cover plate (41) is bolted Pipe (31) bottom is poured, junction is equipped with splice plate (35) and screw hole (34);It pours the connection of pipe (31) upper end and pours hopper (28), Hopper (28) lower part is poured equipped with sliding wheel (32);The pipe that pours for pouring pipe (31) and sliding wheel (32) and casting platform (29) is slided Road (30) matches.
9. a kind of construction method of steel sheet-pile cofferdam as described in claim 1, which comprises the following steps:
1) prefabricated steel pile casting (4);Prefabricated steel pile casting (4), and weld gusseted on the casing for partially having support function and be used for Support guide frame;
2) steel pile casting (4) is constructed;Steel pile casting (4) is lifted to construction site using crane;
3) leading truck is placed;In leading truck corresponding position, vertical supporting (24) are set, vertical supporting (24) is spliced with steel pipe, And bridging (25) are set on adjacent steel pipe;Then interior leading truck (17) and outer leading truck (16) are placed on support platform (26) and in gusseted;
4) bearing diagonal (5) is constructed;One of bearing diagonal (5) are set on adjacent leading truck, are connected to twice guide table (8) Together;
5) cofferdam (36) construct;Larsen steel sheet pile (1) is hung using crane and rises to position corresponding to inside and outside leading truck, is then slided Positioning fixture (19) on leading truck, Larsen steel sheet pile (1) along guiding point rib (39) slide downward on positioning fixture (19), After the completion of Larsen steel sheet pile (1) construction, pushes the cylindrical bar (22) on positioning fixture (19) to cylindrical slide (23), make to position Fixture (19) inside contracts, and is detached from Larsen steel sheet pile (1), then moves to the next position and cylindrical bar (22) is pushed outwardly exposing and determine Position fixture (19), carries out the construction of next Larsen steel sheet pile (1);
6) casting platform (29) is constructed;Fixed rack (27) is fixed on the steel pile casting (4) at both ends, then by casting platform (29) sliding rail preformed groove (33) is chimeric with fixed rack (27), and the two is made to be stitched together;
7) device installation is poured;Device will be poured using crane to transfer along pour pipe slideway (30) on casting platform (29), Make to pour hopper (28) clamping connection on casting platform (29), then back cover plate (41) is connected to and pours pipe (31) bottom;
8) back cover;Concrete is cast in place bottom along pouring hopper (28) and pour pipe (31);
9) vertically and horizontally Construction of Supporting;Setting vertically and horizontally supports at the top of cofferdam (36);
10) balance sand pocket (13) construction;It places and hangs peaceful (11) at the top of leading truck, and place volume on hanging peaceful (11) Machine (14) are raised, balance sand pocket (13) is placed in cofferdam (36) two sides using hoist engine (14), controls balance sand by hoist engine (36) The lifting or decline of bag (13).
CN201811645414.4A 2018-12-30 2018-12-30 Steel sheet pile cofferdam and construction method thereof Active CN109653225B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811645414.4A CN109653225B (en) 2018-12-30 2018-12-30 Steel sheet pile cofferdam and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811645414.4A CN109653225B (en) 2018-12-30 2018-12-30 Steel sheet pile cofferdam and construction method thereof

Publications (2)

Publication Number Publication Date
CN109653225A true CN109653225A (en) 2019-04-19
CN109653225B CN109653225B (en) 2020-12-25

Family

ID=66118052

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811645414.4A Active CN109653225B (en) 2018-12-30 2018-12-30 Steel sheet pile cofferdam and construction method thereof

Country Status (1)

Country Link
CN (1) CN109653225B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110965556A (en) * 2019-11-20 2020-04-07 中建桥梁有限公司 Large-area underwater concrete pouring method
CN111691443A (en) * 2020-06-22 2020-09-22 福建省华策建设集团有限公司 Larsen steel sheet pile cofferdam and construction method thereof
CN114482077A (en) * 2022-04-13 2022-05-13 三亚宏岩岩土工程有限公司 Foundation ditch intelligence braced system with antiseismic impervious effect

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6231271B1 (en) * 1999-04-05 2001-05-15 Stab Cat, Inc Apparatus and method for lifting piles
CN106013192A (en) * 2016-06-15 2016-10-12 中铁港航局集团有限公司 Method of constructing cofferdam after integrally lowering multiple layers of inner bracings of steel sheet pile cofferdam
JP6132606B2 (en) * 2013-03-14 2017-05-24 株式会社技研製作所 Mounting method of clamp device in pile press-in device
CN206359983U (en) * 2017-01-04 2017-07-28 中建筑港集团有限公司 One kind is used for steel plate sunk pile roller stopping means
CN208167737U (en) * 2018-04-25 2018-11-30 江苏省交通工程集团有限公司 A kind of U-shaped steel sheet pile pile sinking limiting device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6231271B1 (en) * 1999-04-05 2001-05-15 Stab Cat, Inc Apparatus and method for lifting piles
JP6132606B2 (en) * 2013-03-14 2017-05-24 株式会社技研製作所 Mounting method of clamp device in pile press-in device
CN106013192A (en) * 2016-06-15 2016-10-12 中铁港航局集团有限公司 Method of constructing cofferdam after integrally lowering multiple layers of inner bracings of steel sheet pile cofferdam
CN206359983U (en) * 2017-01-04 2017-07-28 中建筑港集团有限公司 One kind is used for steel plate sunk pile roller stopping means
CN208167737U (en) * 2018-04-25 2018-11-30 江苏省交通工程集团有限公司 A kind of U-shaped steel sheet pile pile sinking limiting device

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110965556A (en) * 2019-11-20 2020-04-07 中建桥梁有限公司 Large-area underwater concrete pouring method
CN111691443A (en) * 2020-06-22 2020-09-22 福建省华策建设集团有限公司 Larsen steel sheet pile cofferdam and construction method thereof
CN111691443B (en) * 2020-06-22 2021-09-28 福建省华策建设集团有限公司 Larsen steel sheet pile cofferdam and construction method thereof
CN114482077A (en) * 2022-04-13 2022-05-13 三亚宏岩岩土工程有限公司 Foundation ditch intelligence braced system with antiseismic impervious effect
CN114482077B (en) * 2022-04-13 2022-06-28 三亚宏岩岩土工程有限公司 Foundation ditch intelligence braced system with impervious effect of antidetonation

Also Published As

Publication number Publication date
CN109653225B (en) 2020-12-25

Similar Documents

Publication Publication Date Title
CN101838993B (en) Construction technology of steel sheet pile cofferdam for Yellow River Channel internal support table construction
CN109653225A (en) Steel sheet-pile cofferdam and its construction method
CN108330995A (en) Construction method of steel sheet pile cofferdam in deep water thick silt layer environment
CN104878733B (en) A kind of drilling platform leg segment folding technique
CN111456019A (en) Safe construction method for foundation pit excavation
CN110258539A (en) Cast-in-situ bored pile and its construction method in water
CN111058458A (en) Construction method and structure based on cutter suction type ground connecting wall local replacement row pile support
CN106948353A (en) A kind of deep water combined steel plate pile cofferdam construction method
CN110172977B (en) Construction method and structure for preventing concrete at pile top of foundation pit supporting steel column filling pile from being excessively poured
CN112878332A (en) Basement elevator shaft sump construction structure and method thereof
CN106351180A (en) Full hydraulic opening self-propelled template system for aqueduct
CN204000905U (en) A kind of Double-Wall Steel Boxed Cofferdam with binder deep water bearing platform construction
CN108643206A (en) Exempt from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device and its construction method
CN214738191U (en) Steel plate caisson structure for local foundation pit
CN107938675A (en) A kind of Vertical spots concrete placings technique and device
CN205917601U (en) Integrally lift up device of bridge arch rib
CN109594581A (en) Cross a river segment pipe structure and its installation method
CN212641437U (en) Pile-forming orifice operation device for large-diameter ultra-deep cast-in-place pile
CN103132508A (en) Pile-filling machine
CN207862964U (en) A kind of land bearing platform construction system
CN210712855U (en) Foundation pit support steel stand bored concrete pile bolck concrete prevents surpassing and irritates construction structures
CN106149732B (en) A kind of deep basal pit faces side large scale hoisting machinery construction method for hanging
CN209837060U (en) Steel sheet pile cofferdam
CN208455615U (en) A kind of prefabricated guide groove structure of concrete cut
CN105926632B (en) Detachable unearthed platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant