CN109610922A - A kind of typical case's landform tower erection construction equipment - Google Patents

A kind of typical case's landform tower erection construction equipment Download PDF

Info

Publication number
CN109610922A
CN109610922A CN201811541805.1A CN201811541805A CN109610922A CN 109610922 A CN109610922 A CN 109610922A CN 201811541805 A CN201811541805 A CN 201811541805A CN 109610922 A CN109610922 A CN 109610922A
Authority
CN
China
Prior art keywords
amplitude modulation
overhead cable
steel tower
rope
main body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811541805.1A
Other languages
Chinese (zh)
Other versions
CN109610922B (en
Inventor
王晓刚
陈孝阳
王李君
陈治明
李雪红
王健
范龙华
罗修明
何洋
袁茂书
黄君蓉
次仁桑布
徐毅
苗峰显
宋洪磊
宋富勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Shu Neng Utilities Electric Co Ltd
State Grid Tibet Electric Power Co Ltd
Original Assignee
Sichuan Shu Neng Utilities Electric Co Ltd
State Grid Tibet Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Shu Neng Utilities Electric Co Ltd, State Grid Tibet Electric Power Co Ltd filed Critical Sichuan Shu Neng Utilities Electric Co Ltd
Priority to CN201811541805.1A priority Critical patent/CN109610922B/en
Publication of CN109610922A publication Critical patent/CN109610922A/en
Application granted granted Critical
Publication of CN109610922B publication Critical patent/CN109610922B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Electric Cable Installation (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of typical landform tower erection construction equipments, including main pole bow segment, rotary four-way connector and the main pole standard paragraphs from top to bottom sequentially coaxially connected in steel tower main body, rotary four-way connector left and right ends are equipped with boom, and hanging piece is equipped with suspension centre rope;It is equipped with lifting component at left and right sides of steel tower main body, is equipped in the middle part of steel tower lower body and produces bracket;Lifting by crane component includes amplitude modulation draw off gear, amplitude modulation angle pulley, overhead cable draw off gear and the overhead cable angle pulley group being successively fixed on side by side on the outside of steel tower lower body, arm head sheave, amplitude modulation trolley and two head angle pulley groups, two pull round pulley, two motor-driven grinding mills, amplitude modulation rope, traction rope, leading block group and two overhead cables;Amplitude modulation trolley both ends are respectively equipped with amplitude modulation rear wheel and amplitude modulation front wheel, and overhead cable lifting lug is arranged below in amplitude modulation trolley.Hanging piece abutting joint can be rapidly completed in the present invention, can effectively improve safety guarantee and construction efficiency.

Description

A kind of typical case's landform tower erection construction equipment
Technical field
Present invention relates particularly to a kind of typical landform tower erection construction equipments.
Background technique
Inner suspended inner guy pole group tower technology, pole have it is light, compact, be conducive to assembling, structure it is simple, convenient for the palm The features such as holding has been widely used, but there is also construction efficiency it is low, security performance is relatively poor the deficiencies of place.Ground type The advanced group of high tower technologies of security performances such as flat arm pole group tower technology, ground type rocker pole lifting group tower technology, have peace The advantages that full performance is high, single lifting hoist is big, lifting is steady, but also have its limitation, exist group tower itself transport, Assemble, debug, remove it is time-consuming and laborious, and it is costly the deficiencies of place.Therefore, these advanced technologies are only in traffic condition It is good, under the conditions of orographic condition is good, steel tower weight itself and structure size are big etc., technical economic benefit is just obvious.
Currently, highlands especially Tibet region iron tower of power transmission line vertical construction, execution conditions are more severe (high Original, High aititude, high and cold, anoxic, long-distance transport is difficult, orographic condition is poor, effective construction time is short etc.), part tower position also in Cliffs and precipices, steel tower construction will face more challenges.It is embraced under these conditions according to derrick crane group tower technology, double flat arm The existing advanced group of tower technology such as bar group tower technology, weight of equipment is possibly even near or above steel tower weight, it is clear that some are obtained not Mistake is repaid, therefore, no matter technically also not ideal from economic aspect.
Currently, highlands especially Tibet region mostly uses inner suspended inner guy pole group tower technology, the technology is because must Palpus dependence control wind rope, which is pulled outwardly, holds funeral rites part to keep and organize at a distance from vertical iron leg tower, relatively so as to cause security performance Difference, the shortcomings such as construction efficiency is low.According to the existing pole with boom class, boom, which bears huge and load, to be caused to set Standby bulky or even weight of equipment may be close to or be more than steel tower weight, and it is larger that difficulty is installed and used in the transport of equipment itself; Meanwhile this method also needs to prevent hanging piece from shaking using control wind rope, causes construction efficiency low, therefore tower erection is constructed Safety, duration etc. face huge challenge.
Summary of the invention
The purpose of the present invention is to overcome the shortcomings of the existing technology, provides a kind of typical landform tower erection construction equipment, To solve in inner suspended inner guy pole group tower technology, because must rely on control wind rope be pulled outwardly hold funeral rites part with keep with organized it is vertical The distance of iron leg tower has that more serious security risk and construction efficiency are low.
To achieve the above object, the technical solution used in the present invention is: providing a kind of typical landform tower erection construction Equipment, main pole bow segment, rotary four-way connector and master including from top to bottom sequentially coaxially connecting in steel tower main body embrace Bar standard paragraphs, rotary four-way connector left and right ends are equipped with the boom for slinging hanging piece, boom inner end and rotary four-way connector Connection, four diagonal sides of steel tower main body are to have organized the main material of vertical iron leg tower, and hanging piece is equipped with suspension centre rope;The steel tower main body is left Right two sides are equipped with the lifting component for keeping hanging piece in place, are equipped in the middle part of steel tower lower body and main pole standard paragraphs are coaxial produces Bracket;
The lifting component include successively be fixed on amplitude modulation draw off gear on the outside of steel tower lower body side by side, amplitude modulation turns to Pulley, overhead cable draw off gear and overhead cable angle pulley group, the arm head sheave being fixed in the middle part of boom outer end are covered in boom and can The amplitude modulation trolley to slidably reciprocate, two or so are fixed on the head angle pulley group of main pole head segments upper side side by side, and two It is fixed on the pulley that pulls round produced on bracket, two motor-driven grinding mills being located on the outside of steel tower lower body and amplitude modulation rope, Traction rope, leading block group and two overhead cables, overhead cable angle pulley group is between steel tower main body and overhead cable draw off gear, head Angle pulley group sets the pulley there are two left and right side by side;
Be respectively equipped with amplitude modulation rear wheel and amplitude modulation front wheel in the middle part of amplitude modulation trolley left and right ends, under amplitude modulation trolley in face of Two sides are equipped with overhead cable lifting lug afterwards, and amplitude modulation trolley is located between rotary four-way connector and arm end fixed ear;Amplitude modulation rope one end It is connect with amplitude modulation draw off gear, and successively passes through amplitude modulation angle pulley, arm head sheave and amplitude modulation front wheel, the amplitude modulation rope other end It is connect with boom outer end middle part;Described traction rope one end is connect with the suspension centre rope on hanging piece, and successively by amplitude modulation rear wheel, One head angle pulley group and one pull round pulley, and the traction rope other end is connect with a motor-driven grinding mill;
The leading block group and overhead cable angle pulley group are all provided with there are two the pulley composition that front and back is fixed side by side, and two are slipped Suo Yiduan is connect with overhead cable draw off gear, and successively passes through overhead cable angle pulley group and leading block group, and two overhead cables are another End is connect with an overhead cable lifting lug respectively, and between hanging piece and leading block group, two overhead cables pass through guiding respectively and slide overhead cable The pulley of front and rear sides in wheel group and overhead cable angle pulley group.
Preferably, described traction rope one end is connect with by wireless pulling force meter with the suspension centre rope on hanging piece.
Preferably, being all provided with the head connection arranged side by side there are two front and back at left and right sides of the main pole head segments upper side Ear, front and rear sides are equipped with arm end fixed ear above boom outer end, and ipsilateral head engaging lug and arm end fixed ear pass through drawstring Connection.
Preferably, the main pole standard paragraphs upper end quadrangle pass through respectively four pole bracing wires respectively with steel tower main body pair The main material connection of angle side four.
Preferably, the main pole standard paragraphs lower end is equipped with support pedestal, quadrangle is held by four on the upside of support pedestal Support rope is connect with four main materials of steel tower main body diagonal side respectively.
The invention has the benefit that
1. operation of the present invention personnel by regulation amplitude modulation draw off gear and overhead cable draw off gear, can be rapidly completed hanging piece with The abutting joint of vertical iron leg tower is organized;The device reduces hanging piece to the load of boom using new amplitude modulation mode, is effectively reduced The probability of safety accident occurs;The mode that the smooth rope of hanging piece lifts by crane obliquely can shorten the length of boom, to reduce equipment Structure size and weight, to improve the operating performance of equipment itself.Becoming after two overhead cable tightenings prevents hanging piece from lifting by crane Guide rail in the process can be avoided hanging piece and shake or even collide with vertical iron leg tower is organized, keeps hanging piece quickly smooth Lifting, construction efficiency can be effectively improved, and further decrease occur safety accident probability.
2. present invention starting motor-driven grinding mill is by traction wire saws hanging piece, while gradually cooperation tightening overhead cable, work as traction rope It is just tensioned and starts, two motor-driven grinding mills can realize sync pulling under the monitoring of wireless pulling force meter substantially, it is ensured that two A boom stress balance, further increases safety guarantee and construction efficiency.When needing using unilateral lifting, can also would sit idle for Boom on traction rope connection wireless pulling force meter after be anchored in ground, equally realize that two are hung under the monitoring of wireless pulling force meter The stress balance of arm.
3. main pole standard paragraphs upper end quadrangle of the invention is connect by four pole bracing wires with steel tower main body, main pole standard The support pedestal of section lower end is connect by four bearing ropes with four main materials of steel tower main body diagonal side, four pole bracing wires and four Bearing rope collective effect make this group of tower equipment it is firm be suspended in steel tower main center.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of typical landform tower erection construction equipment;
Fig. 2 is the portion the A structural schematic diagram of typical landform tower erection construction equipment;
Fig. 3 is the portion the B structural schematic diagram of typical landform tower erection construction equipment;
Fig. 4 is the portion the C structural schematic diagram of typical landform tower erection construction equipment;
Fig. 5 is the portion the D structural schematic diagram of typical landform tower erection construction equipment;
Fig. 6 is the portion the E structural schematic diagram of typical landform tower erection construction equipment;
Fig. 7 is the portion the F structural schematic diagram of typical landform tower erection construction equipment;
Fig. 8 is the boom structure schematic diagram of typical landform tower erection construction equipment.
Wherein: 1, amplitude modulation draw off gear;2, amplitude modulation angle pulley;3, overhead cable draw off gear;4, amplitude modulation rope;5, overhead cable;6, Hanging piece;7, leading block group;8, wireless pulling force meter;9, traction rope;10, arm head sheave;11, arm end fixed ear;12, amplitude modulation is small Vehicle;13, overhead cable lifting lug;14, amplitude modulation rear wheel;15, drawstring;16, boom;17, rotary four-way connector;18, main pole head section Section;19, head engaging lug;20, head angle pulley group;21, pole bracing wire;22, main pole standard paragraphs;23, bearing rope;24, Support pedestal;25, bracket is produced;26, pulley is pulled round;27, check band;28, steel tower main body;29, overhead cable angle pulley group; 30, amplitude modulation front wheel;31, suspension centre rope;32, main material.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, below in conjunction with the specific embodiment of the invention and Technical solution of the present invention is clearly and completely described in corresponding attached drawing.
With reference to Fig. 1-8, the present embodiment provides a kind of typical landform tower erection construction equipments, including in steel tower main body 28 Main pole bow segment 18, rotary four-way connector 17 and the main pole standard paragraphs 22 from top to bottom sequentially coaxially connected, rotation four 17 left and right ends of pass joint are equipped with the boom 16 for slinging hanging piece 6, and 16 inner end of boom is connect with rotary four-way connector 17, iron 28 4 diagonal sides of tower main body are to have organized the main material 32 of vertical iron leg tower, and hanging piece 6 is equipped with suspension centre rope 31;The steel tower main body 28 is left Right two sides are equipped with the lifting component for keeping hanging piece 6 in place, are equipped in the middle part of 28 lower end of steel tower main body coaxial with main pole standard paragraphs 22 Produce bracket 25.
The lifting component includes the amplitude modulation draw off gear 1 for being successively fixed on 28 lower end outside of steel tower main body side by side, amplitude modulation Angle pulley 2, overhead cable draw off gear 3 and overhead cable angle pulley group 29, the arm head sheave 10 being fixed in the middle part of 16 outer end of boom, set In boom 16 and the amplitude modulation trolley 12 that can slidably reciprocate, two or so are fixed on the bar of main 18 upper end of pole bow segment side by side Head angle pulley group 20, two are fixed on to produce and pull round pulley 26 on bracket 25, and two are located at 28 lower end of steel tower main body The motor-driven grinding mill and amplitude modulation rope 4 in outside, traction rope 9, leading block group 7 and two overhead cables 5, overhead cable angle pulley group 29 Between steel tower main body 28 and overhead cable draw off gear 3, head angle pulley group 20 sets the pulley there are two left and right side by side.
Amplitude modulation rear wheel 14 and amplitude modulation front wheel 30, amplitude modulation trolley are respectively equipped in the middle part of 12 left and right ends of amplitude modulation trolley 12 below front and rear sides be equipped with overhead cable lifting lug 13, amplitude modulation trolley 12 be located at rotary four-way connector 17 and arm end fixed ear 11 it Between;Described 4 one end of amplitude modulation rope is connect with amplitude modulation draw off gear 1, and successively passes through amplitude modulation angle pulley 2,10 and of arm head sheave It is connect in the middle part of amplitude modulation front wheel 30,4 other end of amplitude modulation rope and 16 outer end of boom;Suspension centre on described 9 one end of traction rope and hanging piece 6 31 connection of rope, and pulley 26 successively is pulled round by 14, head angle pulley groups 20 of amplitude modulation rear wheel and one, it leads 9 other end of messenger is connect with a motor-driven grinding mill.
The leading block group 7 and overhead cable angle pulley group 29 are all provided with the pulley fixed side by side there are two front and back and form, and two 5 one end of root overhead cable is connect with overhead cable draw off gear 3, and successively passes through overhead cable angle pulley group 29 and leading block group 7, and two 5 other end of overhead cable is connect with an overhead cable lifting lug 13 respectively, and overhead cable 5 is between hanging piece 6 and leading block group 7, two overhead cables Pass through the pulley of front and rear sides in leading block group 7 and overhead cable angle pulley group 29 respectively.
Described 9 one end of traction rope is connect with by wireless pulling force meter 8 with the suspension centre rope 31 on hanging piece 6.
The head engaging lug 19 arranged side by side there are two front and back, boom are all provided at left and right sides of main 18 upper end of pole bow segment 16 front and rear sides above outer end are equipped with arm end fixed ear 11, and ipsilateral head engaging lug 19 and arm end fixed ear 11 pass through drawstring 15 connections.
The 22 upper end quadrangle of main pole standard paragraphs by four pole bracing wires 21 respectively with 28 diagonal side four of steel tower main body Root main material 32 connects.
Main 22 lower end of pole standard paragraphs is equipped with support pedestal 24, and 24 upside quadrangle of support pedestal passes through four bearing ropes 23 connect with steel tower main body 28 diagonal side, four main materials 32 respectively.
In implementation process, traction rope 9 generates the horizontal component pullled towards 16 outer end of boom at amplitude modulation trolley 12, to adjust Width trolley 12 provides the power mobile to 16 outer end of boom, and can indirectly control outside horizontal component by amplitude modulation draw off gear 1 Size;Traction rope 9 generates the horizontal component pullled towards 16 inner end of boom at amplitude modulation trolley 12, for amplitude modulation trolley 12 provide to The mobile power in 16 inner end of boom, and the size of inside horizontal component can be indirectly controlled by overhead cable draw off gear 3;To reach The purpose of 6 lateral position of hanging piece can be indirectly controlled, hanging piece 6 can be rapidly completed and has organized the abutting joint of vertical iron leg tower.Together When, traction rope 9, overhead cable 5 and amplitude modulation trolley 12 can also reduce the pulling force of boom 16 vertically downward, to reduce the lotus of boom 16 It carries, can be effectively reduced the probability that safety accident occurs.
Hanging piece 6 is suspended on overhead cable 5 by leading block group 7, after two overhead cables 5 are tightened by overhead cable draw off gear 3, two Root overhead cable 5 becomes the guide rail for preventing hanging piece 6 from shaking during lifting, can be avoided hanging piece 6 and shakes or even found section with organizing Steel tower collides, and after the height in place of hanging piece 6 meets, stops drawing and eases out overhead cable 5, then eases out the satisfaction of amplitude modulation rope 4 again and hangs The radius in place of part 6 is finally transferred hanging piece 6 and is completed in place, so that hanging piece 6 be enable quickly smoothly to lift by crane, can effectively mention High construction efficiency.
In conclusion operator can be rapidly completed and be hung by regulation amplitude modulation draw off gear 1 and overhead cable draw off gear 3 Part 6 and the abutting joint for having organized vertical iron leg tower;The device reduces hanging piece 6 to the load of boom 16 using new amplitude modulation mode, The probability that safety accident occurs is effectively reduced;The mode that the smooth rope 5 of hanging piece 6 lifts by crane obliquely can shorten the length of boom 16, To reduce the structure size and weight of equipment, to improve the operating performance of equipment itself.Two overhead cables 5 become anti-after tightening Only guide rail of the hanging piece 6 during lifting can be avoided hanging piece 6 and shake or even collide with vertical iron leg tower is organized, make to hang Part 6 quickly can be lifted by crane smoothly, can effectively improve construction efficiency, and further decrease the probability that safety accident occurs.
Start motor-driven grinding mill by traction rope 9 draw hanging piece 6, while gradually cooperation tightening overhead cable 5, when traction rope 9 just Tensioning starts, and two motor-driven grinding mills can realize sync pulling under the monitoring of wireless pulling force meter 8 substantially, it is ensured that two are hung 16 stress balance of arm, further increases safety guarantee and construction efficiency.When needing using unilateral lifting, can also would sit idle for Traction rope 9 on boom 16 is anchored in ground after connecting wireless pulling force meter 8, equally realizes two under the monitoring of wireless pulling force meter 8 The stress balance of a boom 16.
Main 22 upper end quadrangle of pole standard paragraphs is connect by four pole bracing wires 21 with steel tower main body 28, main pole standard paragraphs The support pedestal 24 of 22 lower ends is connect by four bearing ropes 23 with steel tower main body 28 diagonal side, four main materials 32, and four poles are drawn Line 21 and four 23 collective effects of bearing rope make this group of tower equipment it is firm be suspended in 28 center of steel tower main body.
Above embodiment is used to illustrate the present invention, rather than limits the invention, in spirit of the invention In scope of protection of the claims, to any modifications and changes that the present invention makes, protection scope of the present invention is both fallen within.

Claims (5)

1. a kind of typical case's landform tower erection construction equipment, includes from top to bottom sequentially coaxially to connect on steel tower main body (28) Main pole bow segment (18), rotary four-way connector (17) and main pole standard paragraphs (22), rotary four-way connector (17) left and right two End is equipped with the boom (16) for slinging hanging piece (6), and boom (16) inner end is connect with rotary four-way connector (17), steel tower main body (28) four diagonal sides are to have organized the main material (32) of vertical iron leg tower, and hanging piece (6) is equipped with suspension centre rope (31), it is characterised in that: institute It states and is equipped with the lifting component for keeping hanging piece (6) in place at left and right sides of steel tower main body (28), be equipped in the middle part of steel tower main body (28) lower end With main pole standard paragraphs (22) it is coaxial produce bracket (25);
The lifting component includes amplitude modulation draw off gear (1), the amplitude modulation for being successively fixed on steel tower main body (28) lower end outside side by side Angle pulley (2), overhead cable draw off gear (3) and overhead cable angle pulley group (29) are fixed on the arm end in the middle part of boom (16) outer end Pulley (10) is covered in boom (16) and the amplitude modulation trolley (12) that can slidably reciprocate, and two or so are fixed on main holding pole head side by side The head angle pulley group (20) of portion segment (18) upper end, two are fixed on to produce and pull round pulley on bracket (25) (26), two motor-driven grinding mills and amplitude modulation rope (4), traction rope (9), leading block positioned at steel tower main body (28) lower end outside Group (7) He Lianggen overhead cable (5), overhead cable angle pulley group (29) are located between steel tower main body (28) and overhead cable draw off gear (3), bar Head angle pulley group (20) sets the pulley there are two left and right side by side;
It is respectively equipped with amplitude modulation rear wheel (14) and amplitude modulation front wheel (30) in the middle part of amplitude modulation trolley (12) left and right ends, amplitude modulation is small Front and rear sides are equipped with overhead cable lifting lug (13) vehicle (12) below, and amplitude modulation trolley (12) is located at rotary four-way connector (17) and arm end is solid Determine between ear (11);Described amplitude modulation rope (4) one end is connect with amplitude modulation draw off gear (1), and successively passes through amplitude modulation angle pulley (2), it is connect in the middle part of arm head sheave (10) and amplitude modulation front wheel (30), amplitude modulation rope (4) other end and boom (16) outer end;It is described to lead Messenger (9) one end is connect with the suspension centre rope (31) on hanging piece (6), and is successively turned by amplitude modulation rear wheel (14), a head It is pulled round pulley (26) to pulley blocks (20) and one, traction rope (9) other end is connect with a motor-driven grinding mill;
The leading block group (7) and overhead cable angle pulley group (29) are all provided with the pulley fixed side by side there are two front and back and form, and two Root overhead cable (5) one end is connect with overhead cable draw off gear (3), and successively passes through overhead cable angle pulley group (29) and leading block group (7), two overhead cable (5) other ends are connect with an overhead cable lifting lug (13) respectively, and overhead cable (5) is located at hanging piece (6) and leading block Between group (7), two overhead cables pass through the pulley of front and rear sides in leading block group (7) and overhead cable angle pulley group (29) respectively.
2. typical case's landform tower erection construction equipment according to claim 1, it is characterised in that: the traction rope (9) one End is connect with by wireless pulling force meter (8) with the suspension centre rope (31) on hanging piece (6).
3. typical case's landform tower erection construction equipment according to claim 1 or 2, it is characterised in that: the main holding pole head The head engaging lug (19) arranged side by side there are two front and back, front and back above boom (16) outer end are all provided at left and right sides of portion segment (18) upper end Two sides are equipped with arm end fixed ear (11), ipsilateral head engaging lug (19) and arm end fixed ear (11) and are connected by drawstring (15) It connects.
4. typical case's landform tower erection construction equipment according to claim 3, it is characterised in that: the main pole standard paragraphs (22) upper end quadrangle is connect with four main materials (32) of steel tower main body (28) diagonal side respectively by four pole bracing wires (21).
5. typical case's landform tower erection construction equipment according to claim 4, it is characterised in that: the main pole standard paragraphs (22) lower end is equipped with support pedestal (24), on the upside of support pedestal (24) quadrangle by four bearing ropes (23) respectively with steel tower main body (28) four main material (32) connections of diagonal side.
CN201811541805.1A 2018-12-17 2018-12-17 Typical topography iron tower assemblage construction equipment Expired - Fee Related CN109610922B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811541805.1A CN109610922B (en) 2018-12-17 2018-12-17 Typical topography iron tower assemblage construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811541805.1A CN109610922B (en) 2018-12-17 2018-12-17 Typical topography iron tower assemblage construction equipment

Publications (2)

Publication Number Publication Date
CN109610922A true CN109610922A (en) 2019-04-12
CN109610922B CN109610922B (en) 2020-12-15

Family

ID=66010394

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811541805.1A Expired - Fee Related CN109610922B (en) 2018-12-17 2018-12-17 Typical topography iron tower assemblage construction equipment

Country Status (1)

Country Link
CN (1) CN109610922B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111734203A (en) * 2020-06-24 2020-10-02 国网四川雅安电力(集团)股份有限公司 Tower device is salvageed in segmentation assemblage on built-in formula tower
EP4001553A1 (en) * 2020-11-17 2022-05-25 European Trans Energy GmbH Jury mast guide
CN115324416A (en) * 2022-03-14 2022-11-11 中铁一局集团电务工程有限公司 Integral hoisting construction process for iron tower
CN115434558A (en) * 2022-10-12 2022-12-06 国网四川电力送变电建设有限公司 Experimental tool for turning pulley of tower leg of suspension holding pole group
CN117023429A (en) * 2023-08-31 2023-11-10 华东送变电工程有限公司 Folding-preventing device for rocker arm holding pole

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003041806A (en) * 2001-07-27 2003-02-13 Mitsubishi Heavy Ind Ltd Vibration preventing structure for individual member
US7059095B1 (en) * 2002-10-11 2006-06-13 Stevens James A Anchored monopole upgrade system
CN101209805A (en) * 2007-12-21 2008-07-02 王树声 Method and equipment for hanging iron tower
CN201655133U (en) * 2009-12-11 2010-11-24 河北省电力公司石家庄培训中心 Transmission tower model for assembly installation training
CN102359303A (en) * 2011-10-31 2012-02-22 湖北省输变电工程公司 Extra-high voltage common circuit iron tower assembling method
CN202346637U (en) * 2011-10-31 2012-07-25 湖北省输变电工程公司 Holding rod of double-flat-arm spinning self-lifting seat
CN202625662U (en) * 2012-04-13 2012-12-26 四川电力送变电建设公司 Self-balancing amplitude modulation hold pole
CN204883293U (en) * 2015-08-26 2015-12-16 葛洲坝集团电力有限责任公司 Transmission line iron tower assemblage safety automatic alarm system
CN205955358U (en) * 2016-08-12 2017-02-15 内蒙古科技大学 Group's tower device of interior floated armful of pole of acting as go -between

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003041806A (en) * 2001-07-27 2003-02-13 Mitsubishi Heavy Ind Ltd Vibration preventing structure for individual member
US7059095B1 (en) * 2002-10-11 2006-06-13 Stevens James A Anchored monopole upgrade system
CN101209805A (en) * 2007-12-21 2008-07-02 王树声 Method and equipment for hanging iron tower
CN201655133U (en) * 2009-12-11 2010-11-24 河北省电力公司石家庄培训中心 Transmission tower model for assembly installation training
CN102359303A (en) * 2011-10-31 2012-02-22 湖北省输变电工程公司 Extra-high voltage common circuit iron tower assembling method
CN202346637U (en) * 2011-10-31 2012-07-25 湖北省输变电工程公司 Holding rod of double-flat-arm spinning self-lifting seat
CN202625662U (en) * 2012-04-13 2012-12-26 四川电力送变电建设公司 Self-balancing amplitude modulation hold pole
CN204883293U (en) * 2015-08-26 2015-12-16 葛洲坝集团电力有限责任公司 Transmission line iron tower assemblage safety automatic alarm system
CN205955358U (en) * 2016-08-12 2017-02-15 内蒙古科技大学 Group's tower device of interior floated armful of pole of acting as go -between

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111734203A (en) * 2020-06-24 2020-10-02 国网四川雅安电力(集团)股份有限公司 Tower device is salvageed in segmentation assemblage on built-in formula tower
CN111734203B (en) * 2020-06-24 2021-07-20 国网四川雅安电力(集团)股份有限公司 Tower device is salvageed in segmentation assemblage on built-in formula tower
EP4001553A1 (en) * 2020-11-17 2022-05-25 European Trans Energy GmbH Jury mast guide
CN115324416A (en) * 2022-03-14 2022-11-11 中铁一局集团电务工程有限公司 Integral hoisting construction process for iron tower
CN115434558A (en) * 2022-10-12 2022-12-06 国网四川电力送变电建设有限公司 Experimental tool for turning pulley of tower leg of suspension holding pole group
CN115434558B (en) * 2022-10-12 2023-08-25 国网四川电力送变电建设有限公司 Tool for suspension pole group tower leg steering pulley experiment
CN117023429A (en) * 2023-08-31 2023-11-10 华东送变电工程有限公司 Folding-preventing device for rocker arm holding pole
CN117023429B (en) * 2023-08-31 2024-03-26 华东送变电工程有限公司 Folding-preventing device for rocker arm holding pole

Also Published As

Publication number Publication date
CN109610922B (en) 2020-12-15

Similar Documents

Publication Publication Date Title
CN109610922A (en) A kind of typical case's landform tower erection construction equipment
CN103613031A (en) Simple transformer hoisting device
CN207339088U (en) Transmission line of electricity straight line pole aerial earth wire overhauls stent
CN104538887B (en) A kind of lightning conducter lifts converter
CN201171148Y (en) Machine for supporting overhead pround wire
CN101525108B (en) Method and device for reducing over-high deflection in amplitude changing process of caterpillar-band crane arm support
CN203850726U (en) Wire lifter on 10 kV power distribution telegraph pole
CN213171204U (en) Construction equipment hoisting device
CN203278097U (en) Electric pole cross arm erecting device
CN203359893U (en) Portable lift
CN109346996A (en) A kind of power construction wire tensioning device and line tightening method
CN217555571U (en) Multifunctional hoisting device for hoisting materials on electric pole
CN202917897U (en) Cable hoisting horizontal pulley
CN202542743U (en) Auxiliary reeving mechanism for mounting tower crane
CN202988609U (en) Diagonal bracing type derrick crane
CN216235734U (en) Vertical transportation hoisting structure for curtain wall unit plate
CN101934994A (en) Building high-altitude vertical hoisting double-guide cable system and assisting method
CN201793342U (en) Double guide cable system for overhead vertical lifting of building
CN202063655U (en) Anti-tilting safe device of tower type crane
CN210855091U (en) Simple movable heavy object vertical lifting equipment
CN213679578U (en) Electric power overhauls instrument lifting means
CN208843629U (en) A kind of crane upper mechanism is from dismantling device and crane
CN202190023U (en) Wire bracing device for overhead wire
CN208454364U (en) A kind of chemical industry equipment lifting maintenance unit
CN207738353U (en) Lifting hook pulley component and the crane for including the lifting hook pulley component

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201215

Termination date: 20211217