CN109604043A - Pulp pump replacement faulty equipment realizes that iron ore mill selects quantity-produced method - Google Patents

Pulp pump replacement faulty equipment realizes that iron ore mill selects quantity-produced method Download PDF

Info

Publication number
CN109604043A
CN109604043A CN201811506618.XA CN201811506618A CN109604043A CN 109604043 A CN109604043 A CN 109604043A CN 201811506618 A CN201811506618 A CN 201811506618A CN 109604043 A CN109604043 A CN 109604043A
Authority
CN
China
Prior art keywords
pulp pump
iron ore
faulty equipment
ore mill
production
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811506618.XA
Other languages
Chinese (zh)
Inventor
范泽宇
杨秀超
陈文超
杨世伟
邓大军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Panzhihua Gangcheng Group Co Ltd
Original Assignee
Panzhihua Gangcheng Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Panzhihua Gangcheng Group Co Ltd filed Critical Panzhihua Gangcheng Group Co Ltd
Priority to CN201811506618.XA priority Critical patent/CN109604043A/en
Publication of CN109604043A publication Critical patent/CN109604043A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B03SEPARATION OF SOLID MATERIALS USING LIQUIDS OR USING PNEUMATIC TABLES OR JIGS; MAGNETIC OR ELECTROSTATIC SEPARATION OF SOLID MATERIALS FROM SOLID MATERIALS OR FLUIDS; SEPARATION BY HIGH-VOLTAGE ELECTRIC FIELDS
    • B03BSEPARATING SOLID MATERIALS USING LIQUIDS OR USING PNEUMATIC TABLES OR JIGS
    • B03B7/00Combinations of wet processes or apparatus with other processes or apparatus, e.g. for dressing ores or garbage
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B03SEPARATION OF SOLID MATERIALS USING LIQUIDS OR USING PNEUMATIC TABLES OR JIGS; MAGNETIC OR ELECTROSTATIC SEPARATION OF SOLID MATERIALS FROM SOLID MATERIALS OR FLUIDS; SEPARATION BY HIGH-VOLTAGE ELECTRIC FIELDS
    • B03BSEPARATING SOLID MATERIALS USING LIQUIDS OR USING PNEUMATIC TABLES OR JIGS
    • B03B9/00General arrangement of separating plant, e.g. flow sheets

Landscapes

  • Paper (AREA)

Abstract

The invention discloses a kind of Pulp pump replacement faulty equipments to realize that iron ore mill selects quantity-produced method, is related to Process Control of Mineral Dressing technical field, solves iron ore mill and selects in continuous production, the problem of faulty equipment flexibility difference is replaced by cage.The technical solution adopted by the present invention is that: Pulp pump replacement faulty equipment realizes that iron ore mill selects quantity-produced method, iron ore mill selects any appliance in production line to break down, the outlet end of the upstream equipment of faulty equipment connects input pipe, input pipe is connected to medial launder, Pulp pump is placed in medial launder, the arrival end of the upstream device of the efferent duct and faulty equipment of Pulp pump is connected, and Pulp pump maintains iron ore mill to select production line continuous production.The present invention is in iron ore mill choosing production, Pulp pump replacement faulty equipment to continue to produce, while repairing to faulty equipment, avoids faulty equipment from influencing rhythm of production, maintains the continuous production of whole production line;Pulp pump can be connected with multiple devices, strong flexibility, can also realize that cross-line produces.

Description

Pulp pump replacement faulty equipment realizes that iron ore mill selects quantity-produced method
Technical field
The present invention relates to Process Control of Mineral Dressing technical fields, specifically in PRODUCTION OF IRON POWDER, are set using Pulp pump to failure It is standby temporarily to be replaced, to realize that iron ore mill selects quantity-produced method.
Background technique
PRODUCTION OF IRON POWDER process carries out gradually mill to ferrous material using ball mill, magnetic separator, grader and selects and be classified, thus Reach and promotes metal Ferrum content to reach iron powder product requirement.There are failure rate, equipment for ball mill, magnetic separator, grader use Longer using the time, failure rate is higher.Magnetic separator and grader online repair time are relatively short, and half a day can repair and finish, Select Influence of production smaller on iron ore mill.However, ball mill maintenance time is long, replaces one big ball mill whole lining and need five days Left and right replaces one small ball mill whole lining and needs three days or so, if the failures such as end cover of ball mill then need it is longer Time, even up to half month.
Ball mill, magnetic separator, grader etc. are that iron ore mill selects quantity-produced necessaries, and any appliance breaks down, It is both needed to whole production line halt production, finishing to faulty equipment maintenance can just resume production, and seriously affect production process.Applicant Zeng Cai It realizes that iron ore mill selects continuous production with cage replacement faulty equipment, but since cage is relatively cumbersome and takes up a large area, and twists Cage takes up a large area and imports and exports apart from relatively fixed, therefore cage is only applicable to replace big ball mill.Cage is in production scene Applicability be not it is very strong, such as magnetic separator or small ball mill failure, then it is poor to replace effect;In addition, cage can only be directly connected to The equipment of faulty equipment upstream and downstream two sides can not achieve cross-line production.
Summary of the invention
The present invention provides a kind of Pulp pump replacement faulty equipment and realizes that iron ore mill selects quantity-produced method, solves iron ore mill It selects in continuous production, the problem of faulty equipment flexibility difference is replaced by cage.
The technical solution adopted by the present invention to solve the technical problems is: Pulp pump replaces faulty equipment and realizes iron ore mill choosing Quantity-produced method, iron ore mill select any appliance in production line to break down, the outlet end of the upstream equipment of faulty equipment Input pipe is connected, input pipe is connected to medial launder, placement Pulp pump in medial launder, under the efferent duct and faulty equipment of Pulp pump The arrival end for swimming equipment is connected, and Pulp pump maintains iron ore mill to select production line continuous production.
Further, the medial launder isFlat drum.
Further, the Pulp pump is vertical slag slurry pump, the diameter of the bottom of vertical slag slurry pump isIt is vertical Formula Pulp pump is installed on the middle part of medial launder.
It is specific: the model 40PV-SP of the vertical slag slurry pump, 20 meters of lift, flow 15m3/h。
The beneficial effects of the present invention are: replacing faulty equipment in iron ore mill choosing production by Pulp pump and continuing to produce, simultaneously The faulty equipment is repaired, avoids faulty equipment from influencing rhythm of production, maintains the continuous production of whole production line.The present invention Overall operation to production line is a strong guarantee, and installation and dismounting are convenient, and are not influenced by place.Due to iron ore There are faulty equipments for mill choosing production, but adjust rhythm of production by control blanking velocity and water, can make up the failure lacked and set Standby defect can meet product quality requirement.In the mill choosing production of Pulp pump iron ore, Pulp pump can be connected with multiple devices, spirit It is active strong, and cross-line production may be implemented.
Specific embodiment
The invention will be further described below.
Pulp pump replacement faulty equipment of the present invention realizes that iron ore mill selects quantity-produced method, and iron ore mill selects in production line Ball mill, magnetic separator, grader any appliance break down, and the outlet end of the upstream equipment of faulty equipment connects input pipe, defeated Enter pipe and be connected to medial launder, places Pulp pump, the entrance of the upstream device of the efferent duct and faulty equipment of Pulp pump in medial launder End is connected, and Pulp pump maintains iron ore mill to select production line continuous production.It replaces faulty equipment by Pulp pump to continue to produce, while right The faulty equipment repairs, and faulty equipment is avoided to influence rhythm of production, and operating rate can be started by improving equipment, maintains whole production The continuous production of line.
The slurry of upstream equipment production of the medial launder for temporarily storing faulty equipment, it is right due to containing particle in slurry Pulp pump and water wheels have stronger abrasion condition, therefore Pulp pump preferably selects wear-resisting vertical slag slurry pump.For example, vertical slag The model 40PV-SP of stock pump, 20 meters of lift, flow 15m3/h。
Pulp pump is placed in medial launder, and slurry is pumped into the upstream device of faulty equipment, medial launder inner wall and slurry Certain gap is retained between pump, such as medial launder isFlat drum;While the bottom of Pulp pump Diameter is Pulp pump is installed on the middle part of medial launder.Slurry pump discharge connection efferent duct connection flexibly, it can be achieved that Cross-line production.

Claims (4)

1. Pulp pump replacement faulty equipment realizes that iron ore mill selects quantity-produced method, it is characterised in that: iron ore mill selects production line In any appliance break down, the outlet end of the upstream equipment of faulty equipment connects input pipe, and input pipe is connected to medial launder, Pulp pump is placed in medial launder, the arrival end of the upstream device of the efferent duct and faulty equipment of Pulp pump is connected, and Pulp pump maintains Iron ore mill selects production line continuous production.
2. Pulp pump replacement faulty equipment as described in claim 1 realizes that iron ore mill selects quantity-produced method, feature exists In: the medial launder isFlat drum.
3. the Pulp pump replacement faulty equipment as described in right wants 1 or 2 realizes that iron ore mill selects quantity-produced method, feature exists In: the Pulp pump is vertical slag slurry pump, and the diameter of the bottom of vertical slag slurry pump isDuring vertical slag slurry pump is installed on Between slot middle part.
4. Pulp pump replacement faulty equipment as claimed in claim 3 realizes that iron ore mill selects quantity-produced method, feature exists In: the model 40PV-SP of the vertical slag slurry pump, 20 meters of lift, flow 15m3/h。
CN201811506618.XA 2018-12-10 2018-12-10 Pulp pump replacement faulty equipment realizes that iron ore mill selects quantity-produced method Pending CN109604043A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811506618.XA CN109604043A (en) 2018-12-10 2018-12-10 Pulp pump replacement faulty equipment realizes that iron ore mill selects quantity-produced method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811506618.XA CN109604043A (en) 2018-12-10 2018-12-10 Pulp pump replacement faulty equipment realizes that iron ore mill selects quantity-produced method

Publications (1)

Publication Number Publication Date
CN109604043A true CN109604043A (en) 2019-04-12

Family

ID=66008151

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811506618.XA Pending CN109604043A (en) 2018-12-10 2018-12-10 Pulp pump replacement faulty equipment realizes that iron ore mill selects quantity-produced method

Country Status (1)

Country Link
CN (1) CN109604043A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101708483A (en) * 2009-11-07 2010-05-19 核工业烟台同兴实业有限公司 Tailing dry-heaping equipment and processing technique thereof
CN106040409A (en) * 2016-08-24 2016-10-26 孙召华 Ore-dressing system and ore-dressing technology for reducing content of sulphur in iron ore concentrate and for sorting cobalt concentrate
CN206474276U (en) * 2017-01-06 2017-09-08 中国矿业大学 A kind of new type mining sub-material box structure
CN108579981A (en) * 2017-12-29 2018-09-28 攀枝花钢城集团有限公司 Cage replaces faulty equipment and realizes that iron ore mill selects quantity-produced method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101708483A (en) * 2009-11-07 2010-05-19 核工业烟台同兴实业有限公司 Tailing dry-heaping equipment and processing technique thereof
CN106040409A (en) * 2016-08-24 2016-10-26 孙召华 Ore-dressing system and ore-dressing technology for reducing content of sulphur in iron ore concentrate and for sorting cobalt concentrate
CN206474276U (en) * 2017-01-06 2017-09-08 中国矿业大学 A kind of new type mining sub-material box structure
CN108579981A (en) * 2017-12-29 2018-09-28 攀枝花钢城集团有限公司 Cage replaces faulty equipment and realizes that iron ore mill selects quantity-produced method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王笏曹: "《钢铁工业给水排水设计手册》", 31 January 2002 *

Similar Documents

Publication Publication Date Title
CN103350037B (en) Overflow particle size control method for cyclone
CN205740928U (en) High-quality water-coal-slurry prepares processing system
CN107619895B (en) Device for blowing coal powder into blast furnace
CN109604043A (en) Pulp pump replacement faulty equipment realizes that iron ore mill selects quantity-produced method
CN103418303B (en) Device and method for stably adding sludge in sintering
CN102022311A (en) Electric energy control method and electric energy control system for dedusting equipment
CN204022450U (en) A kind of flotation pulp distributing box
CN104874472B (en) Automatic separating device for fine-sized slime in tailings conveying manifolds
CN103480660A (en) Independent water supply method and device for pre-through-water cooling device before bar material finish rolling
CN205258225U (en) Magnetism paper tape filter
RU2465056C1 (en) Ore suspension separation complex
RU2464102C1 (en) Ore suspension separation complex
CN210022008U (en) Sintering mixes quick-witted water distribution device that becomes more meticulous
CN203355681U (en) Stable sintering sludge addition device
CN107262224A (en) A kind of zinc oxygen leaching method for preparing raw material and two sections of vertical stirring mill series connection open-circuit grinding systems
CN103993158B (en) Process and system for removing alkali metals out of iron and steel making fly ash
CN103834818B (en) Oxygen adding system and method for reactor iron removing
CN108579981A (en) Cage replaces faulty equipment and realizes that iron ore mill selects quantity-produced method
CN103525958B (en) A kind of without granulation pump-type high temperature furnace slag water quenching technology and system
CN208266232U (en) A kind of scattered volume spray cooling system of STAINLESS STEEL WIRE
CN205926067U (en) Iron ore beneficiation system of pelletizing, two products of sintering
CN110423024A (en) The processing method and dedicated treatment facility of slag during a kind of blast furnace or mine heat furnace smelting
CN110801933A (en) Method for improving raw coal sorting effect
CN203556458U (en) Ore pulp box
CN203907234U (en) Slurry pipeline conveying system of double concentration basins

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190412

RJ01 Rejection of invention patent application after publication